About this file

This is a Request for Proposals (RFP) issued by the Rose Bowl Operating Company (RBOC) in partnership with the City of Pasadena, California, for a Construction Manager at Risk (CMAR) to provide preconstruction and design-assist services for the Rose Bowl Stadium Plumbing Infrastructure Enhanced Maintenance Project. The project involves the replacement and rehabilitation of water, sewer, and gas distribution systems beneath the stadium concourse while maintaining continuous operations at the active venue. The RFP is structured as a Base Bid for the Water Maintenance Project plus two optional Add Alternates: Alternate 1 for the Sewer Maintenance Project and Alternate 2 for the Gas Maintenance Project, each defined by separate 100% construction document sets issued July 17, 2026. The proposal submission deadline is September 21, 2026, at 2:30 p.m., with a mandatory pre-proposal meeting scheduled for September 9, 2026, at 9:00 a.m. at 1001 Rose Bowl Drive, Pasadena, California. The question submission deadline is September 11, 2026, at 5:00 p.m. Interviews are scheduled for September 22-23, 2026 (hold dates). The contract is structured in two phases: Phase 1 includes preconstruction services and a funded subsurface field investigation program, while Phase 2 (optional) consists of construction services contingent on RBOC exercising its option and authorizing funding.

The Base Bid Water Maintenance Project is funded through a State of California grant administered by the City of Pasadena. Alternate 1 (Sewer Maintenance Project) is funded through federal Community Project Funding administered by the U.S. Environmental Protection Agency and carries additional federal compliance requirements including certified payroll administration and Buy America documentation. Alternate 2 (Gas Maintenance Project) is eligible under the same State grant as the Base Bid but creates no obligation on RBOC. RBOC reserves the right to accept any, all, or none of the alternates in any combination, subject to availability of funds. Proposers must provide separate pricing for each line item, combined-execution credits for each award combination, and incremental schedule impacts. The evaluation is based on best value criteria including qualifications, relevant experience, technical proposal, detailed price breakdown, schedule alignment, and team composition and availability. The RFP requires proposers to demonstrate directly relevant wet-utility experience, capability in open-cut main replacement and trenchless sewer rehabilitation, expertise in live-venue event-window phasing with water and fire service continuity, subsurface risk management expertise, and commitment to Pasadena-based subcontractors and local workforce. Selection will result in no more than five finalists being shortlisted for interviews and final scoring. The Contractor must acknowledge that initial pricing will be held through Phase 2 with potential decreases through approved value engineering opportunities. Phase 1 pricing shall include preconstruction services, a field investigation program with potholing and utility verification, and development of a Guaranteed Maximum Price (GMP) for Phase 2.

View the file

Other files

File Type Posted
RBOC_Plumbing_Infra_Sewer_Plan_Check_Comment_Response_Matrix.xlsx XLSX spreadsheet
RBOC_Plumbing_Infra_Water_Plan_Check_Comment_Response_Matrix_.xlsx XLSX spreadsheet
Sewer_Maintenance_Project_-_Plan_Check_Revision_1.pdf PDF
Water_Maintenance_Project_-_Plan_Check_Revision_1_.pdf PDF
WO_798158_RBOC_1001_ROSE_BOWL_DRIVE_PASADENA_CA_NEW_.pdf PDF
099742017-_RBOC_Plumbing_Infra_-_Sewer_Maintenance_Project_Issue_for_Bid.pdf PDF
LA-01286-14_RoseBowlPlumbing_UtilityRecsLtr_8-13-2026.pdf PDF
25270-PW_03-11-2026_ROSE_BOWL_-_UTILITY_SURVEY.pdf PDF
REQUIRED_FORMS_-_AAs_-_SIG-LEGAL-STATUS_-_DECLARATION_OF_NONCOLUSION_08022024_v2.pdf PDF
Subcontractor_Listing_(1)_-_RBOC_CMAR.pdf PDF
099742017-_RBOC_Plumbing_Infra_Gas_Maintenance_100_Plans_2026-09-11_Item_4_NEW_S.pdf PDF
RBOC_Plumbing_Infra_Specs_for_IFB_PDFs_-_NEW_Y_Addendum_No._3.zip ZIP file
Copy_of_Bid_Form_v3_-_082826_addendum.xlsx XLSX spreadsheet
Rose_Bowl_Stakeholder_Calendar_for_RFP_-_to_send.xlsx XLSX spreadsheet
099742017-_RBOC_Plumbing_Infra_-_Water_Maintenance_Project_Issue_for_Bid.pdf PDF
Civil_Litigation_History_Certification_ver02_-_RBOC_CMAR.pdf PDF
Public_Contract_Code_Disclosure_-_RBOC_CMAR.pdf PDF
[P]_Proof_of_Authority_(2)_-_RBOC_CMAR_Plumbing.pdf PDF
CONFLICT_OF_INTEREST_(5).pdf PDF
DESIGNATED_REPRESENTATIVESdocx.pdf PDF
Declaration_of_Elibility_to_Contract_(not_debarred)_-_RBOC_CMAR.pdf PDF
DISQUALIFICATION_DISCLOSURE_(4).pdf PDF
Pasadena_Taxpayer_Protection_Amendment_Disclosure_(2).pdf PDF
RELEVANT_EXPERIENCE_FORM.pdf PDF
Exclusive_Negotiation_Agreement__TEMPLATE.pdf PDF
DoIT_Technical_Questionnaire.xlsx XLSX spreadsheet
Unique_Entity_ID_(SAM).pdf PDF
Disclosure_of_Lobbying_Activities.pdf PDF
Federal_Required_Certification_(4).pdf PDF
Emergency_FEMA_TC.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS

CONSTRUCTION MANAGER AT-RISK PLUMBING

INFRASTRUCTURE ENHANCED MAINTENANCE PROJECT

FOR THE

ROSE BOWL

CITY OF PASADENA, CALIFORNIA

Request for Proposals - Construction Manager At-Risk Plumbing Infrastructure Enhanced Maintenance Project Release Date: Wednesday, August 26, 2026

Attachments:

A - DISQUALIFICATION_DISCLOSURE (4)

B - CONFLICT_OF_INTEREST (5)

D - Pasadena_Taxpayer_Protection_Amendment_Disclosure (2) E - DESIGNATED REPRESENTATIVESdocx

F - RELEVANT EXPERIENCE FORM

H - Copy of Bid Form v3 - 082826 addendum I - Public_Contract_Code_Disclosure_-_RBOC_CMAR N - Rose Bowl Stakeholder Calendar for RFP - to send O - 099742017- RBOC Plumbing Infra - Water Maintenance Project Issue for Bid P - Proof_of_Authority_(2)_-_RBOC_CMAR_Plumbing Q - Declaration_of_Elibility_to_Contract_(not_debarred)_-_RBOC_CMAR R - Civil_Litigation_History_Certification_ver02_-_RBOC_CMAR S - 099742017- RBOC Plumbing Infra Gas Maintenance 100 Plans 2026-09-11 Item 4 NEW S T - LA-01286-14_RoseBowlPlumbing_UtilityRecsLtr_8-13-2026 U - Subcontractor_Listing_(1)_-_RBOC_CMAR V - REQUIRED FORMS - AAs - SIG-LEGAL-STATUS - DECLARATION OF NONCOLUSION 08022024 v2 W - 099742017- RBOC Plumbing Infra - Sewer Maintenance Project Issue for Bid

X - 25270-PW_03-11-2026_ROSE BOWL - UTILITY SURVEY

Y - RBOC Plumbing Infra Project Manual Specs IFB - NEW Y Addendum No. 3 Z - Sewer CCTV Inspection Records (GPRS, 2025) NEW AA - Water Maintenance Project - Plan Check Revision 1 BB - Sewer Maintenance Project - Plan Check Revision 1 CC - RBOC Plumbing Infra Water Plan Check Comment Response Matrix DD - RBOC Plumbing Infra Sewer Plan Check Comment Response Matrix

Release Date: Wednesday, August 26, 2026

1. Introduction

1. Summary

1. The Rose Bowl Operating Company (“RBOC”) is seeking statements of qualifications, technical proposals, and price proposals (“Proposal(s)”) for a Construction Manager at Risk (“CMAR” or “Contractor”) to provide preconstruction/design-assist services including a funded subsurface field investigation program and, if RBOC's option to authorize Phase 2 is exercised, construction services for the Rose Bowl Stadium Plumbing Maintenance Project (the “Project”): the replacement and rehabilitation of the stadium's water, sewer, and gas distribution systems beneath the stadium concourse, implementing the replacement program recommended by the Rose Bowl Sewer and Water Asset Management Plan (2022), as indicated below and described in greater detail in the Contract Documents enumerated in the City's Standard Form of Agreement. The work will be performed at an operating stadium: the venue remains in continuous event use throughout construction, and the stadium's domestic plumbing and fire protection service share a single combined system that must remain in service. The Base Bid and each alternate are defined by a separate 100% Construction Document set, identified in paragraph 5 below.

2. The RBOC is seeking a CMAR that excels in the following key areas, which are evaluated under the criteria set forth in section 6:

A. Directly relevant wet-utility experience.

B. Open-cut main replacement and trenchless sewer rehabilitation.

C. Live, occupied venue event-window phasing and water/fire service continuity.

D. Subsurface risk management.

E. A collaborative mindset to achieve optimal value within the Project budget and the stadium's event calendar.

F. Financial strength and a strong safety record.

G. Commitment to Pasadena-based subcontractors and local workforce.

3. A Selection Committee shall review the Proposals and, based on the criteria identified in the RFP, the committee shall select no more than 5 of the highest scoring finalists to shortlist, interview, and complete final scoring pursuant to P.M.C. Section 4.08.047, competitive selection, using the CMAR alternative project delivery method, authorized under P.M.C. Sections 4.08.136 and 4.08.027 and by the RBOC Board of Directors on August 6, 2026. The Proposer recommended for award of the contract will be evaluated and determined on a best value basis, based on qualifications, relevant experience, technical proposal, detailed price proposal cost breakdown, ability to guarantee that the initially proposed pricing included in this RFP response will be held through Phase 2 with the option of being decreased if value engineering opportunities are proposed and approved, proposed schedule which aligns with the phased site logistics, construction approach, proposed team including their availability and percentage dedicated to this project and interviews. Interviews will be used to validate and, where warranted, adjust scores under the published Evaluation Criteria; no separate interview points are awarded.

4. Construction Manager at Risk is a two-phased project delivery process:

A. Preconstruction/Design-Assist Services, including the Phase 1 Field Investigation Program (“Phase 1”), Release Date: Wednesday, August 26, 2026

B. An option for (2) Construction (“Phase 2”). If the RBOC authorizes Phase 2 it will either issue an amendment to the Phase 1 contract or a separate contract for Phase 2.

Note: The RBOC is not obligated to authorize Phase 2 or issue a contract for Phase 2 Construction. It is RBOC's intent to reach a mutually agreeable Guaranteed Maximum Price (GMP) prior to an award of a Phase 2 contract/amendment. See Section 9 (Review and Award Recommendation Process) for further details on the authorization of Phases.

5. The Project is structured as a Base Bid plus two (2) separately priced alternates. Each package is defined by its own 100% Construction Document set, all issued July 17, 2026 under Kimley-Horn Project ID 099742017: Base Bid — Water Maintenance Project (Sheets CW0.0 through CW4.0), replacement of the stadium's water distribution mains, valves, and service laterals; Alternate 1 — Sewer Maintenance Project (Sheets CS0.0 through CS4.0), cleaning and cured-in-place pipe lining of the stadium sewer system with major and minor spot repairs and selected new laterals; and Alternate 2 — Gas Maintenance Project (Sheets CG0.0 through CG4.2), abandonment of the existing underground gas distribution system and installation of new medium-density polyethylene gas distribution following the Water Maintenance Project in joint trench where possible.

6. RBOC may accept any, all, or none of the alternates, in any combination, at award or at a later date, subject to the Availability of Funds provision of this RFP. Alternates shall be priced on the basis of execution concurrent with the Base Bid under a single mobilization, and the Price Proposal requires stated combined-execution credits and schedule increments for each award combination. See Section 6 (Scope of Work), Section 6.9 (Price Proposal — Bid Form and OpenGov Line Items), and Attachment [S] (Bid Form). Award, if any, will be made to the responsive and responsible Proposer whose Proposal is determined to provide the best value under the published Evaluation Criteria. For scoring purposes the Evaluated Cost is computed identically for every Proposer; RBOC may thereafter accept alternates in any combination, at the prices proposed, within the acceptance window stated in this

RFP.

7. Funding: the Base Bid is funded through a State of California grant administered by the City of Pasadena. Alternate 1 is funded through a federal Community Project Funding grant administered by the U.S. Environmental Protection Agency and therefore carries the federal requirements set out in Section 7.7, which apply only if Alternate 1 is awarded. Proposers shall price the federal compliance burden within their Alternate 1 pricing. Alternate 2 is eligible under the same State grant as the Base Bid; it is priced for evaluation and possible award. Alternate 2 is expected to be executed concurrently with the Base Bid. Pricing Alternate 2 creates no obligation on RBOC. Clarifications specific to the Gas Maintenance Project (permit route and timing, points of connection, and re-pressurization sequencing) will be resolved with the selected CMAR during Phase 1 preconstruction, and Alternate 2 pricing shall remain open for acceptance through completion of GMP development as provided in Section 6.4. If elected, Alternate 1 shall be executed concurrently with the Base Bid unless RBOC issues a separate or delayed Notice to Proceed as provided below. In all cases, the CMAR shall maintain cost accounting, certified payroll, and material documentation that segregates all Alternate 1 work from all other work in detail sufficient to support federal reporting and audit; no adjustment to the Base Bid price will be made for that segregation. RBOC further reserves the right to issue a separate or delayed Notice to Proceed for Alternate 1, and the Price Proposal requires the Proposer to state the schedule and cost effect of an Alternate 1 Notice to Proceed issued up to 120 days after the Base Bid Notice to Proceed. RBOC may assign or reallocate funding sources among award packages at or after award; any such reallocation shall not change the Contract price. Any package funded in whole or in part with federal funds shall carry the requirements of Section 7.7.

2. Background

Release Date: Wednesday, August 26, 2026

The City of Pasadena is an ethnically diverse community that is home to approximately 142,017 people. Pasadena is the ninth-largest city in Los Angeles County. It is one of the primary cultural centers of the San Gabriel Valley. The City covers approximately 22.5 square miles, with an average of ten residents per acre. The median age of its residents is approximately 36.9 years.

There are over 100,000 jobs in a wide variety of industries in the City of Pasadena.

Location:

The City of Pasadena is a diverse community that is home to approximately 142,017 people. Pasadena is the ninth-largest city in Los Angeles County. It is one of the primary cultural centers of the San Gabriel Valley. The

City covers approximately 22.5 square miles, with an average of ten residents per acre. The median age of its residents is approximately 36.9 years. There are over 100,000 jobs in a wide variety of industries in the City of

Pasadena.

The Rose Bowl:

The Rose Bowl Stadium, opened in 1922 and designated as both a National Historic Landmark and a California

Historic Civil Engineering Landmark, stands as one of the most iconic sport and entertainment venues in the world. The selected CMAR's work must adhere to all legal requirements to maintain the Rose Bowl Stadium's designated Landmark status. Known globally as “America's Stadium,” the venue has hosted five Super Bowls, two Olympic Games, and countless events of historic significance across college football, international soccer, concerts, and civic life. The stadium is an enduring symbol of excellence and pride for the City of Pasadena and the State of California.

Rose Bowl Lasting Legacy Campaign:

The Rose Bowl Lasting Legacy Campaign is a multi-phase initiative focused on eight major capital improvements timed around the 2028 Olympic Game.

Rose Bowl Stadium Plumbing Infrastructure Project:

Rose Bowl Stadium Plumbing Infrastructure Project lays the groundwork of the stewardship the Rose Bowl Lasting Legacy Campaign, renewing the core utility infrastructure on which every event at the venue depends.

Through this campaign and its supporting capital projects, the RBOC seeks to preserve and elevate the venue's historic stature while preparing it to meet the demands of the 21st Century. The 100% Construction Documents title the three packages the Water, Sewer, and Gas Maintenance Projects; certain funding, design, and Board records refer to the same work as the Rose Bowl Stadium Plumbing Infrastructure Project. Both names refer to this Project.

Impetus:

At the stadium's 100-year mark, RBOC commissioned the Rose Bowl Sewer and Water Asset Management Plan, which found that most of the stadium's underground water and sewer lines have exceeded the typical 50-year design life, (some in service for as many as 85 years at the time of the report) and documented a history of pipe breaks repaired under emergency conditions rather than through planned replacement.

Condition:

Release Date: Wednesday, August 26, 2026

The stadium is served by a single 12-inch lateral with a 10-inch meter (east side, near Gate B) carrying both domestic and fire protection demand. Distribution is a 12-inch ductile iron outer loop, an 8-inch segment, and a 6-inch cast iron inner loop dating to 1935. The venue sits in a flood plain on miscellaneous rock and old fill and has experienced subsurface movement and cave-ins that have ruptured utility lines. Record drawings for a system of this age are incomplete, and repeated leaks in the existing underground gas piping have been attributed to unstable soils that prior remediation has not resolved. The sewer system discharges to the City's collection system through a single 12-inch main at the south end of the brick plaza; a CCTV survey and NASSCO condition assessment has not yet been performed; it will be conducted as part of the Project, and the resulting condition report will be provided to Proposers by addendum if available prior to the Proposal Submission Deadline, or to the selected CMAR during Phase 1.

Work:

The water scope is maintenance replacement of aging mains. The designed water scope abandons the 6-inch cast iron inner loop, upsizes the 8-inch segment to 12-inch, and maintains a combined fire and domestic system for reliability and ease of operator maintenance. Sewer rehabilitation (Alternate 1) is by cured-in-place pipelining with major and minor spot repairs and selected new laterals, to be informed by the CCTV survey and NASSCO condition assessment once performed. Gas replacement (Alternate 2) abandons existing underground gas system in favor of new MDPE distribution following the water alignment in joint trench where possible.

3. Contact Information

Deadline for Questions

The deadline to submit questions related to this solicitation is Friday, September 11, 2026, prior to 5:00 pm.

Questions regarding this solicitation should be submitted directly through the City's eProcurement Portal Q&A function. Do not contact any City employee or official regarding this solicitation. Any questions submitted after the date and time specified may not be considered.

Project Contact:

Evan Stein Director of Projects and Facilities Email: estein@rosebowlstadium.com Phone: (714) 595-4027 Procurement Contact:

Nancy Silver Chief Compliance Officer Email: nsilver@rosebowlstadium.com Phone: (626) 577-3100 Ext: 224 Department:

Rose Bowl

4. Timeline mailto:estein@rosebowlstadium.com tel:(714)595-4027 mailto:nsilver@rosebowlstadium.com tel:(626)577-3100;ext=224

Release Date: Wednesday, August 26, 2026

Release Project Date August 26, 2026

Pre-Proposal Meeting (Mandatory) September 9, 2026, 9:00am

1001 Rose Bowl Drive, Pasadena CA 91103.

Question Submission Deadline September 11, 2026, 5:00pm

Proposal Submission Deadline September 21, 2026, 2:30pm

Interviews Day 1 (Hold) September 22, 2026

Interviews Day 2 (Hold) September 23, 2026

Release Date: Wednesday, August 26, 2026

2. General Instructions

1. NOTICE REGARDING DISCLOSURE OF CONTENTS OF DOCUMENT

All responses to this Request for Proposal (RFP) accepted by the City of Pasadena (City) shall become the exclusive property of the RBOC/City. At such time as the RBOC Chief Executive Officer recommends a contractor to the RBOC Board of Directors, and such recommendation, with any recommended contract appears on the RBOC Board agenda, all proposals accepted by the RBOC/City shall become a matter of public record and shall be regarded as public, with the exception of those elements of each proposal which are defined by the contractor as business or trade secrets and plainly marked as "Trade Secret", "Confidential" or "Proprietary". Each element of a proposal which a contractor desires not to be considered a public record must be clearly marked as set forth above, and any blanket statement (i.e. regarding entire pages, documents or other non-specific designations) shall not be sufficient and shall not bind the RBOC/City in any way whatsoever. If disclosure is required or permitted under the California Public Records Act or otherwise by law, the RBOC/City shall not in any way be liable or responsible for the disclosure of any such records or part thereof.

2. Funding Source

This procurement is funded by Department of Water Resources. Vendors must submit all required documents with their proposal.

3. Electronic Submission and Delivery Instructions

Parties interested in responding are required to submit proposals electronically through the City of Pasadena's eProcurement Portal no later than 2:30 pm on Monday, September 21, 2026.

Please upload sufficiently early electronically through the city's eProcurement Portal before the time and day listed in the Notice Inviting Proposals. Proposals must be received in the system prior to the deadline.

The entire proposal must be formatted on standard-size 8½”x11” pages; 12 point font only. The "Technical Proposal," "Additional Data," and "Statement of Qualifications" can be no more than 50 grand total pages.

The Price Proposal must include all costs associated with the Technical Proposal as described in the Price Proposal instructions in the “#Proposer's Submittals/Checklist.”

The Technical Proposal should disclose your technical approach in as much detail as possible, including, but not limited to, the requirements of the technical proposal instructions. Along with all required forms and submittals (See #Attachments, and #Proposer's Submittals/Checklist. No Pricing shall be included in this part.

Proposals received after the Proposal Deadline may not be accepted by the RBOC/City.

https://procurement.opengov.com/portal/pasadena https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=2849715 https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=2849723 https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=2849715

Release Date: Wednesday, August 26, 2026

4. Technical Proposal

The proposal must be prepared in two parts: a "Technical Proposal" and a "Price Proposal." Each of the parts shall be separate and complete in itself so evaluation of one may be accomplished separate from the evaluation of the other. The Technical Proposal should disclose your technical approach in as much detail as possible, including, but not limited to, the requirements of the technical proposal instructions. Along with all required forms and submittals (See #Attachments, and Submittals/Checklist. No Pricing shall be included in this part.

5. Separate Price Proposal

The Price Proposal must include all costs associated with the Technical Proposal as described in the Price Proposal instructions in the “Submittals/Checklist.”

Parties interested in responding are required to submit their Price Proposal with their Technical proposal through the City's eProcurement Portal.

The pricing must include the total price proposed to accomplish all the performance and deliverables requested in this RFP, and offered by your firm. Each Proposer must submit a Price Proposal containing all costs associated with the technical proposal. The price proposal shall describe both the total and the detailed price for which the consultant will commit to complete the total scope of work and end products. The price proposal detail shall describe costs for each professional’s time, for the completion of each proposed task, and for all materials and supplies.

The fee information is relevant to a determination of whether the fee is fair and reasonable in light of the services to be provided. Costs shall include the proposed costs and, if necessary, the approximate number of hours to provide the services as described in your proposal. Any additional fees outside the scope of the agreement must be approved in writing before commencing services for said fees. Vendor’s RFP response must be inclusive of all costs and expenses associated with travel, lodging, and any other incidental costs. The RBOC/City will not separately reimburse costs not included in the proposal.

Reference PRICE PROPOSAL.

Reimbursable cost schedules shall depict only those expenditures that are exclusive to and in support of the scope of services. The proposed reimbursable cost schedule shall include a detailed list of reimbursables.

