This document is a Request for Proposal (RFP) for the Federal Deposit Insurance Corporation's (FDIC) National Conference Room Audio Visual Basic Ordering Agreement (BOA). The solicitation seeks a contractor to transform conference rooms across multiple FDIC regional offices, with an initial Task Order focused on the Atlanta location at 10 10th Street NE. The BOA covers hardware, software, and services for audio/visual upgrades in conference rooms, with pricing structured across five years and multiple room configurations (Mobile, Small, Medium, Large), and requires detailed pricing submissions in an Excel workbook.
Key solicitation details include a proposal due date of 1 p.m. EDT on October 15, 2025, with a site visit for the Atlanta Regional Office scheduled for August 26-27, 2025. The procurement involves comprehensive audio/visual system upgrades, requiring offerors to provide labor rates for key personnel categories including Program Manager, Solution Architect, Installer/Engineer, and Programmer across eight FDIC locations. Offerors must complete specific pricing templates, with potential task orders spanning multiple years and room configurations, and must comply with detailed site-specific requirements for installation, staging, and workplace conduct across various FDIC regional offices.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/AWARD
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. CONTACT INFORMATION 8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. N/A
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ RFP
Price only
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. N/A 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL
SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF.
YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH
HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. FEDERAL DEPOSIT INSURANCE CORPORATION (SIGNATURE OF CO)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
FDIC 3700/55 (3-08)
10. SOCIO-ECONOMIC STATUS
NO
NAICS:
ETHNICITY:
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
OFFER
13a. SUB-CONTRACTING
PERMITTED/APPROVED
YES
SDB
MWOB
SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
YES NO
YES NO
27a. SOLICITATION INCLUDES ATTACHMENTS 27b. AWARD INCLUDES ATTACHMENTS
RFI RFP
Best Value
CORHQ-25-R-0121
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
FDIC 3700/55 (3-08)
Section B - Supplies or Services and Prices/Costs
CLIN # Description Quantity Unit Unit Price Total Price
0001 HW/SW/Services for National Conference
Room A/V BOA
1 EA
Attachments for this section start after this page.
Section B - Supplies or Services and Prices/Costs PAGE 3 OF 141
CONTROLLED//FDIC INTERNAL ONLY#
1. General Instructions Do not modify the structure of this Excel file.
Offeror shall only enter data in the green-shaded cells. All other cells and tabs have calculated fields or contain data entered by FDIC.
Any proposal failing to complete ANY portion with the exception of the "Labor Rates" tab of this pricing workbook may be considered non-responsive.
2. "Labor Rates" Tab
3. Room Configuration "Mobile - Large" Tabs 3-6.
Offerors are required to complete all tabs (Mobile, Small, Medium, and Large), for all years (Year 1 - Year 5). Offerors will be required to provide all equipment associated with each standard room confiugration in the appropriate tabs. Offerors can add or remove rows as needed, but are not allowed to change the other structure of the price workbook (For example; deleting columns). Due to the nature of the rooms, a standard kit (for example; Medium) kit may be modified (add or remove items to fit the requirements of a given room. Offerors will propose yearly Operation and Maintenace (O&M) price in all years (1-5) for the BOA. However, O&M will be will be prorated at the task order level from the installation completion date. Pricing for Specialized Rooms will be done at the Task Order level due to their unique and complex nature.
Offerors are to input labor rates inthe eight locations for all years (1-5). Offeror(s) who are awarded the BOA, but did not propose labor rates in any given location may not be considered for Task Orders in that location. The first four labor rates (Program Manager, System Architech, Installer/Engineer, Programmer) are from the SOO. Use the "Optional" rows for any additional labor rates. If Offeror is not proposing additional labor categories may remove the "Optional" rows. Offerors are also required to provide shipping cost for each standard kit for all locations.
Section B - Supplies or Services and Prices/Costs PAGE 4 OF 141
NONPUBLIC//FDIC BUSINESS#
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
HQ - Virgina Square (VASQ)
Atlanta
Boston
Chicago
Section B - Supplies or Services and Prices/Costs PAGE 5 OF 141
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
Labor Category Year 1 Year 2 Year 3 Year 4 Year 5 Program Manager Solution Archtect Installer/Engineer Programmer Optional Optional Optional Room Configuration Mobile - Shipping Room Configuration Small - Shipping Room Configuration Medium - Shipping Room Configuration Large - Shipping
New York
San Francisco
Dallas
Kansas City
Section B - Supplies or Services and Prices/Costs PAGE 6 OF 141
Item Number
Item # Description Manufacturer Part # Qty Serial # Year 1 Unit Price
(Monthly Price for O&M)
Total Year 1 Price
Year 2 Unit Price (Monthly Price for O&M)
Total Year 2 Price
Year 3 Unit Price (Monthly Price for O&M)
Total Year 3 Price
Year 4 Unit Price (Monthly Price for O&M)
Total Year 4 Price
Year 5 Unit Price (Monthly Price for O&M)
