Exhibit N Sample Subcontract.pdf

PDF 195 KB Posted

Attached to
Fire House Generator and ATS Replacement
Solicitation number
ISD_363232_DA
Issued by

About this file

This is a sample subcontract template for construction work related to the Fire House Generator and ATS Replacement project at Fermi National Accelerator Laboratory (FNAL) in Batavia, Illinois. The document outlines the structure and terms of a firm fixed-price subcontract between Fermi Research Alliance, LLC (FRA) and a potential subcontractor.

The subcontract details requirements for replacing the Fire House Generator and automatic transfer switch, with work to be completed within a specified number of calendar days after Notice-to-Proceed. Key provisions include monthly progress payments with 10% retention until final completion, detailed invoicing requirements, and progress reporting obligations. The subcontractor must submit monthly progress reports describing completed and planned work. The document specifies that Danielle Amico serves as the FRA Procurement Representative and Justin Block as the Technical Representative. The subcontract incorporates several documents including the Statement of Work, General Requirements, Environmental Safety and Health Requirements, Davis Bacon wage rates, and various bonds and forms required for construction projects.

View the file

Other files

File Type Posted
Amendment 02 to RFP 363232.pdf PDF
Rev Exhibit C updated 013100_ESH_Requirements_FermiForward.pdf PDF
Rev Exhibit H Performance Bond FL-40_FFDG.pdf PDF
Rev Exhibit L SARC_Subcontractor Annual RepsCerts Rev 4_FFDG.pdf PDF
QandA_RFP 363232.pdf PDF
Rev Exhibit E Construction Insurance Requirements (01-2025)_FFDG.pdf PDF
Rev Exhibit F Bid Bond FL-41_FFDG.pdf PDF
Rev Exhibit G Payment Bond FL-42_FFDG.pdf PDF
Rev Exhibit J Statement and Acknowledgment (SF1413-23)_FFDG.pdf PDF
Rev Exhibit B updated 010010_General_Requirements_3_2022 FermiForward.pdf PDF
Rev Exhibit D General Terms and Conditions for Construction (01-2025)_FFDG.pdf PDF
Rev Exhibit K Proposal Certifications Form PUR-466_FFDG.pdf PDF
Amendment 01 to RFP 363232.pdf PDF
Exhibit A SOW-Fire House Generator and ATS Replacement.pdf PDF
Exhibit H Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit K Proposal Certifications Form PUR-466 Rev 1 (10142021).pdf PDF
2.0 Price Proposal Form.pdf PDF
Exhibit B 010010_General_Requirements_3_2022 (1).pdf PDF
Exhibit D FRA General Terms and Conditions for Construction (03.2024).pdf PDF
Exhibit G Payment Bond FL-42 (Rev 12.22).pdf PDF
Exhibit I Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit Q Fermilab Site Map-Fire House.pdf PDF
1.0 Request for Proposal_ISD_363232_DA.pdf PDF
Business Visitor Registration Instructions and Directions.pdf PDF
Summary of Required Solicitation Documents.pdf PDF
Exhibit C 013100_ESH_Requirements_3-2022 -FD.pdf PDF
Exhibit F Bid Bond FL-41 (Rev 12.22).pdf PDF
Exhibit M Davis Bacon Wage Rates IL20240008 Mod 11 2024_1018.pdf PDF
Exhibit O Director Safety Letter.pdf PDF
Exhibit P Fire House Generator-Drawing-Markup and notes.pdf PDF
Exhibit E Construction Insurance Requirements 2024.pdf PDF
Exhibit J Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
Exhibit L Subcontractor Annual Representations and Certifications (SARC) Form SARC (Rev 3).pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Subcontract No. XXXXXX Page 1 of 5

SUBCONTRACT NO.

Fermi Research Alliance LLC Kirk Road & Wilson Street P.O. Box 500 – Mail Station 210 Batavia, IL 60510-0500

Subcontractor:

Company Name Company Address City, State Zip Code

FRA Procurement Representative:

Name: Danielle Amico Title: Procurement Specialist IV Phone: 630-840-3207 E-Mail: damico@fnal.gov

Introduction

This is a firm fixed price subcontract (hereinafter “Subcontract”) for the construction work associated with the construction project involving the Fire House Generator and ATS Replacement, as further described herein.

This Subcontract is between Fermi Research Alliance, LLC, and the party identified above as the “Subcontractor.”

This Subcontract is issued under Prime Contract No. DE-AC02-07CH11359 between the United States Government (hereinafter “Government”), represented by the Department of Energy (hereinafter called “DOE”) and Fermi Research Alliance, LLC (hereinafter “FRA”) for the management and operation of the Fermi National Accelerator Laboratory.

Agreement

The parties agree to perform their respective obligations in accordance with the terms, conditions, and provisions of the attached SCHEDULE OF ARTICLES and the documents referenced or incorporated therein, which together with this Signature Page shall collectively constitute the entire Agreement and shall supersede all prior negotiations, representations, or agreements, whether verbal or written.

