Exhibit A - Little Creek 100MT MBH Rev. 0.pdf
PDF 217 KB Posted
- Solicitation number
- N6247025R0019
About this file
This document is a Contract Data Requirements List (CDRL) for a One 100MT Mobile Boat Hoist contract (Solicitation Number N62470-24-R-8005) issued by the Navy Crane Center, Naval Facilities Engineering Systems Command (NAVCRANECEN) located in Virginia Beach, VA. The CDRL outlines 32 specific data items that the contractor must submit throughout the contract lifecycle, including design packages, test procedures, certifications, training documentation, and shipping plans. Each data item has detailed submission requirements, including specific timelines for submission (ranging from 10-25 business days prior to various milestones), review periods, and mandatory electronic or physical documentation formats.
Key submission requirements include providing documents such as an Accident Prevention Plan, MBH Re-assembly Plan, wire rope and shackle certifications, computer documentation, control system inventory, EPA emissions certification, and a shipping plan. Most submissions require government approval before critical contract stages like shop testing, crane shipment, or crane acceptance. The documents must include specific identifiers like crane serial number, contract number, CDRL number, and CLIN number. The government review periods are typically 5-10 business days, with the contractor required to make any necessary resubmissions promptly if initial submissions do not meet requirements.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2
EXHIBIT A
Contract Data Requirements List
1.0
1.1
Code Frequency
DAILY
WEEKLY
BI-WE
MTHLY
BI-MO
QRTLY
2/MTH
XTIME
2TIME/R
ANNLY
SEMIA
OTIME
ONE/R
ASREQ
CP/RQ
2TIME
*DFDEL
ONE/P
1.2
1.3
1.4
Each two months
Annually
DD Forms 1423
Two separate submittals
Monthly
2 separate submittals
One time One time with revisions as required As required
Each six months
X separate submittals
The data items included in this Section are required by the applicable clauses of Federal Acquisition Regulations (FAR) 52.2 and Defense Federal Acquisition Regulation (DFAR) 252.227
The NAVCRANECEN Project Manager shall be notified by email when a submission is submitted via DoD Safe for review. The Government review period will begin on the latter date of: email notification or date of receipt from DoD Safe. If the email or DoD Safe submission are received after 1400 EST, they will be considered received the next business day. Submittal review periods are business days unless otherwise specified. Business days (regular working hours) are defined in the Appendix H under section 3.1.
Contracts Data Requirements List (CDRL)
EXHIBIT A
Daily
Data to be delivered under this contract is identified in Exhibit A (DD Forms 1423) and further described in Exhibit B (DD Forms 1664) and the technical specification. All data submitted shall utilize British System units of measure and the English language exclusively.
Quantities/distribution points listed in block 14 of DD Forms 1423 shall apply to all submissions. Latest edition of referenced document noted in block 4 is required. Codes used in blocks 8 and 10 are described as follows:
Little Creek 100MT MBH Virginia Beach, VA
References include subordinate paragraphs.
Distribution addresses for the submission of data are provided on page 2.
