This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project at Blue Spring State Park. The change order involves FDEP as the state agency and JGP Structural Group, Inc. as the consultant, with key personnel including Jeffrey Parzych, P.E. (consultant representative), Ralph Perkins (FDEP Contract Manager), and Del Cobb (FDEP Project Manager). The contract is identified as FDEP Contract No. CN217, Task Assignment No. TA18, Change Order No. CO6, and Project No. 61257C.
The change order authorizes a time extension of 200 days for the Boardwalk at Swim Area replacement project at Blue Spring State Park. The original task execution date was July 21, 2020, with an original end date of December 31, 2021. The present task end date is June 29, 2024, and the new task end date with this change order is January 15, 2025. The time extension is requested to address Construction Administration (CA) services during construction. There is no change in task amount; the total contract value remains $105,386.37, comprised of $9,823.90 in reimbursement and $95,562.47 in fixed fees. All required signatures from FDEP budget, project management, contract management, and contract authority personnel, as well as the consultant, were obtained between May 30 and June 6, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN217 TA18 CO6 61257C
Blue Spring State Park Boardwalk at Swim Area
JGP Structural Group, Inc.
Jeffrey Parzych P.E. (850) 574-2888 jeff@jgpstructural.com
Ralph Perkins, or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
The purpose of this Change Order is for a time extension of 200 days. please see attached email dated 05/23/2024.
$ 9,823.90 $ 74,787.47 $ 84,611.37 $ 9,823.90 $ 95,562.47 $ 105,386.37
$ 0.00 $ 0.00 $ 0.00 $ 9,823.90 $ 95,562.47 $ 105,386.37
07/21/2020
12/31/2021
06/29/2024
01/15/2025
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.05.30 10:40:34 -04'00'
Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2024.05.30 11:20:27 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.05.30 13:25:59 -04'00'
Jeff Parzych, P.E. Jeffrey Parzych Digitally signed by Jeffrey Parzych Date: 2024.05.30 15:48:19 -04'00'
Bryan Bradner
$ 0.00
Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.06.06 09:55:09 -04'00'
From: Jeffrey Parzych To: Cobb, Del L Subject: Re: Blue Spring - Time Extension Date: Friday, May 31, 2024 11:41:59 AM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Del, We are providing this email to request a time extension for the project, "Boardwalk Replacement at Swim Platform" at Blue Spring State Park (61257C). The current TA for this project expires on 06/29/24. We are requesting an extension of time of 200 days beyond the current expiration date to address CA services during construction.
Please contact me if you have any questions or comments regarding this request.
Respectfully, Jeffrey G. Parzych, PE Principal JGP Structural Group, Inc 1221 W. Tharpe Street Tallahassee, FL 32303 850.574.2888 850.445-0224 c
TALLAHASSEE/NAPLES-FT MYERS
On Fri, May 31, 2024 at 11:23 AM Cobb, Del L <Del.L.Cobb@floridadep.gov> wrote:
Jeff
The 300-day time extension will put us over the Master Contract Agreement. Can you provide another email requesting 200 days to the existing TA and we will ignore the 300 -day time extension email. Let me know if you have any questions or concerns.
Regards.
mailto:jeff@jgpstructural.com mailto:Del.L.Cobb@FloridaDEP.gov mailto:Del.L.Cobb@floridadep.gov
| CN217 TA18 CO6 Blue Spring State Park - Boardwalk Swim Area.pdf |
| Re_ Blue Spring - Time Extension.pdf |
File details come from the government source that posted it. Updated .