Task Assignment Notification Summary

This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) establishing a consulting services contract with MRD Associates, Inc., in partnership with Dune Doctors, LLC. The contract covers pre-engineering services for sand dune stabilization at Dr. Julian G. Bruce St. George Island State Park in Florida. The project manager is Terry McCullum, Jr., and the FDEP contract manager is Ralph Perkins. This represents Phase I of a two-phase project focused on coastal resiliency and dune system restoration along a 4.6-mile Gulf front beach segment.

The total contract value is $155,941.32 on a fixed-price basis with no reimbursable costs. The work comprises nine subtasks including site visits, shoreline and topographic analysis, wind records compilation, a pilot project proposal, pilot project implementation and evaluation, and development of conceptual planting plans at 90% and 100% completion levels, culminating in a final pre-engineering report. The pilot project consists of small-scale restoration experiments at three separate locations to test techniques for vegetation growth and sand accumulation. Services are designed to prevent sand washover into the East Slough and Sugar Hill Beach parking lots while enhancing wildlife habitat. Payment is contingent upon FDEP approval of deliverables for each subtask. The project schedule extends 300 calendar days, and Phase II implementation activities (design, permitting, bidding, construction, and monitoring) are excluded and will be authorized under separate contract.

View the file

Other files

File Type Posted
CN-370000-CN333-T5CO1.pdf PDF
CN-370000-CN333-T6CO1.pdf PDF
CN-370000-CN333-T3.pdf PDF
CN-370000-CN333-T4CO2.pdf PDF
CN-370000-CN333-T7CO1.pdf PDF
CN-370000-CN333-T1.pdf PDF
CN-370000-CN333-A1.pdf PDF
CN-370000-CN333-T2CO2.pdf PDF
CN-370000-CN333-T1CO1.pdf PDF
CN-370000-CN333-T6CO3.pdf PDF
CN-370000-CN333.pdf PDF
CN-370000-CN333-T1CO2.pdf PDF
CN-370000-CN333-T2.pdf PDF
CN-370000-CN333-CMC5.pdf PDF
CN-370000-CN333-T9CO1.pdf PDF
CN-370000-CN333-T4CO1.pdf PDF
CN-370000-CN333-T5CO2.pdf PDF
CN-370000-CN333-T8.pdf PDF
CN-370000-CN333-T7CO2.pdf PDF
CN-370000-CN333-T7.pdf PDF
CN-370000-CN333-T2CO4.pdf PDF
CN-370000-CN333-CMC4.pdf PDF
PC-370000-CN333.pdf PDF
CN-370000-CN333-T9.pdf PDF
CN-370000-CN333-T4.pdf PDF
CN-370000-CN333-T8CO1.pdf PDF
CN-370000-CN333-CMC3.pdf PDF
CN-370000-CN333-T6.pdf PDF
CN-370000-CN333-CMC1.pdf PDF
CN-370000-CN333-T2CO1.pdf PDF
CN-370000-CN333-T6CO2.pdf PDF
CN-370000-CN333-CMC2.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN333 5 FDEP 61458C

Beaches Project

MRD Associates, Inc.

Michael R. Dombrowski, P.E. (850) 654-1555 md@mrd-associates.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Pre-engineering services to assess viability of sand dune stabilization at Dr. Julian G. Bruce St. George Island State Park with particular focus on preventing sand washover into the East Slough and Sugar Hill Beach parking lots, per attached proposal dated June 13, 2023.

Terry McCullum, Jr. or successor

Upon Execution $ 155,941.32 Contract End Date $ 0.00

$ 155,941.32

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.15 15:02:17 -04'00'

Terry McCullum, Jr. Terry McCullum, Jr.

Digitally signed by Terry McCullum, Jr.

Date: 2023.06.15 15:04:00 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.15 16:40:26 -04'00'

Michael R. Dombrowski, P.E. Digitally signed by Michael Dombrowski Date: 2023.06.19 12:35:51 -05'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.06.22 15:45:55 -04'00'

61458C 37501000068 080041/23 423001 131500 U3200 RF $ 155,941.32

$ 155,941.32

Dr. Julian G. Bruce St. George Island State Park

June 13, 2023

Mr. Terry McCullum, Jr.

Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard 260M, MS 520 Tallahassee, Florida 32399

RE: Consultant Contract Number 333, Task Assignment Number 05 Dr. Julian G. Bruce St. George Island State Park Pre-Engineering Native Dune Vegetation

Dear Mr. McCullum, For your review, MRD Associates, Inc., has provided a proposal summary and staff-hour documentation for the services and tasks identified below:

Please review the attached Proposal Summary, deliverables and fees. Should you have any questions regarding this matter, please contact me at 850.654.1555.

Sincerely, Michael R. Dombrowski, P.E.

President md@mrd-associates.com mailto:md@mrd-associates.com

Pre-Engineering – Native Dune Vegetation

St. George Island State Park

Contract Number 333, Task Assignment Number 05

Dr. Julian G. Bruce St. George Island State Park (SGISP) extends along the eastern 8.4 miles of St. George

Island between Florida Department of Environmental Protection Reference Monument R-105 and R-149

(Figure 1). SGISP has experienced extensive coastal and upland erosion due to overtopping of the barrier island, shoreline and beach erosion and leveled dunes. On October 10, 2018, Hurricane Michael made landfall approximately 45 miles northwest of SGISP resulting in storm surge between +8 and +10.6 feet, NAVD88 along St. George Island with a measured debris line at +9.7 feet NAVD88 at the east end of the island (DEP, 2019). The following is an excerpt from DEP (2019) that summarizes the typical post-storm conditions from a major hurricane event that will be considered in the development of this investigation and implementation strategy.

“Near the state park entrance at R105.4 and R106, large storm tide runout channels cross the beach and dune region gulfward of the park road. This area was a region of large washover fans where the storm surge flowed across the island into St. George Sound. This same area experienced similar flooding impacts during Hurricanes Agnes (1972), Elena and Kate (1985), and Dennis

(2005). Between R110 and R117 at East Slough, extensive washover fans exist where the storm surge flowed across this narrow segment of the island. Similar to conditions along East Gulf Beach

Drive, the park segment between the two high public use areas at East Slough (R117.5) and Sugar

Hill (R128), has a generally continuous elongated meandering lake both gulfward and landward of the park road left from the entrapment of the storm surge, between the primary dune field and a more landward ancient dune field. Several more storm tide runout channels cross the beach and dune region gulfward of the park road along this stretch between East Slough and Sugar Hill. East of Sugar Hill between R128 and R149 at the eastern end of St. George Island, there was nearly total inundation of the island during the storm surge, which leveled the dunes and left large washover deposits.”

The focus of this pre-engineering investigation is the 4.6-mile segment of Gulf front beach located between the Park entrance at DEP Monument R-105 and the Sugar Hill Beach (day use) Area at R-128

(Figure 2). This Task Assignment is for Phase I (Task 1.) pre-engineering services that will include, but not limited to, development of a digital PDF Manual, asset organization through a cloud drive, identifying, and mapping out project limits, developing typical sections, conducting a Pilot Project and developing a

Preliminary Opinion of Probable Construction Costs (permitting, design, construction phase services, sand placement and native dune vegetation installation, and post-construction monitoring). Overall, these activities, collectively, aim to provide coastal resiliency by increasing the stability and longevity of the dune system. This restoration effort is designed to encourage dune growth through trapping wind-blown sand (dune vegetation), increase storm protection by limiting the damaging effects of storm surge (dune vegetation enhancement), promote wildlife protection, and increase habitat. In addition, techniques to stabilize beach sand adjacent to specific park road segments and parking lots will also be presented. Phase

II (future authorized Task 2.) will include implementation of the restoration project (design, permitting, bidding, construction, monitoring and evaluation).

MRD Associates, Inc. (MRD) will team with Dune Doctors, LLC (www.DuneDoctors.com) a coastal erosion control firm specializing in the planning, constructing, and maintaining native ecosystems and protective http://www.dunedoctors.com/ landscapes. MRD and Dune Doctors have worked together on numerous dune enhancement and restoration projects over the past 20-years.

The project team will develop and maintain a digital PDF Manual and asset organization system to disseminate our work products. These digital products will include:

Digital PDF Manual: With the completion of each subtask, the documentation, research, and findings will be organized and compiled into a digital pdf manual with hyperlinks to referenced sources. This will help streamline the information and demonstrate how the pre-engineering report was ideated cumulatively with each subtask. We anticipate this manual will contain the site visits, field data, literature review, pilot study, conceptual plan, monitoring program, pre-engineering report, glossary of images, and bibliography.

Asset Organization: The digital assets will be organized and shared through a cloud drive. Images will be organized per site visit into categories.

