Exhibit F - AIA A133-2019 Guaranteed Maximum Price (AIA Exhibit A).pdf
PDF 144 KB Posted
- Attached to
- Big Sky Fire Department Station No. 3
- Solicitation number
- RFQ_QUAL_F-BSFD-0000000001
- Issued by
- Gallatin County, Montana
About this file
This document is an AIA Document A133 - 2019 Exhibit A Guaranteed Maximum Price Amendment for the Big Sky Fire Department Station No. 3 Project. The amendment establishes a Guaranteed Maximum Price (GMP) for the construction project, with specific provisions for the contract sum, commencement date, and substantial completion timeline. While many of the specific financial and project details are left blank in this draft document, it serves as a template for formalizing the construction contract between the Owner and Construction Manager, outlining the framework for pricing, project milestones, and contractual obligations.
The document indicates that the Guaranteed Maximum Price will be a fixed amount that the Contract Sum shall not exceed, which will include the Construction Manager's Fee plus the Cost of the Work. The amendment allows for potential adjustments through Change Orders and provides mechanisms for handling alternates, unit prices, and other project-specific financial considerations. The document is structured to provide flexibility in establishing project-specific details while maintaining a standardized contract format that defines the financial and scheduling parameters of the construction project.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AIA
Document A133
– 2019
Exhibit A
Guaranteed Maximum Price Amendment
AIA Document A133 – 2019 Exhibit A. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,”
“American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of
Architects. This draft was produced at 16:46:37 MT on 03/27/2024 under Order No.4104245127 which expires on 09/01/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (2033796935)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions
Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
AIA Document A201™–2017, General Conditions of the
Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
This Amendment dated the « » day of « » in the year « », is incorporated into the accompanying AIA Document A133™–2019, Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price dated the « » day of « » in the year « » (the “Agreement”) (In words, indicate day, month, and year.)
for the following PROJECT:
(Name and address or location)
THE OWNER:
(Name, legal status, and address)
THE CONSTRUCTION MANAGER:
(Name, legal status, and address)
TABLE OF ARTICLES
A.1 GUARANTEED MAXIMUM PRICE
A.2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
A.3 INFORMATION UPON WHICH AMENDMENT IS BASED
A.4 CONSTRUCTION MANAGER’S CONSULTANTS, CONTRACTORS, DESIGN
PROFESSIONALS, AND SUPPLIERS
ARTICLE A.1 GUARANTEED MAXIMUM PRICE
§ A.1.1 Guaranteed Maximum Price Pursuant to Section 3.2.6 of the Agreement, the Owner and Construction Manager hereby amend the Agreement to establish a Guaranteed Maximum Price. As agreed by the Owner and Construction Manager, the Guaranteed Maximum Price is an amount that the Contract Sum shall not exceed. The Contract Sum consists of the Construction Manager’s Fee plus the Cost of the Work, as that term is defined in Article 6 of the Agreement.
§ A.1.1.1 The Contract Sum is guaranteed by the Construction Manager not to exceed « » ($ « » ), subject to additions and deductions by Change Order as provided in the Contract Documents.
AIA Document A133 – 2019 Exhibit A. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,”
“American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of
Architects. This draft was produced at 16:46:37 MT on 03/27/2024 under Order No.4104245127 which expires on 09/01/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
§ A.1.1.2 Itemized Statement of the Guaranteed Maximum Price. Provided below is an itemized statement of the Guaranteed Maximum Price organized by trade categories, including allowances; the Construction Manager’s contingency; alternates; the Construction Manager’s Fee; and other items that comprise the Guaranteed Maximum Price as defined in Section 3.2.1 of the Agreement.
(Provide itemized statement below or reference an attachment.)
§ A.1.1.3 The Construction Manager’s Fee is set forth in Section 6.1.2 of the Agreement.
§ A.1.1.4 The method of adjustment of the Construction Manager’s Fee for changes in the Work is set forth in Section
6.1.3 of the Agreement.
§ A.1.1.5 Alternates § A.1.1.5.1 Alternates, if any, included in the Guaranteed Maximum Price:
Item Price
§ A.1.1.5.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Exhibit A. Upon acceptance, the Owner shall issue a Modification to the Agreement.
(Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.)
Item Price Conditions for Acceptance
§ A.1.1.6 Unit prices, if any:
(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)
Item Units and Limitations Price per Unit ($0.00)
ARTICLE A.2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ A.2.1 The date of commencement of the Work shall be:
(Check one of the following boxes.)
[ « » ] The date of execution of this Amendment.
[ « » ] Established as follows:
(Insert a date or a means to determine the date of commencement of the Work.)
If a date of commencement of the Work is not selected, then the date of commencement shall be the date of execution of this Amendment.
§ A.2.2 Unless otherwise provided, the Contract Time is the period of time, including authorized adjustments, allotted in the Contract Documents for Substantial Completion of the Work. The Contract Time shall be measured from the date of commencement of the Work.
§ A.2.3 Substantial Completion § A.2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Construction Manager shall achieve Substantial Completion of the entire Work:
(Check one of the following boxes and complete the necessary information.)
[ « » ] Not later than « » ( « » ) calendar days from the date of commencement of the Work.
AIA Document A133 – 2019 Exhibit A. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,”
“American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of
Architects. This draft was produced at 16:46:37 MT on 03/27/2024 under Order No.4104245127 which expires on 09/01/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
[ « » ] By the following date: « »
§ A.2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Construction Manager shall achieve Substantial Completion of such portions by the following dates:
Portion of Work Substantial Completion Date
§ A.2.3.3 If the Construction Manager fails to achieve Substantial Completion as provided in this Section A.2.3, liquidated damages, if any, shall be assessed as set forth in Section 6.1.6 of the Agreement.
ARTICLE A.3 INFORMATION UPON WHICH AMENDMENT IS BASED
§ A.3.1 The Guaranteed Maximum Price and Contract Time set forth in this Amendment are based on the Contract Documents and the following:
§ A.3.1.1 The following Supplementary and other Conditions of the Contract:
Document Title Date Pages
§ A.3.1.2 The following Specifications:
(Either list the Specifications here, or refer to an exhibit attached to this Amendment.)
Section Title Date Pages
§ A.3.1.3 The following Drawings:
(Either list the Drawings here, or refer to an exhibit attached to this Amendment.)
Number Title Date
§ A.3.1.4 The Sustainability Plan, if any:
(If the Owner identified a Sustainable Objective in the Owner’s Criteria, identify the document or documents that comprise the Sustainability Plan by title, date and number of pages, and include other identifying information. The
Sustainability Plan identifies and describes the Sustainable Objective; the targeted Sustainable Measures;
implementation strategies selected to achieve the Sustainable Measures; the Owner’s and Construction Manager’s roles and responsibilities associated with achieving the Sustainable Measures; the specific details about design reviews, testing or metrics to verify achievement of each Sustainable Measure; and the Sustainability Documentation required for the Project, as those terms are defined in Exhibit C to the Agreement.)
Title Date Pages
Other identifying information:
§ A.3.1.5 Allowances, if any, included in the Guaranteed Maximum Price:
(Identify each allowance.)
Item Price
AIA Document A133 – 2019 Exhibit A. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,”
“American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of
Architects. This draft was produced at 16:46:37 MT on 03/27/2024 under Order No.4104245127 which expires on 09/01/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report
§ A.3.1.6 Assumptions and clarifications, if any, upon which the Guaranteed Maximum Price is based:
(Identify each assumption and clarification.)
§ A.3.1.7 The Guaranteed Maximum Price is based upon the following other documents and information:
(List any other documents or information here, or refer to an exhibit attached to this Amendment.)
ARTICLE A.4 CONSTRUCTION MANAGER’S CONSULTANTS, CONTRACTORS, DESIGN PROFESSIONALS, AND
SUPPLIERS
§ A.4.1 The Construction Manager shall retain the consultants, contractors, design professionals, and suppliers, identified below:
(List name, discipline, address, and other information.)
This Amendment to the Agreement entered into as of the day and year first written above.
OWNER (Signature) CONSTRUCTION MANAGER (Signature)
(Printed name and title) (Printed name and title)