Exhibit A_2-1-552 STATEMENT OF WORK_20251029.pdf

PDF 198 KB Posted

Attached to
Wilson Hall Facade Repairs and Restoration
Solicitation number
370886-CD
Issued by

About this file

This Statement of Work (SOW) details facade repairs and restoration for Wilson Hall at Fermi National Accelerator Laboratory, with Project No. 2-1-552. The project will be completed in three phases covering different building elevations (East, North/South, and West), involving comprehensive concrete and masonry restoration work. Specific tasks include removing existing concrete coating, identifying and repairing concrete damage, color and texture matching, applying silane sealer and waterproofing, replacing window sealants, and conducting local CMU repairs at the penthouse. Noisy construction is restricted to hours between 5 PM and dark, with mobilization allowed starting at 4 PM. All personnel must provide Real ID and obtain badging from the Fermilab Badging Office, and a web-based 3D drone model of Wilson Hall is available upon request. A Fermilab Construction Coordinator will be assigned, and the subcontractor is responsible for quality control and documentation of all work performed.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

WILSON HALL FACADE REPAIRS AND RESTORATION

ISD/E Project No. 2-1-552

Introduction and Background

Fermilab requires construction services to complete repairs and restoration of the facade of Wilson Hall.

Scope of Work

The Subcontractor shall provide all work as summarized in this Statement of Work, as shown on drawings set “Project No. 2-1-552 Wilson Hall Repairs and Restoration,” dated April 7, 2025, and specified in the

“Wilson Hall Facade Repairs and Restoration Specification Manual”, dated April 7, 2025.

Work shall include removal of existing concrete coating, identification of the concrete in need of repair by sounding, removal of spalled or delaminated concrete (as described in Section 024119 of the Specification

Manual), color and texture matching of existing concrete and completion of concrete repairs (as described in Section 030100 of the Specification Manual), application of new silane sealer to concrete vertical and underside surfaces (as described in Section 030100 and Section 071900 of the Specification Manual), application of waterproofing coating on skyward facing surfaces (as described in Section 071800 of the

Specification Manual), sealant replacement around windows (as described in Section 079200 of the

Specification Manual), local CMU repairs at the Wilson Hall penthouse (as described in Section 0042000 of the Specification Manual), and application of sealants/coating to repaired masonry (as described in Section

099600 of the Specification Manual). This description is general in nature and is only intended to describe the range and complexity of the required scope of work.

The Subcontractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications.

All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings and technical specifications.

The Subcontractor’s scope of work is not limited to the general work outline described herein. The

Subcontractor shall perform all work required to complete the construction work in accordance with the drawings set “Project No. 2-1-552 Wilson Hall Repairs and Restoration,” dated April 7, 2025, and the

“Wilson Hall Facade Repairs and Restoration Specification Manual”, dated April 7, 2025.

The work described above shall be completed in three phases:

• Phase 1 includes facade repairs and restoration on the East Elevation of Wilson Hall as depicted in the drawings and specifications identified above.

• Phase 2 includes facade repairs and restoration on the North and South Elevations of Wilson Hall as depicted in the drawings and specifications identified above.

• Phase 3 includes facade repairs and restoration on the West Elevation as depicted in the drawings and specifications identified above.

The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and specifications.

Quality Assurance

A Fermilab Construction Coordinator will be assigned to this project. See specification Section 010010, GENERAL REQUIREMENTS.

The Subcontractor is responsible for all activities necessary to manage, control, and document that work complies with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate

Quality Control services are provided for work accomplished on- and off-site by its organization, suppliers, sub-tier contractors, technical laboratories, and consultants. A Project Quality Control Plan is required (see

Specification 014100, QUALITY REQUIREMENTS, Paragraph 1.3 B.).

FFDG–Furnished Property and/or Data

There will be no materials or equipment furnished by FFDG.

A web-based 3D drone model of Wilson Hall depicting the building facades is available upon request.

Security

All personnel working at Fermilab are required to provide Real ID and obtain badging from the Fermilab

Badging Office.

Place of Performance

The work will be performed at Wilson Hall. Refer to the drawings for the specific location. Refer to

Drawings and Specifications for general site working conditions and requirements.

Available work hours for noisy construction are 5 PM to dark, subject to high hazard work authorization.

Subcontractor may begin mobilization for noisy construction at 4 PM. Noisy construction applies mainly to drilling and hammering into the concrete structure as well as window sealant removal and grinding.

File details come from the government source that posted it. Updated .