Subtask 1: Pre-Engineering Services

• Subtask 1A: Site Visit

Description: MRD and Dune Doctors will conduct a site visit to the beach segments and island to document and photograph the on-ground conditions and meet with Park staff. This visit will allow the team to better understand the conditions of the beach, dune, and back-dune area. MRD and

Dune Doctors will also identify opportunities and limitations, potential accesses, and staging areas to be used during construction. Existing native coastal vegetation will be identified including approximate densities, types, and species which will assist in developing the “Planting Plan.” In addition, an aerial drone will be flown (R-104 to R-129) to obtain a geo-referenced aerial (weather dependent). The aerial RTK-enabled drone will collect upland topography and a map showing the island contours between the bay and the approximate location of the mean high water (MHW) line along the 4.6-mile study area using photogrammetry techniques will be produced. These aerials will be cross-referenced with the native dune vegetation identified during the site visit and used to identify shorebird nesting zones and bare areas for potential planting.

Deliverable: Summary of the site visit and drone-generated aerial, and contour plot will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1A

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 64.0 $8,960.00

MRD Associates, Inc. Engineer II $115.00 24.0 $2,760.00

MRD Associates, Inc. Engineer Technician $100.00 0.0 $0.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 24.0 $4,268.16

Dune Doctors, LLC Coastal Restoration Researcher $74.10 32.0 $2,371.20

Subtask 1A Total: $19,879.36

• Subtask 1B: Shoreline, Topographic Changes, and Wildlife Distribution

Description: In addition to the drone-generated aerial and contour plot collected in Subtask 1A, MRD will collect and compile existing Light Detection and Ranging (LiDAR), and beach and offshore survey data from existing sources such as the U.S. Army Corps of Engineers (USACE), National

Oceanographic and Atmospheric Administration (NOAA), U.S. Geological Survey (USGS), Florida

Department of Environmental Protection (DEP) and other public agencies. In addition, MRD will collect and compile available historic aerial photography. The alternative restoration designs will also consider existing case studies, literature, and recent data on natural dune development, native dune vegetation, species habitat, and the interaction of these elements to increase coastal resiliency. The purpose of this Subtask is to develop an understanding of the island topography along with erosion and accretion trends, to map the post-storm limits of dune erosion (inundated dune areas, runout channels, and washover fans), and to account for wildlife density throughout the study area. These sub-tasks will assist in the preparation of a Pilot Project and assess the suitability of locating the alternative designs recommended for restoration. To account for native wildlife nesting and habitats, we hope, through collaboration, that the Florida Parks District 1 biologists will provide GPS locations of documented shorebird nesting, roosting and foraging areas, and sea turtle nesting. If made available, this data will be mapped on the geo-referenced aerials obtained in sub-Task 1A.

Deliverable: Summary report of the shoreline and topographic change review, and comparison of the historic aerials will be provided to the DEP Project Manager in PDF format.

Subtask 1B

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 16.0 $2,240.00

MRD Associates, Inc. Engineer II $115.00 24.0 $2,760.00

MRD Associates, Inc. Engineer Technician $100.00 24.0 $2,400.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 24.0 $4,268.16

Dune Doctors, LLC Coastal Restoration Researcher $74.10 75.0 $5,557.50

Subtask 1B Total: $18,745.66

• Subtask 1C: Wind Records

Description: The location and layout of the vegetation will, in part, be dependent upon winds that are characteristic along this coastline. Historic wind data will be compiled using existing sources from the closest stations to the project site and examined on a seasonal and annual basis, if available. The data will be presented in tabular, and wind rose format.

Deliverable: Summary report of the wind records will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1C

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 2.0 $380.00

MRD Associates, Inc. Senior Engineer $140.00 2.0 $280.00

MRD Associates, Inc. Engineer II $115.00 16.0 $1,840.00

MRD Associates, Inc. Engineer Technician $100.00 0.0 $0.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 0.0 $0.00

Dune Doctors, LLC Coastal Restoration Researcher $74.10 4.0 $296.40

Subtask 1C Total: $2,796.40

• Subtask 1D: Pilot Project Proposal

Description: Based on Subtasks 1A through 1C, MRD and Dune Doctors will develop a Pilot Project proposal that will outline recommended restoration techniques, experiment locations, and up to eight (8) small-scale restoration experiment plans at three (3) separate locations for the DEP and

District Park 1 Biologists to examine and approve. The small-scale restoration will be duplicated at three separate locations within the project limits and mapped on the geo-referenced aerials obtained in sub-Task 1A. Two of the locations will be staged close to the parking lot areas to address ongoing sand maintenance, and the third location will be selected by the DEP and District

1 Park Biologists. MRD and Dune Doctors suggest the third location be within an area that has historically been subject to overwash. Upon approval of the Pilot Project Proposal by the DEP

Project Manager, MRD and Dune Doctors will schedule the site visits outlined in Subtask 1E.

The Pilot Project Proposal will include:

1. Experiment descriptions including plan views, design and details, and vegetation planting plan and quantities.

2. Location of the control section(s) to compare the experiment locations.

3. Limits of design creation and implementation.

4. An outline of the experiment’s processes.

5. A quantitative metric that will be used to compare vegetation growth and sand accumulation across the experiments.

6. Prepare, submit and process a DEP CCCL field permit.

Deliverable: Pilot Study Proposal will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1D

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 6.0 $1,140.00

MRD Associates, Inc. Senior Engineer $140.00 8.0 $1,120.00

MRD Associates, Inc. Engineer II $115.00 24.0 $2,760.00

MRD Associates, Inc. Engineer Technician $100.00 0.0 $0.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 40.0 $7,113.60

Dune Doctors, LLC Coastal Restoration Researcher $74.10 80.0 $5,928.00

Subtask 1D Total: $18,061.60

Subtask 1E: Pilot Project

• Description: To maximize potential restoration success, a Pilot Project comprising small-scale restoration experiments will be implemented. This Pilot Study will test restoration techniques and help identify design issues and conditions that maximize sand accumulation and vegetation growth. MRD and Dune Doctors will conduct two site visits to first implement and then the second to evaluate the Pilot Study. During the first site visit, MRD and Dune Doctors will install the experimental models and allow the vegetation 60 days to establish prior to returning for a second visit. During the second visit, MRD and Dune Doctors will evaluate the vegetation growth and sand accumulation. This will allow the team to test restoration attempts across the study area while accounting for environmental stress factors such as rain and foot traffic erosion. The experiment areas will be compared to the identified control section(s) with no restoration experiments. The small-scale restoration experiments may include, but are not limited to, varying the spacing, angle to the beach and dominant winds, straight and offset rows, mulching, and other installation variations. This Pilot Project will help maximize return on investment when designing the

Conceptual “Planting Plan” outlined in Subtask 1G.

• Subtask 1E.a: First Site Visit - Implementation

For each test within the Pilot Project, the design will include:

i. Installation of the plants following the approved experiment models.

ii. Documentation of the conditions at the time of installation to provide a before-and-after analysis.

Deliverable: Summary report of the First Site Visit - Installation will be provided to the DEP

Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1E.a.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 16.0 $2,240.00

MRD Associates, Inc. Engineer II $115.00 16.0 $1,840.00

MRD Associates, Inc. Engineer Technician $100.00 0.0 $0.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 60.0 $10,670.40

Dune Doctors, LLC Coastal Restoration Researcher $74.10 175.0 $12,967.50

Subtask 1E.a. Total: $29,237.90

• Subtask 1E.b: Second Site Visit - Evaluation

Sixty (60) days following installation, MRD and Dune Doctors will conduct a second site visit to:

i. Evaluate vegetation growth and sand accumulation.

ii. Document the conditions to conduct a before-and-after analysis.

iii. Compare results of the experiment areas to the control section(s).

iv. Compare the Pilot Study results.

Deliverable: Summary report of the Second Site Visit - Evaluation will be provided to the

DEP Project Manager in a PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Subtask 1E.b.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 8.0 $1,120.00

MRD Associates, Inc. Engineer II $115.00 16.0 $1,840.00

MRD Associates, Inc. Engineer Technician $100.00 0.0 $0.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 30.0 $5,335.20

Dune Doctors, LLC Coastal Restoration Researcher $74.10 60.0 $4,446.00

Subtask 1E.b. Total: $14,261.20

• Subtask 1F.a.: Conceptual Planting Plan(s) 90% and Assessment

Description: The goal of this task assignment is to develop recommended strategies for rebuilding and strengthening the dune systems as well as enhancing shorebird nesting sites, roosting and foraging areas, and sea turtle nesting sites. Accounting for the outcome of the Pilot Project, the details of this coastal resiliency strategy will be developed in a Conceptual “Planting Plan,” which will be the basis for a contractor to plant vegetation throughout the project and will be used in the bidding process (separate future authorizations).

MRD and Dune Doctors will prepare and assess conceptual planting plan alternatives to meet the

Department’s goals and objectives for the area(s) identified in Subtask 1A that may need to be mitigated. In addition, techniques to stabilize beach sand adjacent to specific park road segments and parking lots will also be presented.

The topographic contours and aerial photography collected in Task 1A will be plotted and used as a baseline condition to lay out the project. The design will be based on the results and feedback received from the deliverables of Subtask 1A, 1B, 1C, 1D, and 1E in coordination with Dune

Doctors and Florida State Parks District 1 Biologists.

