FINAL LISTING OF QUESTIONS FROM THE PRE-PROPOSAL CONFERENCE HELD March 25 2009.doc
DOC document 114 KB Posted
- Attached to
- DIAC Delivery Order Contract - Construction
- Solicitation number
- Not on record
- Issued by
-
Defense Intelligence Agency
About this file
Final answers to questions from the pre-proposal conference.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0004.PDF | ||
| scan0001.pdf | ||
| ADDITIONAL QUESTIONS FROM THE PRE-PROPOSAL CONFERENCE.doc | DOC document | |
| Amendment 00020001.pdf | ||
| Site Visit Attendance.xls | XLS spreadsheet | |
| 1-110102911-clean.pdf | ||
| Amendment 00010001.pdf | ||
| ANSWERS TO THE QUESTIONS FROM THE PREPOSAL CONFERENCE.doc | DOC document | |
| DD_254_DD_Form.doc | DOC document | |
| FAR 52.232-16.doc | DOC document | |
| E3-110102911.pdf | ||
| M3-110102911.pdf | ||
| M1-110102911.pdf | ||
| M2-110102911.pdf | ||
| Solicitation | — | |
| FP1-110102911.pdf | ||
| M5-110102911.pdf | ||
| DDOC Spec | — | |
| E2-110102911.pdf | ||
| Schedule of Material Submittals.pdf | ||
| PPQ | — | |
| E1-110102911.pdf | ||
| SOW | — | |
| M4-110102911.pdf | ||
| Past Performance Reference List | — |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. If multiple contractors are awarded contracts for this project and must compete for individual task orders, would the DIA please indicate how they will evaluate task order proposals in order to allow the contractor(s) without the lowest bid factors the potential to be successful in a task order award. Otherwise, with the standardized price book, it appears that it is the DIA’s intent to award work only to the proposer with the lowest coefficient, thus limiting the remaining contractor(s)’ ability to provide a sustainable program in support of the DIA’s mission.
Answer: DIA will award each delivery order as a best value, considering not only cost but technical approach.
2. Specifications Sections 2.3.2 and 2.3.3 on pages 13 and 14 of 67 indicate the training and materials to be provided to the DIA by the contractor. Is it the DIA’s intent that each awarded contractor provide the full extent of the items listed, or will the responsibility for providing these items be divided among all awarded contractors?
Answer: It's not DIA's intent to have each contractor provide the training. DIA would allow all selected contractors to share the costs of the training or divide the responsibility to conduct the training.
3. Solicitation page 3 of 47 states that ”The Government anticipates the selection of two contractors but reserves the right to select more or less based on actual need. The minimum quantity of work which will be required under this contract during the basic period and which will be initiated by one or more delivery orders will not be less than $250,000 per contract. The maximum dollar value of all awarded contracts shall not exceed $25,000,000 for the basic contract period” ( or Options).
Q: If the DIA will be making two awards or more, will the Bond requirement also be reduced proportionate to the number of awardees. (e.g. $25M -1, $12.5- 2, …)
Answer: Paragraph H-3 (a) states the requirement for bonding. DIA would expect each contractor to provide the full bond amount as indicated in the solicitation - as any single contractor could execute the full amount of the base period and option years.
Q: The Bonding requirements favor a much larger organization; however, this is a set-aside contract for Small Businesses. Given the difficulty of small businesses to obtain this bonding (average annual revenues for small businesses cannot exceed $31M, page 30 of 47), would the DIA consider reducing the bonding requirement to increase the participation by the entire Small Business community?
Answer: Paragraph H-3 (a) states the requirement for bonding. DIA would expect each contractor to provide the full bond amount as indicated in the solicitation - as any single contractor could execute the full amount of the base period and option years.
4. Considering that the above RFI, and especially considering that the unanswered questions of April 1, have significant potential to impact the contractors’ coefficients, would the DIA please consider an extension to allow the DIA responses to be properly analyzed, allowing the contractors to provide the most accurate coefficients in their proposals?
Answer. Amendment #2 to the solicitation extended the date to 21 April, 2009.
5. Will the DIA please provide the CAD files associated with the seed project?
Answer: We will not provide .cadd files. We did provide .pdf files.
6. The scope of work on Page 3 of 67 (Specifications) states the contract could include project locations within 100 miles or in the Capital Region. To assist the proposer in developing a more accurate coefficient, would the DIA please provide a breakdown of the number of projects expected to be assigned in each facility under this contract?
Answer: Geographical area; includes Washington, DC, some counties in Maryland and some counties in Virginia. See Page 13 of 47, paragraph H.5 (a) of the solicitation for a complete listing of the counties.
We do not know the location of future projects at this time as the DIA mission dictates the requirement for projects is very unpredictable. However, based on past DDOC contracts, the majority of the projects will be within the greater Washington, D.C. Metropolitan area.
7. Would DIA please indicate the percentage of projects requiring the TS/SCI clearance level? If projects with varying level of clearance will be assigned under this contract, will the DIA please provide an estimate of the percentage of projects expected under each level of clearance?
Answer: All of the DIAC and Expansion is TS/SCI. IAW Note 4 of the RFP, “The majority of work required will be in SCIF facilities and appropriate clearances will be required IAW the specifications.” Plan on all of the projects requiring the TS/SCI.
8. Page 5 of 67 (Specification) Office Facilities – The DIA indicates that the contractor’s trailer should not to exceed 60’, single width. This trailer size seems small for the staffing and volume of work expected. Would DIA allow a larger trailer to accommodate the necessary staff to successfully meet the requirements of this contract?
Answer: No. There is very limited space available and the area will have to accommodate trailers for each contractor as well as other contractors supporting DIA.
9. Items 1.5.1 and 1.5.3 on page 5 of 67 of the Specifications indicate the contractor is responsible for utility connections. Please provide information regarding what utilities are available and at what distance they are located from the office site?
Answer: The only existing utility that is available at the trailer site is electric. In the past, other contractors have had a chemical toilet with weekly service, and bottled water.
10. The Solicitation indicates that the DIA anticipates the selection of two contractors, or more based on actual need. In the event that an award is made to multiple contractors, how will the work under this contract be distributed among them? Is it the DIA’s intent to compete task orders under this contract? What is the expected distribution of contract value among awarded contractors?
Answer: It is DIA’s intent to compete task orders under this contract. The distribution of task orders is dependent on how well the contractor meets the needs of the requirement for each task order. The only guaranteed value is the yearly minimum of $250,000 per contractor.
11. On page 33 of 47, the Solicitation offers information for submittal of our proposal via mail, and indicates that electronic submittal is acceptable for our Past Performance Questionnaires.
Answer: FedEx or Mail only.
12. Section L, Item III, on page 34 of 37 in the instructions for the Demonstration Project, the Solicitation indicates that the Offeror should apply the “applicable co-efficient” to their estimate. This will result in the Offeror’s price being revealed prior to the evaluation of the Pricing volume. Would the DIA consider instead requiring an estimate for the Demonstration Project utilizing a coefficient of 1.0 for evaluation purposes?
Answer: No. Part of the evaluation is to determine how each contractor understands RS Means and the estimating process.
13. Paragraph 2.1.1 of the Specifications, on Page 7 of 67, indicates that the DIA requires the Offeror to provide two highly qualified personnel in the role of PM and Alternate, holding a P.E. license. Typically under an IDIQ contract of this size, the services of a P.E. are needed only sporadically, and are provided by an external member of the team. Requiring a small business to carry two full-time licensed P.E.s also qualified to serve as the PM and Alternate could present an significant burden on their resource allotment and could substantially increase the cost to the DIA. Would the DIA consider removing this requirement from the PM and allowing the services to be provided by an approved A/E firm on an as-needed task-order basis? If this is not possible, then would the DIA consider allowing the P.E. services to be provided by a member of the contractor’s PMS other than the PM?
Answer: It's DIA requirment that the on site PM and alternate be licensed Professional Engineers (PE).
14. Paragraph 3.4 on pages 28-29 of the Specifications lists several design analysis items (e.g., Civil, Architectural/Structural, Mechanical, Electrical etc.) that are to be included in the coefficient. The cost and unpredictability of the necessity for design analysis will require the contactor to increase its coefficient to account for the possibility of this requirement, thus increasing the cost to the DIA for every task order, whether or not design analysis is required. To reduce both the risk to the contractor and the cost to the Government, would the Government consider removing design analysis from the coefficient and instead including it, as needed, in individual delivery orders? If this is not possible, can the Government provide an estimate of how much of the work will require design analysis for the various disciplines?
Answer. Since DIA has very limited design capability, so, virtually every delivery order will require some level of design. DIA will typically provide concept designs for each delivery order. Not knowing future requirements, DIA can not provide an estimate of how much of the work will require design analysis for the various disciplines.
15. According to Paragraph 3.2 on page 16 of the Specifications, the “concept of the DIAC program provides for 35% design level effort.” To reduce both the risk to the contractor and the cost to the Government, would the Government consider removing 35% design requirement from the coefficient and instead including it, as needed, in individual delivery orders? If this is not possible, in order to assist the Offeror in providing the most cost-effective coefficient, will the Government provide an estimate of the number of task orders that will require this level of design or should the Offeror anticipate in their cost and schedules, the delivery of 35% design documents on all projects under this contract?
Answer. Since DIA has very limited design capability, so, virtually every delivery order will require some level of design. DIA will typically provide concept designs for each delivery order. Not knowing future requirements, DIA can not provide an estimate of how much of the work will require design analysis for the various disciplines.
