This Statement of Work outlines requirements for a generator replacement project at the Fermilab Fire Department in Kane County, IL. The project requires installation of a new 50KVA (40kW) 480VAC 3-phase natural gas generator with sound attenuation and associated equipment including a 100amp transfer switch, natural gas line, ground ring, and protective bollards.
Key deliverables include demolition of existing equipment, installation of the new generator system with required safety features (LOTO capability, cold weather package, event history controller), trenching and electrical work, load bank testing, and site restoration. The contractor must comply with Fermilab safety requirements including hazard analysis, daily safety briefings, and proper badging (REAL ID required). All building outages must occur during normal business hours when temperatures are above freezing and be coordinated with the POC. The provided image shows the red exterior wall of the building where the generator will be installed between parking spaces and the building.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Fermilab POC: Justin Block POC email: jblock@fnal.gov POC: phone: 630-488-6851 Project: Fire Dept generator replacement County: Kane
Deliverables
• Demo as per site conditions for new installation
• Supply all O&M manuals for generator and transfer switch
• Install generator on west side of building between parking spaces and building exterior
• Supply and install new 50KVA (40kW) 480VAC 3 phase Natural Gas generator o Controller must have ability to view event history o Included battery charger o Cold weather package (block heater) o Battery disconnect switch, LOTO capable o LOTO capable output breaker
• Supply and install Sound Attenuated Level 2 Enclosure, rated to comply with NFPA 37 4.1.4 when installed next to building
• Supply and install QTY-1) 100amp 480vac NEMA 3R transfer switch with manual transfer option without exposure to conductors inside cabinet such as Russelectric RTS03.
• Provide start up and Load bank testing
• Supply and install natural gas line from high pressure line on North side of building to generator
• Supply and install natural gas regulator
• Provide and install ground ring
• Provide trenching, hydrovac, and backfill as required for electrical/gas line work
• Provide and install conduit and wire as per electrical scope as follows:
QTY-3) 1 ½” conduits for normal, emergency, and load power QTY-1) 1” conduit for battery charger, block heater, etc.
mailto:jblock@fnal.gov
• Conduit to be GRC/EMT as per site conditions and NEC
• Provide final grading and landscaping to match current conditions
• Provide QTY-4) 4” Concrete filled Safety bollards for equipment protection
• Provide snow fencing and pavement clean-up as required
• Update schedules as required
• LOTO as required
• Label all cables, wire, and circuits.
• Remove and dispose of old generator, disconnect and remove electrical back to nearest junction box
• Remove and dispose of old fuel tank
• Remove and dispose of old transfer switch, disconnect electrical back to nearest junction box
• Restore pavement under old generator to match rest of parking lot
• Remove and re-install current switch and load bank connections with new generator to provide load bank abilities.
• Provide and install lamicoid equipment designation labels
• Provide arc flash calculations for equipment being installed and install labels. E-tap is preferred analysis software
• Remote annunciator panel and e-stop to be installed inside the building
• Load bank test generator after installation 1 hr stepping up to full power in 25% increments and 1 hour at 100% power. Monitor lube oil press/temp, coolant temp, NG pressure, ambient temperature, phase voltages, phase currents, freq, KW loading, battery voltage
• Perform installations in accordance with attached markup drawing and supplemental notes.
• Provide snow fence/barriers as needed to
Additional
• Outages to the building must occur within normal business hours when temperature is above freezing. Outages must be coordinated with POC.
• Procure ALL necessary equipment, vehicles, lifts, materials for the job
• Provide necessary work safety planning and documents o Provide written Hazard Analysis in advance of the start of the work for approval by Fermilab Safety personnel o Perform a Daily Onsite Job Hazard Analysis prior to commencing any site activities.
o Coordinate with Fermilab to perform Lock Out/Tag‐Out (LOTO) activities as required by project scope of work.
o Perform equipment inspections as required.
• Attend ½ hour Fermilab orientation for all onsite technicians, including sub-contractors. Arrive 15 minutes early
• Install / uninstall personnel protective grounding, as required.
• Supply all ladders and/or lifts and required safety equipment (fall protection) as required
• Submit personnel information for proper Fermilab badging requirements for work onsite in advance of work start o REAL ID is now required for access to Fermilab
• Mobilize all necessary equipment
• Portable toilet if required by on site personnel.