Enclosure 2 RTO-RTO (Campaign and ELV) 7SEP2023 Final.pdf

PDF 775 KB Posted

Attached to
Wallops Range Contract (WRC) Federal contract opportunity
Solicitation number
80GSFC23R0009FRFP
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document outlines requirements for concurrent range support services for an Expendable Launch Vehicle mission and sounding rocket campaign in 2025. NASA's Wallops Range and Mission Management Office requires range instrumentation, operations, and service support for an ELV launch from Wallops Flight Facility in November 2025 with a 10-day launch window and downrange site in Bermuda, as well as range support for a sounding rocket campaign at Poker Flat Research Range in Alaska from November to December 2025 consisting of two individual rockets launched 30 seconds apart each night during optimum science windows. The contractor shall provide a project manager and personnel to support both missions, traveling to Bermuda and Alaska, utilizing NASA's facilities, instrumentation, and institutional assets defined in the tables provided. The response is due by March 2025, and the period of performance is from March to December 2025.

View the file

Other files for this federal contract opportunity

Other files attached to Wallops Range Contract (WRC), newest first.
File Type Posted
80GSFC23R0009 RFI-6.pdf PDF
80GSFC23R0009 RFI-5.pdf PDF
80GSFC23R0009 - SF33 - 11-27-2023.pdf PDF
80GSFC23R0009 Amendment 003.pdf PDF
80GSFC23R0009 RFI-3.pdf PDF
80GSFC23R0009 Amendment 002.pdf PDF
Attachment A - WRC SOW 9NOV2023.pdf PDF
Enclosure 1 - Phase-in SOW - Rev. 1.pdf PDF
Exhibit A - Cost Plus FF Hybrid CORE 10-6-2023 - Rev. 1.pdf PDF
Exhibit B - WRC Exh RTO Cost - Rev. 1.pdf PDF
Attachment S - OCI-Plan-Data-Requirements - Rev.1.pdf PDF
Plug Numbers for Cost Exhibits A and B - Rev.1.pdf PDF
Plug Numbers for Cost Exhibits A and B.pdf PDF
80GSFC23R0009 RFI-1.pdf PDF
80GSFC23R0009 Amendment 001.pdf PDF
ROC II Contract Historical Data - 2.pdf PDF
ROC II Contract Historical Data - 1.pdf PDF
Exhibit C - PPQ.pdf PDF
Enclosure 2 RTO-Sounding Rocket 46-031 Requirements.pdf PDF
Attachment L - Contract Historical Data.pdf PDF
CBA-2023-222 KBR.pdf PDF
Attachment F - IT Security Management Plan REV.pdf PDF
Final Request for Proposal (RFP) Cover Letter signed.pdf PDF
Enclosure 1 - Phase-in SOW 28MAR.pdf PDF
Attachment Q - DEIA Plan.pdf PDF
IAM AW and KBR - ROC II - Fully Executed CBA - 2022.PDF PDF
CBA-2023-223 Saalex Solutions Inc..pdf PDF
CBA-2023-224 Rothe Enterprises Inc..pdf PDF
Attachment A-WRC SOW_GO_Chem 11SEP2023FINAL.pdf PDF
Attachment G-533 Attach Core and IDIQ--Both Onsite and Offsite.pdf PDF
Attachment C - IAGP.pdf PDF
WRC - FRFP-80GSFC23R0009 Final.pdf PDF
Exhibit A - Cost Plus FF Hybrid CORE 10-6-2023.pdf PDF
Exhibit B - WRC Exh RTO Cost 9-15-23.pdf PDF
Enclosure 3 - Government WRC QASP.pdf PDF
Enclosure 2 RTO-ELV Requirements.pdf PDF
Attachment S - OCI-Plan-Data-Requirements.pdf PDF
Attachment O - GFP.pdf PDF
Attachment E - Small Business Subcontracting Plan.pdf PDF
Attachment B - Direct Labor Rates_Indirect Rates and Fee.pdf PDF
Attachment N - Contractor Proposed Enhancements.pdf PDF
IAM AW and Saalex- ROC II - CBA -Final (signed).pdf PDF
Attachment K - OCI Avoidance Plan.pdf PDF
Enclosure 4 - IT Security Management Plan Template.pdf PDF
Enclosure 2 RTO-Sounding Rocket 36-360 Requirements.pdf PDF
Attachment R - DEIA Plan.pdf PDF
Attachment P - Requirements Statements List.pdf PDF
Attachment M IT Security Applicable Docs.pdf PDF
Attachment J - DD254 - WRC.pdf PDF
Attachment I - Quality Assurance Plan.pdf PDF
Show all 50

Wallops Range Contract (WRC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enclosure X Representative Task Order

Concurrent Missions: Sounding Rocket Campaign and Expendable Launch Vehicle (ELV)

Background:

In recent years, WFF has demonstrated a unique ability to support diverse missions that are geographically separated but nearly concurrent. An example of this type of mission set is a sounding rocket campaign at

Poker Flat Research Range (PFRR) in Fairbanks, Alaska, consisting of multiple rockets launched almost simultaneously, and an ELV mission launched at WFF.

The NASA Range and Mission Management Office (RMMO) has been tasked with range services and support in multiple areas for both missions. For the sounding rocket campaign, hardware is designed, fabricated, and tested at WFF then shipped to PFRR for final integration, assembly, and launch. RMMO is only responsible for range services in support of the pre-launch testing and launch operations.

For the ELV mission, the payload and launch vehicle are assembled, integrated, tested, and fueled at WFF facilities by the vehicle owner but with some ground and facilities operations support by RMMO, and then launched from the WFF Range with a downrange support site at Bermuda.

Scope:

For the ELV mission, RMMO has been tasked as the range instrumentation, operations, and service provider.

RMMO will support processing and integration facilities utilized by the ELV mission, as well as ordnance storage, fueling facilities, and various operational control centers. The ELV mission will be conducted at

WFF. The mission consists of an ELV rocket carrying a Cygnus spacecraft loaded with cargo to resupply the International Space Station (ISS). RMMO will utilize both on- range and off-range assets to meet the operational support requirements. On-range at WFF, the full spectrum of range support will be required, including pre-launch maintenance and sustainment, pre-mission testing, launch operations, and post-launch data processing and deliverables in the following areas: See attached Range Requirements Document from an ELV mission.

1. Radar services and operations (including tracking and surveillance)

2. Telemetry services and operations

3. Command Destruct services and operations

4. Communications and timing services and operations

5. Meteorological services and operations

6. Surveillance services and operations

7. Data handling services and operations (processing and displays)

8. Optical services and operations (photo and video)

RMMO will also setup a downrange site in Bermuda. In Bermuda, range support will be required including pre-mission testing, launch operations, and post-launch data processing and deliverables in the following areas:

1. Radar services and operations

2. Telemetry services and operations

3. Command Destruct services and operations

For the sounding rocket campaign mission, RMMO has been tasked as the range instrumentation, operations, and service provider. The campaign will be conducted at PFRR in Alaska and consists of two individual sounding rockets (46.031 Terrier Malemute & 36.360 Black Brant) containing payloads to study the aurora. Each rocket will launch 30 seconds apart. See attached Range requirements document.

The WFF Range is required to provide the full spectrum of range support, including pre-mission testing, launch operations, and post-launch data processing and deliverables in the following areas:

1. Surveillance radar services and operations

2. Telemetry services and operations

3. Voice and data communications, timing, and command uplink command services and operations

4. Data handling services and operations (processing and displays)

5. Optical services and operations (photo and video)

6. Meteorological Operations (launch balloon sondes, monitor instrumentation, provide weather forecasts)

For purposes of this RTO, assume that this tasking is received in March of Year 2025.

The ELV launch is scheduled for November (the actual day is still shown as “TBD”) of Year 2025 and the ELV launch window is linked tightly to the ISS operational schedule but is a ten-day window with a specific 5-minute window on each day.. The Contractor is aware the launch dates for ISS Resupply missions have historically varied from the initial schedule.

The sounding rocket campaign mission window opens on November 10 of Year 2025 and, driven by a desire for heliophysics phenomena such as aurora effects, will have a launch window every night until all missions in the series are launched/completed. Optimum science conditions vary annually but are usually expected to begin around

November 10th and, on average, start to diminish at the end of the month, though some years have seen launch windows extend into mid-December.

The concurrent support of both ELV and sounding rocket campaign is required.

Task Parameters:

The following Range instrumentation will be provided by NASA (both mobile and fixed):

1. Telemetry systems

2. Timing systems

3. RF monitoring and communications systems

4. Voice and data communication systems

5. Command systems

6. Radar systems (precision tracking, surveillance, meteorological)

7. Data processing and display systems

8. Meteorological systems

9. Optical systems (photo and video)

10. Power systems

For additional details on Range instrumentation, see tables provided in this document.

NASA will provide all institutional facilities for this effort at no cost to the contractor.

RMMO will provide a Project Manager for the ELV and campaign missions.

Period of Performance

March 01 – December 31, 2025

Travel

Travel to Bermuda to support ELV mission

Travel to Poker Flat Research Range (PFRR) in Fairbanks, AK to support Sounding Rocket campaign.

Applicable Documents

RMMO will provide the following documents at task initiation:

1. Operational Requirements Document

2. Ground Safety Requirements Document

3. Flight Safety Requirements Document

Performance Metrics

IAW Wallops Range Contract (WRC) SOW

Task Deliverables

For this RTO, provide the following:

• A description of the approach that the KTR will use to meet the requirements of the overall task and how that approach will help ensure a successful set of missions in multiple locations.

• Cost Proposal for this scope of work as detailed above.

Special Requirements

N/A

Range Instrumentation

Use the below equipment table for the purposes of assigning assets to the RTO missions. Assets are assumed to be located at WFF unless stated otherwise.

File details come from the government source that posted it. Updated .