About this file

This is a bid form for a Construction Manager at-Risk (CMAR) plumbing infrastructure maintenance project at the Rose Bowl Stadium in Pasadena, California, administered by the Rose Bowl Operating Company. The project encompasses the replacement and rehabilitation of the stadium's water, sewer, and gas distribution systems beneath the stadium concourse, based on recommendations from the Rose Bowl Sewer and Water Asset Management Plan (2022). The work must be executed at an operating venue with continuous event use, requiring careful coordination to maintain the stadium's domestic plumbing and fire protection service throughout construction. The bid form is structured to capture costs across multiple CSI trade divisions, including general requirements, site demolition and hardscape work, trenching and earthwork, paving, concrete, piping materials and installation, and backflow preventer components. The form accommodates pricing for a base bid focused on water maintenance and seven alternatives addressing sewer infrastructure, gas infrastructure, modified work scheduling, and federal funding reporting requirements under BABA (Buy American/Build American Act) provisions.

The bid form is designed as a template for multiple contractors to submit parallel pricing proposals, with columns for three contractor submissions and unit cost breakdowns presented on both a cost-per-item and cost-per-square-foot basis. Line items include labor, materials, and equipment costs, with subtotals calculated before overhead, profit, insurance, bonding, and gross receipts tax additions. The form explicitly excludes permit fees, geotech fees, and deputy inspector fees from contractor responsibility. The structure indicates a phased procurement approach with preconstruction and design-assist services in Phase 1, and conditional authorization of Phase 2 construction services contingent on RBOC's discretionary option exercise. Key selection criteria emphasize directly relevant wet-utility experience, open-cut main replacement and trenchless sewer rehabilitation capabilities, live-venue event-window phasing expertise, subsurface risk management, financial strength, safety record, and commitment to Pasadena-based subcontractors and local workforce.

View the file

Other files

File Type Posted
Construction_Manager_At-Risk_Plumbing_Infrastructure_Enhanced_Maintenance_Project_(Addendum_#4_Revision).pdf PDF
RBOC_Plumbing_Infra_Sewer_Plan_Check_Comment_Response_Matrix.xlsx XLSX spreadsheet
RBOC_Plumbing_Infra_Water_Plan_Check_Comment_Response_Matrix_.xlsx XLSX spreadsheet
Sewer_Maintenance_Project_-_Plan_Check_Revision_1.pdf PDF
Water_Maintenance_Project_-_Plan_Check_Revision_1_.pdf PDF
WO_798158_RBOC_1001_ROSE_BOWL_DRIVE_PASADENA_CA_NEW_.pdf PDF
RBOC_Plumbing_Infra_Specs_for_IFB_PDFs_-_NEW_Y_Addendum_No._3.zip ZIP file
099742017-_RBOC_Plumbing_Infra_Gas_Maintenance_100_Plans_2026-09-11_Item_4_NEW_S.pdf PDF
LA-01286-14_RoseBowlPlumbing_UtilityRecsLtr_8-13-2026.pdf PDF
099742017-_RBOC_Plumbing_Infra_-_Sewer_Maintenance_Project_Issue_for_Bid.pdf PDF
Subcontractor_Listing_(1)_-_RBOC_CMAR.pdf PDF
REQUIRED_FORMS_-_AAs_-_SIG-LEGAL-STATUS_-_DECLARATION_OF_NONCOLUSION_08022024_v2.pdf PDF
25270-PW_03-11-2026_ROSE_BOWL_-_UTILITY_SURVEY.pdf PDF
099742017-_RBOC_Plumbing_Infra_-_Water_Maintenance_Project_Issue_for_Bid.pdf PDF
Rose_Bowl_Stakeholder_Calendar_for_RFP_-_to_send.xlsx XLSX spreadsheet
Civil_Litigation_History_Certification_ver02_-_RBOC_CMAR.pdf PDF
Declaration_of_Elibility_to_Contract_(not_debarred)_-_RBOC_CMAR.pdf PDF
[P]_Proof_of_Authority_(2)_-_RBOC_CMAR_Plumbing.pdf PDF
Public_Contract_Code_Disclosure_-_RBOC_CMAR.pdf PDF
RELEVANT_EXPERIENCE_FORM.pdf PDF
Pasadena_Taxpayer_Protection_Amendment_Disclosure_(2).pdf PDF
DESIGNATED_REPRESENTATIVESdocx.pdf PDF
CONFLICT_OF_INTEREST_(5).pdf PDF
DISQUALIFICATION_DISCLOSURE_(4).pdf PDF
Emergency_FEMA_TC.pdf PDF
Exclusive_Negotiation_Agreement__TEMPLATE.pdf PDF
DoIT_Technical_Questionnaire.xlsx XLSX spreadsheet
Federal_Required_Certification_(4).pdf PDF
Unique_Entity_ID_(SAM).pdf PDF
Disclosure_of_Lobbying_Activities.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Analysis Template

PROJECT:Rose Bowl Plumbing Infrastructure
ADDRESS1001 Rose Bowl Drive Pasadena, CA. 91103PLUMBING MAINTENANCE PROJECT

BID FORM

CLIENT:Rose Bowl Operating Company
DATE:Contractor Name:Contractor Name 02Contractor Name 03
Date:DATE EstimateDATE Estimate
CSITrade DescriptionQTYUnitCost/UnitCostCost/SFCostCost/SFCost
BASE BID: WATER MAINTENANCE PROJECTERROR:#DIV/0!$ -ERROR:#DIV/0!$ -
01 01 00General RequirementsERROR:#DIV/0!ERROR:#DIV/0!
01 01 00General Conditions
01 01 00Traffic Control
01 15 10Survey / Utility LocatingERROR:#DIV/0!ERROR:#DIV/0!
02 40 00Sawcutting / Site Hardscape Demolition & Haul OffERROR:#DIV/0!ERROR:#DIV/0!
11 00 00Equipment
31 40 00Trenching / Over-Excavation / EarthworkERROR:#DIV/0!ERROR:#DIV/0!
31 40 00Spoils Export - Haul Off
31 40 00Dirt Backfill / Recompaction
32 12 16AC PavingERROR:#DIV/0!ERROR:#DIV/0!
32 17 13Parking StripingERROR:#DIV/0!ERROR:#DIV/0!
32 30 01Site ConcreteERROR:#DIV/0!ERROR:#DIV/0!
32 30 01Sand / CLSM Material
32 30 01Sand / CLSM Placement (Labor)
33 05 00Geogrid, Tracer Wire, Warning Tape, Other Materials
33 05 00Geogrid, Tracer Wire, Warning Tape, Other Material Placement (Labor)
33 10 00Site Domestic Water Piping / Accessory MaterialERROR:#DIV/0!ERROR:#DIV/0!
33 10 00Site Domestic Water Piping / Accessory Installation (Labor)
33 10 00Backflow Preventer Material
33 10 00Backflow Preventer Installation (Labor)
SUBTOTAL$ - 0$ - 0$ - 0
Overhead and ProfitERROR:#DIV/0!ERROR:#DIV/0!
Insurance / BondingERROR:#DIV/0!ERROR:#DIV/0!
Gross Receipt TaxERROR:#DIV/0!ERROR:#DIV/0!

Total Project Cost $ - 0 ERROR:#DIV/0! $ - 0 ERROR:#DIV/0! $ - 0

#AlternatesQTYUnitCost/UnitCostCost/SFCostCost/SFCost
1Sewer Infrastructure Materials (Alternative 1)
2Sewer Infrastructure Labor (Alternative 1)
3Gas Infrastructure Materials (Alternative 2)
4Gas Infrastructure Labor (Alternative 2)
5Cost Variance Associated with 6 Day Work Week (Mon - Sat) (All)
6Cost Variance Associated with BABA / Federal Funding Reporting Requirements (Water - Base Bid)
7Cost Variance Associated with BABA / Federal Funding Reporting Requirements (Sewer - Alternative 1 only)
8Cost Variance Associated with BABA / Federal Funding Reporting Requirements (Gas - Alternative 2 only)
Exclusions
1Permit Fees.
2Geotech Fees and Deputy Inspector Fees.