Attachment 4 - Demonstration Project Statement of Work

Text of this file

HHM402-09-R-0090

Past Performance Questionnaire

ATTACHMENT 4

STATEMENT OF WORK

Provision of Management, Labor, Equipment and Material

For

Supporting the Defense Intelligence Agency

Bolling Air Force Base, Washington, DC 20344

Date:

27 August, 2008 Project Title: Build Mechanical Room Project No.: 1-110102911 Project Engineer: Chris Irby Project Manager: Donald F. Richardson

Quality Assurance: Jerry Gaither Part 1 - General

1.1. Scope: Under the provisions of Contract Number ________________ and in accordance with this Statement of Work (SOW) the contractor shall provide all management, labor, equipment and material necessary to build a new mechanical room and replace existing AHU 52. The delivery order shall require the contractor to furnish all facilities, management, supervision, labor, materials, equipment and supplies, excepting those noted herein as Government Furnished for the accomplishment of the specific task(s) desired by the Government.

1.2. Duration of Project: It is estimated that accomplishing the stated task(s) shall take 120 calendar days to complete. The contractor shall make every effort to complete the project within the time allowed, however, where substantial completion of work would allow beneficial occupancy of the facility, such must occur on or before 31 July 2009. This delivery order shall commence on the date of notice to proceed and continue until the specified date of completion, substantial completion date (where one is specified) or any other date rendered under this contract (Change Clause) and properly modified by the Contracting Officer or his designated representative

1.3. Location of Project: Work required under this Statement of Work shall occur at the Defense Intelligence Analysis Center, Bolling Air Force Base, Washington, DC. Where special permits, approvals or authorities are required at the location of this work, the contractor shall not undertake any work unless and until all permits, approvals or authorities are received and official notification is made by the Contracting Officer.

1.4. Quality Control/Quality Assurance: The contractor’s Quality Control Plan as submitted incident to the award of the overarching contract shall be incorporated by reference herein as though appearing in its entirety.

1.5. Security: The contractor shall be responsible for the security of the work site, his equipment, any Government-issued equipment and/or materials, project materials, tools, vehicles and related items used by the contractor and under his direct control. The contractor assumes all liability for the actions of his employees or those of any subcontractor or tier III entity while engaged in work within any DIA facility.

Part 2 - Government Furnished Property and Services

2.1 None

Part 3 - Specific Tasks

3.1. General: Build new mechanical room and replace existing AHU 52.

3.2. Management: The contractor shall provide qualified management and supervisory staff to accomplish the provision of such services cited within this Statement of Work. Such personnel shall possess appropriate training and experience commensurate with the task requirements, licenses and certifications as may be required for operation of specific tools and equipment. A listing of key management and supervisory staff shall be provided to the Contracting Officer prior to Notice-to-Proceed being issued for any delivery order(s).

3.3. Labor: The contractor shall provide or otherwise contract for all labor, craftsmen, tradesmen and general labor as required to accomplish work called for under this Statement of Work. Such labor shall be trained and possess no less than “apprentice” or “journeyman” certification in skilled trades. The terms and conditions of the original contract shall apply to the provision of labor incorporated by reference as though appearing herein in total.

3.4. Specific Tasks:

Architectural:

As shown in drawing A1 and summarized below:

1. Demolish CMU walls.

2. Move existing door.

3. Build new CMU walls and install door.

4. Modify dropped ceiling as needed.

Mechanical:

As shown in drawings M1 through M5 and summarized below:

1. Demolish ductwork, VAV boxes, diffusers and controls in the phasing order shown.

2. Install new AHU, ductwork, VAV boxes, diffusers and controls in the phasing order shown.

3. Reconfigure existing fresh air ductwork.

4. Provide wet-tap on existing chilled water lines and install new chilled water lines.

5. Install condensate pump and condensate piping.

6. Provide air and water balancing.

7. Modify existing Honeywell control system. Provide new Honeywell DDC controls.

8. Install new smoke detectors on the new AHU and connect to existing Honeywell fire alarm system.

9. Demolish old AHU 52 in Print Plant ceiling. Seal all openings in the Print Plant wall.

10. Commission the new AHU system.

Fire Protection:

Perform sprinkler modifications as shown in drawing FP-1

Electrical:

As shown in drawings E1 through E3 and summarized below:

1. Provide 480 volt, 3 phase circuit for new AHU 52.

2. Install new variable speed drive for AHU 52.

3. Reconfigure lighting fixtures and switching.

4. Reconfigure receptacles.

5. Provide 120 volt circuit for new condensate pump.

6. Demolish existing variable speed drive and circuit.

Part 4 - Submittals Fill in as appropriate

4.1. Construction schedule

4.2. Construction estimate

4.3. One set of marked up as-built drawings (after construction completed).

4.4. Testing and Balancing Reports

4.5. Materials/Equipment

1. Air Handling Unit

2. Condensate Pump

3. Variable Volume Boxes

4. Honeywell controls.

5. Fire sprinkler layout drawing.

6. Variable speed drive.

Fill in as appropriate

Other files

File Type Posted
Amendment 0004.PDF PDF
FINAL LISTING OF QUESTIONS FROM THE PRE-PROPOSAL CONFERENCE HELD March 25 2009.doc DOC document
scan0001.pdf PDF
ADDITIONAL QUESTIONS FROM THE PRE-PROPOSAL CONFERENCE.doc DOC document
Amendment 00020001.pdf PDF
Site Visit Attendance.xls XLS spreadsheet
1-110102911-clean.pdf PDF
Amendment 00010001.pdf PDF
ANSWERS TO THE QUESTIONS FROM THE PREPOSAL CONFERENCE.doc DOC document
DD_254_DD_Form.doc DOC document
FAR 52.232-16.doc DOC document
E3-110102911.pdf PDF
M3-110102911.pdf PDF
M1-110102911.pdf PDF
M2-110102911.pdf PDF
Solicitation —
FP1-110102911.pdf PDF
M5-110102911.pdf PDF
DDOC Spec —
E2-110102911.pdf PDF
Schedule of Material Submittals.pdf PDF
PPQ —
E1-110102911.pdf PDF
M4-110102911.pdf PDF
Past Performance Reference List —
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .