This is a Prevailing Wage Determination issued by the State of Maryland Department of Labor, Division of Labor and Industry, for project PJ-610-230-001 located in Anne Arundel County. The project encompasses phased renovation of an existing duty office (approximately 5,288 gross square feet, single-story structure), demolition of an existing garage building, and construction of a new Maintenance Garage at Barrack J of the Maryland State Police. The determination was issued on December 10, 2025, and identifies mandatory prevailing wage rates applicable to all laborers and mechanics employed on the project. The determination is effective through June 2, 2026.
The prevailing wage rates are established under Maryland State Finance and Procurement Article Section 17-201 through 17-226 and are mandatory for the successful bidder and all subcontractors. The determination specifies hourly rates and fringe benefit payments for 72 distinct job classifications, ranging from laborers and equipment operators to skilled trades including electricians, plumbers, carpenters, ironworkers, and roofers. Wage rates vary by classification, with basic hourly rates ranging from $17.00 to $52.71 and fringe benefit payments from $2.24 to $26.64. The prevailing wage rates were derived from the 2025 locality survey for Anne Arundel County. Contractors requiring additional prevailing wage rate classifications beyond those listed may contact the Prevailing Wage Unit at (410) 767-2342 or prevailingwage@dllr.state.md.us.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF MARYLAND
DEPARTMENT OF LABOR
DIVISION OF LABOR AND INDUSTRY
PREVAILING WAGE SECTION
10946 Golden West Drive, Suite 160
Hunt Valley, MD 21031
(410) 767-2342
CLASSIFICATION MODIFICATION
REASON
BORROWED
FROM
FRINGE
BENEFIT
PAYMENT
BASIC
HOURLY
RATE
AD $50.92 $24.61 BALANCING TECHNICIAN
AD $38.80 $15.57 BRICKLAYER
AD $35.89 $14.60 CARPENTER
AD $35.89 $14.60 CARPENTER - SHORING SCAFFOLD BUILDER
AD $35.10 $15.33 CARPET LAYER
AD $32.40 $17.34 COMMUNICATION INSTALLER TECHNICIAN
AD $35.89 $14.60 DRYWALL - SPACKLING, TAPING, & FINISHING
AD $49.50 $21.14 ELECTRICIAN
AD $48.99 $18.89 ELEVATOR MECHANIC
The wage rates to be paid laborers and mechanics for the locality described below is announced by order of Commissioner of Labor and Industry.
It is mandatory upon the successful bidder and any subcontractor under him, to pay not less than the specific rates to all workers employed by them in executing contracts in this locality. Reference: Annotated Code of Maryland State Finance and Procurement, Section 17-201 thru 17-226.
These wage rates were taken from the locality survey of 2025 for Anne Arundel County, issued pursuant to the Commissioner's authority under State Finance and Procurement Article Section 17-209, Annotated Code of Maryland or subsequent modification.
**Note: If additional Prevailing Wage Rates are needed for this project beyond those listed below, contact the Prevailing Wage Unit. Phone: (410) 767-2342, email: prevailingwage@dllr.state.md.us.
Name and Title of Requesting Officer:
Department, Agency or Bureau:
Project Number
PJ-610-230-001
Oz Ozturk - Procurement Officer
MDGS
301 W Preston St., Room 1405 Baltimore, MD 21201
Location and Description of work:
Anne Arundel County: The Project generally consists of the phased renovation of the existing duty office, the demolition of the existing Garage building, and the construction of a new Maintenance Garage at Barrack J of the Maryland State Police and other Work as indicated within the Contract Documents. The renovation work area is approximately 5,288 gross square feet and is a single-story structure.
Determination Number
64252
Date of Issue: Dec 10, 2025
BUILDING CONSTRUCTION
6/2/2026 3:20 PM Page 1 of 4
AD $17.00 510 $2.24 FIREPROOFER - BY HAND
AD $27.00 510 $5.22 FIREPROOFER - SPRAYER
AD $30.21 $10.68 FIRESTOPPER
AD $36.65 $14.61 GLAZIER
AD $40.77 $20.42 INSULATION WORKER
AD $48.25 $21.11 IRONWORKER - FENCE ERECTOR
AD $27.99 $4.58 IRONWORKER - ORNAMENTAL
CR $30.18 $24.09 IRONWORKER - REINFORCING
AD $37.86 $26.22 IRONWORKER - STRUCTURAL
AD $39.50 $17.52 MILLWRIGHT
AD $29.16 $12.01 PAINTER
AD $36.37 $16.21 PAINTER-INDUSTRIAL
AD $37.74 $17.64 PILEDRIVER
AD $20.00 510 $2.24 PLASTERER - MIXER
AD $47.78 $25.93 PLUMBER
AD $35.18 $15.12 POWER EQUIPMENT OPERATOR - BACKHOE
AD $33.23 $15.12 POWER EQUIPMENT OPERATOR - BROOM / SWEEPER
AD $35.18 005 $15.12 POWER EQUIPMENT OPERATOR - BULLDOZER