16. Paragraph 3.2 on page 16 of the Specifications states that “some portions of a design may require up to a 65% to 80% design effort.” Will the DIA provide an estimate of the number of task orders that will require this level of design? To reduce both the risk to the contractor and the cost to the Government, please confirm that the costs associated with this higher level of design will be reimbursable as a separate line item in individual delivery orders?
Answer. Since DIA has very limited design capability, so, virtually every delivery order will require some level of design. DIA will typically provide concept designs for each delivery order. Not knowing future requirements, DIA can not provide an estimate of how much of the work will require design analysis for the various disciplines. DIA would consider allowing appropriate architectural and engineering fees depending on the level of design required.
17. The RFP currently requires a P.E. as a member of the PMS, and as such, the cost of any services associated with these individuals is included in the coefficient. However, additional services may be necessary when the requirements of the SOW for an individual delivery order are outside of the discipline/area of specialty of the contractor’s P.E.s. Please confirm that any additional costs will be reimbursed as a separate line item in the pricing of the delivery order.
Answer: This is considered overhead and should be included in the contractor's coefficient.
18. Paragraph H-5 on page 13 of the RFP states that the Means Facilities Database will be updated at the beginning of each option period. Given the current economic volatility and the likely mid-year award date, would the government consider updating the Means database as updates become available from RS Means?
Answer: Paragraph 3.2.1.2 of Technical Exhibit #3 states: “cost estimates shall be based upon current RS Means Cost data…”. So, quarterly RS Means downloads will be acceptable. Although this implies that the contractor will provide these updates to DIA. Each option period is the beginning of each subsequent year of the contract.
19. Please confirm that Davis Bacon wage decisions will only be updated once each year, at the exercise of the option.
Answer: Confirmed. Davis Bacon wage decisions will only be updated once each year, at the exercise of the option.
20. Item 4.6.4 on page 41 0f 67 of the Specifications indicates that the protection and storage of Government property should be included in the contractor’s coefficient. Please provide further insight as to the nature, frequency and level of effort of this requirement to be included into the contractor’s coefficient. Additionally, please confirm that, should DIA require the moving of substantial amounts of property such as may be included in the SOW for a large-scale renovation project, the cost for a more significant endeavor will be assigned as a line item on a per delivery order basis.
Answer. No, the cost for a more significant endeavor will NOT be assigned as a line item on a per delivery order basis, but will be included in the contractor's coefficient.
21. Volume I, Past Performance Section: A. When addressing past performance evaluation criteria set forth in Section M of the Solicitation, the Offerer shall provide, as a minimum, a past performance reference listing of all of their most recent and relevant past performance data from Federal, State and Local Government contracts from the past three (3) years from date of issuance of this solicitation. This list will be used to confirm the receipt of past performance questionnaires. A sample past performance questionnaire that may assist offerers in organizing the requested information is included in the solicitation as Attachment# 2. Although offerers are not required to use this format, as a minimum all the information identified below shall be addressed in the listing.
Q. Can past performance evaluations be submitted on delivery orders under a TOCC/MATOCC contract or does the contract need to have the evaluation? Answer: Please see section M, Page 43 of the solicitation.
22. If a teaming arrangement is contemplated, provide complete information as to the arrangement including any relevant and current recent past performance information on previous teaming arrangements with the same partner in accordance with the requirements of
Para. I.A. above. Each party to the arrangement must provide a list of past and present relevant contracts and PPQs as specified within this section. Past performance information required by this section shall also be provided for any proposed subcontractors that will be performing a significant portion of the work. The Government may use other past performance information obtained from government offices and commercial sources to assess contractor experience.
Q. Does a subcontract relationship constitute a teaming arrangement?
Answer: Yes, although the prime must adhere to FAR 52.219-14, limitations on subcontracting. Additionally, reference page 3 of the technical specifications.
23. In the TECHNICAL SPECIFICATIONS, 2. CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS AND SERVICES,
2.1. PE 2.1.1. Program Manager (PM). The PM and alternate shall be a licensed professional engineer and maintain a Top Secret/SCI
Clearance or be able to obtain a clearance within 30 days after the contract award date. The solicitation, offer and award does not reference that the prime contractor is to posses or provide documentation that a Facility Clearance is required.
Q. Is proof of a facility clearance required for the prime contractor?
Answer: Yes.
Q. Will the subcontractors personnel need to have a TS/SCI?
Answer: Contractors shall adhere to the security requirements in the performance of this contract – IAW DD Form 254 listed in Section J. The highest classification involved in the performance of this contract is TS/SCI.
24. III. VOLUME III, TECHNICAL PART 2, DEMONSTRATION PROJECT: Utilizing the Demonstration Project Statement of Work, Attachment # 4, and associated Drawings, Attachment # 5, the Contractor shall provide a complete Statement of Work, RS Means cost estimate, associated drawings/sketches, and all other documentation as required by the contract specifications paragraph 3. The demonstration project proposal shall be thorough enough to be evaluated by the government evaluation team. This will be a “typical” project similar to that, which may be issued throughout the duration of this contract. The project is multi-disciplined and covers a wide variety of construction aspects. This submission will become the standard for all future projects upon contract award so attention to detail and conformance with the format listed in the specifications is imperative. For the purposes of the demonstration project the Contractor must use electronic estimating software utilizing current R.S. Means construction cost data. The RS Means City Cost Index will be Washington DC. Any RS Means estimating software format is acceptable; however, as a minimum, the Demonstration Project cost estimate will clearly show the RS Means line item number in CSI format, description of the item, unit of measure, quantity of units required, cost per unit and total cost for all units per line item, city cost index and applicable coefficient.
Q. Can the wage scale for the Build Mechanical Room be provided? We understand that the prime contractor will provide all prices via RS Means (to include correct index). To verify these prices (CSI Division of work), we would like to get backup prices by the subcontractors.
Answer: Please use the appropriate Davis-Bacon Wage Determination for the wage scale for “Build Mechanical Room”. It’s your decision on whether to obtain back up pricing information from sub-contractors.
Q. To develop a Statement of Work (SOW), a site visit is required.
Will a site visit be provided for the demonstration project?
Answer: No, a site visit was conducted on March 25, 2009.
25. 4. IV. VOLUME IV, PRICE: Volume IV, B. Section B Offerers will insert the coefficients for all contract line item numbers (CLINs) 0001AA-4001AA through 0001AF-4001AF. The Government reserves the right to request additional pricing information after receipt and evaluation of proposals.
Q. This section does not clarify if there will be a classified and or a non-classified coefficient. Will there be a classified and non-classified coefficient?
TECHNICAL SPECIFICATIONS Questions:
26. CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS AND SERVICES, 2.1. PERSONNEL, 2.1.1. Program Manager (PM and alternate shall be a licensed professional engineer and maintain a Top Secret/SCI Clearance or be able to obtain a clearance within 30 days after the contract award date.
Q. Please explain why the Program Manger is to be a licensed engineer rather then a engineer? Answer: It’s our requirement that the onsite PM be a licensed Professional Engineer (PE).
Q. If our team has a Licensed A/E, can the A/E serve as the licensed professional engineer to work under a Program Manager (PM) engineer (not licensed)? Note all design documents will be signed/stamped by the A/E of record. Our experience with construction program managers, is the PM has attributes in managing the contractibility, budget, and schedule of a project or a group of projects. The Lic Engineers are professional people that are certifying and validating the designs. Answer: It’s your decision on how you will meet the requirements of the solicitation. However, your management approach will be evaluated as stated in the solicitation, Part IV, pages 43-47.
Q. If the program manger is not a licensed engineer, will this disqualify the contractor or rate lower in this section? Answer: The requirement is that the onsite PM be a licensed Professional Engineer (PE).
Q. How does this section rate on the contract evaluation? Answer: See Section M, page 43 of the solicitation to see how this will be evaluated.
27. The Contractor shall provide a qualified PM and a qualified alternate who shall be responsible for the performance of all aspects of the work, and shall be located at the DIAC. Will the PM need to be on site for the duration of the MAC or only when delivery orders (DO) are issued? If the PM is to be on site for the duration of the MAC, how will we invoice for the PM, if they are part of the coefficient that is a multiplier to the DO? Answer: The PM is required to be onsite for the duration of the contract. His cost is part of the overhead for the contract and is included in the Contractor’s Coefficient.
28. 2. 2.2 PROGRAMS, 2.2.3. Quality Control Plan. The Contractor shall provide a Quality Control Plan (QCP) proposed to implement the requirements of the Contract Clause entitled "Inspection of Construction" (FAR Clause 52.246-12). The QCP shall become a compliance document for all work accomplished under all DOs. The plan shall identify personnel, procedures, control, instructions, test, records, and forms to be used. Work will be permitted to begin only after acceptance of the QC Plan or acceptance of an interim plan appli-cable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a QC Plan or another interim plan containing the additional features of work to be started. Any subsequent modifications shall be submitted to the CO for acceptance before implementation. The CO reserves the right to request modify-cations to the QCP if it does not prove effective, and may take actions to remove the acting Quality Control Manager(QCM) if deemed necessary.
a. QCP provided under this section is for Corporate Quality Control. Under the US Army Corps of Engineers (ACOE) Construction
Quality Management, a QCP is to be site and job specific. It is the intent of the section to submit a Corporate QCP and a DO QCP for the demonstration project? Answer: The Contractor’s Quality Control Plan should be the Corporate Level Plan, with Activity Hazard Analysis conducted during delivery order execution. IAW paragraph 2.2.3 of TE#3, “The QCP shall become a compliance document for all work accomplished under all Dos.” DIA would expect that QC Plan to be delivered 30 days after contract award.
