Draft Technical Exhibit for room installation timeframe.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Draft Request for Proposal (RFP) for Enterprise Classroom Program (ECP)
Solicitation number
W911S024R0005
Issued by

About this file

This document contains a draft request for proposal for an enterprise classroom program contract opportunity and a related technical exhibit. The draft RFP seeks proposals for a single award indefinite delivery/indefinite quantity contract as an 8(a) small business set-aside to provide turnkey classroom sustainment and technology services. The contract would have a one-year base period and two one-year options and utilize firm-fixed price contract line items. The technical exhibit outlines timelines and tasks for various classroom installation types, including basic lecture, enhanced lecture, collaboration, and simulation rooms, with timeframes ranging from 120 to 300 days per room plus 15 days for final documentation preparation. Installation planning and preparation tasks cover areas such as site surveys, requirements documentation, equipment design, installation schedules and logistics, testing, training and final deliverables submission.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Classroom Type# days to complete
Basic Lecture105 + 15 for final doc prep = 120 dyas

Standard Lecture 105 + 15 for final doc prep = 120 dyas

Enhanced Lecture 165 + 15 for final doc prep = 180 dyas

Colaboration 285 + 15 for final doc prep = 300 dyas

Simulation 285 + 15 for final doc prep = 300 dyas

Typical timeline/events for technology refresh/upgrade

Project Start
Charter0.5
Installation/School Kick Off Meeting0.5
Requirements
Site Survey5
Site Survey Trip Report1
Site Survey Trip Report - ECP Approved (w/in 10 days)1
Requirements Matrix
RAD5
RAD - Peer Review2
RAD - School Approved2
RAD - ECP Approved1
EDP
EDP Construction5
EDP - Peer Review5
EDP - School Approved2
EDP - ECP Approved (w/in 45 days RAD approval)5
EDP MEL signed by Engineer1
Installation Planning
Install SOW to Contracts1
Kick-Off Deck Received from Contracts1
Kick Off Meeting1
Material Ordered/Received3
Install Schedule Planning1
Install Travel Request - approved (3 weeks prior to install)1
Install Travel Request - COR Approved1
Installation Preparation
Ship Instructor Computer to School
(30 days prior)5
Pre-Install Meeting w School POC & Team (2 weeks prior to install)1
A/V Control Processor Customization3
Equipment Inventory List (10 days prior to install)1
Pre-Fabrication Testing3
Pre-Fab QA/QC - Loaded on SharePoint3
Pre-Fab QA/QC - ECP Approved1
Installation5 days per room
Quality Check1
Onsite QA/QC - School Approved1
End User Training Complete - School Approved3
Project installation complete room ready for use75+
Final Documentation Preparation
Uplaod List of Material (LOM)within 5 days of installation completion
Upload List of Software (LOS) N/Awithin 5 days of installation completion
Uplaod A/V Control Processor Codewithin 5 days of installation completion
Uplaod EDP As-Builtwithin 10 days of installation completion
Uplaod Rev C As-Built Drawingswithin 10 days of installation completion
Upload Electrical Task List (in EDP)within 10 days of installation completion
Uplaod Operator Manual (Equipment Manuals w LOM)within 10 days of installation completion
Uplaod Source and Compiled Code (same as 7.3)within 10 days of installation completion
Uplaod Warrantieswithin 10 days of installation completion
Uplaod Photographswithin 10 days of installation completion
Uplaod Training Manualwithin 10 days of installation completion
Uplaod QA/QC Checklistwithin 10 days of installation completion
Uplaod Site Surveywithin 10 days of installation completion
Uplaod Final Deliverables - ECP Approvedwithin 10 days of installation completion
Final Deliverables - Contracts notifiedwithin 10 days of installation completion
Project Complete95+