Exhibit B_Construction Drawing Set (Wilson Hall).pdf
PDF 35 MB Posted
- Attached to
- Wilson Hall Facade Repairs and Restoration
- Solicitation number
- 370886-CD
About this file
This document is a comprehensive construction drawing set for the Wilson Hall Facade Repairs and Restoration project at Fermi National Accelerator Laboratory. The detailed technical drawings outline a phased restoration approach for Wilson Hall's exterior, divided into three distinct phases: Phase 1 covering the East Elevation, Phase 2 addressing the North and South Elevations, and Phase 3 focusing on the West Elevation. The restoration work includes extensive concrete repair, silane sealer application, waterproofing, sealant replacement, and preservation of the existing board-formed concrete facade aesthetic.
The project scope involves comprehensive surface preparation, including 100% concrete surface sounding, repair of deteriorated concrete areas, application of new silane sealer, traffic membrane installation, and window sealant replacement. The drawings specify precise repair techniques, such as sawcut perimeter repairs, reinforcement preservation, and matching existing concrete color and texture. The contract anticipates completing Phase 1 in 2026, with Phases 2 and 3 designated as unilateral options potentially exercisable in 2027-2030, with each phase expected to be completed within 180 calendar days of receiving a Notice to Proceed. The project is being managed by Fermi Forward Discovery Group, LLC (FFDG) under the Department of Energy's Fermi National Accelerator Laboratory.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WILSON ST.
RING RD.
HWY. 56 BUTTERFIELD RD.
TO
IN
TE
RS
TA
TE
I-
FA
RN
SW
O
RT
H
CONSTRUCTION
KAUTZ RD.
ENTRANCE
ROAD B
KI
RK
R D.
(NO TRUCKS)
PINE ST.
ENTRANCE
AREA
MAIN
INJECTOR
MAIN
KA
UT
Z
RD
PINE ST. (OUT)
PINE ST. (IN) LABORATORY
AREA
HOLTER RD
CENTRAL
WILSON ST.
ENTRANCE
BURLINGTON NORTHERN R.R.
BATAVIA RD.
RECEIVING
ENTRANCE
BATAVIA RD.
(LOAD LIMIT-6 TONS)
EL
G
IN
J
O
LI
ET
E
AS
TE
RN
R .R
CO
M
M O
NW
EA
LT
H
ED
IS
O N
PO
W
ER
L
IN
ES
ROAD
C
BATAVIA RD.
SWENSON
D-0 FA
RM
R D
FE
LD
O
TT
R D
CDF
ROAD D
EO
LA
R D.
TO RT. 59
FERMILAB
VILLAGE
TO HWY 59
LOCKED
GATE
RAILYARD
STORAGE
WILSON ST.
HWY 38 ROOSEVELT RD.
TRAFFIC
CONSTRUCTION
MUON CAMPUS
DISC
OVE
RY
RD.
PI
P
II
FE
YNMAN
C.C
FIXED TARGET AREA
NEUTRINO AREA
PROTON AREA
INDUSTRIAL AREA
EOLA RD. ENTRANCE
(NO ACCESS)
P-112
T
IN
D
IAN
C
R
EEK R
O
AD
W
NORTH
S E
PROJECT
NO SCALE
SITE PLAN
SITE BOUNDARY LINES
ON SITE CONST. ROUTES
LEGEND
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:2
WILSON HALL FACADE REPAIRS AND
RESTORATION
COVER PAGE
S000WH
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
TCV
RSH
KC
WILSON HALL FACADE REPAIRS AND RESTORATION
SGH PROJECT No. 240714.00
SHEET LIST (WILSON HALL)
Sheet Number Sheet Name
S000WH COVER PAGE
S001WH GENERAL NOTES
S002WH SITE PLAN AND PROTECTIVE CANOPY PLAN
S100WH- P1 OVERALL PLAN PHASE 1 SCOPE
S100WH- P2 OVERALL PLAN PHASE 2 SCOPE
S100WH- P3 OVERALL PLAN PHASE 3 SCOPE
S101WH- P1 ROOF PLAN PHASE 1
S101WH- P2 ROOF PLAN PHASE 2
S101WH- P3 ROOF PLAN PHASE 3
S200WH- CR1-P1 EAST ELEVATION - SOUNDING EXTENTS - PHASE 1
S200WH- CR2-P1 EAST ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 1
S200WH- CR3-P1 EAST ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 1
S200WH- WP1-P1 EAST ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENTS - PHASE 1
S201WH- CR1-P2 NORTH ELEVATION - SOUNDING EXTENTS - PHASE 2
S201WH- CR2-P2 NORTH ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 2
S201WH- CR3-P2 NORTH ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 2
S201WH- WP1-P2 NORTH ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENT - PHASE 2
S202WH- CR1-P2 SOUTH ELEVATION - SOUNDING EXTENTS - PHASE 2
S202WH- CR2-P2 SOUTH ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 2
S202WH- CR3-P2 SOUTH ELEVATION - SILANE SEALER APPLICATION EXTENTS- PHASE 2
S202WH- WP1-P2 SOUTH ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENTS - PHASE 2
S203WH- CR1-P3 WEST ELEVATION - SOUNDING EXTENTS - PHASE 3
S203WH- CR2-P3 WEST ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 3
S203WH- CR3-P3 WEST ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 3
S203WH- WP1-P3 WEST ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENTS - PHASE 3
S204WH-CR2 16TH FLOOR PLAN - SUSPECTED/KNOWN DETERIORATION - ALL PHASES
S205WH-CR2 ROOF PLAN - SUSPECTED/KNOWN DETERIORATION - ALL PHASES
S206WH -
CR1&CR2-P1
ROOF SECTIONS - EAST PENTHOUSE - SOUNDING AND SUSPECTED/KNOWN DETERIORATION -
PHASE 1
S206WH - CR3-P1 ROOF SECTIONS - EAST PENTHOUSE WALL - SILANE SEALER APPLICATION EXTENTS - PHASE 1
S207WH-
CR1&CR2-P3
ROOF SECTIONS - WEST PENTHOUSE - SOUNDING AND SUSPECTED/KNOWN DETERIORATION -
PHASE 3
S207WH- CR3-P3 ROOF SECTIONS - WEST PENTHOUSE WALL - SILANE SEALER APPLICATION EXTENTS - PHASE 3
S300 TYPICAL DETAILS
S301 TYPICAL DETAILS
S302 TYPICAL DETAILS
S303 TYPICAL DETAILS
VICINITY PLAN
PROJECT No. 2-1-552
WILSON HALL OVERALL VIEW
REVISIONS
REV. DESCRIPTION DATE
1 100% Construction Set 04/07/25
N/A
ABBREVIATION WORD OR PHRASE
& And @ At AB Anchor Bolt ACI American Concrete
Institute ADDL Additional AISC American Institute of Steel
Construction ALT Alternate APPROX Approximate ARCH Architect ASD Allowable Strength Design ASTM American Society for
Testing and Materials
BP Base Plate BLKG Blocking BM Beam BOT Bottom BRG Bearing BS Both Sides BTWN Between
CC Center to Center CJ Control Joint CIP Cast-in-place CL Center Line CLR Clear CMU Concrete Masonry Unit COL Column CONC Concrete CONN Connection CONST Construction CONT Continuous CTBR Counterbore CTR Center
DBA Deformed Bar Anchor DBL Double DET Detail DIA, ∅ Diameter DIAG Diagonal DL Dead Load DN Down DO Ditto DWG Drawing
(E) Existing EA Each EF Each Face EJ Expansion Joint EL Elevation EMB Embedment EOS Edge of Slab EQ Equal EQUIP Equipment ES Each Side ES&H Environment, Safety, and
Health EW Each Way
FDN Foundation FF Finish Floor FG Finish Grade FIN Finish FLR Floor FOC Face of Concrete FOM Face of Masonry FFDG Fermi Forward Discovery
Group, LLC FRP Fiber Reinforced Polymer FS Far Side FT Foot, Feet FTG Footing
GL Grid Line GR Grade
HA Hazard Analysis HDG Hot-dip Galvanized HGR Hanger HK Hook HORIZ Horizontal HSB High Strength Bolt HT Height
IBC International Building Code ICC International Code Council IN Inch, Inches INT Interior INV Inverted
K Kips KSI Kips per Square Inch
LBS Pounds LL Live Load LONG Longitudinal LTWT Lightweight
MAX Maximum MB Machine Bolt MECH Mechanical MFR Manufacturer MI Malleable Iron
ABBREVIATION WORD OR PHRASE
MIL 0.001 Inch MIN Minimum MISC Miscellaneous MPII Manufacturer's Printed
Installation Instructions
(N) New NO or # Number NS Near Side NTS Not to Scale NWT Normal Weight
OC On Center OD Outside Diameter OH Opposite Hand OPNG Opening OPP Opposite OSHA Occupational Safety and
Health Administration
PAF Powder-Actuated Fasteners
PART Partial PCF Pounds per Cubic Foot PSF Pounds per Square Foot PSI Pounds per Square Inch
RAD Radius REINF Reinforcing REQ Required RF Roof RO Rough Opening RND Round RR Remove & Replace
SAD See Architectural Drawings SCHED Schedule SEOR Structural Engineer of
Recordm SHT Sheet SIM Similar SMD See Mechanical Drawings SOG Slab on Grade SS Stainless Steel SSE Specialty Structural
Engineer STG Staggered STD Standard STRUCT Structural SYM Symmetrical
T&B Top and Bottom TOC Top of Concrete TOW Top of Wall TYP Typical
UON Unless Otherwise Noted
VERT Vertical VIF Verify in Field VTBW Vehicular-Traffic-Bearing
Waterproofing
W Width W/ With W/O Without WTS Welded Threaded Stud WWR Welded Wire Reinforcing
STRUCTURAL ABBREVIATIONS GENERAL REFERENCE SYMBOLS
GRID TYPES
GRID
LEVEL LINE
FIRST FLOOR
0' - 0"
NAME OF FLOOR LEVEL
INDICATES HEIGHT WITH RESPECT TO PROJECT DATUM
SECTION SYMBOL
X
SXXX
DETAIL NUMBER
SHEET NUMBER OF WHERE THE DETAIL IS DRAWN
DIRECTION OF VIEW
ELEVATION SYMBOL
X
SXXX
DIRECTION OF VIEW
DETAIL NUMBER
SHEET NUMBER OF WHERE THE DETAIL IS DRAWN
PLAN DETAIL SYMBOL
X
SXXX
DETAIL NUMBER
SHEET NUMBER OF WHERE THE DETAIL IS DRAWN
NORTH ARROW REFERENCE
ARROW DIRECTION TOWARDS NORTH
REVISION SCOPE AND NUMBER
REVISION NUMBER. REVISION HISTORY CAN BE
FOUND IN THE TITLE BLOCK
REVISION CLOUD INDICATING EXTENT OF REVISION
MATCH LINE REFERENCE
MATCHLINE SEE X/SXXX
STANDARD TITLE SYMBOL
X FIRST FLOOR PLAN
1/4" = 1'-0"
DETAIL NUMBER ON SHEET
NAME OF ASSOCIATED DETAIL
SCALE OF DETAIL
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
1.
2.
A.
B.
C.
D.
3.
4.
5.
6.
1.
2.
A.
B.
C.
D.
1.
A.
B.
C.
D.
E.
a.
1.
2.
A.
B.
C.
PART 1 - GENERAL NOTES (Applicable to All Sheets)
Maintain a copy of all applicable contract documents, including approved shop drawings, at the site during all work covered under this contract.
Existing dimensions shown on the Drawings are based on the original building drawings and limited field measurements;
actual dimensions in the field may be different than shown.
All dimensions, elevations, and conditions shall be verified in the field by the Subcontractor and any discrepancies shall be brought to the attention of the Engineer for clarification before proceeding with the affected part of the Work. Verify all dimensions and field conditions prior to the submission of shop drawings or start of related Work. Upon receipt of shop drawings, the Engineer will assume that all field dimensions, elevations, and conditions have been verified by the subcontractor and that the shop drawings accurately reflect such verifications unless stated otherwise on the shop drawings.
Notify the Engineer immediately if existing conditions vary from those shown on the Drawings in a manner that precludes execution of the Work as shown. Do not disturb unexpected, previously concealed condition until the Engineer reviews.
The Drawings (plans, elevations, sections, and details) and Specifications show the overall intent and performance requirements of the Work; an individual detail is not provided for every condition. For conditions where a specific detail is not provided on the design drawings or a concealed condition arises, the Subcontractor should document existing conditions and provide proposed details consistent with those areas detailed on the design documents. The shop drawing shall provide the same level of aesthetics and compliance with performance criteria as indicated for detailed areas and stipulated in the project specifications.
Deficient work and/or work by the Subcontractor not in conformance with the Contract Documents shall be repaired at the subcontractor's expense. The Subcontractor shall compensate FFDG for services arising from deficient Work, review of modifications/subcontractor substitution, or expediting of submittals.
Subcontractor shall coordinate site restrictions and requirements with FFDG and shall submit an operations, logistics, and safety plan for review prior to starting work.
Subcontractor shall protect the existing building from the weather, damage, dust, debris, and unauthorized access during construction.
Maintain safe access to building and egress points at all times during construction.
Subcontractor shall protect existing building components to remain during Work on adjacent building components during construction.
All Work done in accordance with the Drawings shall be new unless noted otherwise.
PART 2 - GENERAL SITE WORKING CONDITIONS
The work will be taking place on the exterior of a occupied and in use facility. Subcontractor shall allow for the extra time necessary in their schedule. Notify and coordinate with FFDG if additional weekday shifts and/or weekends are required to perform the Work.
Normal Lab business hours are Monday through Friday 6:00am to 6:00pm. Available work hours are 6:30 am to dark Monday through Friday, subject to FFDG requirements.
Coordinate interior work and noisy work with FFDG. Subcontractor shall notify FFDG of noisy activities not previously discussed at weekly progress meetings prior to starting work activity.
PEAK HOUR NOISE RESTRICTIONS: FFDG will require Subcontractor to limit construction noise during normal business hours. This noise restriction applies mainly to drilling and hammering into the concrete structure as well as window sealant removal and grinding. While working at Wilson Hall and Ramsey Auditorium, the subcontractor's construction activities must comply with the Fermilab's peak hour noise restrictions between the hours of 6:30 am and 5 pm. No additional compensation will be provided for meeting this specification.
NOISY WORKING HOURS: Noisy construction applies mainly to drilling and hammering into the concrete structure as well as window sealant removal and grinding. Available work hours for noisy construction are 5 pm to dark, subject to high hazard work authorization. Subcontractor may begin mobilization for noisy construction at 4pm.
Do not perform any work outside available hours unless approved in writing by FFDG. Provide at least 48 hrs advance notice for requests to perform Work outside available hours.
Subcontractor to submit trash and construction debris disposal method in writing to be approved by FFDG and Engineer.
Limited storage and staging space may be available on site. Coordinate use with FFDG. FFDG reserves the right to refuse storage of any materials.
Subcontractor to provide temporary fencing around work area for the duration of Construction to ensure a secure perimeter.
Subcontractor to provide public access to the building through the existing doorways and provide canopies to protect from work above.
PART 3 - REQUIRED TRAINING
All training must be documented and submitted to FFDG for approval. All workers must have all required training. Please see Specifications 013100 for required training and additional information.
3.1 Required Safety Training
All documentation of training shall be submitted to FFDG prior to beginning construction.
Training includes, but may not be limited to the following:
Fall protection training for construction Fall protection competent person Mobile Elevating Work Platform (City of Chicago scaffold training required) Silica dust / respirator training
3.2 Expected Safety-Related Submittals
The following submittals are required to be submitted by the subcontractor and approved by FFDG ES&H prior to beginning work:
Hazard analysis form Site specific safety program Fall protection plan and fall rescue plan Subcontractor must coordinate with the Construction Coordinator to request that FFDG locate existing utilities in concrete walls, floors, ceiling (deck).
Subcontractor must provide for silica monitoring, reference Div. 01 Specifications, Attachment D, for further guidance.
Prior to the disturbance of concrete materials, the Fermilab Silica Guidelines must be followed, and the HA must describe the work steps, hazards and mitigations regarding the control of silica containing dust.
3.3 High Hazard Work
Work utilizing fall protection is considered high hazard work.
High Hazard Work outside of normal Lab business hours requires the following planning and prior approval prior to starting the High Hazard Work:
An adequate justification for such work outside of normal hours has been submitted to FFDG and approved. Such approval will only be granted by FFDG when it is in the interests of heightened safety at Fermilab.
The Subcontractor shall submit the hazard analysis for high hazard work, along with the justification, for review a minimum of seven (7) days in advance of any such operations outside normal hours and receive specific and written approval.
If such approval is granted, the Subcontractor shall conduct and document Pre- and Post job briefings on the work plan and safety mitigations included in the hazard analysis.
1.
2.
3.
1.
2.
3.
PART 4 - OTHER REQUIREMENTS
4.1 Dust Control and Silane/Coating Plan
Subcontractor to submit a dust control plan outlining dust mitigation measures and/or protective plans. Surrounding cars and facilities to be protected from dust.
Subcontractor to submit a methodology for application of the silane sealer and traffic coating. Surrounding cars and facilities to be protected from overspray or accidental application.
Damage to parked cars or facilities shall be repaired at the contractor's expense.
4.2 Suspended Scaffold
Subcontractor to submit a suspended scaffold plan showing intended locations, tie-off points, scaffold components and sizes, and number of expected drops.
A Licensed Structural Engineer in the State of Illinois shall stamp and seal the suspended scaffold plan and provide calculations providing information about the counterweights, tie-off points, and other design elements as required.
Subcontractor shall obtain the City of Chicago scaffold safety training and carry the cards for inspection by FFDG on site at any time.
1.
2.
1.
2.
3.
PART 5 - MOCKUPS
5.1 Board Formed Concrete
The existing construction is comprised of board formed concrete. The restoration will preserve and protect this aesthetic.
Processes that alter or damage the architectural nature of the facade are not permitted. Repairs shall match the existing facade in both texture and color.
5.2 Mockups
Develop concrete repair mixes for each type of repair to match the original in hardened cement paste color, aggregates, and similar proportions. Mix design(s) should be durable and mockups will be required to illustrate preparation work, anchorage, installation, and finish. Three concrete repair types (slab topside, vertical repair, and slab underside) are included in the work.
Multiple mockups may be required until the desired color and texture match is approved by FFDG.
See Specifications 030100 Concrete Repair for additional information.
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:2
WILSON HALL FACADE REPAIRS AND
RESTORATION
GENERAL NOTES
S001WH
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
TCV
RSH
KC
REVISIONS
RESTRICT ACCESS
USING FENCING
PROVIDE OVERHEAD
PROTECTION CANOPY AT ALL
DOORS TO REMAIN IN USE
DURING CONSTRUCTION, TYP
PROTECT
SKYLIGHTS AT
LEVEL 1 DURING
CONSTRUCTION
CANOPY/OVERHEAD
PROTECTION
LEGEND
SKYLIGHT TO PROTECT
ROOF DECK (CLOSED BY
FERMILAB)
RESTRICT ACCESS USING
FENCING DURING
CONSTRUCTION
PROTECT SKYLIGHT AT ROOF LEVEL
EXISTING PLAZA DECK -
FERMILAB WILL CLOSE
AS NEEDED DURING
CONSTRUCTION
PROVIDE OVERHEAD
PROTECTIVE CANOPY
DURING CONSTRUCTION -
ENTIRE WIDTH OF SOUTH
ELEVATION
RESTRICT ACCESS
USING FENCING
LOADING DOCK
TO REMAIN IN
SERVICE.
PROVIDE HIGH
BAYS FOR
TRUCKS
PROTECT
ELECTRICAL SWITCH
FROM DEBRIS/ DUST/
SANDBLASTING
ACTIVITIES
1 THIS LEGEND IS COLOR CODED. PRINT THESE
DRAWINGS IN COLOR TO MAINTAIN LEGEND.
NOT TO SCALE
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs \tc va ch on \D oc um en ts \S _2 4_ R _t cv ac ho n.
rv t
4/ 7/ 1:
:1
WILSON HALL FACADE REPAIRS AND
RESTORATION
SITE PLAN AND PROTECTIVE CANOPY
PLAN S002WH
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
SITE PLAN
PLAN TRUE
REVISIONS
8 7 6 5 4 3 2 1
A
D
G
K
S200WH-
CR2-P1
WILSON
HALL
0'
-0 " A
T
LE
VE
L
2' -9
" A T
LE
VE
L
213'-0" ±
VA
R
IE
S:
ALL VERTICAL AND UNDERSIDE SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
WINDOW SEALANT
REMOVAL AND
REPLACEMENT ENTIRE
WINDOW PERIMETER, TYP
PATCH AND RECOAT
TRAFFIC MEMBRANE
ON TOP OF WINDOW
LEDGES, TYP
S302
TYP
NOT TO SCALE
SCOPE OF WORK LEGEND - TYPICAL EACH FLOOR
ALL CONCRETE SURFACES:
(E) COATING REMOVAL FROM VERTICAL AND UNDERSIDE SURFACES
(ASSUME 100% POWER WASH; 20% CHEMICAL CLEAN, 20% SANDBLAST)
SOUND ALL CONCRETE SURFACES (TOPSIDE, UNDERSIDE, VERTICAL)
REPAIR AS REQUIRED. TO MATCH (E) COLOR AND TEXTURE PER MOCKUP.
