CN-370000-CN217-T29CO2.pdf
PDF 3 MB Posted
- Contract number
- CN217
- Issued by
- Florida
About this file
This Task Assignment Change Order Form is issued by the Florida Department of Environmental Protection (FDEP) and involves JGP Structural Group, Inc., a structural engineering firm based in Tallahassee, Florida. The change order modifies an existing contract (CN217, Task Assignment #29) for dock repair services at Cayo Costa State Park. The document is signed by authorized representatives from FDEP, including the Budget Representative, Project Manager, and Contract Manager, as well as by Jeffrey Parzych, PE, representing JGP Structural Group, Inc.
The change order authorizes additional engineering and permitting services required due to site damage caused by Hurricane Ian. The modification adds $14,880.00 in fixed fee costs to the existing task assignment, bringing the total contract value to $48,751.10 ($658.60 reimbursable plus $48,092.50 fixed fee). The additional services include three subtasks: asbestos survey and lead paint testing ($3,940.00), site visit and revised final design documents ($7,270.00), and permitting services to revise and resubmit permit applications to the South Florida Water Management District and Army Corps of Engineers ($3,670.00). The change order also extends the task execution period by 365 calendar days, with the new task end date set for June 28, 2024. Payment is structured as fixed fee compensation upon FDEP's approval of deliverables for each subtask, with all work to be completed within specified timeframes ranging from two to four weeks from receipt of task approval.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN217 29 2 61335C
Cayo Costa State Park Dock Repair
JGP Structural Group, Inc
Jeffery Parzych PE 850.574.2888 jeff@jgpstructural.com
Ralph M Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Additional services required for permitting due to site impact by Hurricane Ian to be added to existing TA, per attached proposal dated January 8, 2023, and requested time extension.
$ 658.60 $ 33,212.50 $ 33,871.10 $ 658.60 $ 33,212.50 $ 33,871.10 $ 0.00 $ 14,880.00 $ 14,880.00
$ 658.60 $ 48,092.50 $ 48,751.10
06/01/2021
06/30/2022
06/29/2023
06/28/2024
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.03.14 08:58:04 -04'00'
Terry McCullum, Jr. Terry McCullum, Jr.
Digitally signed by Terry McCullum, Jr.
Date: 2023.03.14 10:26:07 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.03.14 11:17:07 -04'00'
Jeffery Parzych PE Jeffrey Parzych Digitally signed by Jeffrey Parzych Date: 2023.03.15 07:17:53 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.03.15 15:42:09 -04'00'
61335C FD091 37800000000 0088040/23 408001 U3200 131500 PF $ 14,880.00
$ 14,880.00
McCullum, Terry
From: Jeffrey Parzych <jeff@jgpstructural.com> Sent: Tuesday, March 7, 2023 8:50 AM To: McCullum, Terry Subject: Cayo Costa State Park Dock Repairs Project
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Terry, We are requesting a time extension for the task assignment regarding the noted project, #61335C - Cayo Costa State Park Dock Repairs. The current TA expires on 06/29/23. We believe an extension of 365 days would be appropriate.
Respectfully, Jeffrey G. Parzych, PE Principal JGP Structural Group, Inc 1221 W. Tharpe Street Tallahassee, FL 32303 850.574.2888 850.445-0224 c
TALLAHASSEE/NAPLES-FT MYERS
ll�I J
II JGP STRUCTURAL GROUP, INC.
January 8, 2023
Mr. John Goss
Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3900 Commonwealth Boulevard, MS 520
Tallahassee, FL 32399
RE:
Engineering Soluti011S
CN217 - Dock Repair
Cayo Costa State Park - Change Order #02
Modifications due to Hurricane Ian (Subtask 2A, 4A and SA)
Dear Mr. Goss;
For your review, JGP Structural Group, Inc., has provided a proposal summary and man-hour documentation for the services and tasks identified in the attached sheets.
Please review the attached Proposal Summary and deliverables.
Sincerely, JGP Structural Group, Inc.
Jeffrey G. Parzych, PE
President
1221 W. Tharpe Street, Tallahassee, Florida 32303
Phone: 850-574-2888, Fax: 850-574-2788
1 E-mail: contact@jgpstructural.com
Dock Repair
Cayo Costa State Park
CN217, TA #29 Change Order 01
Subtask 2A: Asbestos Survey and Lead Paint Testing
Description:
• JGP shall coordinate the asbestos survey and lead paint testing that will be performed for the project. CAD documents and information will be provided by JGP to the testing company for inclusion in their report.
• Southern Earth Sciences, SES, Inc. shall provide asbestos and lead paint testing for the project.
This work includes sampling and testing of deck and railing elements and any sealants/caulks if they are present. The sampling will include remaining portions of dock.
Deliverable: An Asbestos Survey and Lead Paint Testing Report for the structure will be provided to BDC for review. The survey proposed by SES is intended to be a full and comprehensive survey to meet the NESHAP (National Emissions Standard for Hazardous Air Pollutants). Samples will be collected according to EPA guidelines. The report and information will be provided in PDF format within 4 weeks after receipt of execution of the Task Assignment for this work. If additional testing is required it will be performed at the provide rate as an additional service.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name
JGP Structural Group, Inc.