Total Year 5 Price
1 $0.00 $0.00 $0.00 $0.00 $0.00
2 $0.00 $0.00 $0.00 $0.00 $0.00
3 $0.00 $0.00 $0.00 $0.00 $0.00
4 $0.00 $0.00 $0.00 $0.00 $0.00
5 $0.00 $0.00 $0.00 $0.00 $0.00
6 $0.00 $0.00 $0.00 $0.00 $0.00
7 $0.00 $0.00 $0.00 $0.00 $0.00
8 $0.00 $0.00 $0.00 $0.00 $0.00
9 $0.00 $0.00 $0.00 $0.00 $0.00
10 $0.00 $0.00 $0.00 $0.00 $0.00
11 $0.00 $0.00 $0.00 $0.00 $0.00
12 $0.00 $0.00 $0.00 $0.00 $0.00
13 $0.00 $0.00 $0.00 $0.00 $0.00
14 $0.00 $0.00 $0.00 $0.00 $0.00
15 $0.00 $0.00 $0.00 $0.00 $0.00
16 $0.00 $0.00 $0.00 $0.00 $0.00
17 $0.00 $0.00 $0.00 $0.00 $0.00
18 $0.00 $0.00 $0.00 $0.00 $0.00
19 $0.00 $0.00 $0.00 $0.00 $0.00
20 $0.00 $0.00 $0.00 $0.00 $0.00
21 $0.00 $0.00 $0.00 $0.00 $0.00
22 $0.00 $0.00 $0.00 $0.00 $0.00
23 $0.00 $0.00 $0.00 $0.00 $0.00
24 $0.00 $0.00 $0.00 $0.00 $0.00
25 $0.00 $0.00 $0.00 $0.00 $0.00
26 $0.00 $0.00 $0.00 $0.00 $0.00
27 $0.00 $0.00 $0.00 $0.00 $0.00
28 $0.00 $0.00 $0.00 $0.00 $0.00
29 $0.00 $0.00 $0.00 $0.00 $0.00
30 $0.00 $0.00 $0.00 $0.00 $0.00
31 $0.00 $0.00 $0.00 $0.00 $0.00
32 $0.00 $0.00 $0.00 $0.00 $0.00
33 $0.00 $0.00 $0.00 $0.00 $0.00
34 $0.00 $0.00 $0.00 $0.00 $0.00
35 $0.00 $0.00 $0.00 $0.00 $0.00
36 $0.00 $0.00 $0.00 $0.00 $0.00
37 $0.00 $0.00 $0.00 $0.00 $0.00
38 $0.00 $0.00 $0.00 $0.00 $0.00
39 $0.00 $0.00 $0.00 $0.00 $0.00
40 $0.00 $0.00 $0.00 $0.00 $0.00
41 $0.00 $0.00 $0.00 $0.00 $0.00
42 $0.00 $0.00 $0.00 $0.00 $0.00
43 $0.00 $0.00 $0.00 $0.00 $0.00
44 $0.00 $0.00 $0.00 $0.00 $0.00
45 $0.00 $0.00 $0.00 $0.00 $0.00
46 $0.00 $0.00 $0.00 $0.00 $0.00
47 $0.00 $0.00 $0.00 $0.00 $0.00
48 $0.00 $0.00 $0.00 $0.00 $0.00
50 $0.00 $0.00 $0.00 $0.00 $0.00
51 Operations and Maintenance Support - (In accordance with in Section 3.4 of the
SOO)
$0.00 $0.00 $0.00 $0.00 $0.00
Mobile Year 1 Total $0.00 Mobile Year 2 Total $0.00 Mobile Year 3 Total $0.00 Mobile Year 4 Total $0.00 Mobile Year 5 Total $0.00
Year 2 Year 3 Year 4 Year 5 Mobile Configuration
Year 1
Section B - Supplies or Services and Prices/Costs PAGE 7 OF 141
Item # Description Manufacturer Part # Qty Serial # Year 1 Unit Price
(Monthly Price for O&M)
Total Year 1 Price
Year 2 Unit Price (Monthly Price for
O&M)
Total Year 2 Price
Year 3 Unit Price (Monthly Price for
O&M)
Total Year 3 Price
Year 4 Unit Price (Monthly Price for
O&M)
Total Year 4 Price
Year 5 Unit Price (Monthly Price for
O&M)
Total Year 5 Price
1 $0.00 $0.00 $0.00 $0.00 $0.00
2 $0.00 $0.00 $0.00 $0.00 $0.00
3 $0.00 $0.00 $0.00 $0.00 $0.00
4 $0.00 $0.00 $0.00 $0.00 $0.00
5 $0.00 $0.00 $0.00 $0.00 $0.00
6 $0.00 $0.00 $0.00 $0.00 $0.00
7 $0.00 $0.00 $0.00 $0.00 $0.00
8 $0.00 $0.00 $0.00 $0.00 $0.00
9 $0.00 $0.00 $0.00 $0.00 $0.00
10 $0.00 $0.00 $0.00 $0.00 $0.00
11 $0.00 $0.00 $0.00 $0.00 $0.00
12 $0.00 $0.00 $0.00 $0.00 $0.00
13 $0.00 $0.00 $0.00 $0.00 $0.00
14 $0.00 $0.00 $0.00 $0.00 $0.00
15 $0.00 $0.00 $0.00 $0.00 $0.00
16 $0.00 $0.00 $0.00 $0.00 $0.00
17 $0.00 $0.00 $0.00 $0.00 $0.00
18 $0.00 $0.00 $0.00 $0.00 $0.00
19 $0.00 $0.00 $0.00 $0.00 $0.00
20 $0.00 $0.00 $0.00 $0.00 $0.00
21 $0.00 $0.00 $0.00 $0.00 $0.00
22 $0.00 $0.00 $0.00 $0.00 $0.00
23 $0.00 $0.00 $0.00 $0.00 $0.00
24 $0.00 $0.00 $0.00 $0.00 $0.00
25 $0.00 $0.00 $0.00 $0.00 $0.00
26 $0.00 $0.00 $0.00 $0.00 $0.00
27 $0.00 $0.00 $0.00 $0.00 $0.00
28 $0.00 $0.00 $0.00 $0.00 $0.00
29 $0.00 $0.00 $0.00 $0.00 $0.00
30 $0.00 $0.00 $0.00 $0.00 $0.00
31 $0.00 $0.00 $0.00 $0.00 $0.00
32 $0.00 $0.00 $0.00 $0.00 $0.00
33 $0.00 $0.00 $0.00 $0.00 $0.00
34 $0.00 $0.00 $0.00 $0.00 $0.00
35 $0.00 $0.00 $0.00 $0.00 $0.00
36 $0.00 $0.00 $0.00 $0.00 $0.00
37 $0.00 $0.00 $0.00 $0.00 $0.00
38 $0.00 $0.00 $0.00 $0.00 $0.00
39 $0.00 $0.00 $0.00 $0.00 $0.00
40 $0.00 $0.00 $0.00 $0.00 $0.00
41 $0.00 $0.00 $0.00 $0.00 $0.00
42 $0.00 $0.00 $0.00 $0.00 $0.00
43 $0.00 $0.00 $0.00 $0.00 $0.00
44 $0.00 $0.00 $0.00 $0.00 $0.00
45 $0.00 $0.00 $0.00 $0.00 $0.00
46 $0.00 $0.00 $0.00 $0.00 $0.00
47 $0.00 $0.00 $0.00 $0.00 $0.00
48 $0.00 $0.00 $0.00 $0.00 $0.00
50 $0.00 $0.00 $0.00 $0.00 $0.00
51 Operations and Maintenance Support - (In accordance with in Section 3.4 of the
SOO)
$0.00 $0.00 $0.00 $0.00 $0.00
Small Year 1 Total $0.00 Small Year 2 Total $0.00 Small Year 3 Total $0.00 Small Year 4 Total $0.00 Small Year 5 Total $0.00
Year 5 Small Configuration
Year 1 Year 2 Year 3 Year 4
Section B - Supplies or Services and Prices/Costs PAGE 8 OF 141
Item # Description Manufacturer Part # Qty Serial # Year 1 Unit Price
(Monthly Price for O&M)
Total Year 1 Price
Year 2 Unit Price (Monthly Price for
O&M)
Total Year 2 Price
Year 3 Unit Price (Monthly Price for
O&M)
Total Year 3 Price
Year 4 Unit Price (Monthly Price for
O&M)
Total Year 4 Price
Year 5 Unit Price (Monthly Price for
O&M)
Total Year 5 Price
1 $0.00 $0.00 $0.00 $0.00 $0.00
2 $0.00 $0.00 $0.00 $0.00 $0.00
3 $0.00 $0.00 $0.00 $0.00 $0.00
4 $0.00 $0.00 $0.00 $0.00 $0.00
5 $0.00 $0.00 $0.00 $0.00 $0.00
6 $0.00 $0.00 $0.00 $0.00 $0.00
7 $0.00 $0.00 $0.00 $0.00 $0.00
8 $0.00 $0.00 $0.00 $0.00 $0.00
9 $0.00 $0.00 $0.00 $0.00 $0.00
10 $0.00 $0.00 $0.00 $0.00 $0.00
11 $0.00 $0.00 $0.00 $0.00 $0.00
12 $0.00 $0.00 $0.00 $0.00 $0.00
13 $0.00 $0.00 $0.00 $0.00 $0.00
14 $0.00 $0.00 $0.00 $0.00 $0.00
15 $0.00 $0.00 $0.00 $0.00 $0.00
16 $0.00 $0.00 $0.00 $0.00 $0.00
17 $0.00 $0.00 $0.00 $0.00 $0.00
18 $0.00 $0.00 $0.00 $0.00 $0.00
19 $0.00 $0.00 $0.00 $0.00 $0.00
20 $0.00 $0.00 $0.00 $0.00 $0.00
21 $0.00 $0.00 $0.00 $0.00 $0.00
22 $0.00 $0.00 $0.00 $0.00 $0.00
23 $0.00 $0.00 $0.00 $0.00 $0.00
24 $0.00 $0.00 $0.00 $0.00 $0.00
25 $0.00 $0.00 $0.00 $0.00 $0.00
26 $0.00 $0.00 $0.00 $0.00 $0.00
27 $0.00 $0.00 $0.00 $0.00 $0.00
28 $0.00 $0.00 $0.00 $0.00 $0.00
29 $0.00 $0.00 $0.00 $0.00 $0.00