Deferred delivery (rarely used)
Change pages as required when procuring
One time preliminary & revisions draft
Quarterly Semimonthly
Weekly Each two weeks
Exhibit A Page 1 of 25 Rev. 0
NAVCRANECEN
JEBLC
DCMA
NAVCRANECEN:
email:
phone:
JEBLC
email:
phone:
Navy Crane Center, Naval Facilities Engineering Systems Command
Little Creek 100MT MBH Virginia Beach, VA
Distribution addresses for the submission of data:
Abbreviations used:
Joint Expeditionary Base Little Creek
Defense Contract Management Agency
Director, Navy Crane Center
Virginia Beach, VA 23459 ricky.hartman@socom.mil 757-763-3704
Joint Expeditionary Base Little Creek
Naval Facilities Engineering Systems Command
Supply Officer, NSWG-8, 1600 Seabee Dr, BLDG CB-318
Attn: Brittany Copeland brittany.a.copeland2.civ@us.navy.mil 757-967-3842
Attn: Ricky Hartman
Portsmouth VA 23709-1044
Project Manager - Code 01 Norfolk Naval Shipyard, Bldg 491
Exhibit A Page 2 of 25 Rev. 0
Data Item Page
A001 4 A002 5 A003 6 A004 7 A005 8 A009 9 A010 10 A011 11 A012 12 A013 13 A016 14 A017 15 A018 16 A020 17 A022 18 A025 19 A026 20 A027 21 A028 22 A029 23 A030 24 A032 25
CONTRACT DATA REQUIREMENTS LIST
TABLE OF CONTENTS
Little Creek 100MT MBH
Virginia Beach, VA
STATUS REPORT
DESIGN PACKAGE
REQUEST FOR INFORMATION
OPERATION AND MAINTENANCE MANUAL
CERTIFICATION, WIRE ROPE
CERTIFICATION, SLINGS
CERTIFICATION, CONTRACTOR'S SELF TEST
TEST PROCEDURES & REPORTS
CRANE REMOVAL / INSTALLATION PLAN
ACCIDENT PREVENTION PLAN
PROPERTY TRANSFER VERIFICATION
CONFERENCE MINUTES
CONTRACTOR CRANE ENTRY PACKAGE
TRAINING COURSE OUTLINE
FREQUENCY ALLOCATION APPLICATION
CERTIFICATION, PUBLIC DOMAIN SOFTWARE
COMPUTER DOCUMENTATION
CONTROL SYSTEM INVENTORY
EVALUATION STATUS
CERTIFICATION, SHACKLES
MBH SHIPPING PLAN
CERTIFICATION, EPA EMISSIONS
Exhibit A Page 3 of 25 Rev. 0
TDP X TM
7. DD 250 REQ
LT
8. APPL CODE
A 0 1 0 1
0 2
H. DATE
12/4/2024
10. FREQUENCY
MTHLY
16. REMARKS
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
INITIAL SCHEDULE:
Provide initial schedule within 10 business days of contract award. Provide a submission in accordance with blocks 4 and 5. The contractor will be notified within 10 business days if revision and resubmission is required. Resubmittals, if required, shall be provided to NAVCRANECEN within 5 business days after return of Government review comments.
MONTHLY STATUS REPORT:
Provide monthly status report and schedule by the first day of the month. Provide updated schedule when events change the schedule. Provide a submission in accordance with blocks 4 and 5. The contractor will be notified within 10 business days if revision and resubmission is required. Resubmittals, if required, shall be provided to NAVCRANECEN within 5 business days after return of Government review comments.
In addition to the narrative report described in block 4, the crane contractor shall prepare and submit a detailed graphic and tabular schedule showing design, manufacturing, delivery and acceptance activities for the crane. Initial schedule submission shall be the baseline from which monthly progress shall be measured.
Each monthly report after the initial submission should address issues that will potentially delay, or have delayed, the schedule previously provided. This report shall also identify all NCC-to-Contractor issues that have not been resolved.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
ONSITE WORK SCHEDULE:
Provide onsite work schedule a minimum of 30 calendar days prior to the contractor's desired mobilization date. Provide submission in accordance with blocks 4 and 5.
ONSITE WORK DAILY STATUS REPORT:
Provide daily status report by close of business, starting at mobilization date through acceptance date while onsite work is being performed. Provide submission in accordance with block 4.
In addition to the narrative report described in block 4, the crane contractor shall provide a narrative of work events during the reported business day, significant observations and concerns identified, and a schedule of events for the remainder of business days on site.
