DDOC Spec

856 KB Posted

Attached to
DIAC Delivery Order Contract - Construction
Solicitation number
Not on record
Issued by

About this file

Attachment 1 - Specifications

Text of this file

HHM402-09-R-0090

Past Performance Reference List

Attachment 1

DIAC DELIVERY ORDER CONTRACT

(DDOC)

TECHNICAL SPECIFICATIONS

SOLICITATION NUMBER: HHM402-09-R-0090

Facility Engineering Division 26 January 2009

TABLE OF CONTENTS

1.
SCOPE OF WORK
1.1
Duration
1.2
Contractor Coefficient
1.3
Applicable Codes, Regulations and Standards
1.4
Work Types
1.5
Government Furnished Facilities / Utilities
2.
CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS AND SERVICES
2.1
Personnel
2.2
Programs
2.3
Equipment, Materials and Training Services
3.
COMMENCEMENT OF WORK
3.1
Project Requirement Types
3.2
Commencement Documents
3.3
Design Guidance
3.4
Design Analysis
3.5.
Summary Of Monthly / Annual Climatological Data, Bolling AFB
4.
PROSECUTION OF WORK
4.1
Liquidated Damages
4.2
Prosecution Documents
4.3
Hours of Operation
4.4
Order of Work
4.5
Worksite Standards
4.6
Worksite Procedures
4.7
Affirmative Procurement
4.8
Progress Payments
4.9
Project Progress Meetings
4.10
Project Schedules
5.
COMPLETION OF WORK
5.1
Final / Beneficial Occupancy Inspections
5.2
Completion Documentation
5.3
Equipment Training
Technical Exhibit 1
Applicable Codes, Regulations and Standards
Technical Exhibit 2
List of Acronyms
Technical Exhibit 3
DIA SOW Package Format
Technical Exhibit 4
DIA CADD Standards
Technical Exhibit 5
Summary Of Climatologically Data
Technical Exhibit 6
DIA Outage Request Form
Technical Exhibit 7
Affirmative Procurement
Technical Exhibit 8
DIA Construction Data Worksheet
Technical Exhibit 9
DIA Equipment Warranty/Guarantee Record

1. SCOPE OF WORK. This is an indefinite delivery, indefinite quantity (IDIQ) contract for a broad range of maintenance, installation, repair, minor and major upgrade/remodel/renovation work on real property at the Defense Intelligence Agency’s Defense Intelligence Analysis Center (DIAC) located on Bolling Air Force Base (BAFB), Washington DC and other, yet, unspecified locations of interest within 100 miles of the National Capital Region. The Contractor shall provide all facilities, material, labor, equipment, transportation and supervision necessary to perform the DIAC Delivery Order Contract (DDOC) requirements. The primary goal of the DDOC Contract is the swift acquisition of engineering requirements where Contractor responsiveness is paramount. Once the contracting officer (CO) notifies the Contractor of an existing requirement, the Contractor shall expeditiously prepare a proposal to be awarded. During the contract period, the Facility Engineering Division (DAL-1) will identify tasks and the Contracting Officer (CO) will issue individual project requests to the Contractor for design as required and subsequent Delivery Orders (DO) for completion. Types of projects include, but are not limited to, major and minor capital improvements, alterations and interior/exterior remodeling/renovation/repairs. Project disciplines may include, but not be limited to, one or more of the following: civil, structural, architectural, mechanical, plumbing, fire protection, communications, intrusion/detection, audio/visual systems, and electrical disciplines; petroleum/oil/lubricants systems; asphalt and concrete pavements, masonry, various roofing systems, earthworks and landscaping, environmental and hazardous abatements, aerial and underground utilities, power and heat generation. The Contractor shall be required to maintain a management office in the assigned DIAC Compound on BAFB to perform all general management operations associated with this contract, including but not limited to receiving work requests and other related requirements to accomplish each individual delivery order. The work may include tasks in various trades; such as carpentry, pavement repair, roofing, demolition, concrete masonry, welding, etc. IAW FAR 52.219-14, Limitations on Subcontracting, the prime contractor shall perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees. In performance of work by special trade contractors, the contractor shall perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees. All project time and schedules for this contract are calculated and represented as calendar days. The attached Technical Exhibits (TE’s) are mandatory and considered part of this Scope of Work.

1.1.

Duration. The duration is for one year from the date of award with four (4) one (1) year option periods.

1.2.

Contractor Coefficient. The contractor in each DO shall, for the life of the contract, provide to the Government certain labor, equipment, materials, and rentals/fees that are considered field overhead, therefore part of the contractor’s coefficient. Those requirements/responsibilities are identified throughout this Statement of Work (NOTE: Where notification of a coefficient requirement/responsibility is stated, all associated sub-paragraphs are also applicable as part of the coefficient. Other coefficient statements may be found in these sub-paragraphs referring to additional requirement/responsibilities.) TE-3 is a table which includes, but is not limited to, the contractor coefficients referenced in this SOW.

1.3. Applicable Codes, Regulations, and Standards. All work under this contract shall comply with the most current local, state, and federal regulations, to include any subsequent updates as they occur. The codes applicable for the District of Columbia are listed in the UFC 1-200-01, which references International Building Code (IBC) 2003 and National Fire Protection Agency (NFPA) Code among others. These codes shall be followed for all designs, material, and work performed under this contract. If there is a conflict between the codes and/or regulations and these contract specifications, the most stringent requirements shall govern at all times. The Contractor shall maintain a copy of each of these documents available for use during the term of this contract. The Codes, Regulations and Standards listed in TE-1 - APPLICABLE CODES, REGULATIONS and Standards are not all inclusive and do not relieve the Contractor from compliance with any unlisted Code, Regulation, or Standard required under law to perform work on Bolling Air Force Base, Washington, DC. Supplements and/or amendments to listed publications may be issued during the life of the contract. The contractor shall be responsible for obtaining current changes to the publications. The contractor shall immediately implement changes that result in a decrease or have no effect in the contract price condition, and notify the CO in writing of the changes and their implementation. Should a decrease in contract price result, the contractor shall provide a proposal for a reduction in the DO price to the CO and DAL-1. Before implementing any change that will result in an increase in contract price, the contractor shall submit to the CO a price proposal within 15 calendar days. The CO and the contractor shall negotiate the change into the contract IAW FAR 52.243-4, Changes. Failure of the contractor to submit a price proposal within 15 calendar days, entitles the Government to performance according to such change at no increase in contract price (unless the time requirement is waived by the Contracting Officer according to paragraph (c) of the “Changes” clause).

1.3.1. Standards. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

1.3.1.1. Code of Federal Regulations (CFR). Occupation, Safety and Health Administration (OSHA) General Industry Safety and Health Standards (29 CFR 1910), Publication V2206, OSHA Industry Standards (29 CFR 1926). One source of these regulations is OSHA Publication 2207, which includes a combination of both Parts 1910 and 1926 as they relate to construction safety and health. They are for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402.

Internet site: www.access.gpo.gov/nara/cfrcfr-retrieve.html

1.3.1.2. Federal Standard (Fed. Std.).

1.3.1.2.1. Federal Standard 313, Material Safety Data Sheets (MSDS). For each DO issued against this contract, the Contractor shall for all required MSDSs, prepare and submit one copy to the DIA Occupational Health, Safety, and Environmental Compliance Office (DAL-3) and three copies to the Contracting Officer IAW EM 385-1-1, Safety and Health Requirements Manual.

1.3.1.2.2. Use of Asbestos Containing Material or any Class 1 ozone depleting chemical compounds is prohibited.

1.3.1.2.3. Definition of Hazardous Materials. Refer to hazardous and toxic materials/ substances included in Subparts H and Z of 29 CFR 1910 and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, lead-based paint, polychlorinated biphenyls (PCBs), explosives and radioactive material, but may include others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging, pipe coverings, and vinyl floor tile and/or its associated mastic.

1.3.2. Acronyms. A list of acronyms is provided in TE-2 - LIST OF ACRONYMS.

1.4 WORK TYPES.

1.4.1. Standard Work. Government work hours are defined as the period from 6:00 a.m. to 5:00 p.m. (0600 hrs to 1700 hrs), Monday through Friday, excluding Federal holidays and other days when the Government is closed. All work shall be performed during this period unless otherwise authorized by the CO (access to work sites may be restricted to this period due to mission requirements) and approved at least 48 hours in advance, or unless otherwise specified in the DO. The contractor shall submit a request in writing to the CO to work outside standard work hours at least five (5) workdays in advance.

1.4.2. Non-Standard Work. Defined as the period outside of Standard Work. Only work specified by the CO or Contracting Officers Representative (COR), prior to issuance of a DO, or subsequent modification can be identified as work requiring non-standard work hours. The contractor shall submit a request in writing to the CO or COR to work outside standard work hours at least 48 hours in advance unless otherwise specified in the DO. In the technical/cost proposal submitted for each delivery order, the contractor shall clearly identify those items of work scheduled for accomplishment during non-standard time and include justification for the request.

1.5. GOVERNMENT FURNISHED FACILITIES/UTILITIES.

1.5.1. Office Facilities. The government will provide space on the West side of the DIAC, building 6000, where the contractor may park a trailer for shop space and materials. The contractor shall provide a modular building or trailer, not to exceed 60 feet, single width, for his/her own shop space and material storage. The color of the building or trailer must match the existing building color scheme. The Government reserves the right, at contractor expense, to require the contractor to relocate to another on-base location one time during the contract performance. The contractor is responsible for mobilization, set-up, and utility connections. The contractor shall anchor the building securely, install appropriate skirting, and provide safe and proper entrances and exits. The contractor shall perform housekeeping of the facilities to include, but not limited to sweeping, mopping, dusting, waste disposal, grass cutting, weed control, snow/ice removal and other operations necessary to present a neat appearance at all times, or as otherwise directed by the CO. All labor, equipment, materials and rentals/fees required to perform all housekeeping, vegetation maintenance, and snow/ice removal shall be at no additional cost to the Government and is considered part of the Contractor’s coefficient. In the event of a fire or any damage to the building, the contractor shall notify Naval District Washington Fire Department (NDWFD), CO, and Contracting Representative (COR), immediately. The contractor is responsible for insuring his/her own contents. The government shall not be liable for any loss or damage to the contractor's property, including stock, or for expenses incidental to such loss or damage.

1.5.2. Open Storage Area. The government will provide an area on Bolling AFB/DIAC for the contractor to use as open storage. This open storage area is located to the West side of building 6000. Contractor shall maintain the storage area fence IAW 4.5.2 to include annual replacement of the fabric visual screen each April.

1.5.3 Utilities at Contractor’s Office Space. The government will furnish utility services IAW para. 1.4. The contractor shall provide gas and electrical meters connected to the modular building or trailer for the purpose of reimbursing the government for the quantities consumed by the contractor. Utility services shall be charged to the contractor at the Non-federal reimbursable rate IAW AFI 32-1061, Providing Utilities To Us Air Force Installations.

1.5.4. Utilities at Job Sites. If available, the government will also provide utilities (electricity and water) at any construction site. Utility services furnished to the contractor by the government from the government’s existing system outlets and supplies will be at no cost to the contractor. When required, the government will furnish the contractor water from a fire hydrant designated by the CO, with the coordination of the base fire department. The contractor shall provide and install a gate valve and provide a hydrant wrench. The contractor shall be liable for any damage caused to government property resulting from improper operation of the fire hydrant(s). The government will not provide utilities at the contractor’s open storage area.

1.5.5. Contractor Identification Signs. The contractor may erect a sign for his/her office and/or storage area. The sign(s) shall be in compliance with base requirements and color scheme. The sign and proposed location must be approved by the Contracting Officer at the DIAC before being erected.

1.5.6. Communication Services. The government will not provide communication services (telephone, IT, facsimile, etc.) to the contractor's modular building/trailer. Associated communications equipment, connections, and services shall be at the contractor's expense. However, the government will allow the contractor use of telephone services within the DIAC.

1.5.7. Refuse Collection. The contractor will provide refuse collection services for all contractor facilities. The contractor is responsible for disposing of construction debris and contractor-generated refuse at construction sites safely and IAW AAFB and/or BAFB policy.

1.5.8. Insect and Rodent Control. The government will provide insect and rodent control for all government-furnished facilities. When the contractor detects an insect or rodent problem, he/she shall notify the appropriate facility inspector for entomology services. The contractor will provide insect and rodent control for all contractor facilities and construction sites.

1.5.9. Grounds Maintenance. The government will provide grounds maintenance for all government-furnished facilities excluding contractor’s trailer and open storage area.

1.5.10 Security Police and Fire Protection. The government will provide security police and fire protection to the extent necessary to ensure a secure and safe installation. In return for these services, the contractor shall adhere to the security and fire directives, instructions, and policies of Bolling AFB and Navy District Washington (NDW).

1.5.11 Emergency Medical Services. In the event of a severe emergency, BAFB Medical Clinic, during hours of operation or NDW Emergency Services, will respond and transport, if necessary, a contractor employee to one of the local hospitals. The contractor shall reimburse the government for these services. The Bolling AFB Clinic will provide only life threatening emergency medical treatment to employees of the Contractor for injuries incurred while working at the installation. The Contractor shall reimburse the USAF, for treatment provided at the current reimbursement rate for non-beneficiaries IAW AFR 168-7. The Contractor shall provide the caregiver with the name of a physician and/or hospital to which injured personnel can be transferred for further treatment and care after receiving initial emergency treatment. Thereafter, the employee’s physician shall provide all follow-on care.

2. CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS and SERVICES. The Contractor shall not employ persons for work on this contract if such employee is identified to the Contractor by the CO as a potential threat to the health, safety, security, general well being, or operational mission of the installation and its population. Where reading, understanding, and discussing safety and environmental warnings are an integral part of a contract employee’s duties, that contract employee shall be able to understand, read, write, and speak English (speaking skills are not required if a Contractor employee is hearing impaired). Construction within Sensitive Compartmentalized Information Facilities (SCIF’S) shall be performed by U.S. firms using only U.S. cleared personnel.

2.1. PERSONNEL.

2.1.1. Program Manager (PM). The Contractor shall provide a qualified PM and a qualified alternate who shall be responsible for the performance of all aspects of the work, and shall be located at the DIAC. The Contractor shall submit for approval by the CO, a detailed resume of the PM and alternate prior to assumption of duties, and any subsequent replacement of each position in sufficient time to allow proper evaluation. The PM and alternate shall have a minimum of 5 years experience with programs of similar size and scope. The name of this person and alternate(s), who shall act for the Contractor when the PM is absent, shall be designated in writing to the CO prior to issuing the Notice to Proceed, NTP. The PM and alternate(s) must be able to read, write, speak, and understand the English language. The PM and alternate shall be a licensed professional engineer and maintain a Top Secret/SCI Clearance or be able to obtain a clearance within 30 days after the contract award date.

