This document is a Table X-1 Acceptance Test for Electric Elevators form (ASME A17.1-2019/CSA B44:19) containing inspection results for an elevator system. The test was performed by Cornelius Myers of NOESA, with Corporate Elevator Asset Management and Armstrong Elevator conducting the performance testing.
The form lists 29 specific test requirements including door operations, safety systems, braking mechanisms, and emergency features. Most items were tested on 12/5 with some marked as "N/A". Notable results include an emergency brake test measurement of 7.5" with 8.5°g, items 22-23 marked as "RETURNED PROPERLY", and item 27 (Firefighters' Emergency Operation) marked as "MODIFIED". Additional technical specifications noted at the bottom indicate values for electric (380), 3PT (450), Pull (230), "428 FT/min", and "21° sldr".
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
G.H. Forbes Associates
| AC 08-DEC-2023 |
| Photo 1: P3 controller Photo 2: P3 machine |
| Photo 3: Inside P3 controller – terminal wires |
| Photo 4: Disconnect switches and new electrical panel |
| Photo 5: Cab interior |
| Photo 6: Cab interior |
| END OF REPORT |