15. TOTAL
J. DATE
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
6. REQUIRING OFFICE
NAVCRANECEN
3. SUBTITLE
14. DISTRIBUTION
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Status Report
9. DISTRIBUTION
STATEMENT
4. AUTHORITY
DI-MGMT-80368A
5. CONTRACT REFERENCE
Para. 4.11
12. DATE OF FIRST SUBMISSION
See Block 16
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
F. CONTRACTOR
A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
Physical Copy
Electronica. ADDRESSEE
NAVCRANECEN
Exhibit A Page 4 of 25 Rev. 0
LT
8. APPL CODE
A
0 1 0 1
NAVCRANECEN 0 1
1 1
NAVCRANECEN 0 0
2 0
NAVCRANECEN 1 0
2 0
6 4
H. DATE
12/4/2024
NAVCRANECEN
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
JEBLC
DESIGN PACKAGE:
Each design package submitted (initial and subsequent) shall be considered a final submittal and shall be complete containing all the most updated drawing and submittal revisions in accordance with blocks 4 and 5. NAVCRANECEN reserves the right to reject and require resubmittal of any incomplete design package. NAVCRANECEN will determine acceptability within 15 business days after initial design package submittal. All subsequent Government review periods shall be complete within 10 business days of receipt of resubmission. The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval of Design Package is required 20 business days prior to shop test.
After NAVCRANECEN design approval and prior to shop test, the Contractor shall submit a complete set of approved design drawings.
POST-SHOP TEST AS-BUILT DRAWINGS:
All as-built drawing deficiencies identified prior to crane shipment (including during shop test) shall be corrected prior to crane shipment unless NAVCRANECEN approves deferring this requirement. The corrected (or most recent if corrections are deferred) as-built drawing package shall be furnished via physical paper and electronic copies in accordance with blocks 4 and 5 at the time of crane shipment.
NAVCRANECEN will determine acceptability within 10 business days after crane acceptance. All subsequent Government review periods shall be complete within 10 business days of receipt of resubmission. The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
FINAL AS-BUILT DRAWINGS:
Upon Government approval of the Post-Shop Test As-Built Drawings, these drawings become the Final As-Built Drawings. Provide the approved Final As-Built Drawings on CD-ROM and paper copy in accordance with blocks 4 and 5 no later than 20 business days after crane acceptance. Submit printed drawings and CD-ROM(s) via overnight private courier. NAVCRANECEN will determine acceptability within 10 business days after submittal. All subsequent Government review periods shall be complete within 10 business days of receipt of resubmission.
FINAL CD-ROM AS-BUILTS
JEBLC
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A002
2. TITLE OF DATA ITEM
Design Package
4. AUTHORITY
Para 4.1, Para 4.2, Para 4.3, Para 4.10, Para 4.15.3
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
5. CONTRACT REFERENCE
See Block 16
See Block 16
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
10. FREQUENCY
ASREQ
9. DISTRIBUTION
STATEMENT
DI-SESS-81000F, DI-SDMP-81261,
DI-AVCS-80700A
A. CONTRACT LINE ITEM NO. B. EXHIBIT
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Electronica. ADDRESSEE
14. DISTRIBUTION
F. CONTRACTOR
3. SUBTITLE
6. REQUIRING OFFICE
NAVCRANECEN
Physical Copy
DD Form 1423-1, JUN 90 Previous editions are obsolete
15. TOTAL
16. REMARKS
JEBLC
DESIGN PACKAGE
POST-SHOP TEST AS-BUILTS
FINAL PAPER AS-BUILTS
JEBLC
J. DATE
12/4/2024
Exhibit A Page 5 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 0 0
0 1
H. DATE
12/4/2024
F. CONTRACTOR
3. SUBTITLE
A. CONTRACT LINE ITEM NO. B. EXHIBIT
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A003
2. TITLE OF DATA ITEM
Request For Information
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
6. REQUIRING OFFICE
NAVCRANECEN
9. DISTRIBUTION
STATEMENT
4. AUTHORITY
DI-SESS-80639E/80640E/80642E as modified by NCC
5. CONTRACT REFERENCE
Para 4.13
a. ADDRESSEE
10. FREQUENCY
ASREQ
14. DISTRIBUTION
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
Physical Copy
ElectronicSee Block 16
J. DATE
16. REMARKS NAVCRANECEN
REQUEST FOR INFORMATION:
The Contractor shall prepare and submit a Request For Information (RFI) in accordance with blocks 4 & 5 when requesting information or requesting a change to a contract requirement. Contractor shall submit an RFI as often as required.
NAVCRANECEN will provide a response within the negotiated response date.
The RFI shall be submitted electronically in .pdf file format. The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: The Contractor shall propose a response need date. Final need date shall be agreed upon with the NAVCRANECEN Project Manager.
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
JEBLC
15. TOTAL
Exhibit A Page 6 of 25 Rev. 0
TDP TM X
LT
8. APPL CODE
A
0 1 1 1
1 0 1 0
0 0 2 0
5 2
H. DATE
12/4/2024
15. TOTAL
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
J. DATE
10. FREQUENCY
ASREQ
14. DISTRIBUTION
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
9. DISTRIBUTION
STATEMENT
See Block 16
5. CONTRACT REFERENCE
Para. 4.1, Para. 4.3, Para. 4.4, Para. 4.9
[N62470-24-R-8005]
1. DATA ITEM NO.
A004
2. TITLE OF DATA ITEM
Operations & Maintenance Manual
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT
3. SUBTITLE
One 100MT Mobile Boat Hoist
ElectronicPhysical Copy
6. REQUIRING OFFICE
NAVCRANECEN
a. ADDRESSEE
A
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
4. AUTHORITY
DI-TMSS-80527C
16. REMARKS PRE-FINAL O&M
NAVCRANECEN
JEBLC
JEBLC
JEBLC
NAVCRANECEN
PRE-FINAL O&M MANUAL (PAPER & ELECTRONIC):
Furnish pre-final paper and electronic copies of the technical manual in accordance with blocks 4 and 5 at the time of crane shipment. Paper copy manual shall be on site prior to beginning government inspection. NAVCRANECEN will determine acceptability within 10 business days after crane acceptance. All subsequent Government review periods shall be complete within 10 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval of Pre-Final O&M Manual is required within 5 business day after crane acceptance.
FINAL O&M MANUAL (PAPER AND CD-ROM):
Upon Government approval of the Pre-Final Submission, provide the approved Final O&M Manual on CD-ROM and paper copy in accordance with blocks 4 and 5 no later than 20 business days after Pre-Final O&M Manual approval. Submit printed manuals and CD-ROM(s) via overnight private courier.
FINAL O&M MANUAL CD-ROM:
Provide data in PDF format, bookmarked as a minimum based on the manual information required by block 5.
FINAL O&M MANUAL PAPER:
Paper copies of the final manual shall be bound in durable, water-resistant, hard-cover binders and shall include the approved Final As-Built Drawings reduced in size to 11-in x 17-in.
NAVCRANECEN will determine acceptability within 10 business days after submittal.
All subsequent Government review periods shall be complete within 10 business days of receipt of resubmission.
FINAL O&M CD-ROM
FINAL O&M PAPER
NAVCRANECEN
Exhibit A Page 7 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
1 2
H. DATE
12/4/2024
10. FREQUENCY
ONE/R
16. REMARKS
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
WIRE ROPE CERTIFICATION:
Provide data a minimum of 10 business days prior to shop test in accordance with blocks 4 and 5. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval is required a minimum of 1 business day prior to shipment of the crane.
15. TOTAL
J. DATE
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
6. REQUIRING OFFICE
NAVCRANECEN
3. SUBTITLE
14. DISTRIBUTION
1. DATA ITEM NO.
A005
2. TITLE OF DATA ITEM
Certification, Wire Rope
9. DISTRIBUTION
STATEMENT
4. AUTHORITY
DI-MISC-80678, para 10.3.2
5. CONTRACT REFERENCE
Para. 4.1, Para. 4.5, Para. 4.5.1
12. DATE OF FIRST SUBMISSION
See Block 16
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
F. CONTRACTOR
A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
Physical Copy
Electronica. ADDRESSEE
NAVCRANECEN
Exhibit A Page 8 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
1 2
H. DATE
12/4/2024
F. CONTRACTOR
3. SUBTITLE
6. REQUIRING OFFICE
10. FREQUENCY
NAVCRANECEN
9. DISTRIBUTION
STATEMENT
4. AUTHORITY
a. ADDRESSEEONE/R
14. DISTRIBUTION
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
Physical Copy
See Block 16 Electronic
1. DATA ITEM NO.
A009
2. TITLE OF DATA ITEM
Certification, Slings
DI-MISC-80678, para 10.3.2
5. CONTRACT REFERENCE
Para. 3.2.2.3 Para. 4.1, Para. 4.5.3
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT
16. REMARKS NAVCRANECEN
JEBLC
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
J. DATE
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete
SLING LOAD TEST CERTIFICATION:
Provide slings' load (proof) test report data a minimum of 25 business days prior to shop test in accordance with blocks 4 and 5. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
Report shall clearly provide the name of manufacturer, the link or ring's unique serial number, the working load limit, proof load, and hold duration.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval of submitted sling report with all required supporting documentation is required a minimum of 10 business days prior to shipment of crane.
Exhibit A Page 9 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 0 1
0 2
H. DATE
12/4/2024
J. DATE
Brittany Copeland Christopher Halligan 12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
15. TOTAL
G. PREPARED BY I. APPROVED BY
CERTIFICATION OF CONTRACTOR'S SELF TEST:
Provide the completed contractor's self test a minimum of 5 business days prior to shop test in accordance with blocks 4 and 5. NAVCRANECEN will determine acceptability within 2 business days after receipt. All subsequent Government review periods shall be complete within 2 business days of receipt of resubmission.
NOTIFICATION OF SHOP TEST:
Provide notification of the date shop testing will start a minimum of 10 business days prior to the shop test in accordance with blocks 4 and 5. NAVCRANECEN will acknowledge within 3 business days after receipt.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval of Certification of Contractor Self Test required 3 business days prior to shop test of the crane.
JEBLC
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
16. REMARKS NAVCRANECEN
9. DISTRIBUTION
STATEMENT
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
ONE/R See Block 16 a. ADDRESSEE Physical Copy
Electronic
4. AUTHORITY 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
DI-NDTI-80809B Para. 4.1, Para. 4.15.1 Para. 4.15.2 NAVCRANECEN
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A010 Certification, Contractor's Self Test
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
CONTRACT DATA REQUIREMENTS LIST Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Exhibit A Page 10 of 25 Rev. 0
LT
8. APPL CODE
A
0 1 0 1
0 1 0 1
0 1 0 1
0 1 0 1
0 1 1 1
1 10
H. DATE
12/4/2024
SHOP TEST PROCEDURE
SHOP TEST RECORD &
DEFICIENT ITEMS LIST
REQUEST TO SHIP &
UPDATED DEFICIENT ITEMS
NOTIFICATION OF
GOVERNMENT FIELD
FIELD TEST RECORD
JEBLC
NAVCRANECEN
15. TOTAL
16. REMARKS
SHOP TEST PROCEDURE:
Provide Shop Test Procedure for review at least 25 business days prior to shop test in accordance with blocks 4 and 5. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
SHOP TEST RECORD & DEFICIENT ITEMS LIST:
Completed Shop Test Record and Deficient Items List shall be submitted within 5 business days of completion of test, and prior to crane shipment. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
REQUEST TO SHIP & UPDATED DEFICIENT ITEMS LIST:
Request to Ship and updated Deficient Items List with corrective actions identified shall be submitted at least 2 business days prior to crane shipment. NAVCRANECEN will determine acceptability within 1 business day after receipt. All subsequent Government review periods shall be complete within 1 business day after resubmission.
NOTIFICATION OF GOVERNMENT FIELD INSPECTION:
Notify Government of projected Contractor's inspection test completion date 5 business days prior to expected completion. Notify Government immediately after Contractor's preliminary inspection and test is complete.
FIELD TEST RECORD:
Completed Field Test Record shall be submitted within 3 business days of completion of test.
NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
Note: The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation. Government approval of Contractor developed Shop Test Procedure is required a minimum of 10 business days prior to shop test. Government approval of Shop Test Record & Deficient Items List and Request to Ship & Updated Deficient Items List is required prior to crane shipment. Government approval of Field Test Record is required prior to crane acceptance.
NAVCRANECEN
JEBLC
NAVCRANECEN
JEBLC
NAVCRANECEN
JEBLC
J. DATE
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
NAVCRANECEN
4. AUTHORITY
DI-NDTI-80809B, DI-QCIC-81110
5. CONTRACT REFERENCE
a. ADDRESSEE
10. FREQUENCY
ONE/R
14. DISTRIBUTION9. DISTRIBUTION
STATEMENT
Para. 4.1, Para. 4.15.1, Para. 4.15.2, Para. 4.15.3, Para 4.15.4,Appendix B, Appendix C
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
See Block 16
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A011
2. TITLE OF DATA ITEM
Test Procedures and Reports
A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Physical Copy
Electronic
F. CONTRACTOR
3. SUBTITLE
NAVCRANECEN
6. REQUIRING OFFICE
Exhibit A Page 11 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 0 1
0 2
H. DATE
12/4/2024
NAVCRANECEN
JEBLC
F. CONTRACTOR
3. SUBTITLE
NAVCRANECEN
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A012
2. TITLE OF DATA ITEM
MBH Re-assembly Plan
6. REQUIRING OFFICE4. AUTHORITY
OT-24206
5. CONTRACT REFERENCE
Para. 4.1, Para. 4.17, Appendix H, Appendix E
a. ADDRESSEE
10. FREQUENCY
ONE/R
14. DISTRIBUTION9. DISTRIBUTION
STATEMENT
Physical Copy
ElectronicSee Block 16
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
15. TOTAL
16. REMARKS
MBH RE-ASSEMBLY PLAN:
Provide a detailed re-assembly/installation lift and rigging plan in accordance with blocks 4 and 5 a minimum of 15 business days prior to Pre-installation Conference, but no later than 25 business days prior to mobilization should the conference be delayed.
NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval required by earlier event of 2 business days prior to crane shipment or 5 business days prior to desired entry of Contractor mobile crane or material handling equipment.
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
J. DATE
Exhibit A Page 12 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
1 2
H. DATE
12/4/2024
NAVCRANECEN
JEBLC
F. CONTRACTOR
3. SUBTITLE
NAVCRANECEN
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A013
2. TITLE OF DATA ITEM
Accident Prevention Plan
6. REQUIRING OFFICE4. AUTHORITY
OT-24206
5. CONTRACT REFERENCE
Para. 4.1, Para. 4.6, Appendix E
a. ADDRESSEE
10. FREQUENCY
ONE/R
14. DISTRIBUTION9. DISTRIBUTION
STATEMENT
Physical Copy
ElectronicSee Block 16
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
15. TOTAL
16. REMARKS
ACCIDENT PREVENTION PLAN:
Provide an Accident Prevention Plan (APP) written by the contractor for the specific work and hazards of the contract and in accordance with blocks 4 and 5. Submit a minimum of 15 business days prior to Pre-installation Conference, but no later than 25 business days prior to mobilization should the conference be delayed.
NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
Prior to submission of the APP, the contractor and subcontractors shall meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.
The APP should contain blank sign in sheets for the briefings held prior to each unique feature of work. A hardcopy of the APP shall be present on the worksite at all times.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government acceptance required prior to mobilization at site and crane shipment.
