This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP), Bureau of Design and Construction, dated December 16, 2025. The change order modifies Consultant Contract Number 333, Task Assignment Number 06, Change Order Number 03 for the Grayton Beach State Park Beach Re-Nourishment project located in Grayton Beach State Park. The consultant performing the work is MRD Associates, Inc., a coastal protection engineering company, with principal contact Thomas Pierro, PE. The FDEP contract manager is Vu Nguyen, and the project manager is Amber Douglas. The change order was approved by all required parties, including Budget Representative Tamika Bass, Contract Authority Michael W. Foster Jr., PE, and the consultant representative.
The change order authorizes construction phase services for a coastal restoration project consisting of native dune vegetation planting at nine sites within the Grayton Beach area, along with vehicle access relocation. The contract scope includes seven subtasks: Final Design Drone Survey ($3,580.00), Pre-Construction Meeting ($6,520.00), Site Visit #1 ($2,975.00), Site Visit #2 ($2,975.00), Records Management and Requests for Payment ($10,790.00), Substantial Completion ($4,585.00), and Post-Construction Vegetation Monitoring ($7,115.00). The total fixed fee for this change order is $38,540.00 with no reimbursable costs. The net increase from this change order is $38,540.00, bringing the total task amount including all previous change orders to $120,770.00. Payment will be made upon FDEP approval of deliverables for each subtask. The task execution date is July 26, 2023, with an end date of July 26, 2026, and no change in duration from this particular change order.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN333 06 03 61460C
Beach Re-Nourishment
MRD Associates, Inc.
Thomas Pierro, PE (561) 756-2535 tpierro@coastalprotectioneng.com
Vu Nguyen (850) 245-2630 Vu.Nguyen@FloridaDEP.gov
Change order is for the construction phase of the Grayton Beach Beach Re-Nourishment Project, per attached Change Order dated December 16, 2025.
$ 0.00 $ 27,560.00 $ 27,560.00 $ 500.00 $ 81,730.00 $ 82,230.00 $ 0.00 $ 38,540.00 $ 38,540.00
$ 500.00 $ 120,270.00 $ 120,770.00
07/26/2023
07/26/2026
07/26/2026
07/26/2026
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2025.12.19 15:55:06 -05'00'
Amber Douglas Amber Douglas Digitally signed by Amber Douglas Date: 2025.12.19 16:03:12 -05'00'
Vu Nguyen Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.12.22 08:20:40 -05'00'
Thomas Pierro, PE Digitally signed by Thomas P Pierro Date: 2025.12.22 16:45:33 -05'00'
Michael W. Foster, Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2026.01.05 11:05:09 -05'00'
61460C 37501016033 080041/23 423001 U3200 131500 QK $ 38,540.00
$ 38,540.00
Grayton Beach State Park
December 16, 2025
Amber Douglas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard 260M, MS 520 Tallahassee, Florida 32399
RE: Consultant Contract Number 333, Task Assignment Number 06 Change Order Number 03 Grayton Beach State Park Sand Placement and Dune Restoration Construction Phase Services
Dear Ms. Douglas, For your review, MRD Associates, Inc., has provided a proposal summary and person-hour documentation for the services and tasks detailed in the attached Task Assignment proposal as identified below:
Construction Phase – including pre-construction meeting services, addressing contractor inquiries and submittals, construction observation and site visits, permit compliance, substantial and final completion, project certification (permit closeout), dune vegetation monitoring, and project closeout.
Should you have any questions regarding this matter, please feel free to contact me directly at 850.654.1555.
Sincerely, Thomas Hurlimann, E.I.
Coastal Engineer THurlimann@Coastalprotectioneng.com
Cc: Dylan Nestler, P.E.
Thomas P. Pierro, P.E., D.CE
Sincerely, Thomas Hurlimann, E.I.
Beaches Project Grayton Beach State Park
Contract Number 333, Task Assignment Number 06 Change Order Number 03 Construction Phase Services
This Task Assessment is for Construction Phase Services of a coastal restoration project consisting of native dune vegetation planting as recommended in the report entitled “Grayton Beach State Park – Beaches Project, Pre-engineering Report”, dated February 7, 2024, prepared for the Florida Department of Environmental Protection, Bureau of Design and Construction, prepared by MRD Associates, Inc.
(MRD).The best option includes vegetation planting at nine (9) sites identified in the pre-engineering report and includes the relocation of the vehicle access. The project limits are within the Grayton Beach (Florida Department of Environmental Protection (DEP) Reference (R-) Monuments R-67.5 to R-71, and R- 72 to R-78). MRD Associates, Inc. (MRD) will provide construction phase services for the Florida Department of Environmental Protection (DEP), Bureau of Design and Construction (BDC).
Subtask 4: Construction Phase Services
This task includes construction related surveying services and all coastal engineering consulting services for the pre- and during-construction phase of the proposed project.
Subtask 4A: Final Design Drone Survey
Description: A drone will be flown between R-73 and R-74. The aerial RTK enabled drone will collect upland topography referenced to NAVD 88. and map vegetation from the approximate mean high water (MHW) line landward approximately 400 feet.
Deliverables: Adrone generated aerial and contour plot will be provided to the DEP Project Manager in PDF format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4A
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 2.0 $ 280.00 MRD Associates, Inc. Engineer II $115.00 20.0 $2,300.00 MRD Associates, Inc. Engineer Technician $100.00 10.0 $1,000.00 MRD Associates, Inc. Administrative/Clerical $65.00 0.0 $ 0.00
Subtask 4A Total: $3,580.00
Subtask 4B: Pre-Construction Meeting
Description: MRD will attend an in-person pre-construction meeting to support the BDC in presenting an overview of the PROJECT and scope of work, review the construction methodology, review the Construction Drawings and Technical Specifications, construction schedule, verify construction access and work areas, and the specific conditions and monitoring requirements of the DEP with the CONTRACTOR, sub-CONTRACTORs, DEP, Florida Fish and Wildlife Conservation Commission (FWC), and USFWS staff, shorebird monitor and other involved parties as necessary.
MRD shall provide a written summary of conclusions reached at the meeting to all participants.
Deliverables: A summary report of the pre-construction meeting will be provided to the DEP Project Manager in PDF format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4B
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 0.0 $ 0.00 MRD Associates, Inc. Engineer II $115.00 48.0 $5,520.00 MRD Associates, Inc. Engineer Technician $100.00 10.0 $1,000.00 MRD Associates, Inc. Administrative/Clerical $65.00 0.0 $ 0.00
Subtask 4B Total: $6,520.00
Subtask 4C: Site Visits
This subtask is for site visits
Subtask 4C.1: Site Visit #1
Description: MRD will be present for a site visit during the vehicle access relocation. The Observation will be conducted to assess how construction is proceeding with regard to compliance with the construction plans, contract document, and permit authorizations granted for the work.
Deliverables: A summary of the site visit will be provided to the DEP Project Manager in PDF format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4C.1
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 0.0 $ 0.00 MRD Associates, Inc. Engineer II $115.00 25.0 $2,875.00
MRD Associates, Inc. Engineer Technician $100.00 1.0 $ 100.00 MRD Associates, Inc. Admin/Clerical $65.00 0.0 $ 0.00
Subtask 4C.1 Total: $2,975.00
Subtask 4C.2: Site Visit #2
Description: MRD will be present for a site visit during the vehicle access relocation. The Observation will be conducted to assess how construction is proceeding with regard to compliance with the construction plans, contract document, and permit authorizations granted for the work.
Deliverables: A summary of the site visit will be provided to the DEP Project Manager in PDF format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4C.2
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 0.0 $ 0.00 MRD Associates, Inc. Engineer II $115.00 25.0 $2,875.00 MRD Associates, Inc. Engineer Technician $100.00 1.0 $ 100.00 MRD Associates, Inc. Administrative/Clerical $65.00 0.0 $ 0.00
Subtask 4C.2 Total: $2,975.00
Subtask 4D: Records Management, RFI, Requests for Payment
MRD shall obtain the CONTRACTOR's Daily Progress Reports through the duration of the project from mobilization through demobilization from the project site. MRD shall address questions concerning the Construction Drawings and Specifications and address other issues requiring coordination or technical support. MRD shall attend progress meetings with the CONTRACTOR and the CONTRACTOR's associated sub-CONTRACTORs as appropriate during construction and shall provide a written summary of the meeting.
MRD shall notify immediately the DEP BDC and the appropriate District Office of DEP of any non-compliance with any condition or limitation specified in the permit. The written report shall contain a description of and cause of noncompliance; and the period of noncompliance, including dates and times; or, if not corrected, the anticipated time the noncompliance is expected to continue, and steps being taken to reduce, eliminate, and prevent recurrence of the noncompliance.
MRD will review the Contractor’s verification surveys and pay request for work elements. MRD shall review for accuracy of computation and completeness the Contractor's periodic payment invoice and will make a recommendation to the BDC. MRD shall verify if the section was filled to specifications and assist the BDC in evaluating the periodic and final payments to the Contractor.
Deliverables: The agenda of the progress meetings and copies of the contractor’s progress reports will be provided to the DEP Project Manager in PDF format. Copies of completed payment reviews will be submitted to the DEP Project Manager in pdf format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4.D
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 0.0 $ 0.00 MRD Associates, Inc. Engineer II $115.00 86.0 $9,890.00 MRD Associates, Inc. Engineer Technician $100.00 9.0 $ 900.00
Subtask 4.D Total: $10,790.00
Subtask 4.E: Substantial Completion
Description: Following notification by the CONTRACTOR that construction activities have been completed, MRD shall conduct a visual inspection (substantial completion) of the beach and staging areas and prepare a punch list of remaining tasks to be completed by the CONTRACTOR including demobilization of equipment and material, and the restoration of access and staging areas. This list shall be furnished to the BDC and CONTRACTOR to track the progress of final clean
up. At this site visit, the vegetation that has not survived the 10 day monitoring period will be identified and that information will be provided to BDC.
Deliverables: Copy of substantial punch list and summary of 10 day plan survivability summary will be submitted to the DEP Project Manager in pdf format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4.E
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 0.0 $ 0.00 MRD Associates, Inc. Engineer II $115.00 39.0 $4,485.00 MRD Associates, Inc. Engineer Technician $100.00 1.0 $ 100.00
Subtask 4.E Total: $4,585.00
Subtask 4.F: Post Construction Monitoring
Description: Dune planting success on will be evaluated after 6 months to assess whether at least 85% of the initial planting is surviving and to document how the vegetation is colonizing outside the initial planting limits. If it is determined that in certain areas there are deficiencies within the first year of planting and within the one-year contractor warranty period, MRD will support DEP BDC in their coordination with the CONTRACTOR to have the replanting completed. Field measurements will be conducted along transects spaced approximately every 1,000 feet between the planting limits. The survey methodology shall consist of stretching a 100-foot long tape along either a north or east axis from the seaward edge of the vegetation to a point located along the landward edge of the installed dune plantings. The survey shall begin at the zero mark and proceed along recording data at every foot mark making a visual observation 90 degrees perpendicular to the tape from above (101 observations per transect). Data recorded shall include plant species or bare earth present, and whether the mark fell on the plant itself or a stem of it.
Any stems not attached to a plant that are at the survey mark shall be considered as bare earth.
Additionally, dead plants shall not be counted and considered as bare earth if present under the survey mark. The results of the survey will be summarized in a report and provided to the DEP Project Manager
Deliverables: A summary report of the vegetation planting will be provided to the DEP Project Manager in PDF format.
Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4.F
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
MRD Associates, Inc. Principal Engineer $190.00 0.0 $ 0.00 MRD Associates, Inc. Senior Engineer $140.00 0.0 $ 0.00 MRD Associates, Inc. Engineer II $115.00 61.0 $7,015.00 MRD Associates, Inc. Engineer Technician $100.00 1.0 $ 100.00 MRD Associates, Inc. Admin/Clerical $65.00 0.0 $ 0.00
Subtask 4.F Total: $7,115.00
Project Schedule:
Activity Duration (Calendar Days)
Subtask 4.A Final Design Drone Survey TBD
Subtask 4.B Pre-Construction Meeting TBD
Subtask 4.C.1: Site Visit #1 TBD
Subtask 4.C.2: Site Visit #2 TBD
Subtask 4.D: Records Management, RFI, Requests for Payment TBD
Subtask 4.E: Post-Construction Site Visits and Submittals TBD
Subtask 4.F: Post Construction Vegetation Monitoring TBD
Summary of Fees:
Subtask Description Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 4.A Final Design Drone Survey $3,580.00 $0.00
Subtask 4.B Pre-Construction Meeting $6,520.00 $0.00
Subtask 4.C.1: Site Visit #1 $2,975.00 $0.00
Subtask 4.C.2: Site Visit #2 $2,975.00 $0.00
Subtask 4.D: Records Management, RFI, Requests for Payment $10,790.00 $0.00
Subtask 4.E: Post-Construction Site Visits and Submittals $4,585.00 $0.00
Subtask 4.F: Post Construction Vegetation Monitoring $7,115.00 $0.00
Total Fixed Price Cost: $38,540.00
Total Reimbursable Cost: $0.00
Overall Total Cost: $38,540.00 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK