CR232410_Backup_Exhibit G Project Schedule.pdf
PDF 254 KB Posted
- Solicitation number
- RFP27007069
- Issued by
- Providence County, Rhode Island
About this file
This is a project schedule exhibit for the University of Rhode Island's permanent PFAS water treatment facility design-build program, developed in coordination with Weston & Sampson and state purchasing agencies. The project encompasses the design, construction, and operationalization of a permanent water treatment facility to address per- and polyfluoroalkyl substances contamination in URI's water supply. The schedule establishes two parallel procurement tracks: an operations contract and a design-build contract, both commencing January 23, 2023, with completion targeted for January 31, 2029. Key procurement milestones include RFP posting on August 4-5, 2026; a pre-bid meeting scheduled for August 5-11, 2026; a Q&A period running through September 10, 2026; addenda issuance through September 21, 2026; and bid opening on September 22-24, 2026. The design-build contract execution includes tentative award on September 24, 2026, state purchase order issuance by November 30, 2026, and pre-construction activities commencing December 1, 2026. Construction is scheduled to begin November 22, 2027, and conclude December 15, 2028, with system startup and final regulatory approvals extending through January 31, 2029.
The project schedule identifies multiple stakeholder coordination requirements across state and university departments, including URI Purchasing, Risk Management, Office of General Counsel, Business Office, Rhode Island Department of Health, Rhode Island Department of Environmental Management, and the Rhode Island State Building Code Office. The design-build vendor is responsible for producing 30 percent design plans by February 19, 2027, responding to URI comments by March 2, 2027, and obtaining necessary regulatory approvals from RIDOH, RIDEM, and RISBCC by April 13, 2027. The schedule establishes guaranteed maximum price negotiation based on approved plans by April 22, 2027, with construction spanning 280 days. Final inspections and regulatory approvals by RIDOH and RISBCC are scheduled for completion by January 31, 2029. The operations contract track parallels the design-build schedule through purchase order issuance, with the new operations vendor engaged for co-management during facility startup and transitioning to full facility management by January 31, 2029.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP Exhibit G – Project Schedule
ID ID Task Name Duration Start Finish Predecessors
1 1 PFAS Water Treatment Facility Program 1 day Mon 1/23/23 Mon 1/23/23
2 2 Rescind DBO contract 0 days Mon 5/4/26 Mon 5/4/26
3 3 Operations Contract 1573 days? Mon 1/23/23 Wed 1/31/29
4 4 W&S review of Operation Contract, best practices 22 days Thu 5/21/26 Fri 6/19/26 2
5 5 URI Coordination with URI and State Purchasing 14 days Mon 6/22/26 Thu 7/9/26 4
6 6 URI discussion of Operational Options 14 days Mon 6/22/26 Thu 7/9/26 4
7 7 URI Coordination with Risk Management 14 days Mon 6/22/26 Thu 7/9/26 4
8 8 URI Coordination with OGC/external legal 22 days Mon 6/22/26 Tue 7/21/26 4
9 9 Prepare and distribute draft operations contract for internal review 7 days Wed 7/22/26 Thu 7/30/26 8,5,6,7
10 10 Affirm CFS funding, issue CR, commence bidding 3 days Fri 7/31/26 Tue 8/4/26 9
11 11 RFP posted on RIDOA Purchasing website 0 days Tue 8/4/26 Tue 8/4/26 10
12 12 Pre-bid meeting 5 days Wed 8/5/26 Tue 8/11/26 11
13 13 Q&A period 22 days Wed 8/12/26 Thu 9/10/26 12
14 14 Issue Addenda 7 days Fri 9/11/26 Mon 9/21/26 13
15 15 Bid Opening 3 days Tue 9/22/26 Thu 9/24/26 14
16 16 Tentative Award Letter issued 0 days Thu 9/24/26 Thu 9/24/26 15
17 17 Pre-award meeting 5 days Fri 9/25/26 Thu 10/1/26 16
18 18 State Purchase Order issued 42 days Fri 10/2/26 Mon 11/30/26 17
19 19 URI Purchase Order issued 0 days Mon 11/30/26 Mon 11/30/26 18
20 20 Pre-operations meeting w/ design-build vendor, URI team 5 days Tue 12/1/26 Mon 12/7/26 19
21 21 New Operations vendor co-management of new PFAS faciliity 3 mons Fri 4/7/28 Thu 6/29/28 56
22 22 New Operations vendor management of new PFAS facility 0 days Wed 1/31/29 Wed 1/31/29 59
5/4
URI staff,Weston & Sampson
URI Purchasing,URI staff
URI staff,URI Utilities
Katie Kohm Esq.,URI OGC,URI Purchasing,URI staff
Katie Kohm Esq.,URI Purchasing,URI staff
URI CPDD
URI Business Office,URI CPDD
8/4
RIDOA Purchasing,URI CPDD,Weston & Sampson
RIDOA Purchasing,URI CPDD,Weston & Sampson,URI Utilities
RIDOA Purchasing,URI CPDD,URI Utilities,Weston & Sampson
RIDOA Purchasing
9/24
Operations Vendor,URI CPDD,URI Utilities,Weston & Sampson
RIDOA Purchasing
11/30
Northeast Water Solutions,Operations Vendor,URI CPDD,URI Utilities,Weston & Sampson
Northeast Water Solutions,Operations Vendor,URI CPDD,URI Utilities
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Permanent PFAS Facilit
Date: Mon 8/24/26
ID ID Task Name Duration Start Finish Predecessors
23 23 1 day? Mon 1/23/23 Mon 1/23/23
24 24 Design-Build Contract 1573 days? Mon 1/23/23 Wed 1/31/29
25 25 1 day? Mon 1/23/23 Mon 1/23/23
26 26 W&S review of DBO bid results, validate changes in scope 22 days Thu 5/21/26 Fri 6/19/26 2
27 27 CPDD review and discussion of cost increases, update schedule & cashflow
10 days Tue 6/30/26 Mon 7/13/26 26
28 28 Update Consent Agreement schedule with RIDOH via Mike Donnegan 45 days Mon 6/22/26 Fri 8/21/26 26
29 29 Request authorization for DB approach via State of RI 7 days Tue 7/14/26 Wed 7/22/26 27
30 30 URI coordination with Risk Management 10 days Tue 7/14/26 Mon 7/27/26 27
31 31 URI coordination with OGC/external legal 14 days Tue 7/14/26 Fri 7/31/26 27
32 32 URI coordination with URI Treasury and Business Office 14 days Tue 7/14/26 Fri 7/31/26 27
33 33 Affirm CFS funding, issue CR, commence bidding 3 days Mon 8/3/26 Wed 8/5/26 31
34 34 RFP posted on RIDOA Purchasing website 0 days Wed 8/5/26 Wed 8/5/26 33
35 35 Pre-bid meeting 1 day Thu 8/6/26 Thu 8/6/26 34
36 36 Q&A period 22 days Fri 8/7/26 Mon 9/7/26 35
37 37 Issue addenda 10 days Tue 9/8/26 Mon 9/21/26 36
38 38 Bid Opening 3 days Tue 9/22/26 Thu 9/24/26 37
39 39 Tentative Award Letter Issued 0 days Thu 9/24/26 Thu 9/24/26 38
40 40 Pre-award meeting 5 days Fri 9/25/26 Thu 10/1/26 39
41 41 State Purchase Order issued 42 days Fri 10/2/26 Mon 11/30/26 40
42 42 URI Purchase Order issued 0 days Mon 11/30/26 Mon 11/30/26 41
43 43 Pre-construction meeting 7 days Tue 12/1/26 Wed 12/9/26 42
44 44 Affirmation of base scope, cost estimating, billable line items 7 days Thu 12/10/26 Fri 12/18/26 43
45 45 Vendor produces 30% design plans for URI review and approval 45 days Mon 12/21/26 Fri 2/19/27 44
46 46 Vendor responds to URI comments, adjusts plans 7 days Mon 2/22/27 Tue 3/2/27 45
47 47 Vendor sends Construction Phase Application to RIDOH for approval 30 days Wed 3/3/27 Tue 4/13/27 46
48 48 Submit preliminary plans to SBCC/SFMO for information 7 days Wed 3/3/27 Thu 3/11/27 46
49 49 Vendor submits updated RIPDES/stormwater plans to RIDEM for approval
30 days Wed 3/3/27 Tue 4/13/27 46
50 50 RIDOH design approval 0 days Tue 4/13/27 Tue 4/13/27 47
51 51 SBCC permit approval and/or concurrance 0 days Thu 3/11/27 Thu 3/11/27 48
52 52 RIDEM permit approval 0 days Tue 4/13/27 Tue 4/13/27 49
53 53 DB Vendor completes design & pricing 20 days Fri 3/12/27 Thu 4/8/27 51
54 54 URI and vendor negotiate GMP pricing based on appoved plans, issue
Exhibit A
10 days Fri 4/9/27 Thu 4/22/27 53
55 55 URI DB vendor construction of permanent water treatment facility 280 days Mon 11/22/27 Fri 12/15/28 54
56 56 Startup of new system, engage new Operations vendor 250 days Fri 4/23/27 Thu 4/6/28 54
57 57 RIDOH, RISBCC Final Inspections, 128 forms 7 days Mon 12/18/28 Tue 12/26/28 55
58 58 RIDOH issues Final Approval 26 days Wed 12/27/28 Wed 1/31/29 57
59 59 RISBCC issues Certificate of Completion 26 days Wed 12/27/28 Wed 1/31/29 57
60 60 URI Permanent Water Treatment Facility Online 0 days Tue 12/26/28 Tue 12/26/28 57
Katie Kohm Esq.,URI CPDD,URI Utilities,Weston & Sampson
URI Business Office,URI CPDD,URI Utilities,Weston & Sampson
Mike Donnegan Esq.,URI CPDD,URI OGC,URI Utilities
RIDOA Purchasing,URI CPDD,URI Purchasing
Katie Kohm Esq.,RIDOA Purchasing,URI CPDD,URI Utilities
Katie Kohm Esq.,RIDOA Legal,RIDOA Purchasing,URI CPDD,URI Utilities,Weston & Sampson
URI Business Office,URI CPDD,URI Treasury
RIDOA Purchasing,RIDOH,URI Business Office,URI CPDD,URI Purchasing
8/5
RIDOA Purchasing,URI CPDD,URI Utilities,Weston & Sampson
RIDOA Purchasing,URI CPDD,URI Utilities,Weston & Sampson
RIDOA Purchasing,URI CPDD,URI Utilities,Weston & Sampson
RIDOA Purchasing
9/24
URI CPDD,URI Utilities,Weston & Sampson
RIDOA Purchasing
11/30
DB Vendor,URI CPDD,URI Utilities,Weston & Sampson
DB Vendor,URI Business Office,URI CPDD
DB Vendor,URI CPDD,URI Utilities,Weston & Sampson
DB Vendor,URI CPDD,URI Utilities,Weston & Sampson
DB Vendor,RIDOH,URI CPDD,URI Utilities,Weston & Sampson
DB Vendor,RISBCC,URI CPDD,Weston & Sampson
DB Vendor,RIDEM,URI CPDD,URI Utilities,Weston & Sampson
4/13
3/11
4/13
DB Vendor,URI CPDD,URI Utilities,Weston & Sampson
DB Vendor,RIDOA Purchasing,URI CPDD,URI OGC,URI Purchasing,URI Utilities,Weston & Sampson
DB Vendor,URI CPDD,URI Utilities,Weston & Sampson
DB Vendor,Northeast Water Solutions,Operations Vendor,URI CPDD,Weston & Sampson
DB Vendor,RIDOH,RISBCC,URI CPDD,URI Utilities,Weston & Sampson
12/26
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Permanent PFAS Facilit
Date: Mon 8/24/26
File details come from the government source that posted it. Updated .