SEE DETAILS ON AND
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
PATCH AND RECOAT TRAFFIC MEMBRANE ON TOP OF WINDOW LEDGES,
AND PLAZA WALLS [SIKALASTIC PEDESTRIAN TRAFFIC 1500]
WINDOW SEALANT REMOVAL & SEALANT REPLACEMENT [DOWSIL 756]
PROTECT IN PLACE WILSON HALL LETTERING
S300 S301
CONCRETE BEAM REPAIR (ROOF ONLY)
SOUND ALL CONCRETE SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
APPLICATION OF NEW TRAFFIC MEMBRANE ON TOP SURFACES
[SIKALASTIC PEDESTRIAN TRAFFIC 1500]
MASONRY PENTHOUSE REPAIR (ROOF ONLY)
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED (ASSUME 100% POWER WASH;
20% CHEMICAL CLEAN, 20% SANDBLAST)
REPAIR CMU AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF NEW COATING [SIKAGARD 550W ELASTOCOLOR]
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:3
WILSON HALL FACADE REPAIRS AND
RESTORATION
OVERALL PLAN PHASE 1 SCOPE
S100WH- P1
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
OVERALL PLAN - PHASE 1
PLAN TRUE
REVISIONS
D
G
K
S201WH-
CR2-P2
S202WH-
CR2-P2
1 WILSON
HALL
0'
-0 " A
T
LE
VE
L
2' -9
" A T
LE
VE
L
213'-0" ±
VA
R
IE
S:
ALL VERTICAL AND UNDERSIDE SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
PATCH AND RECOAT
TRAFFIC MEMBRANE
ON TOP OF PLAZA
WALLS, TYP
VERTICAL PLAZA WALL
SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE
SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW
SILANE SEALER, TYP
PROTECT IN PLACE WILSON
HALL LETTERING
S201WH-
CR1-P2
S201WH-
CR1-P2
S201WH-
CR1-P2
SIM.
S201WH-
CR1-P2
SIM.
S201WH-
CR1-P2
S201WH-
CR1-P2
SIM.
NOT TO SCALE
SCOPE OF WORK LEGEND - TYPICAL EACH FLOOR
ALL CONCRETE SURFACES:
(E) COATING REMOVAL FROM VERTICAL AND UNDERSIDE SURFACES
(ASSUME 100% POWER WASH; 20% CHEMICAL CLEAN, 20% SANDBLAST)
SOUND ALL CONCRETE SURFACES (TOPSIDE, UNDERSIDE, VERTICAL)
REPAIR AS REQUIRED. TO MATCH (E) COLOR AND TEXTURE PER MOCKUP.
SEE DETAILS ON AND
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
PATCH AND RECOAT TRAFFIC MEMBRANE ON TOP OF WINDOW LEDGES,
AND PLAZA WALLS [SIKALASTIC PEDESTRIAN TRAFFIC 1500]
WINDOW SEALANT REMOVAL & SEALANT REPLACEMENT [DOWSIL 756]
PROTECT IN PLACE WILSON HALL LETTERING
S300 S301
CONCRETE BEAM REPAIR (ROOF ONLY)
SOUND ALL CONCRETE SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
APPLICATION OF NEW TRAFFIC MEMBRANE ON TOP SURFACES
[SIKALASTIC PEDESTRIAN TRAFFIC 1500]
MASONRY PENTHOUSE REPAIR (ROOF ONLY)
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED (ASSUME 100% POWER WASH;
20% CHEMICAL CLEAN, 20% SANDBLAST)
REPAIR CMU AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF NEW COATING [SIKAGARD 550W ELASTOCOLOR]
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:3
WILSON HALL FACADE REPAIRS AND
RESTORATION
OVERALL PLAN PHASE 2 SCOPE
S100WH- P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
OVERALL PLAN - PHASE 2
PLAN TRUE
REVISIONS
D
G
K
S203WH-
CR2-P3
WILSON
HALL
0'
-0 " A
T
LE
VE
L
2' -9
" A T
LE
VE
L
213'-0" ±
VA
R
IE
S:
ALL VERTICAL AND UNDERSIDE SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
WINDOW SEALANT
REMOVAL AND
REPLACEMENT ENTIRE
WINDOW PERIMETER, TYP
PATCH AND RECOAT
TRAFFIC MEMBRANE
ON TOP OF WINDOW
LEDGES, TYP
S302
1 TYP
NOT TO SCALE
SCOPE OF WORK LEGEND - TYPICAL EACH FLOOR
ALL CONCRETE SURFACES:
(E) COATING REMOVAL FROM VERTICAL AND UNDERSIDE SURFACES
(ASSUME 100% POWER WASH; 20% CHEMICAL CLEAN, 20% SANDBLAST)
SOUND ALL CONCRETE SURFACES (TOPSIDE, UNDERSIDE, VERTICAL)
REPAIR AS REQUIRED. TO MATCH (E) COLOR AND TEXTURE PER MOCKUP.
SEE DETAILS ON AND
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
PATCH AND RECOAT TRAFFIC MEMBRANE ON TOP OF WINDOW LEDGES,
AND PLAZA WALLS [SIKALASTIC PEDESTRIAN TRAFFIC 1500]
WINDOW SEALANT REMOVAL & SEALANT REPLACEMENT [DOWSIL 756]
PROTECT IN PLACE WILSON HALL LETTERING
S300 S301
CONCRETE BEAM REPAIR (ROOF ONLY)
SOUND ALL CONCRETE SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
APPLICATION OF NEW TRAFFIC MEMBRANE ON TOP SURFACES
[SIKALASTIC PEDESTRIAN TRAFFIC 1500]
MASONRY PENTHOUSE REPAIR (ROOF ONLY)
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED (ASSUME 100% POWER WASH;
20% CHEMICAL CLEAN, 20% SANDBLAST)
REPAIR CMU AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF NEW COATING [SIKAGARD 550W ELASTOCOLOR]
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:4
WILSON HALL FACADE REPAIRS AND
RESTORATION
OVERALL PLAN PHASE 3 SCOPE
S100WH- P3
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
OVERALL PLAN - PHASE 3
PLAN TRUE
REVISIONS
C
D G
H K
BEAM REPAIR, TYP:
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
ALL CONCRETE SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
MASONRY REPAIR:
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED
REPAIR AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF 100% NEW COATING
CONCRETE REPAIR, WALLS:
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
SCOPE OF WORK LEGEND - TYPICAL EACH FLOOR
ALL CONCRETE SURFACES:
(E) COATING REMOVAL FROM VERTICAL AND UNDERSIDE SURFACES
(ASSUME 100% POWER WASH; 20% CHEMICAL CLEAN, 20% SANDBLAST)
SOUND ALL CONCRETE SURFACES (TOPSIDE, UNDERSIDE, VERTICAL)
REPAIR AS REQUIRED. TO MATCH (E) COLOR AND TEXTURE PER MOCKUP.
SEE DETAILS ON AND
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
PATCH AND RECOAT TRAFFIC MEMBRANE ON TOP OF WINDOW LEDGES,
AND PLAZA WALLS [SIKALASTIC PEDESTRIAN TRAFFIC 1500]
WINDOW SEALANT REMOVAL & SEALANT REPLACEMENT [DOWSIL 756]
PROTECT IN PLACE WILSON HALL LETTERING
S300 S301
CONCRETE BEAM REPAIR (ROOF ONLY)
SOUND ALL CONCRETE SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
APPLICATION OF NEW TRAFFIC MEMBRANE ON TOP SURFACES
[SIKALASTIC PEDESTRIAN TRAFFIC 1500]
MASONRY PENTHOUSE REPAIR (ROOF ONLY)
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED (ASSUME 100% POWER WASH;
20% CHEMICAL CLEAN, 20% SANDBLAST)
REPAIR CMU AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF NEW COATING [SIKAGARD 550W ELASTOCOLOR]
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:4
WILSON HALL FACADE REPAIRS AND
RESTORATION
ROOF PLAN PHASE 1
S101WH- P1
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
RSH
KC
KC
NTS
WILSON HALL ROOF PLAN - PHASE 1
PLAN TRUE
REVISIONS
C
D G
H K
ALL CONCRETE SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
SCOPE OF WORK LEGEND - TYPICAL EACH FLOOR
ALL CONCRETE SURFACES:
(E) COATING REMOVAL FROM VERTICAL AND UNDERSIDE SURFACES
(ASSUME 100% POWER WASH; 20% CHEMICAL CLEAN, 20% SANDBLAST)
SOUND ALL CONCRETE SURFACES (TOPSIDE, UNDERSIDE, VERTICAL)
REPAIR AS REQUIRED. TO MATCH (E) COLOR AND TEXTURE PER MOCKUP.
SEE DETAILS ON AND
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
PATCH AND RECOAT TRAFFIC MEMBRANE ON TOP OF WINDOW LEDGES,
AND PLAZA WALLS [SIKALASTIC PEDESTRIAN TRAFFIC 1500]
WINDOW SEALANT REMOVAL & SEALANT REPLACEMENT [DOWSIL 756]
PROTECT IN PLACE WILSON HALL LETTERING
S300 S301
CONCRETE BEAM REPAIR (ROOF ONLY)
SOUND ALL CONCRETE SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
APPLICATION OF NEW TRAFFIC MEMBRANE ON TOP SURFACES
[SIKALASTIC PEDESTRIAN TRAFFIC 1500]
MASONRY PENTHOUSE REPAIR (ROOF ONLY)
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED (ASSUME 100% POWER WASH;
20% CHEMICAL CLEAN, 20% SANDBLAST)
REPAIR CMU AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF NEW COATING [SIKAGARD 550W ELASTOCOLOR]
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:5
WILSON HALL FACADE REPAIRS AND
RESTORATION
ROOF PLAN PHASE 2
S101WH- P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
RSH
KC
KC
NTS
WILSON HALL ROOF PLAN - PHASE 2
PLAN TRUE
REVISIONS
C
D G
H K
BEAM REPAIR, TYP:
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
ALL CONCRETE SURFACES:
(E) COATING REMOVAL
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER •
MASONRY REPAIR:
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED
REPAIR AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF 100% NEW COATING
CONCRETE REPAIR, WALLS:
SOUND ALL CONCRETE SURFACES
CONCRETE REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER
SCOPE OF WORK LEGEND - TYPICAL EACH FLOOR
ALL CONCRETE SURFACES:
(E) COATING REMOVAL FROM VERTICAL AND UNDERSIDE SURFACES
(ASSUME 100% POWER WASH; 20% CHEMICAL CLEAN, 20% SANDBLAST)
SOUND ALL CONCRETE SURFACES (TOPSIDE, UNDERSIDE, VERTICAL)
REPAIR AS REQUIRED. TO MATCH (E) COLOR AND TEXTURE PER MOCKUP.
SEE DETAILS ON AND
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
PATCH AND RECOAT TRAFFIC MEMBRANE ON TOP OF WINDOW LEDGES,
AND PLAZA WALLS [SIKALASTIC PEDESTRIAN TRAFFIC 1500]
WINDOW SEALANT REMOVAL & SEALANT REPLACEMENT [DOWSIL 756]
PROTECT IN PLACE WILSON HALL LETTERING
S300 S301
CONCRETE BEAM REPAIR (ROOF ONLY)
SOUND ALL CONCRETE SURFACES
REPAIR AS REQUIRED
APPLICATION OF NEW SILANE SEALER TO VERTICAL AND UNDERSIDE
SURFACES [SIKA H-1000]
APPLICATION OF NEW TRAFFIC MEMBRANE ON TOP SURFACES
[SIKALASTIC PEDESTRIAN TRAFFIC 1500]
MASONRY PENTHOUSE REPAIR (ROOF ONLY)
100% POWER WASH
REMOVE (E) COATING WHERE DAMAGED (ASSUME 100% POWER WASH;
20% CHEMICAL CLEAN, 20% SANDBLAST)
REPAIR CMU AS REQUIRED (BLOCK REPAIR AND/OR MORTAR REPAIR)
APPLICATION OF NEW COATING [SIKAGARD 550W ELASTOCOLOR]
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:5
WILSON HALL FACADE REPAIRS AND
RESTORATION
ROOF PLAN PHASE 3
S101WH- P3
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
RSH
KC
KC
NTS
WILSON HALL ROOF PLAN - PHASE 3
PLAN TRUE
REVISIONS
LOADING DOCK DOOR CONNECTION TO HELEN
EDWARDS ENGINEERING
RESEARCH CENTER
DOORDOOR
FOR SCOPE OF WORK IN THIS
AREA ON THE PENTHOUSE
WALLS, SEE THE FOLLOWING:
MASONRY -
CONCRETE -
S206WH - CR3-P1
S101WH- P1
S204WH-CR2
S205WH-CR2
S101WH- P1
S206WH - CR3-P1
S206WH -
CR1&CR2-P1
S200WH- CR2-P1
NOT TO SCALE
LEGEND1:
SOUND ALL CONCRETE SURFACES
INCLUDING VERTICAL, TOPSIDE AND
UNDERSIDE SURFACES.
REPAIR DETERIORATED LOCATIONS IN
ACCORDANCE WITH THE FOLLOWING
DETAILS:
DETAIL(S):
5 / S300
2 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
4 / S300
3 / S300OR
6 / S300OR
TOPSIDE SURFACE
UNDERSIDE SURFACE
VERTICAL SURFACE
NOTE:
FOR LOCATIONS OF SUSPECTED/KNOWN DETERIORATION, SEE SHEET
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:0
WILSON HALL FACADE REPAIRS AND
RESTORATION
EAST ELEVATION - SOUNDING EXTENTS
- PHASE 1 S200WH-
CR1-P1
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
EAST ELEVATION - SOUNDING EXTENTS - PHASE 1
REVISIONS
B B B B B B
B B
EF B B B B B
B
B B B
LOADING DOCK DOOR CONNECTION TO HELEN
EDWARDS ENGINEERING
RESEARCH CENTER
DOORDOOR
FOR SCOPE OF WORK IN THIS
AREA ON THE PENTHOUSE
WALLS, SEE THE FOLLOWING:
MASONRY -
CONCRETE -
S206WH - CR3-P1
S101WH- P1
S204WH-CR2
S205WH-CR2
S101WH- P1
S206WH - CR3-P1
S206WH -
CR1&CR2-P1
NOT TO SCALE
1.
2.
3.
4.
5.