Conceptual Planting Plan will include:

1. Project description including plan views, design and details, and vegetation planting plan and quantities.

2. Limits of design creation, implementation, and evaluation

3. Outline the necessary steps and schedule to implement the conceptual project.

4. A Preliminary Opinion of Probable Construction Costs that will include future tasks

(permitting, design, construction administration services, construction, monitoring, etc...).

5. An estimation and evaluation of vegetation growth and sand accumulation

Deliverable: Summary memorandum of the conceptual planting plan(s), assessment, and 90% complete plans will be provided to the DEP Project Manager in PDF format.

Subtask 1F.a.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 16.0 $3,040.00

MRD Associates, Inc. Senior Engineer $140.00 30.0 $4,200.00

MRD Associates, Inc. Engineer II $115.00 30.0 $3,450.00

MRD Associates, Inc. Engineer Technician $100.00 30.0 $3,000.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 30.0 $5,335.20

Dune Doctors, LLC Coastal Restoration Researcher $74.10 50.0 $3,705.00

Subtask 1F.a. Total: $22,730.20

• Subtask 1F.b: Conceptual Plan 100%

Deliverable: 100% complete plans will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Subtask 1F.b.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 10.0 $1,400.00

MRD Associates, Inc. Engineer II $115.00 10.0 $1,150.00

MRD Associates, Inc. Engineer Technician $100.00 10.0 $1,000.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 10.0 $1,778.40

Dune Doctors, LLC Coastal Restoration Researcher $74.10 10.0 $741.00

Subtask 1F.b. Total: $7,589.40

• Subtask 1G: Pre-engineering Report

MRD will summarize the findings and results of Tasks 1A through 1F and prepare a written report.

The report will include documentation of data and methods used in the performance of the work and will be consistent with DEP guidelines. The report will outline an implementation strategy that will be completed under separate authorization under Phase II, Task 2.

Deliverable: Final Pre-engineering report will be provided to the DEP Project Manager in PDF format.

Subtask 1G

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 24.0 $3,360.00

MRD Associates, Inc. Engineer II $115.00 40.0 $4,600.00

MRD Associates, Inc. Engineer Technician $100.00 16.0 $1,600.00

Dune Doctors, LLC Senior Coastal Restoration Specialist $177.84 40.0 $7,113.60

Dune Doctors, LLC Coastal Restoration Researcher $74.10 60.0 $4,446.00

Subtask 1G Total: $22,639.60

Project Schedule:

Activity Duration (Calendar Days)

Subtask 1A: Site Visit 60 days

Subtask 1B: Shoreline and Topographic Changes 90 days

Subtask 1C: Wind Records 90 days

Subtask 1D: Pilot Project Proposal 90 days

Subtask 1E.a: First Site Visit - Installation 150 Days

Subtask 1E.b: Second Site Visit - Evaluation 210 Days

Subtask 1F.a.: Conceptual Design 90% 240 days

Subtask 1F.b.: Conceptual Design 100% 270 days

Subtask 1G: Pre-engineering Report 300 days

Summary of Fees:

Subtask Description Subtask Fixed

Price Cost Subtask

Reimbursable

Subtask 1A: Site Visit $19,879.36 $0.00

Subtask 1B: Shoreline and Topographic Changes $18,745.66 $0.00

Subtask 1C: Wind Records $2,796.40 $0.00

Subtask 1D: Pilot Project Proposal $18,061.60 $0.00

Subtask 1E.a: First Site Visit - Installation $29,237.90 $0.00

Subtask 1E.b: Second Site Visit - Evaluation $14,261.20 $0.00

Subtask 1F.a.: Conceptual Design 90% $22,730.20 $0.00

Subtask 1F.b.: Conceptual Design 100% $7,589.40 $0.00

Subtask 1G: Pre-engineering Report $22,639.60 $0.00

Total Fixed Price Cost: $155,941.32

Total Reimbursable Cost: $0.00

Overall Total Cost: $155,941.32

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

EXCLUSIONS

Please note that this Task Assignment does not include the following, but these services can be provided under separate authorization: coastal processes modeling and analysis, surveying services by a PLS, coastal risk assessment, upland and offshore geotechnical investigations, final design, environmental, ecological, land use planning, upland construction easements, permit applications or local, State and

Federal regulatory permitting, contract documents, bidding and construction phase services, and post-construction monitoring.

REFERENCES

DEP, 2019. Hurricane Michael Post-Storm, Beach Conditions and Coastal Impact Report. Division of Water

Resources management, Florida Department of Environmental Protection, dated January 2019 (Revised

April 2019).

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK

Figure 1. Location Map

Figure 2. Project Area

2023-06-13 SGISP Pre-Engineering Task Assignment - MRD Associates.pdf
June 13, 2023

File details come from the government source that posted it. Updated .