This is a firm experience document submitted by AECOM in response to the Arizona Department of Transportation's On Call Transit Consultant Services Request for Proposal (BPM007068), specifically addressing Discipline 3: Transit Operations Planning qualifications. AECOM demonstrates extensive experience across multiple transit operations planning categories including route planning, schedule development, service cost estimation, fleet and operational support needs, alternative definition, demand forecasting, and operations and maintenance cost estimation. The proposal documents AECOM's relevant project experience through a detailed table and comprehensive project descriptions covering work completed for Valley Metro (Phoenix), Park City (Utah), Victor Valley Transit (California), VIA Metropolitan Transit (San Antonio), UDOT Cedar City Transit, Chandler, Mesa, DART (Dallas), and CDOT. Key projects highlighted include the Valley Metro Maximum Passenger Load and Running Time Analysis Study, Valley Metro Downtown Hub Bus Routes Study utilizing VISSIM modeling and Remix platform analysis, the Victor Valley Transit Comprehensive Operations Analysis, and the Mesa Transit Master Plan 2050. AECOM emphasizes its 65+ years of experience in Arizona transportation with approximately 200 employees in state offices and its established partnership with ADOT on multiple assignments.
The firm experience document positions AECOM as a qualified contractor capable of executing the broad range of transit operations planning tasks required under the ADOT on-call contract structure. While the document does not address pricing, set-asides, funding sources, or contract financial terms—as those elements are specified in separate proposal sections and the RFP itself—it establishes AECOM's technical qualifications and successful track record delivering transit planning, operations analysis, cost modeling, network redesign, and strategic planning services to transit agencies across the Southwest and beyond. The projects cited demonstrate AECOM's proficiency with industry-standard tools such as Swiftly, Remix, VISSIM, and Python API automation, as well as capabilities in stakeholder engagement, alternatives analysis, and implementation planning required for the twelve-month base term with potential extension to forty-eight months under ADOT's multi-contract, task-order based procurement model.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 1: Transit Planning Studies
Page 1AECOM
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 3: Transit Operations Planning
Page 1AECOM FIRM EXPERIENCE
Firm Experience - Discipline 3: Transit Operations Planning
AECOM proudly presents our firm’s qualifications for the Arizona Department of Transportation (ADOT) request for Discipline 3 (Transit Operations Planning) under the On Call Transit Services solicitation. Having completed a variety of tasks as a trusted partner to ADOT on multiple similar work assignments throughout Arizona, we bring our premier local expertise, supported by national practitioners knowledgeable in all facets of transit services required under this on-call contract.
With over 65 years of experience advancing transportation in Arizona, AECOM brings unparalleled knowledge, with our Arizona offices employing approximately 200 people representing transit and environmental planners, community outreach specialists, and data analysts.
As demonstrated in this section, we are confident our project experience meets the needs of each category and task identified under Discipline 3. Our proposal is formatted to readily present how our team’s qualifications and experience align with the Discipline 3 tasks, with several relevant projects crossing multiple categories. Our team is excited to continue our partnership with ADOT and transit agencies throughout the state to advance transit in Arizona.
DISCIPLINE 3 - TABLE 1 | RELEVANT PROJECT EXPERIENCE
Project Name
Relevant Project Elements
Ro ut e Pl an ni ng
Sc he du le
D ev el op m en t
Es tim at in g Se rv ic e Co st s an d
As so ci at ed F le et
Fl ee t a nd
O pe ra tio na l S up po rt N ee ds
De fin in g
Al te rn at iv es
Ro ut es a nd
Se rv ic e Ty pe
De m an d
Fo re ca st in g
Es tim at in g O pe ra tio ns a nd
M ai nt en an ce C os t
Valley Metro Downtown Hub Bus Routes Study
VIA Metropolitan Transit - Mobility on Demand Support Services
Park City Park & Ride Transit Analysis
Valley Metro Maximum Passenger Load and Running Time Analysis Study
Victor Valley Transit Comprehensive Operations Analysis
UDOT Cedar City Transit Study
Mesa Transit Master Plan 2050
Chandler Transportation Master Plan Update
DART General Planning Consultant
Valley Metro Planning Support Services
CDOT DTR FASTER Transit Capital Program Support Services
Page 2AECOM
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 3: Transit Operations Planning
Page 2AECOM FIRM EXPERIENCE
Relevant Project Descriptions
PARK CITY PARK & RIDE TRANSIT
ANALYSIS | Park City, UT
This study evaluated potential transit service from New Quinn’s Park & Ride lot to the PEG/Vail resort, which is expected to be completed by 2028. AECOM conducted a thorough assessment of transit service characteristics, including proposed routing and stop locations, parking projections for the established horizon years, construction milestones for the resort and parking garages, and fleet inventory. AECOM then developed a service and operations plan for the build-out year of 2028, which included a conceptual schedule and an operations model detailing the recommendation’s total revenue miles and hours. The final deliverable comprised an implementation plan that facilitated phased implementation based on key milestones of construction projects in the study area.
VALLEY METRO MAXIMUM
PASSENGER LOAD AND RUNNING
TIME ANALYSIS STUDY | Phoenix, AZ AECOM analyzed the maximum passenger load, on-time performance, and running times of Valley Metro’s 39 fixed-bus routes. The maximum passenger load for each Valley Metro bus route was analyzed, segmented by vehicle block and day type (weekday, Saturday, and Sunday service) for February 2020, February 2022, and September 2022. Based on the analysis, the appropriate bus length and seating capacity were recommended for future bus purchases and the need to replace 12-year-old 60-foot articulated buses. AECOM and Valley Metro procured a three-month Swiftly license to conduct the on-time performance and running time analysis using Swiftly’s schedule evaluation tools. The data from Swiftly was processed by route, day type (Weekday, Saturday, and Sunday service), time band (AM peak, midday, PM peak, evening, and late-night/early-morning), and seasonal periods (Fall, Spring, Summer) to support a one-year analysis window. A Python script was developed to automate the data exports for each route using Swiftly’s API tool. Further, to ensure the practicality of the recommendations, on-site ride validations were conducted to compare the suggested run times and real-time conditions before implementation.
VALLEY METRO DOWNTOWN HUB
BUS ROUTES STUDY | Phoenix, AZ
Construction of the Valley Metro Light Rail South Central Extension, the Downtown Hub project, and the Phoenix Central Station necessitated rerouting commuter, local, and circulator routes in Downtown Phoenix. Upon completion of construction, the routes need to be returned to prior alignments as soon as possible. AECOM created five different routing scenarios using the Remix platform and developed a final routing recommendation based on post-construction infrastructure conditions, light rail operations, stakeholder feedback, traffic impacts shown through VISSIM modeling, and operational and capital cost comparisons. The interim route recommendation was implemented along with the inauguration of the South- Central extension. The final route implementation is being refined and will be implemented in the upcoming service changes.
VIA METROPOLITAN TRANSIT
- MOBILITY ON DEMAND (MOD)
SUPPORT SERVICES | San Antonio, TX VIA Metropolitan Transit (VIA) broadly explored opportunities to optimize transit network efficiency, that included Mobility on Demand (MOD)/Microtransit services, and other potential future transportation technologies.
Three MOD zones were in operation through a turnkey contract called VIA Link. Additional MOD zones were identified in VIA’s transit plan for implementation in FY 22.
AECOM supported VIA in reviewing RFPs for the MOD rideshare services and MOD innovation zones, by offering suggestions on how to strengthen the RFPs/ addenda based on industry knowledge and best practices.
Additionally, AECOM evaluated operational and maintenance plans that helped VIA determine the full range of opportunities and constraints related to pursuing in-house MOD operations. AECOM conducted research and evaluation of various components for in-house operations, which included vehicle requirements, vehicle types maintenance facility, labor requirements, parking requirements, IT infrastructure, MOD zone management and comparison with turnkey contract. AECOM developed a cost model for operating the MOD services in-house broken down by zone. This included estimates for startup cost (vehicle procurements, technology procurements, staffing cost for administration, etc.) and day-to-day operations cost for each MOD zone.
Page 3AECOM
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 3: Transit Operations Planning
Page 3AECOM FIRM EXPERIENCE
UDOT CEDAR CITY TRANSIT STUDY |
Cedar City, UT
The CCTS is being led by UDOT, in partnership with Cedar City. The study identifies and assesses short- and long-term strategies to enhance public transportation in the Cedar City region and improve fixed-route and paratransit services in the Cedar City study area in Iron County, located in southwest Utah. The plan also explores potential transit connections to nearby communities, including Enoch City, the Town of Brian Head, and surrounding recreational destinations. The study identified key origins, destinations, and unique trip pairs by analyzing Replica trip patterns, focusing on essential locations like grocery stores, health care facilities, and educational institutions.
The study also accounted for recreation and tourism using the skiing visitor data from Brian Head Resort. Additionally, Remix was utilized to develop new routing options for mid-term and long-term scenarios, offering various coverage and frequency options.
VICTOR VALLEY TRANSIT
COMPREHENSIVE OPERATIONS
ANALYSIS | Victor Valley, CA
The Victor Valley Transit Comprehensive Operational Analysis is set at a 7-year horizon to reflect future development and growth. The goal of this COA is to arrest and reverse ridership declines and restructure VVTA’s bus network in Victor Valley to better align with customer needs while making progress towards metrics for high-frequency transit access. The analysis assessed the growth in the high desert region, such as new housing, warehousing, and other developments, to determine current transit needs, along with an onboard survey of existing riders to obtain rider demographics. The re-imagined network resulting from the analysis shall aim to increase transit usage by creating a positive end-to-end user experience that attracts and retains current, former, and future customers.
The assessment of the market and service from this COA resulted in service delivery strategies that would be implemented with existing operating resources.
AECOM was part of the project team that undertook the mission to transform VVTA’s service. The project elements under AECOM’s scope of work included:
| • | Supporting existing system assessment. |
| • | Implementing outreach programs to identify service |
issues.
• Analyzing transfer points in the region and conduct Title
VI analysis for the operation & maintenance facility.
• Supporting the development of alternatives and future needs assessment.
| • | Developing a capital plan for re-imagined system. |
| • | Conducting outreach to solicit public comments on the |
new system.
• Assisting in preparing the final action plan.
Page 4AECOM
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 3: Transit Operations Planning
Page 4AECOM FIRM EXPERIENCE
CHANDLER TRANSPORTATION
MASTER PLAN UPDATE | Chandler, AZ
AECOM developed the transit element of the City of Chandler Transportation Master Plan Update. The transit element folded into the overall Transportation Master Plan update and guided the development of the future transit network. The process used in the preparation of the Transportation Master Plan included a combination of technical research and analysis, coordination with city staff, input from the Transportation Commission, and a series of public and stakeholder engagement activities. The process was incremental, including:
| • | Providing input on vision, goals, and objectives |
| • | Data collection |
| • | Review of prior recommendations |
| • | Analysis and evaluation of the existing transit network |
| • | Analysis and evaluation of existing TNCs and how they |
impact transit use
• Development of recommendations for future transit use and how emerging technologies can support it
• An analysis of potential funding sources for future transit network expansion Key objectives:
| • | Increase transit visibility within Chandler |
| • | Identify opportunities to fund transit enhancements |
| • | Maximize connectivity to the regional transit system |
| • | Integrate community values |
| • | Identify efficiencies for paratransit services |
| • | Lead transit technology innovation in the MAG region |
MESA TRANSIT MASTER PLAN 2050 |
Mesa, AZ
In collaboration with the City of Mesa, AECOM developed the 2050 Transit Master Plan (TMP) to determine the types of transit services, facilities, programs, and system features that will address the city’s short- and long-term needs. The TMP aims to establish a framework for future transit services in Mesa by focusing on productivity, leveraging emerging transit technologies, and evaluating potential new transit markets, while also coordinating with other transportation options such as pedestrian, bicycle, and automobile. Engaging the community and stakeholders was a vital aspect of the TMP’s development.
Mesa’s TMP not only aims to enhance transit efficiency but also adopts an activity center-to-activity center approach, exploring emerging transit technology solutions and linking to major city destinations. This involved a technical assessment of existing transit operations, as well as capital and operational investments, socioeconomic factors, and land use conditions. Alongside TMP efforts, Mesa initiated planning for the General Plan and Transportation Master Plan. Recognizing that elements of the TMP would influence these initiatives, the project team established strategic coordination among the three plans to facilitate their successful development, involving project collaboration, joint outreach activities, and data sharing.
This integration presented a unique opportunity to shape Mesa’s future transit services, enhancing mobility, supporting economic growth, and fostering ridership growth.
Our subconsultant directed public and stakeholder outreach for this initiative, incorporating engaging activities to encourage community involvement, with a focus on creativity, visual appeal, simplicity, and incentives. For instance, the study team participated in “Celebrate Mesa,” a prominent community event in April 2023. Interactive activities centered on a single, straightforward question— creating in-house “ballot boxes” where attendees could “vote” on their preferred future transit modes. They also designed a pop-up banner and t-shirts for staff featuring the same key question. Voters had the chance to win gift certificates. Additionally, interviews were held with the mayor, city council members, the city manager, and assistant/deputy city managers, as well as engaging with stakeholders such as Mesa Community College.
Page 5AECOM
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 3: Transit Operations Planning
Page 5AECOM FIRM EXPERIENCE
DART ON-CALL CONSULTING
SERVICES | Dallas, TX
AECOM mobilized an experienced team of professionals and subconsultants, initiating task orders for a three-year contract supporting the Capital Planning Department at DART. Highlights of AECOM’s projects through the DART con-tracts are detailed below:
• CORE Bus Rapid Transit (BRT) Feasibility Study: The
AECOM team is working with DART to confirm priority projects, preliminary design (10% or other) for projects, schedule, and cost estimates for BRT improvements on 20 key system corridors. The team is developing design guidelines that can be shared with cities and private developers to enhance access to bus routes and better integrate bus stops/amenities.
• City Mobility Area Plans: This project will identify and advance projects, programs or services that can help service area cities and DART achieve their mutual goals.
This collaboration will be done through the development of area plans for each of DART’s 13 cities. Plans will build upon key goals and actions in the DART Transit System Plan and individual city comprehensive, area and/or strategic plans and result in specific recommendations to advance within each city.
• Sustainability Plan: The AECOM team is revising the Sustainability Program to align with DART’s Strategic Vision for seamless integration within the community and to be seen as an economic asset. AECOM is working with DART to update the Sustainability Policy and Plan to take a holistic approach toward enhancing sustainability by not only reducing the environmental footprint but also integrating with the communities. The goal of the project is to help DART reach APTA Silver or Gold level for Sustainability.
• Mobility Hub Concept Plan: The project team is developing three designs for future mobility hubs in the DART service area. The plans incorporate components of the DART Mobility Hub Guidelines, Climate Action Plan, and Strategic Plan. The conceptual designs include land use efficiency, safety and security, sustainability enhancements, and a suite of amenities such as bike/ scooter sharing, pop-up markets, park space and real time information monitors . The first two mobility hub designs have been developed for the Lawnview Station and Deep Ellum Station.
VALLEY METRO PLANNING SUPPORT
SERVICES | Phoenix, AZ
AECOM has served as a partner to Valley Metro through the Planning Support Services contract since 2007 as either a prime or subcontractor.
AECOM has collaborated with Valley Metro and its regional partners to provide comprehensive planning services to support the development and enhancement of transit systems across the Phoenix metropolitan area. Some of the key projects underway or successfully completed in the last 10 years include:
• Capitol/I-10 West Light Rail Extension: AECOM led the alternatives analysis (AA) phase to evaluate potential high-capacity transit (HCT) improvements and determine the locally preferred alternative for a transit investment in the I-10 West Corridor. AECOM conducted technical analyses, including traffic studies, travel demand modeling analysis, development of design and operations concepts, and environmental review. AECOM is currently supporting Valley Metro’s work to advance the original project as two separate projects – CAPEX to the State Capitol Complex, and 10WEST to the Desert Sky Transit Center.
• Valley Metro Fiesta District Alternatives Analysis:
The City of Mesa initiated the Fiesta District AA, in partnership with Valley Metro, to explore the potential of expanding HCT to serve the Fiesta District. This AA included extensive stakeholder and public outreach, multidisciplinary technical analysis, and final acceptance of a Locally Preferred Alternative (LPA).
• Transit Stop Inventory and Accessibility Study:
AECOM evaluated and documented accessibility criteria and compliance of bus stops with the Americans with Disabilities Act (ADA). In the field, teams used Collector, a mobile application, to document and photograph bus stops. Since the field survey and inventory in 2017, Valley Metro has used this information to prioritize funding for cities with bus stops that do not meet ADA requirements.
• Phoenix South Central Corridor HCT: The purpose of the AA was to consider alternative HCT transit modes and routes, including a No-Build option, to develop and present an LPA for subsequent planning and design.
AECOM later supported the final design for the South Central corridor.
Page 6AECOM
Arizona Department of Transportation On Call Transit Consultant Services BPM007068 Discipline 3: Transit Operations Planning
Page 6AECOM FIRM EXPERIENCE
CDOT DTR FASTER TRANSIT CAPITAL
PROGRAM SUPPORT SERVICES |
Colorado
AECOM led strategy and development of CDOT Division of Transit and Rail’s first capital program under Colorado Senate Bill 267/260 funding.
AECOM provided planning and design support for DTR’s Mobility Hub Program.
This includes developing a handbook that sets forth guidelines and a framework to plan and implement mobility hubs. The Mobility Hub Handbook focuses on Bustang Mobility Hubs. Most of these Hubs are in urban areas with higher projected ridership. AECOM also developed project control tools to carry transit projects from planning initiatives and project selection through design and construction. Services also included producing quarterly reports for the Colorado Transportation Commission, preliminary engineering/design, capital cost estimating, and design review.
The project consisted of:
| • | Completion of the Mobility Hub Handbook. |
| • | Completion of the Bustang Mobility Hub Signage |
Standards used throughout the Bustang system statewide.
• Delivery of the four-year Senate Bill 267 Program. This program provided DTR with $192M for capital projects related to transit facilities, including Mobility Hubs and maintenance facilities. Work included:
| • | Preliminary cost estimates for all projects. |
| • | Equity Analysis for each Transportation Planning Region |
(TPR) and Metropolitan Planning Organization (MPO).
• Annual plan development and associated materials presented to the CDOT Transportation Commission.
• Quarterly progress reports to the CDOT Transportation
Commission.