2.1.1.1 Availability. The PM or alternate shall be directly available to the CO and the DAL-1 staff during standard duty hours as outlined in paragraph 1.3.1 above, to meet and discuss contract issues. During non-standard duty hours, the PM or alternate(s) shall be available within 4 hours to meet at the Defense Intelligence Analysis Center (DIAC) with Government personnel (as authorized by the CO) to discuss contract issues.

2.1.1.2 Authority. The PM (or alternate(s) in the absence of the PM) shall have full authority to act for the Contractor on all matters relating to daily operation of this contract. The PM shall have the authority to obligate the company in any aspect of this contract regarding negotiations and DO’s as a minimum, and shall have the authority to hire subcontractors as required.

2.1.2. Program Management Staff (PMS). The PMS shall have all engineering disciplines and support positions of administration, quality control, safety, Computer Aided Drafting and Design/Geographic Information System (CADD/GIS), field supervision and financial management experience. All personnel performing these functions shall maintain all appropriate and applicable federal, state and local certification as required. (NOTE: appropriate Contractor personnel require working knowledge and capability to utilize project management software, to include, but not limited to Microsoft Project ™.)

2.1.2.1. Project Staff. The Contractor shall designate in writing to the CO for each project the assigned Project Manager and Project Superintendent (PS), and any changes in personnel. In addition, all Project Managers and Project Superintendents (PS) shall be able to obtain and maintain a Top Secret/Sensitive Compartmentalized Information (TS/SCI) clearance prior to issuance of the NTP for each delivery order.

2.1.2.2. Quality Control Manager (QCM). The contractor shall have on staff a minimum of one individual solely dedicated as the QCM, and responsible for the Quality Control Program IAW paragraph 2.2.1. The QCM will be required to obtain and maintain a Top Secret/Sensitive Compartmentalized Information (TS/SCI) clearance within 30 days after the contract award date.

2.1.2.3. Government Employees. The Contractor shall not employ any person(s) who is an employee of the United States Government, if employing that person would create a conflict of interest, or the appearance of a conflict of interest. Additionally, the Contractor shall not employ any person who is an employee of the Department of Defense, either military or civilian, unless such person seeks and receives approval according to DODR 5500.7, Joint Ethics Regulations (JER).

2.1.2.3.1. Military Personnel. The Contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours, or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the Contractor’s ability to perform, however, their absence at any time shall not constitute an excuse for non-performance under this contract.

2.1.3. Subcontractors. The Contractor’s PM and PMS shall have the ability to manage and control multiple sub-contractors at multiple work sites. The PM shall provide to the CO a completed Statement of Prime Contractor (SF 1413) within seven calendar days after any subcontractor award regardless of tier as IAW FAR 52-222-11, Subcontracts (Labor Standards). All subcontractors shall comply with appearance requirements as stated in paragraph 2.1.5.

2.1.4. Professional/Technician/Craftsman Qualifications. The PM shall ensure all employees, to include subcontractor employees have valid licensing/certifications to accomplish applicable contract requirements before starting work under this contract, and are in compliance with all federal, state, and local regulations and environmental requirements or laws, and are qualified, competent, and capable of handling all assigned tasks. The absence at any time of the subject personnel and qualifications shall not constitute an excuse for non-performance under this contract. The following qualifications are not all inclusive:

2.1.4.1. Professional Engineer Certification. All designs requiring Professional Engineer (PE) Certification must be stamped and have valid supporting documentation.

2.1.4.2. Technical Competence. All Project Managers, Quality Control Managers and Project Superintendents shall have a minimum of five years of experience performing in that function, and all non-professional and/or technician project managers shall have relevant experience in the discipline they are performing.

2.1.4.3. Motor Vehicles. Personnel operating motor vehicles on roadways must possess a valid driver’s license for the vehicles they operate.

2.1.4.4. Cross-Connection/Back Flow Prevention. Appropriate Contractor personnel must possess State licenses for certified cross-connection and back flow prevention device testing and installation of all anti-siphon or back flow prevention units on all applicable plumbing applications. The Contractor shall make these licenses available for Government inspection, upon request, for each individual that performs this task.

2.1.4.5. Herbicides/Pesticides. Any personnel that apply herbicides/pesticides shall have a current Commercial State Applicator’s License. The Contractor shall make these licenses available for Government inspection, upon request, for each individual that performs this task IAW AFI 32-1053, Pest Management Program.

2.1.5. Personnel Appearance. All Contractor personnel shall present a neat appearance, and shall not wear clothing that depicts any symbol, logo or language deemed racial, lewd or offensive. Contractor personnel shall not be present without proper safety equipment/clothing at all times IAW all applicable OSHA standards. All Contractor personnel shall wear shirts at all times.

2.2. PROGRAMS.

2.2.1. Quality Control Program. All labor, equipment, materials and rentals/fees required to provide the Quality Control Program shall be at no additional cost to the Government and is considered field overhead.

2.2.2. Contractor’s Quality Control. The contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with the contract clause entitled "Inspection of Construction” (FAR 52.246-12) and IAW paragraphs 2.2.3. The quality control system shall consist of plans, procedures, and organization necessary to manage all delivery orders to produce end products which comply with the contract requirements. The system shall cover all DO operations, both on site and off site, and shall be keyed to the proposed scheduling sequence. The government will hold the PM responsible for the quality of work on the job and is subject to removal by the CO for non-compliance with quality requirements specified in the contract.