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
Exhibit A Page 13 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
1 2
H. DATE
12/4/2024
NAVCRANECEN
JEBLC
F. CONTRACTOR
3. SUBTITLE
NAVCRANECEN
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A016
2. TITLE OF DATA ITEM
Property Transfer Verification
6. REQUIRING OFFICE4. AUTHORITY
DI-MISC-80678, para 10.3.2
5. CONTRACT REFERENCE
Para. 4.1, Para. 4.12
a. ADDRESSEE
10. FREQUENCY
ONE/R
14. DISTRIBUTION9. DISTRIBUTION
STATEMENT
Physical Copy
ElectronicSee Block 16
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
15. TOTAL
16. REMARKS
PROPERTY TRANSFER VERIFICATION:
Provide Property Transfer Verification in accordance with blocks 4 and 5 submitted at crane acceptance.
Property Transfer Verification shall be completed on NCC-provided 'Property Transfer Form' with printed name, phone number, signature and date received provided by both the Contractor Representative and Supported Command Representative.
NAVCRANECEN will determine acceptability within 2 business days after receipt. All subsequent Government review periods shall be complete within 1 business day of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation under 'Property Transferred' section along with a description of the items provided.
Note: Government approval is required prior to crane acceptance.
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
Exhibit A Page 14 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 0 0
0 1
H. DATE
12/4/2024
NAVCRANECEN
JEBLC
F. CONTRACTOR
3. SUBTITLE
NAVCRANECEN
Form Approved OMB No. 0704-0188
C. CATEGORY
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO.
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO.
A017
2. TITLE OF DATA ITEM
Conference Minutes
6. REQUIRING OFFICE4. AUTHORITY
DI-ADMIN-81250B
5. CONTRACT REFERENCE
Para. 2.5.1, Para. 2.5.2, Para. 4.1
a. ADDRESSEE
10. FREQUENCY
ASREQ
14. DISTRIBUTION9. DISTRIBUTION
STATEMENT
Physical Copy
ElectronicSee Block 16
11. AS OF DATE
12. DATE OF FIRST SUBMISSION
13. DATE OF SUBSEQUENT SUBM.
See Block 16
15. TOTAL
16. REMARKS
POST-AWARD CONFERENCE MINUTES:
The contractor shall prepare and submit meeting minutes for the Post-Award Conference. Provide data in accordance with blocks 4 and 5 within 5 business days after conference.
PRE-INSTALLATION CONFERENCE MINUTES:
The contractor shall prepare and submit meeting minutes for the Pre-Installation Conference. Provide data in accordance with blocks 4 and 5 within 5 business days after conference.
NAVCRANECEN will determine acceptability within 5 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
G. PREPARED BY
Brittany Copeland
I. APPROVED BY
Christopher Halligan
Exhibit A Page 15 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 0 1
0 2
H. DATE
12/4/2024
CONTRACT DATA REQUIREMENTS LIST Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A018 Contractor Mobile Crane Entry Package
4. AUTHORITY 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
OT-24206
Para. 4.1, Para. 4.14; Appendix E, Appendix H NAVCRANECEN
9. DISTRIBUTION
STATEMENT
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
ONE/R See Block 16 a. ADDRESSEE Physical Copy
Electronic
13. DATE OF SUBSEQUENT SUBM.
See Block 16
11. AS OF DATE
16. REMARKS NAVCRANECEN
15. TOTAL
G. PREPARED BY I. APPROVED BY
CONTRACTOR MOBILE CRANE ENTRY PACKAGE:
Provide complete contractor mobile crane entry package in accordance with blocks 4 and 5 required by earlier event of either as directed by Appendix H paragraph 10.1 or 5 business days prior to desired entry of a Contractor owned mobile crane to the Government job-site.
The MBH Re-assembly/Installation Plan is a part of this entry package and requires approval prior to inclusion and forwarding of the Contractor Mobile Crane Entry Package to the Supported Command.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval required prior to mobile crane entry inspection.