30 $0.00 $0.00 $0.00 $0.00 $0.00
31 $0.00 $0.00 $0.00 $0.00 $0.00
32 $0.00 $0.00 $0.00 $0.00 $0.00
33 $0.00 $0.00 $0.00 $0.00 $0.00
34 $0.00 $0.00 $0.00 $0.00 $0.00
35 $0.00 $0.00 $0.00 $0.00 $0.00
36 $0.00 $0.00 $0.00 $0.00 $0.00
37 $0.00 $0.00 $0.00 $0.00 $0.00
38 $0.00 $0.00 $0.00 $0.00 $0.00
39 $0.00 $0.00 $0.00 $0.00 $0.00
40 $0.00 $0.00 $0.00 $0.00 $0.00
41 $0.00 $0.00 $0.00 $0.00 $0.00
42 $0.00 $0.00 $0.00 $0.00 $0.00
43 $0.00 $0.00 $0.00 $0.00 $0.00
44 $0.00 $0.00 $0.00 $0.00 $0.00
45 $0.00 $0.00 $0.00 $0.00 $0.00
46 $0.00 $0.00 $0.00 $0.00 $0.00
47 $0.00 $0.00 $0.00 $0.00 $0.00
48 $0.00 $0.00 $0.00 $0.00 $0.00
50 $0.00 $0.00 $0.00 $0.00 $0.00
51 Operations and Maintenance Support - (In accordance with in Section 3.4 of the
SOO)
$0.00 $0.00 $0.00 $0.00 $0.00
Medium Year 1 Total $0.00 Medium Year 2 Total $0.00 Medium Year 3 Total $0.00 Medium Year 4 Total $0.00 Medium Year 5 Total $0.00
Year 5 Medium Configuration
Year 1 Year 2 Year 3 Year 4
Section B - Supplies or Services and Prices/Costs PAGE 9 OF 141
Item # Description Manufacturer Part # Qty Serial # Year 1 Unit Price
(Monthly Price for O&M)
Total Year 1 Price
Year 2 Unit Price (Monthly Price for
O&M)
Total Year 2 Price
Year 3 Unit Price (Monthly Price for
O&M)
Total Year 3 Price
Year 4 Unit Price (Monthly Price for
O&M)
Total Year 4 Price
Year 5 Unit Price (Monthly Price for
O&M)
Total Year 5 Price
1 $0.00 $0.00 $0.00 $0.00 $0.00
2 $0.00 $0.00 $0.00 $0.00 $0.00
3 $0.00 $0.00 $0.00 $0.00 $0.00
4 $0.00 $0.00 $0.00 $0.00 $0.00
5 $0.00 $0.00 $0.00 $0.00 $0.00
6 $0.00 $0.00 $0.00 $0.00 $0.00
7 $0.00 $0.00 $0.00 $0.00 $0.00
8 $0.00 $0.00 $0.00 $0.00 $0.00
9 $0.00 $0.00 $0.00 $0.00 $0.00
10 $0.00 $0.00 $0.00 $0.00 $0.00
11 $0.00 $0.00 $0.00 $0.00 $0.00
12 $0.00 $0.00 $0.00 $0.00 $0.00
13 $0.00 $0.00 $0.00 $0.00 $0.00
14 $0.00 $0.00 $0.00 $0.00 $0.00
15 $0.00 $0.00 $0.00 $0.00 $0.00
16 $0.00 $0.00 $0.00 $0.00 $0.00
17 $0.00 $0.00 $0.00 $0.00 $0.00
18 $0.00 $0.00 $0.00 $0.00 $0.00
19 $0.00 $0.00 $0.00 $0.00 $0.00
20 $0.00 $0.00 $0.00 $0.00 $0.00
21 $0.00 $0.00 $0.00 $0.00 $0.00
22 $0.00 $0.00 $0.00 $0.00 $0.00
23 $0.00 $0.00 $0.00 $0.00 $0.00
24 $0.00 $0.00 $0.00 $0.00 $0.00
25 $0.00 $0.00 $0.00 $0.00 $0.00
26 $0.00 $0.00 $0.00 $0.00 $0.00
27 $0.00 $0.00 $0.00 $0.00 $0.00
28 $0.00 $0.00 $0.00 $0.00 $0.00
29 $0.00 $0.00 $0.00 $0.00 $0.00
30 $0.00 $0.00 $0.00 $0.00 $0.00
31 $0.00 $0.00 $0.00 $0.00 $0.00
32 $0.00 $0.00 $0.00 $0.00 $0.00
33 $0.00 $0.00 $0.00 $0.00 $0.00
34 $0.00 $0.00 $0.00 $0.00 $0.00
35 $0.00 $0.00 $0.00 $0.00 $0.00
36 $0.00 $0.00 $0.00 $0.00 $0.00
37 $0.00 $0.00 $0.00 $0.00 $0.00
38 $0.00 $0.00 $0.00 $0.00 $0.00
39 $0.00 $0.00 $0.00 $0.00 $0.00
40 $0.00 $0.00 $0.00 $0.00 $0.00
41 $0.00 $0.00 $0.00 $0.00 $0.00
42 $0.00 $0.00 $0.00 $0.00 $0.00
43 $0.00 $0.00 $0.00 $0.00 $0.00
44 $0.00 $0.00 $0.00 $0.00 $0.00
45 $0.00 $0.00 $0.00 $0.00 $0.00
46 $0.00 $0.00 $0.00 $0.00 $0.00
47 $0.00 $0.00 $0.00 $0.00 $0.00
48 $0.00 $0.00 $0.00 $0.00 $0.00
50 $0.00 $0.00 $0.00 $0.00 $0.00
51 Operations and Maintenance Support - (In accordance with in Section 3.4 of the
SOO)
$0.00 $0.00 $0.00 $0.00 $0.00
Large Year 1 Total $0.00 Large Year 2 Total $0.00 Large Year 3 Total $0.00 Large Year 4 Total $0.00 Large Year 5 Total $0.00
Year 5 Large Configuration
Year 1 Year 2 Year 3 Year 4
Section B - Supplies or Services and Prices/Costs PAGE 10 OF 141
Number
Item # Description Manufacturer Part # Qty Serial # Unit Price Total Price
1 $0.00
2 $0.00
3 $0.00
4 $0.00
5 $0.00
6 $0.00
7 $0.00
8 $0.00
9 $0.00
10 $0.00
11 $0.00
12 $0.00
13 $0.00
14 $0.00
15 $0.00
16 $0.00
17 $0.00
18 $0.00
19 $0.00
20 $0.00
21 $0.00
22 $0.00
23 $0.00
24 $0.00
25 $0.00
26 $0.00
27 $0.00
28 $0.00
29 $0.00
30 $0.00
31 $0.00
32 $0.00
33 $0.00
34 $0.00
35 $0.00
36 $0.00
37 $0.00
38 $0.00
39 $0.00
40 $0.00
41 $0.00
42 $0.00
43 $0.00
44 $0.00
45 $0.00
46 $0.00
47 $0.00
48 $0.00
50 $0.00
Operations and Maintenance Support - (In accordance with in Section 3.4 of the SOO) $0.00
Specialized Base Period Total (Hardware, Software Support Only) $0.00
Task Order 1 - Atlanta Specialized Room - Base Period
Section B - Supplies or Services and Prices/Costs PAGE 11 OF 141
Labor Category Hours Hourly Rate Program Manager Solution Architect Installer/Engineer Programmer Optional Optional Optional
$0.00
Item Number
Item # Description Manufacturer Part # Qty Serial # Unit Price Total Price
Operations and Maintenance Support - (In accordance with in Section 3.4 of the SOO)
$0.00
Specialized Option Period 1 Total $0.00
Item Number
Item # Description Manufacturer Part # Qty Serial # Unit Price Total Price
Operations and Maintenance Support - (In accordance with in Section 3.4 of the SOO) $0.00
Specialized Option Period 2 Total $0.00
Item Number
Item # Description Manufacturer Part # Qty Serial # Unit Price Total Price
Operations and Maintenance Support - (In accordance with in Section 3.4 of the SOO)
$0.00
Specialized Option Period 3 Total $0.00
Item Number
Item # Description Manufacturer Part # Qty Serial # Unit Price Total Price
Operations and Maintenance Support - (In accordance with in Section 3.4 of the SOO)
$0.00
Specialized Optional 4 Total $0.00
$0.00Atlanta Task Order 1 Total
$0.00
Specialized - Option Period 1
Specialized - Option Period 2
Specialized - Option Period 3
Specialized - Option Period 4
Base Period Labor Specialized - Shipping Total
Base Period (All Items)
$0.00
Labor Total $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Section B - Supplies or Services and Prices/Costs PAGE 12 OF 141
Section C - Description/Specifications/Work Statement
Attachments for this section start after the clauses.
