Decision_Matrix.v2_2026-4-17.pdf

PDF 33 KB Posted

Attached to
102" Anacostia Trunk Sewer Rehabilitation Phase 2 - Progressive Design-Build
Solicitation number
106580
Issued by
Prince George's County, Maryland

About this file

This is a Decision Matrix evaluation document for the Washington Suburban Sanitary Commission (WSSC Water) in Maryland for the 102-Inch Anacostia Trunk Sewer Rehabilitation Phase II Progressive Design-Build (PDB) project. The project involves the design and construction of sewer rehabilitation services for a major trunk sewer located in Lower Anacostia, Prince George's County, Maryland. Sealed proposals must be submitted via WSSC's eProcurement Portal prior to 2:00 pm on Tuesday, June 23, 2026. The evaluation matrix allocates points across 12 weighted criteria categories to assess qualified respondents' qualifications and proposed approaches for this large-scale infrastructure project.

The evaluation framework distributes 100 points across four primary categories: DB Team Experience (25%), Key Team Members Qualifications & Experience (20%), Project Management (15%), and Understanding, Approach, Schedule (35%), with an additional 5% allocation for Cost/DB Team Fee. Minimum qualifications include at least 10 years of Design-Build delivery experience with two or more completed PDB projects, completion of at least five similar sewer rehabilitation projects, and at least one project involving a 72-inch or larger sewer of 5,000 feet or longer. Respondents must provide five owner references from past DB or PDB projects and demonstrate key staff experience on large-scale sewer rehabilitation projects. Evaluation criteria also emphasize integrated team history, conflict resolution strategies, innovative methods, transparent GMP development processes using open-book methods, detailed project scheduling, risk allocation strategies, and comprehensive communication plans that maintain stakeholder engagement throughout design and construction phases.

View the file

Other files

File Type Posted
102"_Anacostia_Trunk_Sewer_Rehabilitation_Phase_2_-_Progressive_Design-Build_(Addendum_#9_Revision).pdf PDF
106580_PreBid_Slidedeck_5.26.26.pdf PDF
102-Inch_Anacostia_Pre-Meeting_-_Attendance_report_5-26-26.pdf PDF
Exhibit_C:_Table_C1.pdf PDF
102_ATS_-_TM_-_Condition_Assessment.pdf PDF
Scope_of_Work.pdf PDF
Draft_Agreement.pdf PDF
WSSC_WW_Engineering_BOA_-_TO1_ATS_Condition_Assessment_Briefing.pdf PDF
Special_Conditions_Construction_Prevailing_Wage.pdf PDF
WSSC_Anacostia_Trunk_Sewer_CA_Report_Appendices_DRAFT.pdf PDF
Supplementary_Conditions.pdf PDF
General_Conditions.pdf PDF
WSSC_Anacostia_Trunk_Sewer_CA_Report_Appendices_DRAFT_2024-06-25.pdf PDF
102_ATS_-_TM_-_Condition_Assessment_040219.pdf PDF
Part4-Agreement-3.26.2026_(1).pdf PDF
PDB_Team_Qualifications_(2).pdf PDF
Part1-Addl_Instructions-WSSC-4.21.26_(2).pdf PDF
Pricing_Sheet_(2).pdf PDF
Part3-SupplementaryConditions-3.26.2026_(1).pdf PDF
Evaluation_Team_(1).pdf PDF
Table_C1-4.12.26_(1).pdf PDF
Part2-GeneralConditions-3.26.2026_(1).pdf PDF
Evaluation_Factors_(1).pdf PDF
Mid-Atlantic_Purchasing_Team_Intergovernmental_&_Cooperative_Purchasing_Clause.pdf PDF
#124841_102inch_Anacostia_Trunk_SR_PH2_Participation_Clark.pdf PDF
WSSC_WW_Engineering_BOA_-_TO1_ATS_Condition_Assessment_Briefing_2024-04-22_(1).pdf PDF
Part6-Scope_of_Work-3.26.2026.pdf PDF
01._RFP+Template_102in_ATS_II-4.01.2026_(3).pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WEIGHT CATEGORY CRITERIA RECOMMENDED THRESHOLD / EXPECTATION SCORING CRITERIA

Years of PDB experience

Firm should have substantial experience with Design-Build (DB) delivery, particularly Progressive DB (PDB). At least 10 years of DB delivery experience with 2 or more completed PDB projects.

1–5 pts = Based on number of DB/PDB projects and complexity of projects

Similar Projects Completed

Firm should have completed at least 5 sewer rehabilitation projects similar in size, scope, and complexity to this project. Preference for firms with additional experience or PDB-specific projects. Must have at least one project for 72" or larger sewer of 5,000 feet or longer.

1–5 pts = Based on number and size and scope of similar projects

Owner References

Firm must provide minimum of 5 references from owners (public or private) on past DB or PDB projects. References should reflect quality, collaboration, and project outcomes.

1–5 pts = Based on quality of references on similar projects

Project Executive, Project

Manager, Design Manager, Construction Manager (Key Staff)

Project Executive, Project Manager, Design Manager, and Construction Manager must have experience leading similar DB/PDB projects. Each should have worked on large-scale sewer rehabilitation projects, preferably 3 or more.

1–5 pts = Based on Key Staff experience with PDB projects

Integrated Team History

Key personnel (PMs, Technical Leads) should have prior experience working together on collaborative DB or PDB projects. Preference for teams with multiple shared DB/PDB projects.

1–5 pts = Based on Firm's experience on shared

DB/PDB projects

Approach to Team Integration

Proposal must provide a strong narrative demonstrating how they integrate with owners, designers, and stakeholders. Past examples of successful collaboration will strengthen the proposal.

1–5 pts = Based on strength, clarity, and relevance of narrative and real-life examples

Conflict Resolution Strategy

Proposals should outline a proactive conflict resolution strategy with real-world examples where disputes were effectively managed and resolved without escalation.

1–5 pts = Based on completeness, relevance, and creativity in past resolution strategies

Project Understanding and

Approach

Proposal should demonstrate a clear understanding of the project scope, constraints, risks, and objectives. Should include a detailed tailored project approach and a discussion of the team's consideration of alternatives and specifically address flow management and minimizing bypass requirements.

1–5 pts = Based on clarity, technical depth, and alignment with project needs

Use of Innovative Methods or

Materials

Firm should propose or plan to evaluate new technologies, project approach, and/or materials that enhance value or performance of overall project.

1–5 pts = Based on creativity, practicality, and potential project value

Cost development

Firm must describe their approach to Guaranteed Maximum Price (GMP) development, including the use of open-book methods and early estimates from similar projects.

1–5 pts = Based on transparency, process, and previous GMP experience

Schedule Development A detailed and efficient project schedule should be proposed, supported by examples of effective schedule management on similar PDB contracts.

1–5 pts = Based on feasibility, alignment with goals, and relevant past performance

Risk Allocation Strategy

Proposal should include detailed risk register that outlines a structured strategy for risk allocation, highlighting shared risk/reward models and methods used to avoid scope or budget overruns.

1–5 pts = Based on clarity, structure, and proven success

Open-Book GMP Experience Firm should describe prior experience with open-book cost estimating and collaborative GMP development with owners.

1–5 pts = Based on demonstration of transparency and efficiency in past GMP processes

Communication Plan Proposal must outline a robust communication strategy that keeps all stakeholders informed throughout design and construction.

1–5 pts = Based on clarity, frequency, and inclusion of feedback loops

5% 7. Cost DB Team Fee 1–5 pts = Prorated over range of lowest to highest

3. Project

Management 15%

4. Understanding, Approach, Schedule 35%

Decision Making Matrix

Anacostia Trunk Sewer - Phase II

4/17/2026

25%

1. DB Team

Experience

2. Key Team Members

Qualifications &

Experience

20%