6.
CONCRETE REPAIR NOTES:
THE SYMBOLS PROVIDED IN THE CONCRETE REPAIR LEGEND ABOVE INDICATE A SUSPECTED OR KNOWN CONCRETE REPAIR LOCATION. OTHER REPAIR LOCATIONS WILL BE ADDED FROM INSPECTION AND
SOUNDING OF THE FACADE. CONTRACTOR SHALL SOUND 100% OF CONCRETE SURFACES.
REPAIR ONLY LOCATIONS THAT ARE DETERIORATED.
TYPICAL REPAIR DETAILS ARE SHOWN ON SHEETS AND .
THE BID REPAIR QUANTITIES ARE SHOWN ON BID FORM.
ALL REPAIRS TO MATCH SURROUNDING ORIGINAL CONCRETE (AFTER CLEANING).
REPAIR LOCATIONS SHOWN ARE APPROXIMATE AND BASED ON VISUAL SURVEY FROM JULY 2024 AND SERVE
AS BASIS FOR REPAIR QUANTITIES.
S301S300
LEGEND1:
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON BOTTOM OF SLAB
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON FACE OF SLAB
CRACKING
DELAMINATED CONCRETE
CRACK IS ON BACKSIDE OF ELEMENT SHOWNB
CRACK IS ON EACH FACE OF ELEMENT SHOWNEF
PREVIOUS CONCRETE REPAIR PATCH
DETAIL(S):
1 / S300
4 / S300
5 / S300
5 / S300
5 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
ROOF BEAM CRACKING 1 / S300
6 / S300
6 / S300
6 / S300
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:1
WILSON HALL FACADE REPAIRS AND
RESTORATION
EAST ELEVATION - SUSPECTED/KNOWN
DETERIORATION - PHASE 1 S200WH-
CR2-P1
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
EAST ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 1
REVISIONS
LOADING DOCK DOOR CONNECTION TO HELEN
EDWARDS ENGINEERING
RESEARCH CENTER
DOORDOOR
FOR SCOPE OF WORK IN THIS
AREA ON THE PENTHOUSE
WALLS, SEE THE FOLLOWING:
MASONRY -
CONCRETE -
S206WH - CR3-P1
S101WH- P1
S204WH-CR2
S205WH-CR2
S101WH- P1
S206WH - CR3-P1
S206WH -
CR1&CR2-P1
NOT TO SCALE
LEGEND1:
APPLICATION OF SILANE SEALER; APPLY
ON ALL VERTICAL AND UNDERSIDE
SURFACES.
FOR TREATMENT OF TOPSIDE SURFACES,
REFER TO S100WH AND S101WH SHEETS
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:1
WILSON HALL FACADE REPAIRS AND
RESTORATION
EAST ELEVATION - SILANE SEALER
APPLICATION EXTENTS - PHASE 1 S200WH-
CR3-P1
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
EAST ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 1
REVISIONS
S302
TYPICAL WINDOW
PERIMETER SEALANT
REPLACEMENT
LOADING DOCK DOOR CONNECTION TO HELEN
EDWARDS ENGINEERING
RESEARCH CENTER
DOORDOOR
NOT TO SCALE
LEGEND1:
APPLICATION OF TRAFFIC BEARING
WATERPROOFING MEMBRANE ON LEDGES
DETAIL(S):
1 / S302
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
APPLICATION OF TRAFFIC BEARING
WATERPROOFING MEMBRANE ON BEAM TOP 5 / S302 SIM.
REMOVE AND REPLACE CONCRETE TO
WINDOW SEALANT JOINT
2 / S302
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:2
WILSON HALL FACADE REPAIRS AND
RESTORATION
EAST ELEVATION - WATERPROOFING &
SEALANT REPLACEMENT EXTENTS -
PHASE 1
S200WH-
WP1-P1
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
EAST ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENTS - PHASE 1
REVISIONS
K H G ACD
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
S201WH- CR2-P2
NOT TO SCALE
LEGEND1:
SOUND ALL CONCRETE SURFACES
INCLUDING VERTICAL, TOPSIDE AND
UNDERSIDE SURFACES.
REPAIR DETERIORATED LOCATIONS IN
ACCORDANCE WITH THE FOLLOWING
DETAILS:
DETAIL(S):
5 / S300
2 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
4 / S300
3 / S300OR
6 / S300OR
TOPSIDE SURFACE
UNDERSIDE SURFACE
VERTICAL SURFACE
NOTE:
FOR LOCATIONS OF SUSPECTED/KNOWN DETERIORATION, SEE SHEET
WINDOWS AND DOOR
SOUND VERTIAL
SURFACES OF
COURTYARD WALLS
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:2
WILSON HALL FACADE REPAIRS AND
RESTORATION
NORTH ELEVATION - SOUNDING
EXTENTS - PHASE 2 S201WH-
CR1-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
NORTH ELEVATION - SOUNDING EXTENTS - PHASE 2
NTS
EAST ELEVATION AT PLAZA- SOUNDING EXTENTS - PHASE 2
NTS
EAST ELEVATION AT PLAZA INTERIOR - SOUNDING EXTENTS - PHASE 2
NTS
COURTYARD WALL AT PLAZA SOUNDING - PHOTO - PHASE 2
REVISIONS
REPLACE SEALANT AT DOOR LOWER LEVEL
CRACKING AT
INTERFACE
K H G ACD
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
NOT TO SCALE
1.
2.
3.
4.
5.
6.
CONCRETE REPAIR NOTES:
THE SYMBOLS PROVIDED IN THE CONCRETE REPAIR LEGEND ABOVE INDICATE A SUSPECTED OR KNOWN CONCRETE REPAIR LOCATION. OTHER REPAIR LOCATIONS WILL BE ADDED FROM INSPECTION AND
SOUNDING OF THE FACADE. CONTRACTOR SHALL SOUND 100% OF CONCRETE SURFACES.
REPAIR ONLY LOCATIONS THAT ARE DETERIORATED.
TYPICAL REPAIR DETAILS ARE SHOWN ON SHEETS AND .
THE BID REPAIR QUANTITIES ARE SHOWN ON BID FORM.
ALL REPAIRS TO MATCH SURROUNDING ORIGINAL CONCRETE (AFTER CLEANING).
REPAIR LOCATIONS SHOWN ARE APPROXIMATE AND BASED ON VISUAL SURVEY FROM JULY 2024 AND SERVE
AS BASIS FOR REPAIR QUANTITIES.
S301S300
LEGEND1:
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON BOTTOM OF SLAB
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON FACE OF SLAB
CRACKING
DELAMINATED CONCRETE
CRACK IS ON BACKSIDE OF ELEMENT SHOWNB
CRACK IS ON EACH FACE OF ELEMENT SHOWNEF
PREVIOUS CONCRETE REPAIR PATCH
DETAIL(S):
1 / S300
4 / S300
5 / S300
5 / S300
5 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
ROOF BEAM CRACKING 1 / S300
6 / S300
6 / S300
6 / S300
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:3
WILSON HALL FACADE REPAIRS AND
RESTORATION
NORTH ELEVATION -
SUSPECTED/KNOWN DETERIORATION -
PHASE 2
S201WH-
CR2-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
NORTH ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 2
REVISIONS
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
NOT TO SCALE
LEGEND1:
APPLICATION OF SILANE SEALER; APPLY
ON ALL VERTICAL AND UNDERSIDE
SURFACES.