SUBCONTRACTOR FERMI RESEARCH ALLIANCE, LLC

By: By:

Name: Name:

Title: Title:

Date: Date:

mailto:damico@fnal.gov

Subcontract No. XXXXXX Page 2 of 5

SCHEDULE OF ARTICLES

ARTICLE 1 – SCOPE OF WORK

A. Description. The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to perform the work described in the Statement of Work entitled, “Fire Department Generator Replacement,” Section 010010 - General Requirement (March 2022), Section 013100 - Environment, Safety, and Health Requirements (March 2022) mentioned therein, which the Statement of Work, amendment, and other documents are attached to and hereby made a part of this Subcontract.

B. Location. The principal location for the work to be performed by the Subcontractor shall be the Fermi National Accelerator Laboratory, located in Batavia, Illinois.

C. Acceptance. Acceptance of the work under this Subcontract shall be based on the Subcontractor’s performance and completion of the work in consonance with high professional standards and compliance with the delivery and reporting requirements specified herein.

ARTICLE 2 – PERIOD OF PERFORMANCE

The work shall be completed within ( ) calendar days upon receipt of the Notice-to-Proceed.

ARTICLE 3 – PRICE AND LIMITATIONS

The Firm Fixed-Price (FFP) and compensation for the performance of the work shall be Dollars and /100 ($ ).

The Firm-Fixed Price and the total amount of change order(s) shall be the limit of FRA’s liability for all costs under this Subcontract, any other provision of this Subcontract notwithstanding.

ARTICLE 4 – INVOICES AND PAYMENT

A. Invoices

1. Monthly progress payments shall only be made in accordance with the submitted and FRA-approved project schedule, with the required progress and valuations for each cited task. The FRA Construction Coordinator and the Subcontractor shall review the progress of the Subcontract work monthly to determine the amount of compensation due to the Subcontractor on that month’s invoice. The compensation due to the Subcontractor on that month’s progress payment invoice shall then be determined in accordance with the Subcontractor’s cost-loaded schedule.

2. In making such progress payments, there shall be retained ten (10) percent of the estimated amount until final completion and acceptance of the Subcontract work. However, if FRA finds that satisfactory progress is being achieved, FRA may authorize the making of payments in which a lesser percentage is retained. When the work is substantially complete, FRA shall retain an amount it considers adequate for the protection of the Government and may release to the Subcontractor all or any portion of any excess amount. Also, on completion and acceptance of each separate building, public work, or other division of the Subcontract, on which the price is stated separately in the Subcontract, payment may be made without retention of a percentage.

Subcontract No. XXXXXX Page 3 of 5

The Subcontractor's monthly progress payment invoice shall clearly state as a minimum all the following information:

Subcontractor Name - As stated in the subcontract:

Remittance Address:

Name of person requesting payment:

Telephone Number and/or email address of the person requesting payment:

Subcontractor’s statement that the invoice is correct:

Project Name:

Project Number:

Subcontract Number:

Date of Project Update for this Invoice:

Update Number (as may be applicable):

Total Contract Value $XXXX.XX Total Dollar Value $XXXX.XX Earned to Date: $XXXX.XX Less Previous Payments: $XXXX.XX Less Previous Retention: $XXXX.XX Gross Amount Earned This Update Period: $XXXX.XX

3. All invoices shall be emailed directly to the Fermi National Accelerator Laboratory (FNAL) Accounts Payable Office at apinvoices@fnal.gov. The “subject” line of the email shall state the Subcontractor’s name and the Subcontract number.

If the Subcontractor is unable to submit an invoice by email, it may submit the invoice to the following address:

Fermi National Accelerator Laboratory Accounts Payable P.O. Box 500 Batavia, IL 60510 Apinvoices@fnal.gov

4. A “Final Invoice” shall be submitted within sixty (60) days of completion of the work or expiration or termination of this Subcontract.

5. All invoices shall state the Subcontract number; clearly identify the Subcontractor (including business heading or logo); include invoice date, unique invoice number, and remittance address;

and sufficiently identify and support the payment requested. Invoice(s) in a spreadsheet format are unacceptable, but a spreadsheet can support an invoice. The Subcontractor shall maintain records that support all invoiced amounts and provide them to FRA Procurement Representative upon request.

B. Payment

All invoices except the final invoice shall be payable within thirty (30) days of receipt; provided, however, that payments made thereafter shall not be subject to any penalty, interest, or late charges. Only those items/services identified in this Subcontract, or a Subcontract Modification will be considered for payment.

mailto:apinvoices@fnal.gov mailto:Apinvoices@fnal.gov

Subcontract No. XXXXXX Page 4 of 5

Payments Withheld. FRA may decline to make a progress payment, in whole or in part, to the extent reasonably necessary to protect FRA, if in FRA's opinion, the Subcontractor's application for payment is inaccurate in any material respect. If FRA and the Subcontractor cannot agree on a revised amount, FRA will promptly issue payment for such portion of the application for payment, if any, that it believes is correct or accurate. FRA may also nullify the whole or any part of any progress payment previously issued, to such extent as may be necessary to protect FRA from loss because of:

1. Defective Work not remedied;

2. Third-party claims filed or reasonable evidence indicating probable filing of such claims;

3. Failure of the Subcontractor to make payments properly to Subcontractors or for labor, materials, or equipment in accordance with prior approved Certificates of Payment;

4. Damage to the property of the Department of Energy, FRA, another contractor, or anyone else;

5. Persistent failure to carry out the Work in accordance with the Contract Documents;

6. Failure of the Subcontractor to provide updated monthly reports or progress schedules; or

7. The filing of a notice of claim or encumbrance or attachment or a reasonable basis to believe that a claim or encumbrance may be filed, except if the purported claim or attachment is the result of FRA's nonpayment of an amount contained in a previously submitted Application for Payment as to which no good-faith dispute exists between FRA and Subcontractor.

