The document provided is a Contractor's Cost Proposal Format for elevator maintenance and related services. The key details are:

The contract is for a one-year period from 4/1/2025 to 3/31/2026 to provide full elevator maintenance service at a federal building located in Detroit, Michigan. The contractor is required to comply with ASME safety code requirements, manufacturer recommendations, and all applicable laws and regulations. The cost proposal format includes detailed pricing for direct labor, fringe benefits, other direct costs such as materials and equipment, and indirect costs including general & administrative and profit. No specific pricing amounts are provided, as this appears to be a template document. The related federal contract opportunity is for Solicitation Number 47PF0024R0108 issued by the General Services Administration Public Buildings Service Region 5.

View the file

Other files for this federal contract opportunity

Other files attached to Elevator Maintenance & Related Services, newest first.
File Type Posted
SF30 47PF0024R0108 Amendment 0005.pdf PDF
Section B - 985 Elevator Electronic Offer Sheet 12-16-2024.xlsx XLSX spreadsheet
Q and A as of 12132024.pdf PDF
SF30 47PF0024R0108 Amendment 0004.pdf PDF
2024 Semi for L5.pdf PDF
2024 Parking Garage Elev P1 QEI Report.pdf PDF
Q and As.pdf PDF
2021 5 Year Testing Results.pdf PDF
2024 Parking Garage Elev P2 QEI Report.pdf PDF
2021 F4.pdf PDF
2024 Semi annual testing 1 2 3 6 7 8 and F1 2 3.pdf PDF
2024 Parking Garage Elev P3 QEI Report.pdf PDF
SF30 47PF0024R0108_0003.pdf PDF
SF30 47PF0024R0108 Amendment_0002.pdf PDF
Solicitation Amendment 47PF0024R0108_0001.pdf PDF
Section B 2024 10 29 Rev 1.xlsx XLSX spreadsheet
Exhibit J10 Quality Assurance Surveillance Plan.docx DOCX document
Exhibit J15 Wage Determination.pdf PDF
47PF0024R0108.pdf PDF
Exhibit J13 Electric Traction Elevator Checklist.pdf PDF
Section B 2024 08 19.xlsx XLSX spreadsheet
Exhibit J7 Elevator Inspection Form.pdf PDF
Exhibit J12 Model Subcontracting Plan Template.docx DOCX document
Exhibit J14 Asbestos Notification.docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MechCCP

CONTRACTOR'S NAME:
LOCATION:
985 Federal Building, 985 Michigan Ave, Detroit, MI
DESCRIPTION OF SERVICE:
Elevator Maintenance & Related Services
CONTRACT PERIOD:
4/1/2025 - 3/31/2026
SECTION I - DIRECT LABOR COSTNUMBER OF EMPLOYEES:
1.Journeyman Labormanhours X$per hour =$- 0
2.Mechanic Helper Labormanhours X$per hour =$- 0
3.Supervisory Labormanhours X$per hour =$- 0
4.Vacations:Vacation Hours:- 0
a. (Journeyman)manhours X$per hour =$- 0
b. (Mechanic Helper)manhours X$per hour =$- 0
c. (Supervisor)manhours X$per hour =$- 0
4.Paid Sick Leave:Paid Sick Leave Hours:- 0
a. (Journeyman)manhours X$per hour =$- 0
b. (Mechanic Helper)manhours X$per hour =$- 0
c. (Supervisor)manhours X$per hour =$- 0
5.Holidays:Holiday Hours:- 0
a. (Journeyman)manhours X$per hour =$- 0
b. (Mechanic Helper)manhours X$per hour =$- 0
c. (Supervisor)manhours X$per hour =$- 0
6.TOTAL MANHOURS:- 0
7.TOTAL LABOR COST (Add labor, vacation and holidays):$- 0
8.Health and Welfare- 0hours X$per hour =$- 0
9.Workman's Compensation% of Total Labor Cost =$- 0
10.Social Security Tax% of Total Labor Cost =$- 0
11.Federal Unemployment Tax0.6% of 1st $7,000 per employee =$- 0
12.State Unemployment Tax2.7% of 1st $9,500 per employee =$- 0
13.Other Fringe Benefits (pension, education, etc.)
hours X$per hour =$- 0
14.TOTAL FRINGE BENEFIT COST$- 0
15.TOTAL DIRECT COSTS (Add labor, fringe benefits and payroll tax)$- 0
SECTION II - OTHER DIRECT COSTS
16.Materials(%of Direct Labor Costs)$- 0
17.Equipment(%of Direct Labor Costs)$- 0
18.Subcontracts (please attach separate list)$
19.TOTAL OTHER DIRECT COSTS$- 0
SECTION III - INDIRECT COSTS
20.General and Administrative(%of Direct & Other Costs)$- 0
21.Profit(%of Total Costs and G&A)$- 0
22.TOTAL INDIRECT COSTS$- 0
23.TOTAL COST FOR BASIC SERVICE (for a one-year period)$- 0
(Sum of Direct, Other Direct and Indirect Costs)