This is a Supplementary General Conditions document for the Mopac Print Shop Upgrades Services contract opportunity in Texas. The document outlines two primary contractual requirements that the contractor must satisfy during the contract term.

The contractor is required to obtain and maintain umbrella liability insurance coverage equal to one hundred percent (100%) of the total contract sum, including any selected alternate pricing amounts. This umbrella coverage must be at least as broad as the primary liability coverages and apply in excess of and follow form of those primary coverages. The policy must include "drop down" coverage provisions to ensure protection when underlying primary insurance coverage limits are insufficient or exhausted. Additionally, liquidated damages have been established at $660.00 per calendar day, representing the predetermined compensation for any delays or failures in contract performance.

View the file

Other files

File Type Posted
ESBD_468372_1763566429111_Attachment 3- Evaluation Scoring Matrix.docx DOCX document
ESBD_468372_1763566734172_Attachment 13- Substitute W-9 Instructions.pdf PDF
ESBD_468372_1763566717243_Attachment 12-Progress Assessment Report.xls XLS spreadsheet
ESBD_468372_1763566297325_3202600107 RFP.pdf PDF
ESBD_468372_1763566451408_Attachment 4- Proposal Submission Checklist .docx DOCX document
ESBD_468372_1763566833544_Form 4-Financial Questionnaire.docx DOCX document
ESBD_468372_1763566798243_Form 2 - Cost Proposal.docx DOCX document
ESBD_468372_1763566814723_Form 3- Past Project Performance.pdf PDF
ESBD_468372_1763566880526_Form 6-Substitute W-9 Direct Deposit Form.docx DOCX document
ESBD_468372_1763569019911_ESBD Notification-3202500107 Instructions to Respondents.docx DOCX document
ESBD_468372_1763566699146_Attachment 11- Overview of Progress Assessment Report (PAR).pdf PDF
ESBD_468372_11192025v947_Attachment 7- Project Drawings.pdf PDF
ESBD_468372_11192025v948_Attachment 8- Project Manual.pdf PDF
ESBD_468372_1763566777661_Form 1-Execution of Response.docx DOCX document
ESBD_468372_1763566654514_Attachment 9-Asbestos Documents.pdf PDF
ESBD_468372_1763566910754_Form 7-HUB Subcontracting Plan HSP.pdf PDF
ESBD_468372_1763566488259_Attachment 6- Prevailing Wage Scale.txt TXT text file
ESBD_468372_1763566384526_Attachment 2-Uniform General Conditions.pdf PDF
ESBD_468372_1763566861959_Form 5-Title Page.pdf PDF
ESBD_468372_1763566673897_Attachment 10- HSP Subcontracting Plan Guide.pdf PDF
ESBD_468372_1763566297611_Attachment 1- T&C Architect & Engineer Version (07-31-25).pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 5 - Supplementary General Conditions

1. “Umbrella” Liability Insurance. Contractor must obtain, pay for and maintain umbrella liability insurance during the Contract term, insuring Contractor (or Subcontractor) for the amount equal to one hundred percent (100%) of the Contract Sum (total awarded Contract), including any selected alternate pricing amounts, that provides coverage at least as broad as and applies in excess and follows form of the primary liability coverages required hereinabove. The policy must provide “drop down” coverage where underlying primary insurance coverage limits are insufficient or exhausted.

2. Liquidated Damages. Liquidated damages have been determined as $660.00 per Calendar Day.