2.2.3. Quality Control Plan. The Contractor shall provide a Quality Control Plan (QCP) proposed to implement the requirements of the Contract Clause entitled "Inspection of Construction” (FAR Clause 52.246-12). The QCP shall become a compliance document for all work accomplished under all DOs. The plan shall identify personnel, procedures, control, instructions, test, records, and forms to be used. Work will be permitted to begin only after acceptance of the QC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a QC Plan or another interim plan containing the additional features of work to be started. Any subsequent modifications shall be submitted to the CO for acceptance before implementation. The CO reserves the right to request modifications to the QCP if it does not prove effective, and may take actions to remove the acting Quality Control Manager (QCM) if deemed necessary.

2.2.3.1. Content of the QC Plan. The QCP shall include, as a minimum, the following to cover all DO operations, both on site and off site, including work by subcontractors, fabricators, suppliers, and purchasing agents:

2.2.3.1.1. A description of the quality control organization, including a chart showing lines of authority. As a minimum, the staff shall include a QCM whose responsibility is to implement the QCP.

2.2.3.1.2. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a Quality Control (QC) function:

2.2.3.1.3. A copy of the letter to the QCM signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the QCM, including authority to stop work which is not in compliance with the contract. The QCM shall issue letters of direction to all other various QC representatives outlining duties, authorities, and responsibilities. Copies of these letters will also be furnished to the Government.

2.2.3.1.4. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, off site fabricators, suppliers, and purchasing agents. These procedures shall be IAW paragraphs 2.2.1.

2.2.3.1.5. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

2.2.3.1.6. Procedures for tracking work activity deficiencies from identification through acceptable corrective action. These procedures will establish verification that identified deficiencies have been corrected.

2.2.3.1.7. Reporting procedures, including proposed reporting formats.

2.2.3.2. Coordination Meeting. Before issuance of any delivery order under this contract and prior to acceptance by the Government of the QCP, the contractor shall meet with the CO and COR and discuss the contractor's quality control system. The QCP shall be submitted for review a minimum of five (5) calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the QC operations, control activities, testing, administration of the system for both on site and off site work, and the interrelationship of contractor's management and control with the government's quality assurance. Minutes of the meeting shall be prepared by the government and signed by the contractor, CO, and COR. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the QC system or procedures which may require corrective action by the contractor.

2.2.3.3. Acceptance of Plan. Government acceptance of the contractor's plan is required prior to the contract award. The government reserves the right to require the contractor to make changes in his QCP and operations including removal of personnel, as necessary, to obtain the quality specified.

2.2.3.4. Notification of Changes. After acceptance of the QCP, the contractor shall notify the CO in writing of any proposed change. Proposed changes are subject to acceptance by the CO.

2.2.3.5. Quality Control Organization.

2.2.3.5.1. General. The requirements for the QC organization are a QCM and sufficient number of additional qualified personnel to ensure contract compliance. The contractor shall provide a QC organization which shall be at the site at all times during progress of the work and with complete authority to take any action necessary to ensure compliance with the contract.

2.2.3.5.2. QC manager. The Contractor shall identify as QC manager an individual within his organization at the site of the work who shall be responsible for overall management of QC and have the authority to act in all QC matters for the contractor. The QC manager shall be a construction person with a minimum of five (5) years in related work. This QC manager shall be on the site at all times during work activity and will be employed by the prime contractor. The QC manager shall be assigned no other duties. The contractor shall identify an alternate for the QC manager in the plan to serve in the event of the manager's absence.

2.2.3.5.3. QC Inspectors. In addition to the QCM, the contractor shall provide as part of the QC organization inspectors to assist the QCM for every Construction Specification Institute (CSI) discipline including: electrical, mechanical, civil, structural, environmental, architectural, and materials technician. These individuals shall be directly employed by the prime contractor; be responsible to the QCM, be physically present at the work activity site during work on their areas of responsibility; and have the necessary education and/or experience to be qualified to inspect their trade. These individuals may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the QCP.

2.2.3.5.4. Advisors. The contractor shall have access to professional advisors for each discipline capable of physically visiting the job site within 48 hours of notification to resolve specific technical issues as required. These professional advisors shall have a minimum education and/or experience in accordance with the experience matrix listed herein.

EXPERIENCE MATRIX

AREA
QUALIFICATIONS
Civil
Graduate Civil Engineer with 2 years experience in the type of work being performed on this project or technician with 5 years of related experience.
Mechanical
Graduate Mechanical Engineer with 2 years experience or technician with 5 years related experience
Electrical
Graduate Electrical Engineer with 2 years related experience or technician with 5 years related experience
Structural
Graduate Structural Engineer with 2 years experience or technician with 5 years related experience
Architectural
Graduate Architect with 2 years experience or technician with 5 years related experience
Environmental
Graduate Environmental Engineer with 3 years experience
Concrete, Pavements, Materials
Technician with 3 years experience

2.2.3.5.5. Additional Requirement. In addition to the above experience and education requirements, the QCM shall have completed a professionally endorsed/certified course in Construction Quality Management for Contractors or have comparable experience in construction QC.

