Q&A_12.6.2017.pdf

PDF 76 KB Posted

Attached to
Western Region Pavement Preservation Multiple Award Task Order Contract (MATOC)
Solicitation number
DTFH7017R00002
Issued by

View the file

Other files

File Type Posted
Q&A_1.04.2018.pdf PDF
2016-08-16_Mill_Creek_Rd_Br_over_Yellowstone.pdf PDF
A003_Mill_Creek.pdf PDF
Q&A_1.02.2018.pdf PDF
A004_MATOC_RFP.pdf PDF
Q&A_12.21.pdf PDF
Q&A_12.19.2017(2).pdf PDF
A003_MATOC_RFP.pdf PDF
Q&A_12.19.2017.pdf PDF
A002_Mill_Creek.pdf PDF
Q&A_12.11.2017.pdf PDF
A002_MATOC_RFP.pdf PDF
A001_Mill_Creek.pdf PDF
A001_Joshua_Tree.pdf PDF
A001_MATOC_RFP.pdf PDF
Plan_Request_form_Mill_Creek.pdf PDF
RFP_WRPP_MATOC.pdf PDF
RFP_PP_Joshua_Tree.pdf PDF
FINAL_MT_PARK_NF486(1)_Sign-Off_Plans.pdf PDF
JOTR_C6_RipReport.pdf PDF
RFP_Mill_Creek.pdf PDF
CA_Death_Valley_PROJECT_DESCRIPTION.pdf PDF
MT_Mill_Creek_PROJECT_DESCRIPTION.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project: Western Region Pavement Preservation MATOC

# General Technical Question Answer Date 1 x Please verify no written notice to the CO stating the reason to not bid a Task Order is required for the MATOC RFP.

Offerors are not required to submit a written notice to the CO stating the reason for declining a project on the initial MATOC TO‐RFPs.

12/5/17

2 x

Does “headquarters” on page M‐5 of the MATOC RFP refer to contractor’s headquarters or contracting agency headquarters?

“headquarters” is referring to contractor’s headquarters.

12/5/17

3 x

Does submission requirement ii, page M‐5 of the MATOC RFP, have to follow requirement i of “75 miles from headquarters”?

No 12/5/17

4 x

There is a discrepancy in the point system for Factor 2 of the MATOC RFP. Factor 2 states that all subfactors are equal to 90 points, but all subfactors combined equal 100. Please clarify how many points Factors 2 and Subfactors of Factor 2 are.

An error was made, which will be corrected via an Amendment to the MATOC. Factor 2 is worth 100 points. Subfactor 1 is 30, Subfactor 2 is 40, Subfactor 3 is 10, and Subfactor 4 is 20.

12/5/17

5 x

On page L‐5, the MATOC RFP references “bound volumes”, can you clarify if the envelope is considered bound or shall the contractor bind together contents within the envelope.

Each original and each copy of the Volume must be bound separately. The envelope is not considered bound.

12/5/17

6 x

Referencing page L‐5 on the MATOC RFP, shall the five copies required for volume 1 be submitted within volume 1’s envelope or have their own separate envelope titled the same with “original” and “Copies”?

Offerors may choose to submit the original and separate copies in different envelopes or can submit them in one envelope.

Original and copy submittals must be independently bound.

12/5/17

Check General or Technical

7 x 8 x 9 x

File details come from the government source that posted it.