FOR TREATMENT OF TOPSIDE SURFACES,
REFER TO S100WH AND S101WH SHEETS
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
WINDOWS AND DOOR
SILANE ON VERTIAL
SURFACES OF
COURTYARD WALLS
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:4
WILSON HALL FACADE REPAIRS AND
RESTORATION
NORTH ELEVATION - SILANE SEALER
APPLICATION EXTENTS - PHASE 2 S201WH-
CR3-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
NORTH ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 2
NTS
EAST ELEVATION AT PLAZA INTERIOR - SILANE EXTENTS - PHASE 2
NTS
EAST ELEVATION AT PLAZA- SILANE EXTENTS - PHASE 2
NTS
COURTYARD WALL AT PLAZA- PHOTO - PHASE 2
REVISIONS
AT PLAZA WALLS
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
S303
2_______TYP.
7TH - 15TH
FLOORS
S303
1_______TYP.
2ND - 6TH
FLOORS
NOT TO SCALE
LEGEND1:
REMOVE AND REPLACE CONCRETE TO
CURTAIN WALL SEALANT JOINT
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
DETAIL(S):
REMOVE AND REPLACE CONCRETE TO
WINDOW SEALANT JOINT
1 / S303
APPLICATION OF TRAFFIC BEARING
WATERPROOFING MEMBRANE ON LEDGES
3 / S303
1 / S302
2 / S303
6 / S302 7 / S302 8 / S302
WATERPROOFING
MEMBRANE ON
SKYWARD SURFACES
OF COURTYARD WALLS
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:5
WILSON HALL FACADE REPAIRS AND
RESTORATION
NORTH ELEVATION - WATERPROOFING
& SEALANT REPLACEMENT EXTENT -
PHASE 2
S201WH-
WP1-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
NORTH ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENT - PHASE 2
NTS
COURTYARD WALL AT PLAZA WATERPROOFING - PHOTO - PHASE 2
REVISIONS
A C D KHG
CONNECTION TO RAMSEY AUDITORIUM
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
S202WH- CR2-P2
NOT TO SCALE
LEGEND1:
SOUND ALL CONCRETE SURFACES
INCLUDING VERTICAL, TOPSIDE AND
UNDERSIDE SURFACES.
REPAIR DETERIORATED LOCATIONS IN
ACCORDANCE WITH THE FOLLOWING
DETAILS:
DETAIL(S):
5 / S300
2 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
4 / S300
3 / S300OR
6 / S300OR
TOPSIDE SURFACE
UNDERSIDE SURFACE
VERTICAL SURFACE
NOTE:
FOR LOCATIONS OF SUSPECTED/KNOWN DETERIORATION, SEE SHEET
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:5
WILSON HALL FACADE REPAIRS AND
RESTORATION
SOUTH ELEVATION - SOUNDING
EXTENTS - PHASE 2 S202WH-
CR1-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
SOUTH ELEVATION - SOUNDING EXTENTS - PHASE 2
REVISIONS
B
B
A C D KHG
CONNECTION TO RAMSEY AUDITORIUM
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
NOT TO SCALE
1.
2.
3.
4.
5.
6.
CONCRETE REPAIR NOTES:
THE SYMBOLS PROVIDED IN THE CONCRETE REPAIR LEGEND ABOVE INDICATE A SUSPECTED OR KNOWN CONCRETE REPAIR LOCATION. OTHER REPAIR LOCATIONS WILL BE ADDED FROM INSPECTION AND
SOUNDING OF THE FACADE. CONTRACTOR SHALL SOUND 100% OF CONCRETE SURFACES.
REPAIR ONLY LOCATIONS THAT ARE DETERIORATED.
TYPICAL REPAIR DETAILS ARE SHOWN ON SHEETS AND .
THE BID REPAIR QUANTITIES ARE SHOWN ON BID FORM.
ALL REPAIRS TO MATCH SURROUNDING ORIGINAL CONCRETE (AFTER CLEANING).
REPAIR LOCATIONS SHOWN ARE APPROXIMATE AND BASED ON VISUAL SURVEY FROM JULY 2024 AND SERVE
AS BASIS FOR REPAIR QUANTITIES.
S301S300
LEGEND1:
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON BOTTOM OF SLAB
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON FACE OF SLAB
CRACKING
DELAMINATED CONCRETE
CRACK IS ON BACKSIDE OF ELEMENT SHOWNB
CRACK IS ON EACH FACE OF ELEMENT SHOWNEF
PREVIOUS CONCRETE REPAIR PATCH
DETAIL(S):
1 / S300
4 / S300
5 / S300
5 / S300
5 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
ROOF BEAM CRACKING 1 / S300
6 / S300
6 / S300
6 / S300
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:0
WILSON HALL FACADE REPAIRS AND
RESTORATION
SOUTH ELEVATION -
SUSPECTED/KNOWN DETERIORATION -
PHASE 2
S202WH-
CR2-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
SOUTH ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 2
REVISIONS
ROOF RISING
WALLS. SEE
SCOPE:
S101WH- P2
S204WH-CR2
S205WH-CR2
NOT TO SCALE
LEGEND1:
APPLICATION OF SILANE SEALER; APPLY
ON ALL VERTICAL AND UNDERSIDE
SURFACES.
FOR TREATMENT OF TOPSIDE SURFACES,
REFER TO S100WH AND S101WH SHEETS
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:0
WILSON HALL FACADE REPAIRS AND
RESTORATION
SOUTH ELEVATION - SILANE SEALER
APPLICATION EXTENTS- PHASE 2 S202WH-
CR3-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
SOUTH ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 2
REVISIONS
WATERPROOFING COATING
ON WINDOW LEDGES, TYP
S303 1_______
S303
2_______TYP.
7TH - 15TH
FLOORS
TYP.
2ND - 6TH
FLOORS
NOT TO SCALE
LEGEND1:
REMOVE AND REPLACE CONCRETE TO
CURTAIN WALL SEALANT JOINT
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
DETAIL(S):
REMOVE AND REPLACE CONCRETE TO
WINDOW SEALANT JOINT
1 / S303
APPLICATION OF TRAFFIC BEARING
WATERPROOFING MEMBRANE ON LEDGES
3 / S303
1 / S302
2 / S303
6 / S302 7 / S302 8 / S302
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:1
WILSON HALL FACADE REPAIRS AND
RESTORATION
SOUTH ELEVATION - WATERPROOFING
& SEALANT REPLACEMENT EXTENTS -
PHASE 2
S202WH-
WP1-P2
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
SOUTH ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENTS - PHASE 2
REVISIONS
1 2 3 4 5 6 7 8
DOOR
WINDOW ABOVE CONCRETE
KNEE WALL,
TYP. GROUND FLOOR
CONCRETE KNEE
WALL
FOR SCOPE OF WORK IN THIS
AREA ON THE PENTHOUSE
WALLS, SEE THE FOLLOWING:
MASONRY -
CONCRETE -
S207WH- CR3-P3
S101WH- P3
S204WH-CR2
S205WH-CR2
S101WH- P3
S207WH- CR3-P3
S207WH-
CR1&CR2-P3
S203WH- CR2-P3
NOT TO SCALE
LEGEND1:
SOUND ALL CONCRETE SURFACES
INCLUDING VERTICAL, TOPSIDE AND
UNDERSIDE SURFACES.