2.2.3.5.6. Organizational Changes. When it is necessary to make changes to the QC staff, the contractor shall revise the QCP to reflect the changes and submit the changes to the CO for acceptance. The contractor may adjust the number of inspectors assigned to the organization dependent upon the number of projects underway and their complexity. However, the number of inspectors assigned shall be sufficient to allow each inspector to thoroughly inspect each project in progress at least once a day and to meet any additional QC functional requirements as specified herein.

2.2.3.6. Design Submittals. The QCM shall review all designs IAW paragraph 3.2. The QC organization shall be responsible for certifying that all submittals are in compliance with the contract requirements.

2.2.3.7. Documentation. The Contractor shall maintain current records providing documented evidence that required QC activities and/or tests have been performed. These records shall include the work of subcontractors and suppliers and shall be on a form acceptable to the CO that includes, as a minimum, the following information:

2.2.3.7.1. Contractor/subcontractor and their area of responsibility.

2.2.3.7.2. Operating plant/equipment with hours worked, idle, or down for repair.

2.2.3.7.3. Work performed each day, giving location, description, and by whom.

2.2.3.7.4. Test and/or control activities performed with results and references to specifications/drawings requirements. List deficiencies noted along with corrective action.

2.2.3.7.5. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

2.2.3.7.6. Submittals reviewed, with contract reference, by whom, and action taken.

2.2.3.7.7. Off-site surveillance activities, including actions taken.

2.2.3.7.8. Job safety evaluations stating what was checked, results, and instructions or corrective actions.

2.2.3.7.9. Instructions given/received and conflicts in plans and/or specifications.

2.2.3.7.10. Contractor's verification statement.

2.2.3.7.11. Note. These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. The original and one copy of these records in report form shall be furnished to the government daily within 24 hours after the date(s) covered by the report, except that reports need NOT be submitted for days on which no work is performed. Reports shall be signed and dated by the QCM. The report from the QCM shall include copies of test reports and copies of reports prepared by all subordinate QC personnel.

2.2.3.8. Interface with Government Personnel. The contractor shall host a weekly meeting with government project personnel to address the status of all projects in progress. The meeting shall cover the progress of all work with regard to their respective project schedule, any problems encountered and corrective actions taken, and anticipated delays, if any. The contractor shall provide documentation of these meetings to the CO through the COR for official record.

2.2.3.9. Notification of Noncompliance. The CO will notify the contractor of any detected noncompliance with the foregoing requirements. The contractor shall take immediate corrective action after receipt of such notice. If the contractor fails or refuses to comply promptly, the CO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

2.2.4. Health and Safety Programs. All labor, equipment, materials and rentals/fees required to provide the Health and Safety Programs shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor’s coefficient.

2.2.4.1. Non-Compliance Actions. The CO will notify the Contractor of any noncompliance of health or safety requirements, and the required action to be taken (notification delivered to the Contractor representative at the worksite shall be deemed sufficient). The Contractor shall take immediate corrective action to rectify all violations. If the Contractor fails, or refuses to promptly comply, the CO may issue a Stop Work Order ceasing all, or part of the work for a stop work order issued for non-compliance actions, until satisfactory corrective action has been taken. The Contractor shall not claim for costs, damages or time extensions due to Stop Work Orders based on non-compliance with health or safety requirements.

2.2.4.2. Corps of Engineers Manual, EM 385-1-1, Safety and Health Requirements Manual. The Contractor shall comply with all pertinent provisions of the most current version of the Corps of Engineers Manual, EM 385-1-1, Safety and Health Requirements Manual. The Contractor shall provide copies to the Government IAW paragraph 2.3.2.1. The Contractor is responsible for compliance with the provisions of this manual, to include subcontractors.

2.2.4.3. Records/Notification. The Contractor shall maintain accurate records, and shall notify the CO in the prescribed manner of, all exposure data, accidents resulting in death, traumatic injury, occupational disease, damage to property, materials, supplies and equipment incident to work performed under this contract.

2.3. EQUIPMENT, MATERIALS AND TRAINING SERVICES. All labor, equipment, materials and rentals/fees required for all contractor required, and contractor provided equipment, materials and services to the Government shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor’s coefficient.

2.3.1. Contractor Required Equipment, Materials, and Services. The contractor shall maintain, throughout the life of the contract for its own operations, all equipment, phone and e-mail service in sufficient quantity for its staff to comply with the contract requirements, and that is compatible with the contractor provided equipment, materials and services that the contractor is required to provide to the Government.

2.3.2. Contractor Provided Materials to the Government. All contractor-provided materials listed below (software, books and cameras) shall become the property of the Government. The contractor shall replace, any whole or portion of the items listed below when upgrades are necessary and for defects due to normal wear and tear as directed by the CO at no additional cost to the Government throughout the life of the contract.

2.3.2.1. Technical Library. The contractor shall, within 60 calendar days after contract award, provide one copy of the following manuals/codes to DAL-1 and shall provide updates as published at no additional cost to the Government. All labor, equipment, materials, and rentals/fees required to provide the technical library, shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor’s coefficient.