GENERAL Questions:
1. Can the bid date be extended? Ans: Please see amendment 2 to the solicitation.
2. Will a pre-proposal meeting be held? Ans: Please see page 13 of the solicitation.
29. Will the commissioning need be provided 3rd party? Ans: Commissioning can be executed by anyone that is qualified to perform this action.
30. Will this project need to be completed during non-business hours?
Ans: Currently this project is planned for normal business hours. On some occasions, based on DIA mission requirements some or all of a project will get shifted to after-hours. Under those circumstances the appropriate contract modifications will be issued. Most extensive utility outages that are non-emergency are performed after-hours.
31. Can load calculations be provided for the rooms where the new HVAC Systems are being installed? We would like to verify the size of the unit and components. Ans: If the unit and associated equipment are sized as specified there will not be a problem with the loads.
32. Will the government be responsible for the relocation of furniture, equipment, comms and personnel items? Ans: The government, in particular the DAL-1A PM will coordinate any and all pre-construction preparations.
33. Does the new wall types need to match the existing type or meet UFC? Ans: Wall types need to match the plans and specifications. If there’s further information required on the walls we can get that from the Engineering Staff.
34. Can the existing chilled water pipe and valve schematic and sizes (as-builts) be provided? Ans: The design has been executed by the onsite, long time DIA Mechanical Engineer. For bidding purposes, the plan and specifications are quite accurate as is.
35. If the existing sizes are provided we may be able to use them?
Ans: Use of the existing sizes is acceptable, unless the plan and specs. call for something different.
36. Can the deck height of the offices be provided? Ans: In the original DIAC, which is the location for the demo project, the height from slab-to-slab is 13 ft.
37. What is the new AHU Mechanical roof floor finish? The floor of the mechanical room will be the existing concrete slab and the top of the mechanical room will be the bottom of the second floor slab which will be the corrugated steel pan.
38. Can the wet tapping of the existing 10" CHWS and 8" CHWR be performed during standard work hours for the 2-1/2" taps required for AHU-52? Ans: Wet tapping during normal working hours will be done on a case by case basis. It’s best to assume after-hours for this action.
39. Are there any requirements for pressure testing of the ductwork?
Ans: Yes. Ductwork should be pressure tested.
40. Can all ceilings be removed for the duration of the projects?
Ans: No. Ceilings only in the vicinity of the project can be removed as required.
41. Can work in occupied spaces, hallways, mechanical rooms, etc... be completed during standard working hours? Ans: Currently, other than outages, burning, and any item of work deemed to be unsafe for DIA Personnel and the DIA Mission normal working hours can be assumed.
42. Please provide drawing A1. It is missing from the Demo Project.
a. Statement of Work, Part 3 - Specific Tasks, 3.4 Specific Tasks:, Architectural: " As shown in drawing A1 and summarized below:..."
Ans: Drawing A-1 was provided in amendment 0001.
43. The Statement of Work does not distinguish of the Demo Project will need design services. Provide direction.
a. 3.3. DESIGN GUIDANCE: 3.3.1 Professional Engineer (PE) Certification. A DO RFP may require PE Certification on some or all designs, or portions of designs. Government will direct the contractor as necessary to provide certification.
Ans: Demo Project design can be considered complete as provided.
44. Verify that this project does not fall under the 3.3.3 Historical and Archeological and 3.3.4 The Secretary Of The Interior's
Standards for Rehabilitation.
Ans: This project does not fall under either 3.3.3 or 3.3.4
45. Will the government provide the restroom facilities for this project?
Ans: Yes. There will be more than ample restroom facilities available during the execution of the demo project.
General Questions:
a. What is the geographical areas of work under this contract?
Ans: The Geographical area includes Washington, DC, some counties in Maryland and some counties in Virginia. See Page 13 of 47, paragraph H.5.a.of the proposal for a complete listing of the counties.
b. Does DIA or specific buildings have a standard beyond the UFC or local codes? If so, please provide.
Ans: Please use the UFC as building codes. Depending on the task order, some local codes may also apply.
c. Does the DIA have a Indoor Air Quality Program (IAQ) that will need to be maintained? If so, please provide.
Ans: DIA does have indoor air quality standards that are the same as any U.S. Government Facility. These are included in the UFC codes.
46. Please explain the "The term nonstandard working hours is not to be interpreted as overtime." and why this is part of this section.
The 0001AF-4001 AF CLIN is for overtime or shift work.
a. NOTES: 2.0 If the government directs a work schedule during non-standard hours (see Specs. Para 1.4.2), then the coefficient entered for CLIN 0001AF 4001AF shall be applied against those items of work which will be performed during the nonstandard hours.
