This is a Task Assignment Notification Form from the Florida Department of Environmental Protection (FDEP) issued to MRD Associates, Inc., a coastal, marine, and water resources engineering firm based in Destin, Florida. The task assignment is identified as Contract Number CN333, Task Assignment Number 04, and is managed by the FDEP's Bureau of Design and Construction. The project is located at T.H. Stone Memorial St. Joseph Peninsula State Park in Gulf County, Florida, with FDEP Project Manager Theresa Carron overseeing the work and FDEP Contract Manager Jeff Whitfield serving as the primary point of contact.

This task assignment requires MRD Associates to provide pre-engineering services for a sand placement and dune restoration project at the state park, including survey work, field investigations, conceptual design development, and preliminary engineering services. The scope comprises five subtasks: site visits with drone surveys ($8,920), shoreline position and volume change analysis ($9,440), sand source assessment ($11,720), conceptual design alternatives and assessment ($32,080), and preparation of a final pre-engineering report ($15,480). The total fixed-price cost is $77,640.00 with no reimbursable expenses, and payment is due upon FDEP approval of deliverables for each subtask. The project schedule extends 180 calendar days from the start date of January 15, 2024, with the completion date of 1/15/2024 and final deliverables to be provided in PDF format. The task assignment excludes inlet stability analysis, surveying services, final design, environmental permitting, and post-construction monitoring, which may be provided under separate authorization.

View the file

Other files

File Type Posted
CN-370000-CN333-T5CO1.pdf PDF
CN-370000-CN333-T6CO1.pdf PDF
CN-370000-CN333-T5.pdf PDF
CN-370000-CN333-T3.pdf PDF
CN-370000-CN333-T4CO2.pdf PDF
CN-370000-CN333-T7CO1.pdf PDF
CN-370000-CN333-T1.pdf PDF
CN-370000-CN333-A1.pdf PDF
CN-370000-CN333-T2CO2.pdf PDF
CN-370000-CN333-T1CO1.pdf PDF
CN-370000-CN333-T6CO3.pdf PDF
CN-370000-CN333.pdf PDF
CN-370000-CN333-T1CO2.pdf PDF
CN-370000-CN333-T2.pdf PDF
CN-370000-CN333-CMC5.pdf PDF
CN-370000-CN333-T9CO1.pdf PDF
CN-370000-CN333-T4CO1.pdf PDF
CN-370000-CN333-T5CO2.pdf PDF
CN-370000-CN333-T8.pdf PDF
CN-370000-CN333-T7CO2.pdf PDF
CN-370000-CN333-T7.pdf PDF
CN-370000-CN333-T2CO4.pdf PDF
CN-370000-CN333-CMC4.pdf PDF
PC-370000-CN333.pdf PDF
CN-370000-CN333-T9.pdf PDF
CN-370000-CN333-T8CO1.pdf PDF
CN-370000-CN333-CMC3.pdf PDF
CN-370000-CN333-T6.pdf PDF
CN-370000-CN333-CMC1.pdf PDF
CN-370000-CN333-T2CO1.pdf PDF
CN-370000-CN333-T6CO2.pdf PDF
CN-370000-CN333-CMC2.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN333 04 FDEP-BDC 61400

St Joseph Peninsula State Park Sand Placement

MRD Associates, Inc.

Michael Dombrowski, PE 850.654.1555 md@mrd-associates.com

Jeff Whitfield 850-245-2630 Jeffrey.Whitfield@FloridaDEP.gov

To provide survey, field investigations, conceptual designs, and pre-engineering services for the sand placement project as described in the attached proposal dated 1/10/2022.

Theresa Carron

Upon execution $ 77,640.00 1/15/2024

$ 77,640.00

Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2022.01.27 14:55:43 -05'00'

Theresa Carron Theresa Carron Digitally signed by Theresa Carron Date: 2022.01.28 08:08:22 -05'00'

Jeff Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.01.31 08:48:33 -05'00'

Michael Dombrowski, PE Digitally signed by Michael R.

Dombrowski Date: 2022.01.31 10:43:24 -06'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr.

Digitally signed by Michael W.

Foster Jr.

Date: 2022.02.15 14:24:32 -05'00'

61400 37536060000 140126/22 423001 U1671 131500 QL $ 77,640.00

$ 0.0037202423001373504000014012622

January 10, 2022

Theresa R. Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard 260M, MS 520 Tallahassee, Florida 32399

RE: Consultant Contract Number 333, Task Assignment Number 03 St. Joseph Peninsula State Park Pre-Engineering Sand Placement and Dune Restoration

Dear Ms. Carron;

For your review, MRD Associates, Inc., has provided a proposal summary and man-hour documentation for the services tasks identified below:

Please review the attached Proposal Summary, deliverables and fees. Should you have any questions regarding this matter, please contact me at 850.654.1555.

Sincerely, Michael R. Dombrowski, P.E.

Principal Engineer md@mrd-associates.com mailto:md@mrd-associates.com Carron_T Text Box

Pre-Engineering – Sand Placement and Dune Restoration

T.H. Stone Memorial St. Joseph Peninsula State Park

Contract Number 333, Task Assignment Number 03

This Task Assessment is for pre-engineering services for a sand placement/dune restoration project within

T.H. Stone Memorial St. Joseph State Park (SJSP). Sand placement may be centered on or around the

Michaels Cut breach (near Florida Department of Environmental Protection (DEP) Monument R-72), the primitive campground area just to the north of the location of the former breach between R-67 and R-68, and other potential shoreline segments between DEP Monuments R-65 (northern limits of infrastructure) and R-75 (southern State Park boundary) identified in this investigation. This Task Assignment assumes that an upland sand source will be used to construct the project via a truck-haul and the sand will be placed above the seasonal high water contour.

In general, this Task Assignment will include, but not limited to, identification of and assessment of an upland sand source, identify and map out project limits, develop typical sections, and develop a

Preliminary Opinion of Probable Construction Costs to include future tasks to implement the project

(permitting, design, construction phase services, sand placement and native dune vegetation installation, and post-construction monitoring). A post-construction monitoring, and maintenance plan will also be developed for an “engineered beach” project to provide the necessary information for the constructed project to be eligible for FEMA disaster recovery funding if the projects are damaged by a future storm(s).

Subtask 1: Pre-Engineering Services

• Subtask 1A: Site Visit

Description: MRD will conduct a site visit to the beach segments to document and photograph the on-ground conditions, and meet with Park staff. This will allow the team to get a better idea on the conditions of the beach and dune, identify opportunities and limitations, identify potential construction access, and staging, and sand transfer areas that will be used during construction.

Existing native coastal vegetation will be identified including densities, types and species which will assist in developing the post-sand placement planting plan. In addition, a drone will be flown

(R-65 northern limits of infrastructure to R-75 southern State Park boundary) to obtain a geo-refenced aerial (weather dependent). The aerial RTK enabled drone will collect upland topography and map the approximate location of the mean high water (MHW) line between profile lines using photogrammetry techniques, and to estimate usable beach width that will be used in Subtask 1B.

Deliverable: Summary of the site visit and drone generated aerial and contour plot will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Carron_T Text Box

Fixed Price Cost:

Subtask 1A

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

MRD Associates, Inc. Principal Engineer $190.00 12.0 $2,280.00

MRD Associates, Inc. Senior Engineer $140.00 24.0 $3,360.00

MRD Associates, Inc. Engineer II $115.00 24.0 $2,760.00

MRD Associates, Inc. Engineer Technician $100.00 0.0 $0.00

MRD Associates, Inc. Administrative/Clerical $65.00 8.0 $520.00

Subtask 1A Total: $8,920.00

• Subtask 1B: Shoreline Position and Volume Changes

Description: MRD will review existing beach profiles and literature to develop an understanding of the erosion and accretion trends along the Study Area and assist in the preparation of the conceptual designs and assessing the performance of alternative designs. The shoreline position and volume changes will be based on the report entitled “Eagle Harbor Monitoring Report – 2021, T.H. Stone Memorial St. Joseph Peninsula State Park, Gulf County, Florida”, dated August 25, 2021, prepared by MRD Associates. This monitoring report covers the period between February 24, 2020 (post-construction) and July 1, 2021 (16-month) along the 2.6-mile monitored shoreline extending from DEP Reference Monument R-65 to R-78. The existing shoreline and profile data, and drone data will be compiled and assessed to identify historic shoreline trends, the historic dune location and areas where the dune has been breached from past storm events within the monitored shoreline segments(s) that may be recommended for restoration.

The survey data will provide an estimate of the available area to construct a beach berm with and without a dune feature or other improvements, and also determine any limitations and opportunities. The beach profiles will provide the historic location and configuration of the primary dune – if any. This information is a critical component to estimating the location, width, height and volume of any proposed dune feature. Shoreline and volume changes will be presented in tabular and graphic format.

Deliverable: Summary report of the shoreline position and volume change review, and recommended beach berms and dunes to be restored will be provided to the DEP Project

Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1B

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 16.0 $2,240.00

MRD Associates, Inc. Engineer II $115.00 24.0 $2,760.00

MRD Associates, Inc. Engineer Technician $100.00 24.0 $2,400.00

MRD Associates, Inc. Administrative/Clerical $65.00 8.0 $520.00

Subtask 1B Total: $9,440.00

• Subtask 1C: Sand Source Assessment

Description: Potential upland sand sources will be identified. Borrow pit samples will be evaluated for visual attributes (Munsell color, carbonate and shell content). Sediment quality data will be obtained from the borrow pit operator, if available. A compatibility analysis from existing information will be performed whereby "beach-quality sediment" in the potential borrow pit will be compared with native beach samples (collected and analyzed from the 2008/2009 beach fill project and the 2019 Michael’s Cut project) with respect to the textural and compositional parameters (grain size), color (Munsell), carbonate and silt and shell content, and occurrence of rubble or debris consistent with the requirements of 62B-41.007(2)(j), FAC. The potential volume of beach quality sand will be estimated.

Deliverable: Summary report of the sand source assessment will be provided to the DEP

Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1C

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 24.0 $3,360.00

MRD Associates, Inc. Engineer II $115.00 48.0 $5,520.00

MRD Associates, Inc. Engineer Technician $100.00 8.0 $800.00

MRD Associates, Inc. Administrative/Clerical $65.00 8.0 $520.00

Subtask 1C Total: $11,720.00

• Subtask 1D: Conceptual Designs, Assessment and Summary

MRD will prepare and assess conceptual design alternatives and to meet the Department’s goals and objectives for the shoreline segment(s) identified in Subtask 1A that may need to be mitigated. The beach profiles will be plotted and used as a baseline condition (historic location and configuration of the primary dune – if any) to design the beach and dune construction template. The design options typically evaluated for similar Northwest Florida beaches include the following: no action; beach berm restoration only; dune restoration only; beach berm and dune restoration; and native dune vegetation. Any proposed sand will be placed above the seasonal high water (SHW) line.

For each alternative, the conceptual design will include:

1) Project description including plan views and fill design and details, construction templates, sand volumes and vegetation planting plan and quantities.

2) An assessment of existing upland sand sources to supply the initial restoration project and future nourishment.

3) Characterization of the expected performance including an estimate of nourishment frequency and requirements based on background erosion and the remaining beach and dune in response to a 10-, 20-year, and 30-year storm events.

4) A characterization of permit probability including compliance with DEP and USACE regulatory requirements and criteria, and the USFWS Biological Opinion.

5) Outline the necessary steps and schedule to implement the conceptual project.

6) A Preliminary Opinion of Probable Construction Costs that will include future tasks

(permitting, design, construction administration services, construction, monitoring, etc...).

7) A post-construction monitoring, and maintenance plan for an “engineered beach” project to provide the necessary information for the constructed project to be eligible for FEMA disaster recovery funding if the projects are damaged by a future storm(s).

MRD will meet with the Department to present the preliminary findings. Based on the review and comments by the Department, MRD will proceed with Subtask 1.E.

Deliverable: Summary memorandum of the conceptual design and assessment will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1D

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 16.0 $3,040.00

MRD Associates, Inc. Senior Engineer $140.00 40.0 $5,600.00

MRD Associates, Inc. Engineer II $115.00 160.0 $18,400.00

MRD Associates, Inc. Engineer Technician $100.00 40.0 $4,000.00

MRD Associates, Inc. Administrative/Clerical $65.00 16.0 $1,040.00

Subtask 1D Total: $32,080.00

• Subtask 1E: Pre-engineering Report

MRD will summarize the findings and results of Tasks 1.A through 1.E. and prepare a written report. The report will include documentation of data and methods used in the performance of the work and will be consistent with DEP guidelines. The report will rank the conceptual designs in order of cost-effectiveness and performance and outline an implementation strategy.

Deliverable: Final Pre-engineering report will be provided to the DEP Project Manager in PDF format.

Performance Measure: Deliverables will be reviewed by the DEP Project Manager to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1E

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

MRD Associates, Inc. Principal Engineer $190.00 8.0 $1,520.00

MRD Associates, Inc. Senior Engineer $140.00 32.0 $4,480.00

MRD Associates, Inc. Engineer II $115.00 48.0 $5,520.04

MRD Associates, Inc. Engineer Technician $100.00 24.0 $2,400.00

MRD Associates, Inc. Administrative/Clerical $65.00 24.0 $1,560.00

Subtask 1E Total: $15,480.00

Project Schedule:

Activity Duration (Calendar Days)

Subtask 1A: Site Visit 30 days

Subtask 1B: Shoreline Position and Volume Changes 60 days

Subtask 1C: Sand Source Assessment 90 days

Subtask 1D: Conceptual Design and Assessment 150 days

Subtask 1E: Pre-engineering Report 180 days

Summary of Fees:

Subtask Description Subtask Fixed

Price Cost Subtask

Reimbursable

Subtask 1A: Site Visit $8,920.00 $0.00

Subtask 1B: Shoreline Position and Volume Changes $9,440.00 $0.00

Subtask 1C: Sand Source Assessment $11,720.00 $0.00

Subtask 1D: Conceptual Design and Assessment $32,080.00 $0.00

Subtask 1E: Pre-engineering Report $15,480.00 $0.00

Total Fixed Price Cost: $77,640.00

Total Reimbursable Cost: $0.00

Overall Total Cost: $77,640.00

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

EXCLUSIONS

Please note that this Task Assignment does not include the following, but these services can be provided under separate authorization: inlet stability and processes, surveying services, risk assessment, offshore geotechnical investigations, final design, environmental, ecological, land use planning, upland construction easements, permit applications or local, State and Federal regulatory permitting, contract documents, bidding and construction phase services, and post-construction monitoring.

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK