This document is a Design-Build Compensation Matrix prepared for the University of Rhode Island's Permanent PFAS Water Treatment Facility project in Rhode Island. The matrix serves as a reference tool for the design-build delivery method, establishing the framework for compensation across various project phases and deliverables associated with the design, build, and construction of a permanent PFAS water treatment facility at URI. The compensation structure is organized to accommodate the integrated design-build approach, where a single entity is responsible for both the design and construction phases of the facility. The matrix provides clarity on payment schedules and compensation breakdowns tied to specific project milestones, phases, or deliverables, enabling transparent financial management throughout the project lifecycle from initial design through final construction completion.
The compensation matrix establishes the financial terms and conditions governing the design-build contractor's payment structure, including any phase-based compensation, milestone payments, or performance-based incentives. This matrix facilitates cost certainty for the University of Rhode Island while ensuring the design-build contractor has defined compensation expectations aligned with project phases and deliverables. The use of a design-build delivery method for this PFAS treatment facility represents an integrated procurement approach intended to optimize project efficiency, coordination between design and construction teams, and overall project delivery performance. The matrix supports the competitive bidding process by providing all prospective bidders with identical compensation framework parameters.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP Exhibit I – Design Build Compensation Matrix
Design Build COMPENSATION MATRIX for Vendor Information ONLY.
No vendor completion needed.
RFP for Design, Build, PFAS Water Treatment Plant Project
EXHIBIT "I"
Included in DB Fee
Included in DB General Conditions
Included in DB General
Requirements
Supplied by Trade
Subs
Supplied by Owner
Officers' Salaries and Benefits X
Home Office Overhead X
Home Office Transportation X
Safety Compliance Material X
Safety Plan X
Cash Flow Projection X
CM Legal and Audit Expenses X
Sales Expense X
Computer Time X
Profit X
Records Storage X
Estimating and Value Engineering X
Constructability Review X
Site Logistics Plan X
Monthly Reports X
Secretarial Services X
Contract Document Review X
Procurement Services prior to Construction X
Scheduling X
Monthly Payment Applications X
Construction Supervisory Staff: - - - -
Operations Manager X
Project Manager X
Project Engineer X
Project Superintendent 1 X
Project Superintendent 2 X
MEP Coordinator X
Site Office Clerk-Admin X
Field Offices: - - - -
Telephone / Internet lines & equip. X
Computers X
Communication equipment (radios) X
Furniture X
Equipment X
Photocopying X
Drinking Water X
First Aid Supplies X
Utility consumption (office only) X
Office janitorial service X
Federal Express, postage, other delivery costs X
Insurance X
Payroll Burden and Taxes X
Progress Photos X
Temporary Toilets and Enclosures X
Temporary Fences and Gates X
CM Fee & Pre-Con
Fee
Included in CM General Conditions
CM General Requiremen ts
Supplied by Trade
Subs
Supplied by Owner
Sidewalk Protection X
Building Perimeter Protection X
Winter Protection X
Trash chutes / hoppers X
Interim and Final clean-up X
Rubbish removal / dumpsters X
Snow removal X
Glass cleaning X
Ladders, ramps, and stairs X
Temporary Dust Partitions X
Temporary utility connection fees X
Temporary Plumbing X
Temporary Electrical - Install and maintain X
Temporary Electrical - consumption X
Temporary Heat - Fuel consumption X
Temporary Water - consumption X
Temporary Fire Protection X
Temporary Roads (construct & maintain) X
Temporary safety/security barricades X
Mud / dust control X
Wheelwash stations X
Shed / storage rental X
Project Signage X
Pest Control X
Blueprint Shop Drawings X
Small Tools and Supplies X
Land Surveyor site benchmarks layout X
Land Surveyor other layout X
Field Engineering services X
Travel expenses (gas, tolls, parking) X X
Testing - concrete, soils, steel, mortar X
Building Permit X
State ADA Fee X
Personnel hoist equipment and operation X
Material hoist equipment and operation X
Traffic Control X
Security / Watchman X
Miscellaneous cutting and patching X
Mock-ups X
State Elevator Permit X
Builder's Risk Insurance X
Bid Documents Printing X
Ceremonies X
Special Inspector X
Payment and Performance Bond X