JEBLC
J. DATE
Brittany Copeland Christopher Halligan 12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
Exhibit A Page 16 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
1 2
H. DATE
12/4/2024
CONTRACT DATA REQUIREMENTS LIST Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A020 Training Course Outline
4. AUTHORITY 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
DI-ILSS-81075 as modified by NCC Para. 4.1, Para. 4.8, Para. 4.8.1 NAVCRANECEN
9. DISTRIBUTION
STATEMENT
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
ONE/R See Block 16 a. ADDRESSEE Physical Copy
Electronic
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
16. REMARKS NAVCRANECEN
JEBLCTRAINING COURSE OUTLINE:
Provide a training course outline in accordance with blocks 4 and 5 a minimum of 10 business days prior to crane shipment. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval required before installation of the crane.
DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
15. TOTAL
G. PREPARED BY I. APPROVED BY J. DATE
Brittany Copeland Christopher Halligan 12/4/2024
Exhibit A Page 17 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
2 2
H. DATE
12/4/2024
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
0001 A
CONTRACT DATA REQUIREMENTS LIST Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A022 Frequency Allocation Application
4. AUTHORITY 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
DI-MISC-80678, para 10.3.2 Para. 4.1, Para. 4.7 NAVCRANECEN
9. DISTRIBUTION
STATEMENT
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
ONE/R See Block 16 a. ADDRESSEE Physical Copy
Electronic
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
FREQUENCY ALLOCATION APPLICATION:
Provide Frequency Allocation Application in accordance with blocks 4 and 5 a minimum of 10 business days prior to shop testing. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval required prior to crane acceptance.
16. REMARKS NAVCRANECEN
JEBLC
DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
15. TOTAL
G. PREPARED BY I. APPROVED BY J. DATE
Exhibit A Page 18 of 25 Rev. 0
LT
8. APPL CODE
A 0 1 1 1
1 2
H. DATE
12/4/2024
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
CONTRACT DATA REQUIREMENTS LIST Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A025 Certification, Public Domain Software
NAVCRANECEN
4. AUTHORITY 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
DI-MISC-80678, DI-AVCS-80700A Para. 4.1, Para. 4.5.6 NAVCRANECEN
9. DISTRIBUTION
STATEMENT
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
ONE/R See Block 16 a. ADDRESSEE Physical Copy
Electronic
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
16. REMARKS
J. DATE
15. TOTAL
G. PREPARED BY I. APPROVED BY
PUBLIC DOMAIN SOFTWARE CERTIFICATION:
Provide certification in accordance with blocks 4 and 5 a minimum of 25 business days prior to shop test. NAVCRANECEN will determine acceptability within 10 business days after receipt. All subsequent Government review periods shall be complete within 5 business days of receipt of resubmission.
The crane serial number, contract number, CDRL number, and CLIN number shall be included on submitted documentation.
Note: Government approval is required prior to shop test.
JEBLC
Brittany Copeland Christopher Halligan 12/4/2024 DD Form 1423-1, JUN 90 Previous editions are obsolete Page 1 of 1
Exhibit A Page 19 of 25 Rev. 0
LT
8. APPL CODE
A
0 1 0 1
1 0 1 0
2 2
H. DATE
12/4/2024
One 100MT Mobile Boat Hoist [N62470-24-R-8005]
CONTRACT DATA REQUIREMENTS LIST Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
0001 A
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Physical Copy
Electronic
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A026 Computer Documentation
NAVCRANECEN
4. AUTHORITY 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
DI-AVCS-80700A
Para. 4.1, Para. 4.5, Para. 4.5.6, Para.
4.5.7, Para. 4.18-4.24 NAVCRANECEN
9. DISTRIBUTION
STATEMENT
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
ONE/R See Block 16 a. ADDRESSEE
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
See Block 16
16. REMARKS
JEBLC
PRE-FINAL SUBMISSION
15. TOTAL
G. PREPARED BY I. APPROVED BY
DD Form 1423-1, JUN 90 Previous editions are obsolete
PRE-FINAL COMPUTER…