AD $35.18 $15.12 POWER EQUIPMENT OPERATOR - CONCRETE PUMP
AD $42.00 $19.10 POWER EQUIPMENT OPERATOR - CRANE
AD $42.00 510 $19.10 POWER EQUIPMENT OPERATOR - CRANE - TOWER
AD $35.18 $15.12 POWER EQUIPMENT OPERATOR - DRILL - RIG
AD $35.18 $15.12 POWER EQUIPMENT OPERATOR - EXCAVATOR
AD $35.18 $15.12 POWER EQUIPMENT OPERATOR - FORKLIFT
AD $35.18 $15.12 POWER EQUIPMENT OPERATOR - LOADER
AD $37.24 510 $15.12 POWER EQUIPMENT OPERATOR - MECHANIC
AD $22.00 005 $3.58 POWER EQUIPMENT OPERATOR - ROLLER - ASPHALT
AD $29.60 $15.12 POWER EQUIPMENT OPERATOR - ROLLER - EARTH
AD $33.23 $15.12 POWER EQUIPMENT OPERATOR - SKID STEER (BOBCAT)
AD $38.60 510 $15.75 POWER EQUIPMENT OPERATOR-VACUUM TRUCK
AD $35.10 $15.33 RESILIENT FLOOR
AD $52.71 $14.06 ROOFER/WATERPROOFER
AD $50.92 $24.61 SHEETMETAL WORKER (INCLUDING METAL ROOFING)
AD $45.22 $26.64 SPRINKLERFITTER
AD $47.78 $25.93 STEAMFITTER/PIPEFITTER
AD $45.65 $21.51 STONE MASON
AD $28.85 $12.85 TILE & TERRAZZO FINISHER
AD $34.34 $14.50 TILE & TERRAZZO MECHANIC
AD $26.73 005 $7.65 TRUCK DRIVER - DUMP
AD $26.25 025 $7.60 TRUCK DRIVER - FLATBED
AD $31.50 027 $9.19 TRUCK DRIVER - LOWBOY
LABORER GROUP II
AD $21.34 $6.90 LABORER - ASPHALT RAKER
AD $21.34 $6.90 LABORER - COMMON
6/2/2026 3:20 PM Page 2 of 4
These Informational Prevailing Wage Rates may not be substituted for the requirements of pre-advertisement or onsite job posting for a public work contract that exceeds $250,000 in value and either of the following criteria are met: (1) the contracting body is a unit of State government or an instrumentality of the State and there is any State funding for the project; or (2) the contracting body is a political subdivision, agency, person or entity (such as a county) and the
State funds 25% or more of the project.
Modification Codes:
(AD) 17-209 Annual Determination from Survey Wage Data Received (CH) 17-211 Commissioners’ Hearing (CR) 17-208 Commissioners’ Review (SR) 17-208 Survey Review by Staff
Each "Borrowed From" county is identified with the FIPS 3-digit county code unique for the specific jurisdiction in Maryland.
For additional information on the FIPS (Federal Information Processing Standard) code, see http://www.census.gov/datamap/fipslist/AllSt.txt
AD $21.34 $6.90 LABORER - CONCRETE PUDDLER
AD $21.34 $6.90 LABORER - CONCRETE TENDER
AD $21.34 $6.90 LABORER - CONCRETE VIBRATOR
AD $21.34 $6.90 LABORER - DENSITY GAUGE
AD $21.34 $6.90 LABORER - FIREPROOFER - MIXER
AD $21.34 $6.90 LABORER - FLAGGER
AD $21.34 $6.90 LABORER - GRADE CHECKER
AD $21.34 $6.90 LABORER - HAND ROLLER
AD $21.34 $6.90 LABORER - JACKHAMMER
AD $21.34 $6.90 LABORER - LANDSCAPING
AD $21.34 $6.90 LABORER - LAYOUT
AD $21.34 $6.90 LABORER - LUTEMAN
AD $21.34 $6.90 LABORER - MORTAR MIXER
AD $21.34 $6.90 LABORER - PLASTERER - HANDLER
AD $21.34 $6.90 LABORER - TAMPER
LABORERS GROUP I
AD $27.68 $6.78 LABORER - AIR TOOL OPERATOR
AD $27.68 $6.78 LABORER - ASPHALT PAVER
AD $27.68 $6.78 LABORER - BLASTER - DYNAMITE
AD $27.68 $6.78 LABORER - BURNER
AD $27.68 $6.78 LABORER - CONCRETE SURFACER
AD $27.68 $6.78 LABORER - HAZARDOUS MATERIAL HANDLER
AD $27.68 $6.78 LABORER - MASON TENDER
AD $27.68 $6.78 LABORER - PIPELAYER
AD $27.68 $6.78 LABORER - SCAFFOLD BUILDER
Incidental Craft Data: Caulker, Man Lift Operator, Rigger, Scaffold Builder, and Welder receive the wage and fringe rates prescribed for the craft performing the operation to which welding, scaffold building, rigging, operating a Man Lift, or caulking is incidental.
6/2/2026 3:20 PM Page 3 of 4
The Prevailing Wage rates appearing on this form were originally derived from Maryland’s annual Wage Survey. The Commissioner of Labor & Industry encourages all contractors and interested groups to participate in the voluntary Wage Survey, detailing wage rates paid to workers on various types of construction throughout Maryland.
A mail list of both street and email addresses is maintained by the Prevailing Wage Unit to enable up-to-date prevailing wage information, including Wage Survey notices to be sent to contractors and other interested parties. If you would like to be included in the mailing list, please forward (1) your Name, (2) the name of your company (if applicable), (3) your complete postal mailing address, (4) your email address and (5) your telephone number to PWMAILINGLIST@dllr.state.md.us. Requests for inclusion can also be mailed to: Prevailing Wage, 1100 N. Eutaw Street - Room 607, Baltimore MD 21201-2201.
6/2/2026 3:20 PM Page 4 of 4