Clauses Incorporated By Reference
Clause # Title Date
7.3.2-34 Duty to Deliver or Perform July 2008
Full Text Clauses
7.3.2-21 - Description/Specifications/Work Statement - October 2008 The name/description of the goods or services being acquired is as follows:
National Conference Rooms Audio Visual Upgrades
The specifications for and the description of the work to be performed under this award are fully detailed in a
Statement of Objectives (SOO), which is included as Attachment C-1 to this solicitation.
Section C - Description/Specifications/Work Statement PAGE 13 OF 141
Section C - Description/Specifications/Work Statement PAGE 14 OF 141
Section C - Description/Specifications/Work Statement PAGE 15 OF 141
Section C - Description/Specifications/Work Statement PAGE 16 OF 141 o o o
Section C - Description/Specifications/Work Statement PAGE 17 OF 141
Section C - Description/Specifications/Work Statement PAGE 18 OF 141
Section C - Description/Specifications/Work Statement PAGE 19 OF 141
Section C - Description/Specifications/Work Statement PAGE 20 OF 141
Section C - Description/Specifications/Work Statement PAGE 21 OF 141
Section C - Description/Specifications/Work Statement PAGE 22 OF 141
Section C - Description/Specifications/Work Statement PAGE 23 OF 141
Section C - Description/Specifications/Work Statement PAGE 24 OF 141
Principal Duties and Responsibilities
Section C - Description/Specifications/Work Statement PAGE 25 OF 141
• Leads the design, implementation, and optimization of the architecture of complex audio/video systems that include construction projects.
• Collaborates with multi-disciplinary teams to translates complex business processes and strategy into technical audio video solutions through requirements definition and design.
• Responsible for the design and management of the end to end architecture of the solution and ensure that all the components of the solution integrate together (includes existing audio/video solutions).
• Conceptualize solutions that address customer opportunities and issues.
• Provides overall strategic vision and creates architecture proposals based on audio/video requirements.
• Provide architectural advice, planning guidance, quality assurance, safety regulation and industry standard compliance, and guidance to the project team on project approach and solution
• Adheres to FDIC's enterprise architecture standards.
Qualifications
• BA/BS in Computer Science or related field or an equivalent combination of education and/or experience.
• 3-5 years of progressive experience as a solution architect.
• Minimum 2 years of experience in other technical roles such as developer or systems analyst.
• Strong consultative skills at a cross functional level.
• Demonstrates experience with analysis level UML, activity diagrams, business use cases, business rules, and system level features.
• Demonstrates experience in enterprise architecture frameworks (TOGAF is preferred).
• Demonstrates broad based platform and technical exposure and complete software development lifecycle perspective.
• Demonstrates understanding of latest architecture, technology, solutions, and industry trends.
Section C - Description/Specifications/Work Statement PAGE 26 OF 141
Section C - Description/Specifications/Work Statement PAGE 27 OF 141
Section C - Description/Specifications/Work Statement PAGE 28 OF 141
Region
Address
Washington DC (Head Quarters)
550 17th Street, NW Washington, DC 20429
Atlanta 10 10th Street NE, Suite 900, Atlanta, GA 30309-3849
Section C - Description/Specifications/Work Statement PAGE 29 OF 141 https://www.fdic.gov/about/organization-directory-regional-offices#boston
Boston 15 Braintree Hill Office Park, Suite 200, Braintree, MA 02184-8701
Chicago 300 South Riverside Plaza, Suite 1700, Chicago, IL 60606-3447
Dallas 600 North Pearl Street, Suite 700, Dallas, TX 75201
Kansas City 1100 Walnut St, Suite 2100 Kansas City, MO 64106-2180
New York 1166 Sixth Avenue New York, NY 10036
San Francisco 25 Jessie Street at Ecker Square, Suite 2300, San Francisco, CA, 94105-2780
Section C - Description/Specifications/Work Statement PAGE 30 OF 141
Federal Deposit Insurance Corporation
CONTROLLED//FDIC INTERNAL ONLY
Attachment A - PROJECT SITE REQUIREMENTS
This section applies to all FDIC sites unless otherwise specified in the ensuing sections specific to each site.
1. Work Restrictions
The Contractor shall survey the entire worksite and review existing documentation to be familiar with the existing conditions. This includes all areas of the building, structure, and site affected by the work prior to initiation of work.
During the installation period, the Contractor shall have full use of the designated premises for work, including full use of the indicated work site, limited only by the FDIC's right to perform work, or retain other contractors to perform work, on portions of the project. The Contractor shall limit the use of the premises to the work areas indicated, and to allow for FDIC occupancy and public use.
Each building is to remain fully operational throughout the entirety of the project, with no disruption to tenant operations during FDIC Occupied Hours (2.1). All work areas must be cleaned at the end of every workday.
The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, work should not take place until complete supplies are on hand to perform work.
The Contractor shall coordinate all work activities with the FDIC Oversight Manager (OM) and Technical Monitor (TM) to ensure that proper security and access arrangements are made without impact on the ’schedule.
2. Working Hours
2.1 FDIC Occupied Hours
Each FDIC building is operated at all times and is constantly manned by a guard force and building engineer. At least one means of vehicle access, and one means of pedestrian access must be maintained at all times. The standard working hours for FDIC employees is 6:00 a.m. to 7:00 p.m.
Monday through Friday except Federal Holidays. All work that will produce noise, dust, odors or service disruption detectable within the building interior would preferably be scheduled outside the standard FDIC working hours.
FDIC will occupy the building during the entire project period. Contractors shall cooperate with FDIC and FDIC’s building services to minimize conflicts and facilitate FDIC usage. Contractors shall perform the work so as not to interfere with FDIC's operations.
2.2 Contractor's Working Hours
The following work shall be performed outside of FDIC Occupied Hours:
All work that produces excessive noise, vibration, dust, or odors that may disrupt tenant operations in adjacent spaces. FDIC has the right to request to stop work due to noise, odor, or
Section C - Description/Specifications/Work Statement PAGE 31 OF 141 other concerns, and not be held financially liable for any cost incurred due to a request to stop work during occupied hours.
Keep driveways and entrances serving premises clear and available to FDIC, FDIC's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials
• Schedule deliveries to minimize use of driveways and entrances.
• Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
Work accomplished outside of FDIC Occupied Hours shall be performed at no additional cost to the FDIC. The Contractor shall submit a proposed schedule and gain OM and TM approval at least 72 hours before proceeding with any work during FDIC Unoccupied Hours. Note: All noisy work (hammer drilling, etc.) must be completed before 7:00 a.m. Monday – Friday, excluding Federal Holidays.
3. Loading Dock
Use of any existing loading dock facilities shall be shared with FDIC activities on a first-come-first-served, wait-your-turn basis. Any early-morning delivery of cafeteria supplies and trash removal on FDIC working days have priority. Loading dock activities shall be coordinated with the OM and TM a minimum of 72 hours in advance. Acceptance of deliveries shall be the Contractor’s responsibility.
No storage is available on the loading dock. Storage will be coordinated with the OM and TM.
4. Deliveries and Parking
Deliveries of material must be coordinated and scheduled to avoid encumbering any loading dock, all hallways, or any freight elevator during standard working hours.
4.1 Transportation and Parking
Contractor is responsible for transportation of its employees to and from job site, and parking of vehicles of Contractor or its subcontractors. Parking of vehicles on-site during standard working hours is not permissible. After hours parking may be provided at the discretion of FDIC and coordinated with the OM and TM.
4.2 Seventy-two (72) Hours Advance Notification of Deliveries
The Contractor shall provide seventy-two (72) hours advance notification of all significant deliveries to provide time to schedule inspections of all materials upon delivery prior to unloading.
4.3 Shipping
The contractor shall ship all equipment and materials to the final destination based on the rooms and locations identified under the task order, where FDIC will provide space to store, stage, test, and verify equipment functionality.
Section C - Description/Specifications/Work Statement PAGE 32 OF 141
4.4 Inspection for Transportation Damage
Before any materials are unloaded, all items shall be inspected for damage, water stains, discoloration, or other evidence of moisture acquired at the point of manufacture or in transit or temporary storage.
4.5 Vehicular Traffic
Contractor shall be responsible for obtaining any required permits for blocking streets or curb parking for trucks, etc. as applicable.
4.6 Barricades, Warning Signs, Lights, and Traffic Controls
Provide and maintain barricades, warning signs and lights, and traffic controls. Provide traffic control as necessary for work vehicles entering and leaving site, and for non-work vehicles on or near site. Comply with requirements of public authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
5. Staging and Storage
The Contractor may be provided a staging area within the building, contingent upon FDIC approval, and provided that its use will not interfere with operations of the FDIC. Contractor to identify area required for staging for FDIC review. No FDIC employees will assist with unloading/loading of vehicles(s). The Contractor shall provide all personnel and equipment needed for unloading, moving, and assembling the materials. Pallets shall not be brought into the building; items shall be taken off pallets. FDIC can provide some carts if needed.
6. Clean-Up
Contractor shall ensure all routes of travel through the building interior are free of debris, tools, equipment, supplies, and materials at the conclusion of each work session in order to return the affected space to its original occupied condition.
6.1 During completion of work:
Clean site and work areas daily, including common areas. Enforce requirements strictly. The site is to be kept clean and safe from fire or tripping hazards daily. Separate waste materials per safe handling requirements and dispose of legally.
• Trash Containers - The Contractor shall provide trash bags or containers for all trash, debris, and material residue. Trash includes material containers, wrappers, and covers in addition to food containers, drinking cups, paper bags, and all other trash of any kind resulting from on-going work. Trash is to be removed from the site daily.
• Do not bury or burn waste materials, debris, or rubbish on-site. Do not discharge or wash waste materials, debris, or rubbish down sewers or into waterways.
Site: Maintain site and surrounding areas free of waste materials, debris, and rubbish from work
Section C - Description/Specifications/Work Statement PAGE 33 OF 141 and personnel.
Work Areas: Clean areas where work is in progress to level of cleanliness necessary for proper execution of work.
• Remove liquid spills promptly.
Installed work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.
Handle waste materials, debris, and rubbish in a controlled manner with as few handlings as possible. Do not throw from heights.
During handling and installation, clean and protect work. Apply protective covering where required to ensure protection from damage or deterioration.
6.2 After completing work (prior to inspection):
• Clean spillage and soiling from adjacent surfaces using cleaning agents and procedures recommended by manufacturer of affected surface. Exercise care to avoid scratching or damage to surfaces.
• Repair surfaces stained, marred, or otherwise damaged during work.
• Clean up debris and surplus materials and remove from site. Leave all areas around job site free of debris, materials, equipment and related items after completion of job.
• Collect surplus materials that cannot be reused and deliver to recycling or disposal facility.
Limiting Exposures: Supervise work to assure that no part of work, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during project period.
In areas disturbed by work activities, complete the following cleaning before requesting inspection. Clean surfaces, complying with manufacturer's written instructions.
• Remove tools, construction equipment, machinery, and surplus material from site.
• Clean site of rubbish, waste materials, litter, and other foreign substances.
Remove labels that are not permanent.
Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.
After completing work after inspection:
Leave area clean and ready for occupancy.
Section C - Description/Specifications/Work Statement PAGE 34 OF 141
7. Dumpster
Limited space (e.g. 2 or 3 boxes) is available on-site for a dumpster. Material is expected to be hauled off at the end of each work shift. Stockpiling of debris for more than one calendar day or over use of existing building dumpsters and trash bins is strictly prohibited.
8. Dust and Fume Control
Prevent dust, dirt, fumes, and odors from entering occupied areas. The Contractor shall implement dust control measures to reduce the amount of airborne dust and debris on the site. Air emissions from Contractor equipment shall be minimized to the greatest extent possible and shall not be discharged near air intakes and openings where airborne emissions could be drawn into the building. At no time shall building occupants be exposed to hazardous conditions as a result of work.
• Protect and filter existing air intakes as required.
• Comply with OSHA requirements.
9. Use of Existing Stairs, Elevator, or Freight Elevator
The use of FDIC’s existing stairs and freight elevator is available for use at the site, to be shared with other service providers. Limited periods of exclusive use may be requested with advance notice to the OM and TM. The Contractor shall be responsible for a reasonable duty of care to avoid damage to the freight elevator finishes or for exceeding load limitations.
• Coordinate daily usage with the OM and TM and with requirements for facility operations.
• Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs, elevator cars, and entrance doors and frame, and to maintain means of egress.
• If a freight elevator is available, the Contractor shall use this means.
10. Smoking Restrictions
Contractor shall comply with the FDIC policy of "NO SMOKING" in any FDIC property. This includes restrooms, machine rooms, electrical rooms, roof areas, parking garages, elevators, loading docks, entranceways, etc.
11. Other Prohibited Activities
The possession or use of alcoholic beverages, illegal drugs, firearms, weapons or explosives by Contractor personnel while at an FDIC location is strictly forbidden and any violation shall be cause for an immediate removal of the offender(s) from further work involving the contract.
12. Conservation
Contractor personnel shall comply with all general-use energy conservation and recyclable programs as practiced at the facility in which the work is being performed.
Section C - Description/Specifications/Work Statement PAGE 35 OF 141
LOCATION
FDIC
Head Quarters (Main) 550 17th Street, NW Washington, DC 20429
• FDIC will provide padding in the freight elevator; the dimensions of the elevator are 51” D x 80” W x 110” H and the weight capacity is 2500 lbs.
• Delivery trucks must adhere to municipal restrictions for use of 17th Street when traveling to or from the site.
Section C - Description/Specifications/Work Statement PAGE 36 OF 141
FDIC
Virginia Square (includes Student Residence Center) 3501 Fairfax Drive Arlington, VA 22201
• Hours of delivery/operation:
o Monday through Friday, 7:00 AM – 5:00 PM (accessible 24/7, 7 days per week if some work needs to be conducted after hours) o The standard working hours for FDIC employees is 6:00 a.m. to 6:00 p.m. Monday through Friday except Federal Holidays.
• Lobby marble floors require Masonite protection and corner guards.
• Throughout the course of the project, use the freight elevator designated by the OM and TM for Contractor use. Provide protection pads hung to protect the interior walls and floor protection to cover the elevator floor. Only use the designated protected elevator to carry size appropriate materials and tools. Elevator must be maintained clean daily to prevent debris tracks. Freight elevator access is on P-1 is adjacent to the loading dock.
Section C - Description/Specifications/Work Statement PAGE 37 OF 141
FDIC
Atlanta Regional Office (Main) 10 10th Street NE, Suite 900 Atlanta GA 30309
To be determined.
Section C - Description/Specifications/Work Statement PAGE 38 OF 141
FDIC
Boston Regional Office (Main) 15 Braintree Hill Office Park, Suite 200 Braintree MA 02184
Section C - Description/Specifications/Work Statement PAGE 39 OF 141
FDIC
Chicago Regional Office (Main) 300 South Riverside Plaza, Suite 1700 Chicago IL 60606
Section C - Description/Specifications/Work Statement PAGE 40 OF 141
FDIC
Dallas Regional Office (Main) 600 North Pearl Street, Suite 700 Dallas TX 75201
Section C - Description/Specifications/Work Statement PAGE 41 OF 141
FDIC
Kansas City Regional Office (Main) 1100 Walnut St, Suite 2100 Kansas City MO 64106
Section C - Description/Specifications/Work Statement PAGE 42 OF 141
FDIC
New York Regional Office (Main) 1166 Sixth Avenue New York, NY 10036
Section C - Description/Specifications/Work Statement PAGE 43 OF 141
FDIC
San Francisco Regional Office (Main) 25 Jessie Street at Ecker Square Suite 2300 San Francisco, CA 94105-2780
• Hours of delivery/operation:
o Monday through Friday, 7:00 AM – 5:00 PM (accessible 24/7, 7 days per week if some work needs to be conducted after hours) o The standard working hours for FDIC employees is 6:00 a.m. to 6:00 p.m. Monday through Friday except Federal Holidays.
• Lobby marble floors require Masonite protection and corner guards
• FDIC will provide padding in the freight elevator; the dimensions of the elevator are 51” D x 80”
W x 110” H and the weight capacity is 2500 lbs.
• Address is located in a construction zone, one-way alley on Jessie St. with barricades.
Security will assist in moving the barricades for deliveries and short-term parking. On some days FDIC will have a lot of contractors working in the building, and that section will quickly fill up with service vehicles; accordingly, the contractor will be responsible for its own parking.
• Two business day advance notice for 2 hour delivery window recommended. The contractor shall call main Security Desk 5-10 minutes or more prior to arrival as they can provide updates on parking or deliveries (415-808-8100).
• Truck size limit is 24’ in length given the two lane street access and tight turn in front of the building.
• NO Loading Dock L-gate required for delivery.
Section C - Description/Specifications/Work Statement PAGE 44 OF 141
National Conference Room AV Task Order 1 Statement of Objectives
Section C - Description/Specifications/Work Statement PAGE 45 OF 141
1. Introduction
2. Objectives
3. Scope
3.1 Training and Collaboration Centers
3.2 Equipment, Materials, and Licenses
3.3. System/Solution Acceptance
3.4 Installation Warranty and On-site Support
3.5 Training
4. Prerequisite for Task Order
5. Documentation
6. Key Personnel
7. Schedule and Deliverables
8. Place of Performance
9. Attachments
Section C - Description/Specifications/Work Statement PAGE 46 OF 141
1. Introduction The Federal Deposit Insurance Corporation (“FDIC”) is an independent agency of the U.S.
government that was established by Congress in 1933 to insure bank deposits and help maintain sound conditions in our banking system. In its unique role as deposit insurer of banks and savings associations and primary supervisor of state non-member banks, the FDIC promotes the safety and soundness of insured depository institutions.
2. Objectives
The FDIC is seeking a National Conference Room AV BOA holder to transform two rooms in Atlanta (10 10th Street NE, Suite 900, Atlanta, GA 30309-3849) into a Specialized room type.
This Task Order is for a Specialized room only; all other requirements at Section 2 of the BOA SOO apply.
3. Scope
This Task Order is for a Specialized room only; all other requirements at Section 3 of the BOA SOO apply.
3.1 Training and Collaboration Centers
All requirements at Section 3.1 of the BOA SOO apply.
3.2 Equipment, Materials, and Licenses
All requirements at Section 3.2 of the BOA SOO apply.
3.3. System/Solution Acceptance
All requirements at Section 3.3 of the BOA SOO apply.
3.4 Installation Warranty and On-site Support
All requirements at Section 3.4 of the BOA SOO apply.
3.5 Training
All requirements at Section 3.5 of the BOA SOO apply.
4. Prerequisite for Task Order
All requirements at Section 4 of the BOA SOO apply.
5. Documentation All requirements at Section 5 of the BOA SOO apply.
6. Key Personnel
All requirements at Section 6 of the BOA SOO apply.
Section C - Description/Specifications/Work Statement PAGE 47 OF 141
7. Schedule and Deliverables
The anticipated deliverables for each room include, but are not limited to the requirements at Section 7 of the BOA SOO.
8. Place of Performance The place of performance is Atlanta (10 10th Street NE, Suite 900, Atlanta, GA 30309-3849. This Task Order is for Atlanta only; all other requirements at Section 8 of the BOA SOO apply.