2.3.2.1.1. e4Clicks Project Estimator Premier ™ (e4clicks) software to include: (4 network licenses and 1 stand-alone laptop license)

2.3.2.1.2. R.S. Means ™ Facilities Cost Data module (in bare cost format).

2.3.2.1.3. R.S. Means ™ Repair & Remodeling Cost Data module.

2.3.2.1.4. R.S. Means ™ Assemblies Cost Data module.

2.3.2.1.5. R.S. Means ™ Estimating Guides. As stated in paragraph 3.2.1.3.

2.3.2.1.6. R.S. Means ™ Estimating Handbook.

2.3.2.1.7. R.S. Means ™ Illustrated Construction Dictionary.

2.3.2.1.8. R.S. Means ™ Master Composite Cost Data module

2.3.2.1.9. EM 385-1-1, Safety and Health Requirements Manual. May be obtained from the Government Printing Office, Washington DC 20402. The Contractor is responsible for compliance with the provisions of this manual, to include subcontractors. This publication is available on the Internet: http: www.bocai.org/codes.asp

2.3.2.1.10. UFC 1-200-01 – Electric Code.

2.3.2.1.11. UFC 1-200-01 – Plumbing Code.

2.3.2.1.12. UFC 1-200-01 – Building Code.

2.3.2.1.13. SPECSINTAC ™ on CD ROM, latest edition.

2.3.3 Contractor Provided Training Services to the Government.

2.3.3.1. Software Training. The contractor shall provide the following training at time of contract award and refresher training for assigned DDOC personnel, not to exceed 20 persons per class, when requested by the government.

2.3.3.1.1. e4Clicks Project Estimator Premier ™ Program Training. Provided by an approved source.

2.3.3.1.2. R.S. Means ™ Estimating Guide Training. Provided by an approved source.

2.3.3.1.3 Microsoft Project TM Level I and Level II. Provided by an approved source.

3. COMMENCEMENT OF WORK. For each project, the Contractor will receive a formal Request for Proposal (RFP)/SOW Package. All Government requests will include a work request number, project title, conceptual scope of work, and will state any known special instructions or conditions that may exist. The Contractor shall attend a Pre-Proposal Site Visit to introduce and familiarize the Contractor with the proposed work. Subsequently, the Contractor shall prepare and submit for review a corresponding Contractor (SOW) Package (see paragraph 3.2.1). To facilitate and expedite fiscal year end or emergency requirements, the Government reserves the right to solicit proposals from the contractor in advance of funding. The contractor will provide such proposals at no additional charge or obligation by the Government in case funding does not become available and the project is not awarded. Solicitations issued in advance of funding will be so annotated. The Contractor will have full access to all Record and As-Built drawings, as required for development of the Contractor’s proposal. The Contractor shall be responsible for identifying tasks, refining quantities, preparing design calculations, pricing any Non-Prepriced Items (NPI) or tasks, preparing required design drawings, developing performance times, and submitting a formal proposal in the prescribed format. The Government will respond to any questions the Contractor may have regarding the work and the Contractor shall submit the proposal to the CO. Following Government technical review of the proposal, the CO will conduct negotiations with the Contractor and any other persons deemed necessary, for resolving any variations involving price, time, quantities, and any other relevant items. Following Government acceptance of the negotiated and/or revised proposals, the CO will prepare and issue a DO and a Notice to Proceed (NTP) directing the Contractor to begin work within a specified period of time acceptable to the CO and DAL-1 representative based on mission requirements. The majority of work performed under this contract will be in the occupied DIAC. In the DIAC, the contractor shall accomplish all work in a manner that minimizes inconvenience to the using occupants. The contractor shall perform all work with continuous daily progress. The government will not accept or permit days of no work except for drying or curing of previous work or as directed by the CO (i.e. long lead-time items or materials). In some cases, the government will require the contractor to work around or move furniture or other government equipment within the work area. The contractor must protect all government furniture and equipment within the work area from dust, debris, and damage. The government will hold the contractor responsible for any damages. The contractor shall maintain the work site, hallways, and emergency exits free of debris and safe at all times. Contractor personnel shall strictly adhere to Safety standards and practices at all times during the term of the contract.

3.1. PROJECT REQUIREMENT TYPES. The two types of project requirements are Routine and Emergency. Either of these types may be issued at anytime during the length of this contract. The Government is responsible for determination of project requirement type.

3.1.1. Routine Requirement. Within three calendar days of project notification, unless otherwise directed by the CO, the COR, or authorized representative(s), the contractor shall attend a Pre-Proposal Site Visit (Job Walk) to clarify any project requirements, and/or further define the project scope of work. The Contractor’s proposal shall be submitted to the CO IAW paragraph 3.2.1 within seven calendar days after the Pre-Proposal Site Visit for non-complex work and fourteen calendar days after the Pre-Bid Site Visit for complex work as determined by the Government, unless otherwise directed by the CO.