Total: $980.00
Fixed Price Cost:
Firm Name
SES, Inc.
Total: $2,960.00
Position Classification
Principal Engineer Project Engineer
Clerical
Classification
Project Engineer
Asbestos Sampling
Total for Subtask 2A: $980.00 + $2,960.00=$3,940.00
Subtask 4A: Provide Site Visit and Revised Final Documents
Hourly Rate
$160.00 $95.00 $45.00
Unit Cost
$115/hr
$25.00/ea
Description: JGP Structural Group, Inc. will perform the following:
Hours Total Fixed Price Cost
2 $320.00 6 $570.00 2 $90.00
Units Total Fixed Price Cost
24 $2,760.00
8 $200.00
• JGP will perform site visit(s) to verify existing conditions. The areas of the removed piles (performed by the demolition contractor), the areas of the remaining piles to allow temporary use of the staff dock and the impact of uprooted trees and damage of the existing concrete rip-rap will be documented. This information will be used to modify the previously provided "final" drawings and the permit applications to depict the current conditions regarding the fixed and floating docks.
Portions of the docks were damaged during Hurricane Ian and partial sections of dock were removed by the demolition contractor. Both the demolition drawings and the drawings depicting the previous existing conditions will be modified. Since many of the piles were located adjacent to concrete rip rap information regarding the damaged or disturbed areas including areas where new rip rap will be required will be added to the drawings to address these issues.
• When determining areas of work and repair, due to the observation techniques used, only visible conditions can be noted. Additionally, it must be understood that the drawings do not attempt to identify hidden conditions and defects. Additional work could be required beyond what is noted on the drawings. The extents of some conditions may not be known until construction.
• It is assumed that removed piles were completely removed and no broken sections are present.
• Engineering design, analysis and code verification of elements outside of the scope of work described above is not included.
• The work will be performed with the degree of skill and the standard of care common to the profession. No warranty is expressed or implied by this agreement.
• Trimming of vegetation, if needed, is to be provided by Park personnel.
• The Final design documents shall be formatted to the BOC 24"x36" standard and include the standard BOC border. Each individual sheet shall be clearly labeled and dated.
• The Final technical specifications shall be placed on the drawings or formatted to the BOC 8-
1 /2"x11" standard. The specification sections will be clearly labeled and dated.
• The Final documents shall be submitted to the BOC project manager via electronic file transfer in
PDF and AutoCad format. A revised Opinion of Probable Construction Cost (OPC) will be provided.
Deliverable: The "Revised" Final Design Documents and the opinion of probable cost (0PC) will be provided in electronic format to BOC for review. These documents will be provided within four (4) weeks after receipt of the approved TA.
• JGP will provide the "Revised" Final signed and sealed Design Documents in electronic format to
BDC. Final CAD files will also be provided.
• The 0PC will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
JGP Structural Group, Inc. Principal Engineer $160.00 9 $1,440.00 Project Engineer $95.00 38 $3,610.00
CADD Des/Tech $60.00 34 $2,040.00
Clerical $45.00 4 $180.00
Total for Subtask 4A: $7,270.00
Subtask SA: Permitting Services - Revise and Resubmit Permit Applications
Description: JGP will revise the existing permit applications to depict the current conditions related to the project. These modifications are necessary due to the damage caused by Hurricane Ian. Updated
"Revised" final drawings will be provided to the noted agencies. We anticipate revising the permit applications provided to the following agencies:
• SFWMD - South Florida Water Management District
• Army Corps of Engineers-USACOE
Deliverable: Provide the revised permit applications and drawings to DEP for signing within two (2) weeks of receiving any DEP comments from the subtask 4A submittal. JGP will submit the permit applications to the noted agencies immediately after receipt of the signed applications.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Firm Name Position Classification
JGP Structural Group, Inc. Principal Engineer
Project Engineer
Clerical
Total for Subtask SA: $3,670.00
Proiect Schedule:
Activity Duration (Calendar Days)
Hourly Rate
$160.00
$95.00
$45.00
Subtask 2A:Asbestos/Lead Test. 4 weeks-28 days from receipt of TA
Subtask 4A:Site Visit and Revise 4 weeks- 28 days from receipt of TA
Final Dwgs
Hours Total Fixed
Price Cost
4 $640.00
30 $2,850.00 4 $180.00
Subtask SA: Revise/Resubmit 2 weeks -14 days after receipt of approval of final dwgs
Permit Applications
Summarv of Fees:
Subtask Subtask 2A: Asbestos/Lead Test.
Subtask 4A: Revise Final Dwgs
Subtask SA: Revise/Resubmit Permit Applications
Total Fixed Price Cost:
Total Reimbursable Cost
Overall Total Cost:
Subtask Fixed Price Cost Subtask Reimbursable $3,940.00
$7,270.00 $3,670.00 -
$14,880.00
$14,880.00
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.