ATTACHMENT J - CWBS.pdf
PDF 141 KB Posted
- Solicitation number
- DRFP-NEON-SMBA-2025
About this file
This document is a Contractor Work Breakdown Structure (CWBS) for the Near Earth Orbit Network (NEON) Sounder for Microwave-Based Applications (SMBA) project, dated December 2024. The CWBS establishes a product-oriented framework for reporting program cost, schedule, and technical performance, providing a logical subdivision of project work across multiple levels of detail.
The document outlines a hierarchical structure with four levels of work breakdown, including Level 1 (total contract effort), Level 2 (major contract activities like Engineering Unit, Flight Models, Task Orders, and Mission Operations), Level 3 (specific work content such as Program Management, Systems Engineering, Mission Assurance, Hardware/Software, Integration & Test, Ground Support Equipment, and Launch/Post-Launch Testing), and Level 4 (contractor-defined detailed work descriptions). The CWBS is designed to support uniform planning, reporting status, program visibility, and assignment of responsibilities across the NEON SMBA project's comprehensive scope of work.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Near Earth Orbit Network (NEON)
Sounder for Microwave-Based Applications
(SMBA)
Contractor Work Breakdown Structure
(CWBS)
December 2024
Prepared by:
Tonya Eckert
NEON Deputy Project Manager/Resources
Approved by:
Roger Clason
NEON Series-1 Project Manager
Attachment J: Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary
1. DESCRIPTION / PURPOSE
The CWBS establishes a product-oriented framework for reporting program cost, schedule, and technical performance and provides a basis for uniform planning, reporting status, program visibility, and assignment of responsibilities. Additionally, the CWBS provides a product-oriented logical subdivision of hardware, software, services, facilities, etc., that contribute to and/or make up the total project scope of effort and work. The CWBS dictionary provides a narrative description of the work tasks and effort to be performed in each CWBS element.
2. PREPARATION INFORMATION
Contents:
The CWBS and CWBS dictionary are two distinct project documents used for defining the approved project scope of work. The contents of each document are detailed in the following paragraphs:
CWBS – A logical, hierarchical display of the subdivision of all project work to be completed.
The CWBS shall include the approved element title and element number.
CWBS dictionary – The CWBS dictionary shall briefly describe and document the work content of every CWBS element and relevant efforts associated with each element (e.g., design, development, and manufacturing).
The CWBS levels shall be governed by the Following. The actual letter and number designations can be adapted to meet the needs of the Contractor’s systems
Level 1 - Total contract effort
Level 2 Definitions: Major contract activity as described below
A. Engineering Unit / Non-Recurring Activities – All effort to plan and manage the design of the instrument including detailed design activities, design reviews, risk reduction (engineering models, etc), software development, ground support equipment (GSE) development, verification planning, etc.
B. Flight Model (FM) -1 – All effort related to fabrication, assembly, test, launch operations and on-orbit testing of the satellite
C. FM-2
D. FM-3
E. FM-4
F. FM-5
G. FM-6
H. FM-7
I. FM-8
J. Task Orders K. Mission Operations - Long term mission support including any management, business management support, systems engineering etc that is not unique to a particular mission
Level 3 Definitions (Note: X denotes the Level 2 Contract Activity) – the work content as described is not necessarily all inclusive.
X.01 Program Management – Including program leadership, resource management, program planning (schedule), data management, configuration management, support for major design reviews X.02 Systems Engineering - Including system engineering leadership, interface management (instrument, launch vehicle, ground), system specification definition and flow-down, verification planning, system level analysis and modeling
X.03 Mission Assurance - Including mission assurance leadership, quality engineering, subcontract surveillance, safety, reliability, parts and materials management
X.04 Hardware / Software – All subsystem hardware and software effort including parts and materials which should be accounted for in a separate line. Effort included in each level 2 WBS
X.05 Integration & Test - Including instrument baseline testing and environmental testing and post environment test activities including instrument packing and shipping.
X.06 GSE – design, fabrication, procurement assembly, test and maintenance of electrical, mechanical GSE and mission simulation and GSE software
X.07 Post Delivery Support (PDS) – Any support required after the Pre-Ship Review/Pre- Storage Review including satellite integration and testing and if needed storage costs or testing during storage prior to shipping to spacecraft vendor
X.08 Launch and Post Launch Testing– support for pre-launch planning, launch site support, support for mission unique or special launch services, launch-vehicle integration (spacecraft portion), and the first 6 months of post-launch testing prior to the handoff to NOAA.
X.09 Task Orders X.10 Long Term Support – Long term mission support including any management, business management support, systems engineering etc. that is not unique to a particular mission
Level 4 – The Contractor shall define WBS level within each level 3 and provide a brief description of the work content.
| Near Earth Orbit Network (NEON) |
| Attachment J: Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary |