MT PARK 2013(1)B Gardiner Gateway, Phase 2 Federal contract opportunity
Solicitation number
DTFH70-15-R-00014
Issued by
Department of Transportation Federal Highway Administration

About this file

Amendment A002

View the file

Other files for this federal contract opportunity

Other files attached to MT PARK 2013(1)B Gardiner Gateway, Phase 2, newest first.
File Type Posted
A001_Gardiner_Gateway.pdf PDF
Q A_for_posting_on_FBO.pdf PDF
Q A_for_posting_on_FBO.pdf PDF
Q A_for_posting_on_FBO.pdf PDF
RFP_GardinerGateway.pdf PDF
Plan_Request_form_GardinerGateway.pdf PDF
Park_2013_1B_XS_Combined_all.pdf PDF
Plans_Gardiner_Gateway.pdf PDF
Final-Gardiner_Hydraulics_Report-combined-1r.pdf PDF
Earthwork-data-listing-all.pdf PDF
Geotechnical_Report_06-14.pdf PDF
SWPPP_Gardiner_Gateway_Phase_II_MT_PARK_2013(1)B.pdf PDF
Preliminary-Letter_MT_Park_2013(1)B.pdf PDF
PROJECT_DESCRIPTION_MT_PARK_20131(B).pdf PDF
Park_2013_1B_95_.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A002 02/19/2016 N/A MT PARK 2013(1)B

Gardiner Gateway, Phase 2

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

DTFH70-15-R-00014

9B. DATED (SEE ITEM 11)

02/19/2016

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A

D OTHER (Specify type of modification and authority) N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

MT PARK 2013(1)B, Gardiner Gateway, Phase 2

See page 2 for revisions.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Amendment No. A002, dated 02-19-16 MT PARK 2013(1)B Solicitation No. DTFH70-15-R-00014 Gardiner Gateway, Phase 2

REVISIONS ARE AS FOLLOWS:

SPECIAL CONTRACT REQUIREMENTS

Page F-57, 626.05A Tree protection fence. Revises the height of the woven wire fence and protection of the installed trees with the 47” woven wire fence anchored with t-posts.

Page G-11, 710.02 Woven Wire. Adds the material specifications and for woven wire fabric.

Page Section/Table Revision F-57 626.05A Tree protection fence Revises height of woven wire fence and anchoring with t-posts.

G-11 710.02 Woven Wire Adds material specifications for woven wire fabric.

PLANS

Plan Sheet G.9 Revises the rebar size from #9 to #4.

Plan Sheet G.10 Revises the rebar size from #9 to #4

ENCLOSURES

Pages:

F-57, G-11

Plan Sheets:

G.9, G.10

F-57

Special Contract Requirements Project: MT PARK 2013(1)B, Gardiner Gateway, Phase 2

(d) Cover exposed roots with soil, leaving no airspace.

626.05A Tree protection fence. (Added Subsection).

Protect all installed trees with a 6-foot 47 inch tall woven wire fence anchored by t-posts.

626.06 Excavation for Plant Pits and Beds. Delete the text of this Subsection and substitute the following:

(b) Depth of excavation.

Dig the pits to a depth of 3 feet.

626.07 Setting Plants. Amend as follows:

Delete the text of the first sentence of the second paragraph of this Subsection and substitute the following:

Use manufactured topsoil for the backfill.

Add the following:

Do not plant salvaged trees until inspected and approved by the CO. Do not transplant trees when the temperatures are below 32° Fahrenheit.

626.13 Plant Establishment Period. Delete the text of the first sentence of the first paragraph of this Subsection and substitute the following:

The plant establishment period is a one-year period between spring to spring after completion of the project.

626.14 Acceptance. Add the following:

Material for tree protection fence will be evaluated under Subsections 106.02 and 106.03.

Construction and erection of tree protection fence will be evaluated under Subsections 106.02 and 106.04.

Measurement

626.15 Add the following:

Do not measure manufactured topsoil used for work in this Section for payment.

Do not measure tree protection fence for payment.

Revised by Amendment A002

G-11

Special Contract Requirements Project: MT PARK 2013(1)B, Gardiner Gateway, Phase 2

Section 710. — FENCE AND GUARDRAIL

710.02 Woven Wire. Delete the text of this Subsection and include the following:

Furnish Design 1047-6-11 galvanized fabric conforming to AASHTO M 279 or aluminum coated fabric conforming to ASTM A 584.

710.04A T-Post. (Added Subsection).

Provide a steel post with the following characteristics:

1-1/2-inch minimum width;

6-feet tall;

Corrosion resistant protection; and

Includes an anchor plate.

Revised by Amendment A002

NO SCALE

PLAN VIEW

C e n tu r y L in k B u il d in g

Century Link Building

A

A

SECTION A-A

(Sheet 1 of 2)

A

PLAN VIEW

A

SECTION A-A

PROPERTY 069 PROPERTY 048

G.9

STATE PROJECT

NUMBER

SHEET

MT

PARK 2013(B)

A

M

D e c e m b e r

I n t_ ft

D c m y fi le s p w p r o d u c ti o n d m t-b g j.

d g n

S J a c k s o

B

K u n ih is a

C h e c k e d b y

D e s ig n e d b y

STAIR DETAILS

NOTE:

2% (max.)

7'-2"

#4 Rebar, 12" O.C.

2'-6"

5'-0"

5'-0"

.2

10"

S te p s

Sidewalk, concrete Sidewalk, concrete

Sidewalk, concrete Sidewalk, concrete

S te p

5'-4"

4'-4"

2'-6" 6" Bed course 7

.2

6" Bed course

10"

.2

#4 rebar, 12' O.C

#4 Rebar, 12" O.C

#4 Rebar, 12" O.C

1.

otherwise provide 2" minimum clearance.

Provide 3" minimum clearance for rebar adjacent to soil, 10"

12" O.C #4 Rebar, Revised by Amendment A0022

NO SCALE

STAIR DETAILS

G.10

STATE PROJECT

NUMBER

SHEET

MT

PARK 2013(B)

A

M

D e c e m b e r

I n t_ ft

D c m y fi le s p w p r o d u c ti o n d m t-b g m .d g

S

J a c k s o

B

K u n ih is a

C h e c k e d b y

D e s ig n e d b y

A A

PLAN VIEW

SECTION A-A

PROPERTY 007

(Sheet 2 of 2)

4'-6"

4'-6"

Sidewalk, concrete

Landing

3'-2"

6" Bed course

.2

Landing

#4 Rebar, 12" O.C

12" min.

3"

10"

#4 Rebar, 12" O.C Match elevation of stair below doorway landing

NOTE:

1.

otherwise provide 2" minimum clearance.

Provide 3" minimum clearance for rebar adjacent to soil, See Sheet F.5 for details.

Stone masonry rock wall.

4'-6" 4'-2"

5 Steps 4'-6"

Revised by Amendment A0022

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
A002