When the above grounds in Subparagraphs 1 through 7 stated above are removed, payment shall be made for amounts withheld because of them. Notwithstanding the above provisions of this Paragraph, FRA may also withhold a reasonable portion of any payment for any of the above-stated reasons or any other reason relating to the Subcontractor’s non-performance. FRA shall inform the Subcontractor in writing of such reason for withholding. Questions regarding invoices should be directed to the FRA Procurement Representative.

ARTICLE 5 – SUBCONTRACT ADMINISTRATION

A. Notices, Requests, and Modifications. The Subcontractor shall submit all notices and requests for approval by email to FRA Procurement Representative indicated at the following mail address:

Danielle Amico Fermi Research Alliance LLC P.O. Box 500 – Mail Station 210 Batavia, IL 60510-0500 damico@fnal.gov

Only the FRA Procurement Representative is authorized to modify the terms, conditions, and requirements of this Subcontract, including any changes to the description of the work, and to issue any notices and approvals required by this Subcontract.

B. Justin Block is the FRA Technical Representative for this Subcontract. This individual is designated to monitor the performance of the work and to interpret and clarify the technical requirements but is not authorized to make changes to the work or to modify any of the terms and conditions of this Subcontract, including those related to the completion schedule or pricing.

C. Closeout. The Subcontractor shall, as a condition of full payment, assist FRA after the completion of the work in accomplishing the administrative closeout of this Subcontract, including, as necessary or required, the furnishing of documentation and reports, the disposition of property, the disclosure of any inventions, the execution of any required assignment or release documents, the performance of any audits, and the settlement of any interim or disallowed costs.

mailto:rropos@fnal.gov

Subcontract No. XXXXXX Page 5 of 5

ARTICLE 6 – REPORTS OR DELIVERABLES

Types of Reports

A. The Subcontractor shall prepare and submit the following reports to FRA:

Monthly Progress Reports – An initial progress report, and revisions based on Subcontract changes affecting cost or schedule, shall establish and maintain a time-phased baseline against which performance can be measured. Monthly progress reports shall be submitted by the Subcontractor in a format approved by the FRA Technical Representative. These reports should contain a description of work performed during the month reported and work planned for the next month.

B. Submittal. Reports shall be separately submitted to the following recipients at the following email addresses:

Recipient Email

FRA Technical Representative (Justin Block) FRA Procurement Representative (Danielle Amico) jblock@fnal.gov damico@fnal.gov

ARTICLE 7 - INCORPORATED DOCUMENTS

The following documents are hereby incorporated as a part of this Subcontract.

A. Statement of Work entitled, “Fire Dept Generator Replacement.”

B. Section 010010 - General Requirement (March 2022).

C. Section 013100 - Environment, Safety, and Health Requirements (March 2022).

D. Fermi Research Alliance, LLC General Terms and Conditions for Construction, (03/2024).

E. Insurance Requirements for Construction Subcontracts (08/2024).

F. Payment Bond, FL-42 (Rev. 12-12-2022) SF25A (Rev 8/2016).

G. Performance Bond, FL-40 (Rev. 12-12-2022), SF25 (Rev 08/2016).

H. Statement and Acknowledgment (Standard Form 1413) (Rev 4/2013).

I. Davis Bacon Wage Rates, General Decision, IL20240008, Building and Residential, Modification No. 11, Last Revised Date 10/18/2024.

J. Director Safety Letter K. Fire House Generator – Drawing-Markup and Notes L. Fermilab Site Map – Fire House

ARTICLE 8 – GENERAL PROVISIONS

The FAR and DEAR clauses listed in the Clauses Incorporated by Reference [Clause 17 of FRA General Terms and Conditions for Construction Subcontracts (03/2024)] shall be applicable to this Subcontract based on the value of the Subcontract, the status of the Subcontractor, and the nature and location of the work.

(END OF SCHEDULE OF ARTICLES)

mailto:jblock@fnal.go mailto:rropos@fnal.gov

ARTICLE 1 – SCOPE OF WORK
ARTICLE 2 – PERIOD OF PERFORMANCE
ARTICLE 3 – PRICE AND LIMITATIONS
ARTICLE 4 – INVOICES AND PAYMENT
ARTICLE 5 – SUBCONTRACT ADMINISTRATION
ARTICLE 6 – REPORTS OR DELIVERABLES
ARTICLE 7 - INCORPORATED DOCUMENTS
ARTICLE 8 – GENERAL PROVISIONS