Each Proposer must submit a PRICE Proposal containing all costs associated with the technical proposal. Using the attached Price Proposal in this RFP, provide Proposer’s lump-sum price for performing all services and work called for in the SCOPE OF WORK. The Proposer’s lump-sum price shall include, without limitation:

https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=undefined https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=undefined https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=undefined

Release Date: Wednesday, August 26, 2026

• all designs, equipment, materials, labor, insurance and bond premiums, home office, jobsite, and other overhead, profit and services relating to the Proposer’s performance of its obligations under the Contract (including all work, equipment, materials, labor, and services provided by subcontractors and intellectual property rights necessary to perform the work);

performance of each and every portion of the work

• all costs of obtaining Government approvals other than Government approvals that are the responsibility of the City of Pasadena;

• all costs of compliance with Government rules, except to the extent such compliance is the responsibility of the City of Pasadena;

• all taxes, duties, permits, and other fees or royalties incident to the performance of the

SCOPE OF WORK;

payment of all salaries, wages, benefits, and expenses of the Proposer’s employees;

compensation for all risks, liabilities, and contingencies assigned to the Proposer; and

• all other costs needed or incurred to complete the Project.

• all ProForma Submission Requirements (if required)

6. Pre-Proposal Meeting

See the "Timeline" in the Introduction section (#Introduction). If there is a Mandatory pre-proposal meeting, bidders/proposers are required to attend at the time, date, and location included in the Timeline. If there is a Non-Mandatory pre-proposal meeting, bidders/proposers are not required to attend.

Each bidder/proposer will have the opportunity to clarify and ask questions regarding the Specifications. The Pre-Proposal Meeting will be held at the time, date, and location in the Timeline of this solicitation.

7. Definitions

The words (A) "City", (B) "Department", (C) "Director", or (D) "Contractor", as used in this RFP, shall be understood to refer respectively to (A) the City of Pasadena, California; (B) the several departments therein; (C) the directors of the several City departments; or any of their properly authorized assistants; and ( D) the person, firm or corporation with whom the contract is made by said City or the agent or legal representative who may be appointed to represent such person, firm or corporation in the signing and performance of said contract.

https://procurement.opengov.com/portal/pasadena/projects/296489/document?section=2849713

Release Date: Wednesday, August 26, 2026

3. General Requirements

1. Standard terms and conditions

Prior to the award of any work hereunder, City and contractor shall enter into a written contract in substantially the form attached hereto with such revisions thereto as the City may determine necessary and appropriate. PROPOSERS responding to this RFP are strongly advised to review all the terms and conditions of the contract, and shall be deemed to have accepted them.

2. Firm commitment of availability of service

Once a proposal is opened, a PROPOSER is expected to maintain an availability of service as set forth in its proposal for at least four months after date for opening proposals.

3. RELEVANT EXPERIENCE

Provide experience with governmental agencies for three projects/contracts of similar scope and size that took place in the past ten (10) years. Complete and submit the attached Relevant Experience Form with your proposal to demonstrate experience with projects/contracts of similar scope and size to that which is to be performed.

4. Reservations

The City reserves the right to reject any or all bids or proposals and any item or items therein, and to waive any non conformity of proposals with this RFP, whether of a technical or substantive nature, as the interest of the City may require.

5. Documents to be construed together

The Request for Proposal (RFP), the Proposal, the Non Collusion Affidavit, and all documents referred to in the complete specifications and the Contract to be entered into between the Contractor and the City, and all modifications of said documents, shall be construed together.

6. Patent fees; patent, copyright, trade secret and trademark fees

Each PROPOSER shall include in the price bid any patent fees, royalties and charges on any patented article or process to be furnished or used in the prosecution of the Work.

7. PUBLIC CONTRACT CODE SEC. 9204 NEW PUBLIC WORKS CLAIMS PROCEDURE

Observe attached details regarding Public Contract Code Section 9204. AB 626, approved by the Governor on September 29, 2016, created a new Public Contract Code Section 9204, which specifies new procedural requirements for claims submitted by a contractor on any public works project. These new requirements contain burdens for both private contractors and public entities and are specifically made applicable to charter cities.

Release Date: Wednesday, August 26, 2026

8. Request for Proposal (RFP) quantities:

The quantities contained in the RFP documents are approximate only and are for the sole purpose of comparing proposals. The City may, in accordance with the specifications, request additional services as necessary at the City's sole discretion, as increased by the unit price noted and payment will be made for the amount of services actually provided as determined by the City and accepted at the unit prices noted in the proposal.

9. CHANGE ORDER MANAGEMENT

CHANGE ORDER MANAGEMENT Any additional work identified during the course of the project that is deemed necessary, but outside the original Scope of Services, must be recorded as a Change Order and approved by the City Project Manager in writing before work is started.

10. Taxpayer Protection Act

Under the provisions of the City of Pasadena Taxpayer Protection Act ("TPA"), the Contractor/Organization will be considered a "recipient of a public benefit." The full provisions of the TPA are set forth in Pasadena City Charter, Article XVII. Under the TPA, City public officials who approve this Contract are prohibited from receiving specified gifts, campaign contributions or employment from Contractor for a specified time. As well, if this Contract is to be approved by the City Council, Councilmembers or candidates for Council are prohibited from receiving campaign contributions during the time this Contract is being negotiated (from the due date for an RFP response until award of a contract; this restriction does not apply to competitive and noticed low bid contracts). This prohibition extends to individuals and entities that are specified in the TPA and includes Contractor/Organization and its trustees, directors, partners, corporate officers and those with more than a 10% equity, participation, or revenue interest in Contractor/Organization. Contractor/Organization understands and agrees that: (A) Contractor/Organization is aware of the TPA; (B) Contractor/Organization will complete the forms provided by the City to identify all of the recipients of a public benefit specified in the TPA;

and (C) Contractor/Organization will not make any prohibited gift, campaign contribution or offer of employment to any public official who negotiated and/or approved this Contract, and will not make any prohibited campaign contribution during the time this contract is being negotiated. The Contractor shall submit a copy of the completed TPA form to the City Clerk’s Office if the contract is to be awarded by the City Council via e-mail: OfficialRecords- CityClerk@Cityofpasadena.net or by fax: (626) 744-3921, and submit a copy with the response package. For more information please go to: https://www.cityofpasadena.net/city-clerk/disclosure-reportsax-payer-protection-act-tpa/

11. CONFLICT OF INTEREST STATEMENT ** REVIEW

Release Date: Wednesday, August 26, 2026

The proposing Consultant shall disclose any financial, business or other relationship with the City of Pasadena that may have an impact upon the outcome of the contract or any construction project. The Consultant shall also list current clients who may have a financial interest in the outcome of this contract or the construction project that will follow. The proposing Consultant shall disclose any financial interest or relationship with any construction company that might submit a bid on the construction project related to this solicitation. Proposers must complete and submit the following Form: Conflict of Interest Statement

12. Compliance with the Levine Act (Government Code Section 84308)

The Levine Act precludes an officer of a local government agency, including an elected official, from participating in the award of a contract if he or she receives any political contributions totaling more than $500 in the 12 months preceding the pendency of the contract award, and for 12 months following the final decision, from the person or company awarded the contract.

Proposers should ensure their employees, agents, and consultants are aware of the requirements of the Levine Act before the proposal is submitted, so as to avoid inadvertent violations.

13. Payment of Subcontractors, Suppliers, and Workers

The Prime Contractor shall be solely responsible for the payment of all subcontractors, suppliers, laborers, and any other persons or entities employed in connection with the performance of this Contract.

The RBOC/City shall have no obligation to pay, or to ensure the payment of, any subcontractors, suppliers, or workers directly. The Prime Contractor shall ensure timely and full payment in accordance with all applicable laws, including but not limited to California Public Contract Code §§ 10262 and 10262.5 and Labor Code § 218.7.

Failure to comply with this requirement may result in the withholding of payments, imposition of penalties, and/or other remedies available under the Contract and applicable law.

The Prime Contractor shall also include in all subcontracts a provision requiring subcontractors to pay their lower-tier subcontractors and suppliers in a timely manner consistent with this section.

Release Date: Wednesday, August 26, 2026

4. City Requirements

There are forms included in the section named Submittal/Checklist of these specifications which a bidder or proposer must complete to establish compliance with a number of City Requirements, including, but not limited to, equal employment opportunity and affidavit of non-collusion. These forms and their instructions should be considered an integral part of the specifications and failure to complete them may be grounds, in the sole discretion of the RBOC/City, for rejection of any bidder or proposer.

1. Pasadena Operating Companies

If this solicitation is issued by an Operating Company of the City of Pasadena including the Pasadena Center Operating Company; or Rose Bowl Operating Company; or Pasadena Community Access Corporation: In this solicitation, any reference to the City, shall actually refer to the PCOC, PRHB, or RBOC, or PCAC, e.g. "City" shall refer to the Operating Company, "City Council" to its Board of Directors, and "City Manager" to its Chief Executive Officer.

2. Equal Employment Opportunity in Contracting

Policy - The City of Pasadena is committed to a policy of Equal Employment:

• Contracting. Contractors expressly agree to comply with the City’s ordinances and regulations regarding Equal Opportunity Employment as well as regulations that may be mandated by the source of the funds supporting this contract.

Compliance – To the extent permitted by law, Contractor expressly agrees to establish compliance with the Equal Employment Opportunity Practices Provisions of Chapter 4.08 of the Pasadena Municipal Code, and the Rules and Regulations adopted pursuant to said ordinance.

The successful bidder or proposer may be required to submit documentation during the term of the contract to evidence on going compliance with the City’s Equal Opportunity Practices Provisions. Such documentation may include, but not be limited to certified payroll records and Current Permanent Workforce Utilization reports.

Required Forms – Each bidder or proposer must submit a completed Form AA-1. Failure to submit this form will result in automatic disqualification with no exceptions unless bidder or proposer has an approved Form on file with the City.

Questions regarding Chapter 4.08 of the Pasadena Municipal Code and regulations adopted pursuant thereto should be directed to the Department of Finance, Purchasing Division 626.744.6755.

3. Declaration of Non-Collusion by Contractor

Release Date: Wednesday, August 26, 2026

This form is only applied for formal solicitations $75,000 or more. The City requires that each bidder or proposer executes and submits to the City with the Bid/Proposal, the attached Declaration of Non Collusion in the section named "Submittals/Checklist."

4. SAMPLE CONTRACT

A sample of the contract the successful vendor will be required to enter into with the RBOC/City is attached hereto and by this reference incorporated herein and made part of this solicitation.

5. CHANGE ORDER MANAGEMENT

Any additional work identified during the course of the project that is deemed necessary, but outside the original Scope of Services, must be recorded as a Change Order and approved by the RBOC in writing before work is started.

6. Local Preferences

The City of Pasadena is committed to promoting the economic health and well being of its residents. To this end, contractor agrees to recruit Pasadena residents initially and to give them preference, if all other factors are equal, for any new positions that result from the performance of this contract and which are performed within the City.

7. Pasadena Business License

Awarded bidder or proposer may be required to obtain and pay for any required business license under Title 5 of the Pasadena Municipal Code.

• If the business will not come into the City for the purpose of providing services for this contract they are not required to obtain a business license.

• If the business will only be coming into the city no more than 10 times to work on projects, they are charged 33% of the annual tax (Pasadena Municipal Code Section 5.04.130C)

• If they come into the City more than 10 times they are required to pay the annual fee.

• Any subcontractors used by the awarded bidder or proposer will be required to obtain a license if they will be coming into the City to perform services.

For further information contact Municipal Services Department at (626) 744-4166, Monday- Friday between 7:15 am and 5:15 pm. Additional Information regarding business license fees can be found here: https://www.cityofpasadena.net/finance/licenses/business-licenses/

8. Acceptance of Conditions

By submitting a bid or proposal, each bidder or proposer expressly agrees to and accepts the following conditions:

https://www.cityofpasadena.net/finance/licenses/business-licenses/

Release Date: Wednesday, August 26, 2026

• All parts of the Instructions to bidder or proposer and Specifications will become part of the Contract between the selected bidder or proposer and the RBOC/City;

• The RBOC/City may require whatever evidence is deemed necessary relative to the bidder or proposer financial stability and ability to complete this project;

• The RBOC/City reserves the right to request further information from the bidder or proposer, either in writing or orally, to establish any stated qualifications;

• The RBOC/City reserves the right to solely judge the bidder or proposer representations, and to solely determine whether the bidder or proposer is qualified to undertake the project pursuant to the criteria set forth herein. The bidder or proposer, by submitting a bid, expressly acknowledges and agrees that the judgment of the RBOC/City as to whether or not the bidder or proposer is qualified to perform the project, shall be final, binding and conclusive;

• The RBOC/City reserves the right to reject all bids, waive any irregularity in any of the bids, or cancel or delay the project at any time;

• This bidding process does not commit the RBOC/City to award any contract, and the RBOC/City is not liable for any costs incurred by the bidder or proposer in the preparation and submission of a bid.

9. Pasadena Business

Local Business is defined in the Pasadena Municipal Code section:

4.08.020, O: "Local business" means a business with a fixed place of business located in the city.

To receive any preferences offered to a Pasadena business in this solicitation, a Pasadena business must be located within the City Boundary by the release date of this solicitation.

10. Pasadena Living Wage Ordinance

If this purchase includes a service, and the contract total is at $25,000 or more, it is then subject to the City of Pasadena's Living Wage Ordinance, Pasadena Municipal Code Chapter 4.11. The ordinance requires that contractors providing labor or services to the City under contracts in excess of $25,000 pay no less than the City’s Living Wage to all employees who spend any of their time providing labor or delivering services to the City.

The selected contractor will be required to evidence compliance with the Living Wage Ordinance by submitting payroll records as requested by the City. Each record shall include the full name of each employee performing labor or providing services under the contract; job classification; rate of pay and benefit rate.

Failure to comply with the provisions of the Pasadena Living Wage Ordinance is grounds for termination of the contract and a basis for penalties as stated in Pasadena Municipal Code Chapter 4.11. Questions concerning the Pasadena Living Wage Ordinance should be directed to:

Release Date: Wednesday, August 26, 2026

Finance Department Purchasing Division 626-744-6755 - phone 626-744-6757 – fax

Please visit https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/ for the current calendar year Pasadena Living Wage rate.

11. PAYMENT OF A CITY-WIDE MINIMUM WAGE

If a vendor is providing labor for any subsequent contract resulting from this solicitation, they must comply with the City of Pasadena Minimum Wage as set forth in Chapter 5.02 of the Pasadena Municipal Code. Vendors are encouraged to review the City’s minimum wage information guide at (https://bit.ly/3o3SHMh). The minimum wage ordinance may be found at Pasadena Municipal Code.

12. Errors and Omissions

Bidders or Proposers shall not be allowed to take advantage of any errors or omissions in the Instructions to Bidders/General Instructions or Specifications/Scope of Work. Full instructions will be given if such error or omission is discovered and timely called to the attention of the City.

13. Patent Fees; Patent, Copyright, Trade Secret, and Trademark Fees

Each bidder or proposer shall include in the price bid any patent fees, royalties and charges on any patented article or process to be furnished or used in the prosecution of the Work.

14. Taxes

Price bid or Price Proposals shall include all federal, state, local and other taxes.

15. Certificate of Insurance

Proof of insurance is not required to be submitted with your bid/proposal, but will be required prior to the RBOC/City's award of the contract. Refer to the Insurance requirements in the "Insurance Requirements" section of this document.

16. REQUEST FOR TAXPAYER IDENTIFICATION NUMBER AND CERTIFICATION (IRS Form W-9)

The winning proposal/bid may be required to submit a completed and signed IRS Form W-9.

Failure to submit this form may result in the response being deemed non-responsive.

Link: https://www.irs.gov/pub/irs-pdf/fw9.pdf

17. LIMITATIONS ON LIABILITY

https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/ https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fbit.ly%2F3o3SHMh&data=05%7C02%7Cawatson%40cityofpasadena.net%7Cbb892f95fde0404d371508dc9bbbf790%7C82d9fc002c664402a28fc6bcdc32e491%7C1%7C0%7C638556478819490734%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=zhx6795nsAtQnJvmzYHL5q2Lzw%2FdOCl95da3qPj4Duw%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Flibrary.municode.com%2Fca%2Fpasadena%2Fcodes%2Fcode_of_ordinances%3FnodeId%3DTIT5BULIRE_ARTIGE_CH5.02PACIDEMIWA&data=05%7C02%7Cawatson%40cityofpasadena.net%7Cbb892f95fde0404d371508dc9bbbf790%7C82d9fc002c664402a28fc6bcdc32e491%7C1%7C0%7C638556478819500215%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=AX1DEPBi2FxNNRsdiRGGB1whWvtl2jG%2FQ7SO5QsB%2Fac%3D&reserved=0 https://www.irs.gov/pub/irs-pdf/fw9.pdf https://www.irs.gov/pub/irs-pdf/fw9.pdf

Release Date: Wednesday, August 26, 2026

Bidders acknowledge that they shall provide the goods and/or services without monetary limitations on liability. If Bidders take exception to this requirement, Bidders shall expressly state any exceptions, including the proposed limits of liability, (a) in detail; (b) as a separate line item;

and (c) not part of any form documents submitted. Bidders acknowledge that any exceptions may result in a finding of non-responsiveness.

18. Recycled Product Procurement Mandates Pertaining to Local Governments [Public Contract Code Sections 22150 - 22154]

This section is only applied when buying paper products.

Beginning January 1, 2022, SB 1383 requires jurisdictions (cities, counties, cities and counties, or special districts that provide solid waste collection services) to purchase recycled-content paper products that are recyclable.

SB 1383 builds upon existing laws that require jurisdictions to purchase products that contain minimum recycled content, and adds additional requirements on product recyclability and recordkeeping.

All vendors providing Paper Products and Printing and Writing Paper shall:

• Provide products that contain no less than 30% minimum recycled content and recyclability (described in further detail in State of California, Public Contract Code Sections 22150-22154, under the sections “Recycled-Content Requirements” and “Recyclability Requirements”.

• Provide a written certification and other verification from product vendors, as applicable, certifying that the products meet the recycled-content and recyclability requirements.

19. AVAILABILITY OF FUNDS

The provisions of this Contract relating to payment for products or services shall become effective when funds assigned for the purpose of compensating the Contractor as herein provided are actually available to for disbursement. The RBOC/City shall be the sole judge and authority in determining the availability of funds under this Contract. If any action is taken by the RBOC/City, any state agency, Federal department or any other agency to suspend, decrease, or terminate its fiscal obligations under, or in connection with, this Contract, the RBOC/City may amend, suspend, decrease, or terminate its obligations under, or in connection with, this Contract. In the event of termination, The RBOC/City shall be liable for payment only for products provided or services rendered prior to the effective date of the termination, provided that such products or services were provided or performed in accordance with the provisions of this Contract.

20. Addenda

If any person contemplating submitting a proposal of the items or services listed herein is in doubt as to the true meaning of any part of this RFP, he/she may submit a question through the City's eProcurement Portal Q&A section for an interpretation or correction thereof.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fleginfo.legislature.ca.gov%2Ffaces%2Fcodes_displayText.xhtml%3FlawCode%3DPCC%26division%3D2.%26title%3D%26part%3D3.%26chapter%3D3.5.%26article%3D&data=05%7C01%7Cawatson%40cityofpasadena.net%7C307f17457fcb49d363c108dbba309d38%7C82d9fc002c664402a28fc6bcdc32e491%7C1%7C0%7C638308490511442074%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=kSzPLWUdh6HYJTjfSaMqzITXO6TDf1tcUTo%2BcAV5SJw%3D&reserved=0 https://procurement.opengov.com/portal/pasadena

Release Date: Wednesday, August 26, 2026

Any interpretation or correction of City specifications will be made only by addendum, duly issued by the City representative(s) identified in this solicitation, above. Addenda (if any) shall be made available on the City's eProcurement system, and sent to each vendor included on the "Followers" list in the City's eProcurement system. A vendor's failure to address the requirements of any and all addenda may result in the response (proposal or bid, or alike) not being considered. If the City determines that a time extension is required for the proposal, the City will issue an addendum that will give the new submission date. The vendor is responsible to register on the City's eProcurement Portal and follow the project named Construction Manager At-Risk Plumbing Infrastructure Enhanced Maintenance Project in order to be included in the "Followers" list in the City's eProcurement system to insure they receive all documents including addendums which are available as a download.

The City reserves the right to change any part of these Instructions to PROPOSERS and Specifications any time prior to Deadline for Submissions. Any changes shall be in the form of addenda and will become a part of the Proposal documents and of the contract.

21. Accessibility Compliance Requirements

1. General Compliance

In accordance with Title II of the Americans with Disabilities Act of 1990 (ADA), Section 504 of the Rehabilitation Act of 1973, and all other applicable federal, state, and local disability rights laws, including the California Building Code (CBC) and California Code of Regulations Title 24, the City of Pasadena requires that all services, programs, activities, and facilities provided or utilized under this contract be fully accessible to individuals with disabilities.

The selected Contractor agrees to ensure that all work performed, and all services, programs, or activities provided under this contract comply with the requirements of Title II of the ADA and related laws. This includes, but is not limited to design, construction, communication, technology, and program delivery compliance with:

• The ADA and its implementing regulations (28 CFR Part 35 and Part 36);

• The 2010 ADA Standards for Accessible Design;

• The U.S. Access Board’s Public Rights-of-Way Accessibility Guidelines (PROWAG), as amended;

• Section 504 of the Rehabilitation Act of 1973;

• California Government Code § 4450 et seq.;

• California Code of Regulations (CCR), Title 24, including Chapter 11B of the California Building;

Code governing accessibility to public accommodations and commercial facilities;

• Any other relevant federal, state, or local regulations concerning accessibility and nondiscrimination.

These requirements apply to all aspects of the Contractor’s work, including but not limited to project or program design, facility access, pedestrian pathways, public right-of-way improvements, communications, and digital content or services.

2. Applicability of Accessibility Requirements

Accessibility compliance requirements apply when scope of work includes:

• Digital deliverables (i.e. websites, web applications, mobile applications, electronic documents, multimedia content)

• Physical infrastructure (i.e public facilities, pedestrian pathways, rights-of-way, shared use paths)

• Communication and program delivery (i.e. public meetings, outreach materials, surveys, customer service and payment platforms)

Release Date: Wednesday, August 26, 2026

• Technology procurement or development (software, hardware, ICT systems)

If any portion of the work involves these elements, the Contractor must ensure full compliance with applicable accessibility standards.

3. Digital and Electronic Content

For all digital deliverables (including websites, documents, and applications), the Contractor shall ensure conformance with, at minimum:

• Web Content Accessibility Guidelines (WCAG) 2.1, Level AA, as amended[GS1] ; and

• Section 508 of the Rehabilitation Ace (29 U.S.C. § 794d), where applicable.

All digital materials must undergo both automated and manual accessibility testing, including usability reviews by individuals representing a wide range of functional disability types (e.g., visual, auditory, cognitive, motor), and, if required, remediated prior to final acceptance. Testing must include compatibility with commonly used assistive technologies (e.g., JAWS, NVDA, VoiceOver, ZoomText, Dragon NaturallySpeaking). The Contractor must provide documentation such as Voluntary Product Accessibility Template (VPAT) or equivalent Accessibility Conformance Report (ACR), detailing compliance and describing the testing methodology.

4. Public Rights-of-Way Accessibility (PROWAG)

Any design, construction, or alteration involving pedestrian facilities, sidewalks, curb ramps, crosswalks, or public rights-of-way must conform to the latest applicable version of the U.S. Access Board’s Public Rights-of-Way Accessibility Guidelines (PROWAG), as adopted by the U.S. Department of Justice, Department of Transportation, or other relevant authority.

5. Corrective Action and Liability

The Contractor shall be held responsible for correcting any noncompliant work or deliverables identified by the City of Pasadena or any enforcement agency, at no additional cost.