REPAIR DETERIORATED LOCATIONS IN
ACCORDANCE WITH THE FOLLOWING
DETAILS:
DETAIL(S):
5 / S300
2 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
4 / S300
3 / S300OR
6 / S300OR
TOPSIDE SURFACE
UNDERSIDE SURFACE
VERTICAL SURFACE
NOTE:
FOR LOCATIONS OF SUSPECTED/KNOWN DETERIORATION, SEE SHEET
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:1
WILSON HALL FACADE REPAIRS AND
RESTORATION
WEST ELEVATION - SOUNDING EXTENTS
- PHASE 3 S203WH-
CR1-P3
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
WEST ELEVATION SOUNDING EXTENTS - PHASE 3
REVISIONS
EF B EF B B B BB B EF
DOOR
WINDOW ABOVE CONCRETE
KNEE WALL,
TYP. GROUND FLOOR
CONCRETE KNEE
WALL
FOR SCOPE OF WORK IN THIS
AREA ON THE PENTHOUSE
WALLS, SEE THE FOLLOWING:
MASONRY -
CONCRETE -
S207WH- CR3-P3
S101WH- P3
S204WH-CR2
S205WH-CR2
S101WH- P3
S207WH- CR3-P3
S207WH-
CR1&CR2-P3
NOT TO SCALE
1.
2.
3.
4.
5.
6.
CONCRETE REPAIR NOTES:
THE SYMBOLS PROVIDED IN THE CONCRETE REPAIR LEGEND ABOVE INDICATE A SUSPECTED OR KNOWN CONCRETE REPAIR LOCATION. OTHER REPAIR LOCATIONS WILL BE ADDED FROM INSPECTION AND
SOUNDING OF THE FACADE. CONTRACTOR SHALL SOUND 100% OF CONCRETE SURFACES.
REPAIR ONLY LOCATIONS THAT ARE DETERIORATED.
TYPICAL REPAIR DETAILS ARE SHOWN ON SHEETS AND .
THE BID REPAIR QUANTITIES ARE SHOWN ON BID FORM.
ALL REPAIRS TO MATCH SURROUNDING ORIGINAL CONCRETE (AFTER CLEANING).
REPAIR LOCATIONS SHOWN ARE APPROXIMATE AND BASED ON VISUAL SURVEY FROM JULY 2024 AND SERVE
AS BASIS FOR REPAIR QUANTITIES.
S301S300
LEGEND1:
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON BOTTOM OF SLAB
SPALLED CONCRETE WITH EXPOSED
REINFORCEMENT ON FACE OF SLAB
CRACKING
DELAMINATED CONCRETE
CRACK IS ON BACKSIDE OF ELEMENT SHOWNB
CRACK IS ON EACH FACE OF ELEMENT SHOWNEF
PREVIOUS CONCRETE REPAIR PATCH
DETAIL(S):
1 / S300
4 / S300
5 / S300
5 / S300
5 / S300
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
ROOF BEAM CRACKING 1 / S300
6 / S300
6 / S300
6 / S300
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:2
WILSON HALL FACADE REPAIRS AND
RESTORATION
WEST ELEVATION - SUSPECTED/KNOWN
DETERIORATION - PHASE 3 S203WH-
CR2-P3
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
WEST ELEVATION - SUSPECTED/KNOWN DETERIORATION - PHASE 3
REVISIONS
DOOR
WINDOW ABOVE CONCRETE
KNEE WALL,
TYP. GROUND FLOOR
CONCRETE KNEE
WALL
FOR SCOPE OF WORK IN THIS
AREA ON THE PENTHOUSE
WALLS, SEE THE FOLLOWING:
MASONRY -
CONCRETE -
S207WH- CR3-P3
S101WH- P3
S204WH-CR2
S205WH-CR2
S101WH- P3
S207WH- CR3-P3
S207WH-
CR1&CR2-P3
NOT TO SCALE
LEGEND1:
APPLICATION OF SILANE SEALER; APPLY
ON ALL VERTICAL AND UNDERSIDE
SURFACES.
FOR TREATMENT OF TOPSIDE SURFACES,
REFER TO S100WH AND S101WH SHEETS
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:3
WILSON HALL FACADE REPAIRS AND
RESTORATION
WEST ELEVATION - SILANE SEALER
APPLICATION EXTENTS - PHASE 3 S203WH-
CR3-P3
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
WEST ELEVATION - SILANE SEALER APPLICATION EXTENTS - PHASE 3
REVISIONS
S302
TYPICAL WINDOW
PERIMETER SEALANT
REPLACEMENT
DOOR
WINDOW ABOVE CONCRETE
KNEE WALL,
TYP. GROUND FLOOR
CONCRETE KNEE
WALL
NOT TO SCALE
LEGEND1:
APPLICATION OF TRAFFIC BEARING
WATERPROOFING MEMBRANE ON LEDGES
DETAIL(S):
1 / S302
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN COLOR
TO MAINTAIN LEGEND.
APPLICATION OF TRAFFIC BEARING
WATERPROOFING MEMBRANE ON BEAM TOP 5 / S302 SIM.
REMOVE AND REPLACE CONCRETE TO
WINDOW SEALANT JOINT
2 / S302
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD APPROVED
SUBMITTED
A/E CONSULTANT DATE FERMI LAB DATE
PROJECT NAME.
SHEET NAME:
REVISION NO.FIMS. NO.
INFRASTRUCTURE
SERVICES DIVISION
SUBCONTRACT NO. 720342
001 1
C :\U se rs
\tc va ch on
\D oc um en ts \S
_2
4_
R
_t cv ac ho n.
rv t 4/
7/
1:
:3
WILSON HALL FACADE REPAIRS AND
RESTORATION
WEST ELEVATION - WATERPROOFING &
SEALANT REPLACEMENT EXTENTS -
PHASE 3
S203WH-
WP1-P3
ISD 2-1-552
Is su e D at e
A P R
IL
SGH
MSL/TCV
RSH
KC
NTS
WEST ELEVATION - WATERPROOFING & SEALANT REPLACEMENT EXTENTS - PHASE 3
REVISIONS
C
D G
H K
S207WH-
CR1&CR2-P3
S206WH
CR1&CR2-P1
PROTECT SKYLIGHTS
2 2 11
1 2 2 2
1 1 1
1 1
PH
AS
E
EX
TE
N
TS
PH
AS
E
EX
TE
N
TS
PH
AS
E
EX
TE
N
TS
NOT TO SCALE
LEGEND1:
WALL CRACK
PERPENDICULAR TO PLAN
VIEW
WALL CRACK
DETAILS:
1 THIS LEGEND IS COLOR CODED. PRINT THESE DRAWINGS IN
COLOR TO MAINTAIN LEGEND.
1 DIAGONAL WALL CRACKING
VERTICAL WALL CRACKING
HORIZONTAL WALL CRACKING
4 / S301
1 / S300
MASONRY -
CONCRETE -
SCALE:
PROJECT NO.
SHEET NO.
DESIGNED
DRAWN
CHECKED
APPROVED
CONCEPT
DISCIPLINE
REVIEW
ENG. REVIEWED
ISD…