3.1.2. Emergency Requirement. In the event of an emergency or time sensitive requirement, the PM, or authorized representative(s) response time shall be as soon as directed by the CO. The PM or authorized representative shall attend a Pre-Proposal Site Visit (Job Walk) to clarify any project requirements, and/or further define the project scope of work within one (1) hour, or as directed. The Contractor’s proposal shall be submitted IAW paragraph 3.2.1, or as directed by the CO.

3.2. COMMENCEMENT DOCUMENTS. Contractor design documents shall be developed so that a distinction is made between items that are associated with each classification of work (i.e. Demolition, Minor Construction, Renovation, Repair, Additives, etc.). Categories of work notes shall be affixed throughout the contract documents to clearly distinguish between works that are Demolition (D), Minor Construction (MC), or Repair (R) and further delineate any items that are Additive Bid Items (reflected as “Option #”) and shall be accounted for and priced separately in the cost proposal. Additive Bid Items shall be priced separately. The concept of the DIAC program provides for 35% design level effort. However, some portions of a design may require up to a 65% to 80% design effort depending upon nature/complexity (i.e., mechanical/electrical). All labor, equipment, materials and rentals/fees required to provide all commencement documents shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor’s coefficient.

3.2.1. Statement of Work (SOW) Package. The Contractor shall submit for Government review, three paper copies (may be submitted electronically via e-mail as directed by the CO or COR), and one electronic CD-ROM formatted SOW Package presenting the Contractor’s offer within the timeframe as specified by the CO. The Contractor’s design shall be IAW paragraph 3.3. The format shall be IAW TE-4 - SOW PACKAGE FORMAT, and as a minimum shall include: a cover page; a detailed specification; a detailed cost estimate; all Government requested project design drawings and thorough applicable design calculations IAW paragraph 3.4; and a Material Submittal Schedule (AF Form 66) reflecting proposed product submissions, required contract reports and a Construction Work Schedule (CWS) IAW paragraph 3.2.1.6. When the Contractor desires to offer alternatives, or Value Engineering proposals, the contractor’s SOW package proposal shall clearly state and identify alternatives proposed, their segregated associative costs, a delineation of impacted line items, and advantages and disadvantages for Government evaluation. The Contractor shall provide support, verification and justified reasoning behind their proposal to alter the Government’s RFP.

3.2.1.1. Specifications. The Contractor shall develop project specifications in CSI format utilizing the current edition of the SPECSINTAC TM. Specifications shall be developed using the latest version of Microsoft Word ™ utilized by the agencies at DIAC (currently Office 2003 ™). As a minimum, applicable SPECSINTAC TM sections and paragraphs shall be listed along with the specific requirements of the DO.

3.2.1.2. Cost Estimates. Cost estimates shall be developed using e4Clicks software and be based upon current RS Means ™ Cost Data bare costs data and reflect the Washington, DC City Cost Index. The Contractor’s cost estimates shall include a one page cost summary with detailed sheets showing specific Means line items used, quantities, etc. All estimates shall include both hard and soft copies.

3.2.1.3. Estimating Guides. The following RS Means ™ Cost Data Estimating Guides shall be authorized:

Assemblies Cost Data
Light Commercial
Building Construction
Mechanical
Concrete and Masonry
Plumbing
Electrical
Repair and Remodeling
Facilities Maintenance and Repair
Residential Cost Data
Heavy Construction
Site Work and Landscape

Interior Cost Data

3.2.1.3.1. Unauthorized Sections. RS Means line items from Division 1 in its entirety except Section 01215 (Factors Allowance: Security and Shift Work), Section 01500 (Temporary Facilities and Controls) and Section 01590(Equipment Rental) shall be at no additional cost to the Government and is considered field overhead, therefore part of the Contractor’s coefficient.

3.2.1.3.2. Pre- and Non-Priced Items (NPI). All line items in RS Means ™ Estimating Guides are considered Pre-Priced Data (PPD). When a component, work element, or system does not exist as PPD, it shall be considered as a NPI.

This is the start of the file's text. The full file is on GovTribe.

Other files

File Type Posted
Amendment 0004.PDF PDF
FINAL LISTING OF QUESTIONS FROM THE PRE-PROPOSAL CONFERENCE HELD March 25 2009.doc DOC document
scan0001.pdf PDF
ADDITIONAL QUESTIONS FROM THE PRE-PROPOSAL CONFERENCE.doc DOC document
Amendment 00020001.pdf PDF
Site Visit Attendance.xls XLS spreadsheet
1-110102911-clean.pdf PDF
Amendment 00010001.pdf PDF
ANSWERS TO THE QUESTIONS FROM THE PREPOSAL CONFERENCE.doc DOC document
DD_254_DD_Form.doc DOC document
FAR 52.232-16.doc DOC document
E3-110102911.pdf PDF
M3-110102911.pdf PDF
M1-110102911.pdf PDF
M2-110102911.pdf PDF
Solicitation —
FP1-110102911.pdf PDF
M5-110102911.pdf PDF
E2-110102911.pdf PDF
Schedule of Material Submittals.pdf PDF
PPQ —
E1-110102911.pdf PDF
SOW —
M4-110102911.pdf PDF
Past Performance Reference List —
Show all 25

On GovTribe

Work with this file