9. Attachments All requirements at Section 9 of the BOA SOO apply.
Section C - Description/Specifications/Work Statement PAGE 48 OF 141
$'()�)*+��,��'-)�+-.�*�)*-+(/0��1�2��34��(/5��6(/0��7*-6�+-.�*��8��1��6�+-.�*)�(/�.-59� Section C - Description/Specifications/Work Statement PAGE 49 OF 141
��������������������������� �!!"� #$%&�$'()�)*+��,�'-)�+-.�*�)*-+(/0�1�2��3����(/4��5(/0�6*-5�+-.�*��7(+'�1��5�+-.�*)�(/�.-48�
Section C - Description/Specifications/Work Statement PAGE 50 OF 141
./012�������������������������������������3�405678�� �Section C - Description/Specifications/Work Statement PAGE 51 OF 141
���������������������������� �!!"� #$%&�$'()�)*+�,-��'�)�+�.�*�)*�+(/0��������1�(/2�,3(/0���*�3�+�.�*�-*��������4�����3�+�.�*)�(/�.�25�
#6+���2'�(�)�2�/�.*�-��2*3����/0�.�25�7���8�9�
Section C - Description/Specifications/Work Statement PAGE 52 OF 141
��������������������������� !���������"#�$$�%%&�$'()*�(+,���-.�!/��+���0�,�������-�1+�+����-�.,�2�3�4�5�/-�/�-6���7��(�.����������1��-�8-�9,.+��4�9,.+�!.��:-���.�8�-���;,.+�3����.�8�-��,��8�1<�
Section C - Description/Specifications/Work Statement PAGE 53 OF 141
����������������������������� !"�������#$�%%�&&'�%()*+�),-���./�01��,���2�-�������.�3,�,����.�/-�4�5���6�1.�1�.7���"�)�/����.�3,�����7�������3��.��8.�9-/,����9-/,�0/��:.���/�8�.���;��5����/�8�.��-�� ����
Section C - Description/Specifications/Work Statement PAGE 54 OF 141
������������������������ !����"��#$���%&&'��()�*�)�+,�,�-�.�����,�-�/0��,��-+12���3���!����4150.6+12��7��6�-�/0����668�9�����0���3�����5�����"���:��3��6�-�/0�,�+1�/�5;�
Section C - Description/Specifications/Work Statement PAGE 55 OF 141
����������������������� �!""#�$%���!&&'��()�*�)�+,�,�-�������,�,��-+./�0"1��2��3+-��4��5�-�6 ����7"�0""5�-�6 �,�+.�6�89�
Section C - Description/Specifications/Work Statement PAGE 56 OF 141
���������������������������� !�"#����$$%�&��''�(()�'*+,-�+./0�0���#1��.�0�0���/���2$���3���4$�2$$5���6��0�/��6��7��*8�����.�/�0�����6��1�������$#�5�$��0$%��9���0���5����6��7�$2��$$%:� � �
Section C - Description/Specifications/Work Statement PAGE 57 OF 141
FDIC - ATLANTA RO/FO
10 10TH STREET NW #900 & 10000
ATLANTA, GEORGIA 30309
VOICE/DATA SYSTEMS
SHEET LEGEND
SHEET
NUMBER TITLE REVISED
VOICE/DATA SYSTEMS
LV-00 INDEX/TITLE SHEET 01-11-2024
LV-01 LEVEL 09 - VOICE/DATA FLOOR PLAN 01-11-2024
LV-02 LEVEL 10 - VOICE/DATA FLOOR PLAN 01-11-2024
VOICE/DATA SYMBOL LEGEND
SYMBOL DESCRIPTION CABLING
REQUIREMENTS
ROUGH-IN
REQUIREMENTS
ROUGH-IN ELEVATION
SHEET# DETAIL# ELEVATION#
SINGLE DATA STATION (1) CAT6 - - - -
MULTI-DATA STATION (2) CAT6 UNLESS NOTED
OTHERWISE - - - -
CEILING DATA, WIRELESS ACCESS POINT (1) CAT6 UNLESS NOTED
OTHERWISE - - - -
SINGLE DATA FLOORBOX (1) CAT6 - - - -
MULTI-DATA FLOORBOX DATA (2) CAT6 UNLESS NOTED
OTHERWISE - - - -
WALL FURNITURE FEED SEE FLOORPLAN - - - -
FLOOR CORE FURNITURE FEED SEE FLOORPLAN - - - -
PROJECT
INDEX
LV-00
FD
IC
AT
LA
NT
A
RO
/F O
TH
S
TR
EE
T
NW
AT
LA
NT
A, G
EO
RG
IA
VO
IC
E/
DA
TA
S
YS
TE
M S
DATE:
DRAWN BY:
CHECKED BY:
APPROVED BY:
JLB
JL
JL
JOB NUMBER:
REV# DATE:
REVISION TABLE
DESCRIPTION:
ASBUILTS
0000000
01-11-2024
01-11-2024
PRINTED SHEET SIZE: Arch E1 - 30" x 42"
Pu bl ish ed b y:
J L B
CO
PY
RI
GH
T
T
HI
S
IS
C
OP
YR
IG
HT
ED
A
ND
M
AY
N
OT
B E
US
ED
W
IT
HO
UT
W
RI
TT
EN
P
ER
M
IS
SI
ON
Ó
4825 RIVER GREEN PKWY
DULUTH, GEORGIA 30096
Phone: 770-495-0798 www.ncicabling.com
Section C - Description/Specifications/Work Statement PAGE 58 OF 141
CORHQ-25-R-0121
AutoCAD SHX Text
FF
AutoCAD SHX Text
FF
OFFICE_120
09-034
OFFICE_225
09-036
OFFICE_225
09-038
OFFICE_120
09-040
OFFICE_120
09-042
OFFICE_120
09-044
OFFICE_120
09-046
LARGE
CONFERENCE
09-048
OPEN COLLAB.
09-032
OFFICE_280
09-030
MAIL/COPY RM.
09-049
OFFICE_250
09-026
OFFICE_225
09-024
STORAGE
09-011
OFFICE_225
09-022 MED. CONF.
09-023
OFFICE_325
09-020
OFFICE_120
09-014
OFFICE_225
09-012
OFFICE_150
09-010
OFFICE_150
09-008
OFFICE_120
09-006
OFFICE_120
09-004
OFFICE_120
09-002
OFFICE_120
09-104
OFFICE_225
09-102
OFFICE_120
09-100
OFFICE_120
09-098
OFFICE_120
09-096
OFFICE_120
09-094
OFFICE_120
09-092
OFFICE_120
09-090
OFFICE_150
09-088
OFFICE_150
09-086
OFFICE_225
09-018 OFFICE_225
09-016
COPY/PRINT
09-009
EXEC. CONF.
09-007
DOC. ROOM
09-108
OPEN COLLAB.
09-084
HUDDLE
09-005
HUDDLE
09-003
FILE ROOM
09-105
OFFICE_120
09-110
OFFICE_120
09-111
OFFICE_120
09-112
OFFICE_150
09-082
RECEPTION
09-001 BADGING OFFICE
09-106
STO. ROOM
09-107
FILE ROOM
09-109
ADMIN FILE / STO.
RM
09-122 OFFICE_150
09-080
OPEN COLLAB.
09-021
MED. CONF.
09-025
OFFICE_150
09-078
ELEV. LOBBY
09-000
FILE/ WRK RM
09-089
OFFICE_150
09-076
OFFICE_225
09-028
NURSE STAT.
09-051
SUPPLIES
09-057
EXAM ROOM
09-055
RESTROOM
09-053
LARGE CONF.
09-059
BREAKROOM
09-061
SERVER ROOM
09-069
OFFICE_150
09-074
OFFICE_150
09-072
FILE ROOM
09-063
TECH CAFE
09-065
OFFICE_120
09-067
COPY/PRINT
09-071
OFFICE_150
09-070
EQ3
OPEN COLLAB.