The price for the remaining items of work is calculated using the coefficients entered for CLINS 0001AA-4001AE as applicable based on the estimated bare cost of the project (with the RS Means Washington DC Cost City Index applied). The term nonstandard working hours is not to be interpreted as overtime.
ANS: The intent is to use the coefficient to price work outside of the normal business hours as defined in Technical Exhibit #3. DIA will not pay at the contractor’s overtime rate.
47. Verify that this section COEFFICIENTS are all inclusive of Division 1 "except Section 01215 (Factors Allowance: Security and
Shift Work), Section 01500 (Temporary Facilities and Controls) and Section 01590(Equipment Rental)" of the RS Means data base and that all other CSI Division in RS Means can be utilized for pricing.
a. NOTES: 3.0. Offered coefficients must contain all allowable indirect contractor costs not covered by RS Means Pre-Priced costs, including but not limited to contingencies, overhead, general and administrative expenses, bonding costs and profit. Additional examples of such costs are: gross receipts taxes and payroll taxes, such as FICA, workmen’s compensation, state and federal unemployment taxes for direct payroll employees, superintendents’ salaries, builders’ risk insurance, initial contract startup mobilization and demobilization expenses, individual project mobilization and demobilization expenses and any and all bond premiums.
Coefficients shall also include various overhead expenses, including project estimating, project engineering, site office overhead, field office DDOCC HHM402-09-R-0090 Page 6 of 47 building, furniture, equipment, on-site office staff salaries, vehicle and construction equipment maintenance, office administrative expenses, grounds keeping in and around the field office site and a proportional share of home office overhead. The coefficient shall also include all insurance, special clothing for workers, traffic barricades, flag persons, daily and final cleanup, additional supervision, delivery of materials/ equipment, paperwork fees associated with a particular delivery order and any other field overhead costs attributable to the contract requirements identified within the contract and/or specifications.
aa. 3.2.1.3.1. Unauthorized Sections. RS Means line items from Division 1 in its entirety except Section 01215 (Factors Allowance:
Security and Shift Work), Section 01500 (Temporary Facilities and Controls) and Section 01590(Equipment Rental) shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor's coefficient.
ANS: Verified as the question stated.
48. Will a Profit Coefficient include the companies profit or will this be a multiplier like the Coefficient? Ans: The contractor’s profit shall be included in the contractor’s coefficient.
a. If this is a multiplier, please provide the range or maximum profit percentage? Ans: Not applicable.
b. Will this be set or negotiated? Not applicable. Profit shall be included in the contractor’s coefficient.
5. Verify that quarterly RS Means down loads will be accepted for index and material cost changes.
a. H-5 DAVIS-BACON WAGE RATE(s) APPLICATION: b. At the beginning of each option period, a new Unit Pre-Priced Database (i.e. the
Means Facilities Composite Database) with current year pricing will be incorporated and used to price individual projects in conformance with the terms and conditions specified herein. Therefore, no further adjustment to contract pricing will be permitted to cover any increase or decrease in wages and benefits as a result of:
Ans: Paragraph 3.2.1.2 of Technical Exhibit #3 states: “cost estimates shall be based upon current RS Means Cost data…”. So, quarterly RS Means downloads will be acceptable. Although this implies that the contractor will provide these updates to DIA. Each option period is the beginning of each subsequent year of the contract.
Technical Specifications.
1. Clarify the following "shall provide updates as published at no additional cost to the Government". Is this for the life of the contract, every year? ANS: Yes, updates are required for the life of the contract, with every option year.
2. Contractor Personnel/Programs/Equipment/Materials and Services: 2.3. EQUIPMENT, MATERIALS AND TRAINING SERVICES: 2.3.2.1. Technical Library: The contractor shall, within 60 calendar days after contract award, provide one copy of the following manuals/codes to DAL-1 and shall provide updates as published at no additional cost to the Government.
a. Will this entire section to include 2.3.2.11-2.3.3.1.3 be required per year? ANS: Yes, the required publications listed in TE#3, 2.3.2.11-2.3.3.1.3 are required every year with the most current updates.
b. Can the 2.3.2.1.10 - 2.3.2.1.12 be electric or does this have to be paper/book? ANS: These should be provided in both electronic and paper formats.
c. Where will the training need to be held? On site or near by? Provide a distance in miles from the DIA Building. ANS: Training should be conducted at DIA, or at a facility within the Washington, DC Metropolitan area.
d. Can the Software Training be provided in three consecutive days?
Yes, software training can be conducted in three consecutive days.
e. Will RS Means need to be provided in software or booklet?
ANS: Contractor is required to provide both electronic and book forms of the RS Means guides.
f. Verify that only the 2.3.2.1.1 e4Clicks Project Estimator Premier is the only item that requires multiply copies "e4Clicks Project Estimator Premier (e4clicks) software to include: (4 network licenses and 1 stand-alone laptop license)" ANS: Multiple copies of E4 Clicks are required, as stated.
2. Please verify that all Routine Requirements and Emergency Requirements are to utilize the same Coefficients.
a. 3.1. PROJECT REQUIREMENT TYPES. The two types of project requirements are Routine and Emergency. Either of these types may be issued at anytime during the length of this contract. The Government is responsible for determination of project requirement type.
ANS: The proposal doesn’t mention any difference in contractor coefficients for routine versus emergency.
3. Provide how a sole source subcontract will be provide in NPI if "(a) A minimum of three (3) competitive contractor quotes, which
Request For Information Continued... Date: 03-30-2009 Page 4 RFI#: 2 shall include material(s) description with unit price and installation, labor cost showing labor classification, hourly rate, and number of hours anticipated for each workman, etc."?
a. 3.2.1.3.2. Pre- and Non-Priced Items (NPI).
ANS: Competitive quotes may be obtained from other vendors for comparison.
4. 3.2.1.3.2. Pre- and Non-Priced Items (NPI). Coefficients will not be applied to NPIs. How will the contractor get paid for there coefficient for NPI if the coefficient can not be applied?
ANS: Paragraph 3.2.1.3.2.1 of TE#3 states that: “the negotiated price of an NPI will be based on costs to include…Overhead, profit….”. The Overhead & profit should compensate for no contractor coefficient with an NPI.
5. Can the "Required Quantities" be provided with the construction submittal after NTP? a. 3.2.1.5.1. Required Quantities. Three (3) copies of printed documents and one physical material sample (when applicable) are required for each individual material submittal.
ANS: Yes, the required quantities may be submitted after the NTP for delivery orders.
6. Provide the DIA and Bolling AFB Architectural and Interior Design Standards. a. 3.3. DESIGN GUIDANCE. All designs shall be IAW DIA and Bolling AFB Architectural and Interior Design Standards.
ANS: DIA will publish/provide our standards after contract award. The absence of these interior design standards should not impact the sample project, nor contractor’s proposed pricing. The intent is to follow the International Building Design Guides, which have been incorporated in the applicable UFC.
7. Please provide the approved equal. Is this a performance approved equal for DIA approved equal?
a. 3.3.16. Equipment Manufacturers. All chillers, heat pumps, furnaces, Air Handling Units (AHU) shall be manufactured by "TRANE" or approved equal.
ANS: If the contractor chooses not to provide a TRANE brand, then their submittal should include sufficient product information for DIA to determine if the equipment is “equal”.
8. TABS are part of the CSI Division Section 230593 Testing, Adjusting and Balancing for HVAC in RS Means. Can this be utilized under the RS Mean estimate? a. 3.3.18. Mechanical Systems Testing. All labor, equipment, materials and rentals/fees required to provide mechanical system tests shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor's coefficient.
ANS: Yes, these can all be utilized under the RS Means estimate.
9. Equipment/Plumbing/Electrical/Fire Protection Identification Tags, Placards, and Schematics are part of the CSI Division Section 2202553 Identification for Plumbing Pieing and Equipment in RS Means. Can this be utilized under the RS Mean estimate?
a. 3.3.20. Mechanical Equipment Identification Tags, Placards, and Schematics. All labor, equipment, materials and rentals/fees required to provide all mechanical equipment identification tags, placards, and schematics shall be at no additional cost to the
Government and is considered field overhead, therefore part of the Contractor's coefficient.
b. 3.3.23.3. Plumbing Identification Tags and Schematics. All labor, equipment, materials and rentals/fees required to provide all plumbing identification tags and schematics shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor's coefficient.
c. 3.3.25.13. Electrical Equipment Identification Tags and Schematics. All labor, equipment, materials and rentals/fees required to provide all electrical identification tags and schematics shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor's coefficient.
d. 3.3.26.4. Fire Protection Equipment Identification Tags and Schematics. All labor, equipment, materials and rentals/fees required to provide all fire protection identification tags and schematics shall be at no additional cost to the Government.
ANS: Yes, these can all be utilized under the RS Means estimate.
10. Asbestos and Lead-Based Paint Testing and Samples are part of the CSI Division Section 028213 OSHA Testing in RS Means.
Can this be utilized under the RS Mean estimate?
a. 3.3.24.1. Asbestos and Lead-Based Paint Testing and Samples. All labor, equipment, materials and rentals/fees required to provide all asbestos and lead-based paint samples and testing shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor's coefficient.
ANS: Yes, these can all be utilized under the RS Means estimate.
11. Can the government provide written notification for approval of assumptions?
a. 3.4. DESIGN ANALYSIS. The Contractor shall submit three copies of all required design analysis data with the SOW Package forapproval/review IAW paragraph 3.2.1. The Contractor is responsible for all required field investigations to include any necessary testing to produce a functional and well-planned design in lieu of making assumptions. When field investigations and testing are not feasible due to mission requirements or other government constraints, written notification shall be submitted to the CO or COR prior to submission of the SOW Package for approval of assumptions. When approved for use during design, the Contractor shall include Request For Information Continued... Date: 03-30-2009 Page 5 of 5 RFI#: 2 descriptions and reasons for any assumptions made during the design analysis. All labor, equipment, materials and rentals/feesrequired to provide design analysis shall be included in the Contractor's price proposal.
ANS: DIA can provide written approval of assumptions when appropriate for each task order as part of the submittal approval process.
12. Please define further the Interruption of Utility Service. Is this in general or only if the contractor interrupts the utility service?
a. If the government interrupts the utility, why can't the contract receive delays to the schedule? aa. 4.4.4. Interruption of Utility Services. The contractor shall not hold the government responsible for interruptions of utility service nor liable for contractor delays, damages, or increased costs occasioned by any such interruption of service.
ANS: This is in general. DIA will typically schedule utility outages well enough in advance to enable contractors performing work to adjust schedules. However, much of the equipment at the DIAC in particular is old and there have been several unscheduled outages and interruptions in service as a result of equipment failure. The contractor will not hold the government responsible for these delays, or damages.
Solicitation, Offer, and Award
1. Verify that " all other documentation as required by the contract specifications paragraph 3" refers to Technical Specifications 3
Commencement of Work (this is a general question throughout the document - paragraph refers to the Technical Specification section).
a, III. VOLUME III, TECHNICAL PART 2, DEMONSTRATION PROJECT: Utilizing the Demonstration Project Statement of Work, Attachment # 4, and associated Drawings, Attachment # 5, the Contractor shall provide a complete Statement of Work, RS Means cost estimate, associated drawings/sketches, and all other documentation as required by the contract specifications paragraph 3. ANS: Yes, “all other documentation as required by the contract specifications paragraph 3” refers to Technical Exhibit 3, Part 3, Commencement of Work.
2. Verify that the SPECSINTAC Guide Line section is used for the SOW.
a. Volume III, Technical Part 2 Demonstration Project: (1) The SOW identifies a summary of assumptions, approach, methodologies and any questions regarding the demonstration project. In accordance with contract specifications paragraph 3.2.1.1, ANS: Yes, SPECSINTACT Guide Line section is used in the SOW.
3. Verify that the drawings provided are pursuant to the Government indicated drawings necessary for each individual project.
a. Volume III, Technical Part 2 Demonstration Project: (2) Project Design Drawings Offerer provides accurate and complete drawings and details showing all aspects of work to be executed IAW paragraph 3.2.1.4, and section 3.3, and with thorough applicable design calculations IAW section 3.4 of the contract specifications.
b. 3.2.1.4. Project Drawings. The Government will indicate which drawings are necessary for each individual project.
ANS: Yes, if I understand the question correctly, the drawings are those that are pursuant to the Government indicated drawings.
4. Can the CADD (Auto CADD) files be provided for the Demonstration Project?
ANS: We will not provide .cadd files. We did provide .pdf files.
5. Is it the intent to verify the design from drawings that were provided for the Demonstration Project?
ANS: Yes, it is the intent that bidders verify the design from the drawings provided by DIA.
6. Part 3.2.1.1. of Technical Specs references SPECSINTACT for specifications. Is it acceptable under this task to provide specifications in note form on the drawings in lieu of book specs?
Request For Information Continued... Date: 04-01-2009 Page 2 of 2
RFI#: 3
ANS: It is acceptable under this task to annotate specifications in note form on the drawings in lieu of book specifications.
7. DIA CADD Standards (Technical Exhibit 4) Part 2.2 states that drawings are to be generated in three-dimensional AutoCAD format.
Is it acceptable under this task to prepare standard 2-dimensional AutoCAD drawings?
ANS: DIA CADD Standards. It is acceptable to provide two dimensional Autocadd drawings.
8. What are the requirements for Design Submittals (e.g. 35%, 65%, 95%, 100%, backcheck, etc.)?
ANS: The specific requirement for design drawings will depend on the complexity of the individual task orders and will be determined by the DIA Project Manager and Design Team. Typically, 35%, 65%, 95%, and 100% would be required for complex task orders with significant mechanical, plumbing, electrical, and architectural requirements. Minor space renovation may require less.
9. Are any drawings required to be provided as part of the proposal submission? It would appear that the drawings provided in the RFP are in sufficient detail so as to not require any additional drawings to be prepared by the offerer.
ANS: No additional drawings are required to be provided as part of the submission. However, the more detailed your plan, the better DIA is able to evaluate your proposal.
10. We assume that the variable air volume (VAV) boxes contain dampers only and do not contain electric reheat.
ANS: Your assumption is correct. The variable air volume (VAV) boxes contain only dampers, and no electric reheat.
File details come from the government source that posted it. Updated .