09-068
OFFICE_120
09-050
OFFICE_225
09-052
OFFICE_150
09-054
OFFICE_150
09-056
OFFICE_120
09-058
OFFICE_120
09-060
OFFICE_120
09-062
OFFICE_150
09-064
OFFICE_150
09-066
H P
Pl ot te r
Ac cu rio Pr es s
Bi z
H ub
C
9-020
9-021
9-023
9-022
9-024
9-025
9-195
9-026 9-192
9-0279-133
9-019 9-018
9-088
9-0879-086
9-092 9-093
9-0919-095
9-089
9-090
9-098
9-099
9-097
9-100
9-096
9-108
9-109
9-110
9-111
9-112
9-113
9-117
9-107
9-114
9-076 9-199
9-080
9-078 9-079
9-084 9-085
9-083
9-094
ATL
WAP
09-21
ATL
WAP
09-20
ATL
WAP
09-17
W13 W14
W11 W12
ATL
WAP
09-19
W09 W10
ATL
WAP
09-02
9-076
ATL
WAP
09-18
W17 W18
9-118
9-119
9-120
9-028
9-103
9-104
9-102
9-105
9-101
9-106
9-029 9-030 9-031 9-032 9-034 9-035 9-124 9-036
9-121
9-183 9-184
9-125
W25 W26
9-017 9-016 9-015 9-014 9-013 9-012 9-010 9-009 9-008 9-007 9-005 9-004 9-003 9-002 9-0019-0069-011
9-071 9-070
9-073
9-072
9-074
9-187 9-188 9-065 9-064
9-068
9-186
9-065
9-066
W05 W06 9-063
9-062 9-060 9-059
9-173 9-174 9-175 9-176
9-180 9-179 9-178 9-177
9-193 9-194 9-168 9-169
9-172 9-171 9-170
9-160 9-161 9-162
9-165 9-164 9-163
9-152 9-153 9-154 9-155
9-159 9-158 9-157 9-156
9-061
9-058
9-057
9-056
9-055
9-054
9-053
9-052
9-166
9-050 9-0519-048 9-0499-0479-045 9-0469-043 9-044 9-039 9-042
9-0389-189
9-128
9-130
9-126
9-127
9-134 9-135
9-136 9-137
9-138 9-139 9-140
9-141
9-142 9-143
9-144 9-145
9-146 9-1479-148
9-149 9-150 9-151
9-132 9-1859-131
W01 W02
ATL
WAP
09-16
W07 W08
W29 W30
W27 W28
W01 W02
W23 W24
ATL
WAP
09-04
W21 W22
ATL
WAP
09-03
ATL
WAP
09-03
ATL
WAP
09-02ATL
WAP
09-04
W21 W22
W19 W20
W15 W16
W03 W04
9-069
VOICE/DATA SYMBOL LEGEND
SYMBOL DESCRIPTION CABLING
REQUIREMENTS
ROUGH-IN
REQUIREMENTS
ROUGH-IN ELEVATION
SHEET# DETAIL# ELEVATION#
SINGLE DATA STATION (1) CAT6 - - - -
MULTI-DATA STATION (2) CAT6 UNLESS NOTED
OTHERWISE - - - -
CEILING DATA, WIRELESS ACCESS POINT (1) CAT6 UNLESS NOTED
OTHERWISE - - - -
SINGLE DATA FLOORBOX (1) CAT6 - - - -
MULTI-DATA FLOORBOX DATA (2) CAT6 UNLESS NOTED
OTHERWISE - - - -
WALL FURNITURE FEED SEE FLOORPLAN - - - -
FLOOR CORE FURNITURE FEED SEE FLOORPLAN - - - -
PROJECT
LEVEL 09
VOICE/DATA
FLOOR PLAN
LV-01
4825 RIVER GREEN PKWY
DULUTH, GEORGIA 30096
Phone: 770-495-0798 www.ncicabling.com
FD
IC
AT
LA
NT
A
RO
/F O
TH
S
TR
EE
T
NW
AT
LA
NT
A, G
EO
RG
IA
VO
IC
E/
DA
TA
S
YS
TE
M S
DATE:
DRAWN BY:
CHECKED BY:
APPROVED BY:
JLB
JL
JL
JOB NUMBER:
REV# DATE:
REVISION TABLE
DESCRIPTION:
ASBUILTS
0000000
01-11-2024
01-11-2024
PRINTED SHEET SIZE: Arch E1 - 30" x 42"
Pu bl ish ed b y:
J L B
CO
PY
RI
GH
T
T
HI
S
IS
C
OP
YR
IG
HT
ED
A
ND
M
AY
N
OT
B E
US
ED
W
IT
HO
UT
W
RI
TT
EN
P
ER
M
IS
SI
ON
Ó
Scale:
LV-01
LEVEL 09 - VOICE/DATA FLOOR PLAN
1/8" = 1'
Section C - Description/Specifications/Work Statement PAGE 59 OF 141
CORHQ-25-R-0121
AutoCAD SHX Text @87"
AutoCAD SHX Text @87"
AutoCAD SHX Text @87"
AutoCAD SHX Text @87"
AutoCAD SHX Text
FF
AutoCAD SHX Text @87"
AutoCAD SHX Text @44"
AutoCAD SHX Text
FF
AutoCAD SHX Text
FF
AutoCAD SHX Text @87"
AutoCAD SHX Text
FF
AutoCAD SHX Text
FF
AutoCAD SHX Text
FF
AutoCAD SHX Text
FF
AutoCAD SHX Text @87"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text @44"
AutoCAD SHX Text
FF
TRAINING
10-031
OFFICE_150
10-026
OPEN COLLAB
10-027
MEDIUM
CONFERENCE
10-024
OFFICE_120
10-022
OFFICE_120
10-020
OFFICE_150
10-018
COPY/PRINT
10-021
OFFICE_120
10-014
OFFICE_150
10-002
MEDIUM
CONFERENCE
10-000
FILE ROOM
10-017
COFFEE
10-016
IDF
10-019
GUN ROOM
10-015 EQUIP. ROOM
10-013
INTERVIEW RM
10-005
VAULT ROOM
10-011
FILE ROOM
10-009
EQUIP. ROOM
10-007
COPY/PRINT/STG
10-003
VISITORS RM
10-001
10-053
10-050
10-04610-044 10-052
10-03710-035 10-036
W07 W08
10-034
10-033
10-032
10-031 10-030
W09 W10
10-021
10-02010-019
10-018
10-023
10-022
10-024
10-027 10-028
10-025 10-026
W05 W06
10-017 10-016 10-015
10-059 10-012 10-011 10-009 10-00810-010
ATL
WAP
10-06
10-055 10-056
10-049
10-002
10-003 10-001
10-004 10-006
10-005 10-007
ATL
WAP
10-07
ATL
WAP
10-02
10-060
10-051
VOICE/DATA SYMBOL LEGEND
SYMBOL DESCRIPTION CABLING
REQUIREMENTS
ROUGH-IN
REQUIREMENTS
ROUGH-IN ELEVATION
SHEET# DETAIL# ELEVATION#
SINGLE DATA STATION (1) CAT6 - - - -
MULTI-DATA STATION (2) CAT6 UNLESS NOTED
OTHERWISE - - - -
CEILING DATA, WIRELESS ACCESS POINT (1) CAT6 UNLESS NOTED
OTHERWISE - - - -
SINGLE DATA FLOORBOX (1) CAT6 - - - -
MULTI-DATA FLOORBOX DATA (2) CAT6 UNLESS NOTED
OTHERWISE - - - -
WALL FURNITURE FEED SEE…