This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project involving JGP Structural Group, Inc. The change order, numbered 1, modifies Task Assignment No. 29 under FDEP Contract No. CN217 for the Cayo Costa State Park Dock Repair project (Project No. 61335C). The consultant representative is Jeffrey Parzych, P.E., and the FDEP Contract Manager is Ralph M Perkins. The change order was approved by multiple FDEP officials including Budget Representative Diane Langston, Project Manager Andrew Lippens, Contract Manager Ralph M Perkins, and Contract Authority Michael W. Foster Jr., P.E.

The change order constitutes a time-only extension of the task assignment for an additional 365 days, with no adjustment to the financial terms. The original task execution date of June 1, 2021, and original end date of June 30, 2022, are extended to June 29, 2023. The total task amount remains unchanged at $33,871.10, consisting of $658.60 in reimbursable expenses and $33,212.50 in fixed fees. The net increase to the contract amount is $0.00. JGP Structural Group requested the extension due to the sea grass survey work being time-dependent with the growing season, necessitating completion of the survey work required for the dock repair design. The change order was executed on June 29, 2022.

View the file

Other files

File Type Posted
CN-370000-CN210-TA7.pdf PDF
CN-370000-CN217-CMC1.pdf PDF
CN-370000-CN217-CMC4.pdf PDF
CN-370000-CN217-T15.pdf PDF
CN-370000-CN217-T18CO2.pdf PDF
CN-370000-CN217-T18CO3.pdf PDF
CN-370000-CN217-T18CO6.pdf PDF
CN-370000-CN217-T1CO2.pdf PDF
CN-370000-CN217-T3.pdf PDF
CN-370000-CN217-T32.pdf PDF
CN-370000-CN217-T33.pdf PDF
CN-370000-CN217-T34CO3.pdf PDF
CN-370000-CN217-T34CO4.pdf PDF
CN-370000-CN217-T35.pdf PDF
CN-370000-CN217-T39CO1.pdf PDF
CN-370000-CN217-T40.pdf PDF
CN-370000-CN217-T41CO1.pdf PDF
CN-370000-CN217-T44.pdf PDF
CN-370000-CN217-T5.pdf PDF
CN-370000-CN217-T50.pdf PDF
CN-370000-CN217-T53.pdf PDF
CN-370000-CN217-T58.pdf PDF
CN-370000-CN217-T65.pdf PDF
CN-370000-CN217-T66.pdf PDF
CN-370000-CN217-TA29.pdf PDF
CN-370000-CN217-A1.pdf PDF
CN-370000-CN217-T10CO1.pdf PDF
CN-370000-CN217-T12.pdf PDF
CN-370000-CN217-T16CO4.pdf PDF
CN-370000-CN217-T18.pdf PDF
CN-370000-CN217-T18CO4.pdf PDF
CN-370000-CN217-T2.pdf PDF
CN-370000-CN217-T20.pdf PDF
CN-370000-CN217-T20CO1.pdf PDF
CN-370000-CN217-T21.pdf PDF
CN-370000-CN217-T21CO1.pdf PDF
CN-370000-CN217-T22CO1.pdf PDF
CN-370000-CN217-T34CO2.pdf PDF
CN-370000-CN217-T36.pdf PDF
CN-370000-CN217-T37.pdf PDF
CN-370000-CN217-T38.pdf PDF
CN-370000-CN217-T4.pdf PDF
CN-370000-CN217-T45.pdf PDF
CN-370000-CN217-T48.pdf PDF
CN-370000-CN217-T49CO1.pdf PDF
CN-370000-CN217-T51.pdf PDF
CN-370000-CN217-T54.pdf PDF
CN-370000-CN217-T57.pdf PDF
CN-370000-CN217-T61.pdf PDF
CN-370000-CN217-T67.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN217 29 1 61335C

Cayo Costa State Park Dock Repair

JGP Structural Group, Inc.

Jeffrey Parzych, P.E. 850-574-2888 jeff@jgpstructural.com

Ralph M Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov

Time only extension of task assignment for an additional year, per attached proposal dated 05/26/2022.

$ 658.60 $ 33,212.50 $ 33,871.10 $ 658.60 $ 33,212.50 $ 33,871.10 $ 0.00 $ 0.00 $ 0.00

$ 658.60 $ 33,212.50 $ 33,871.10

06/01/2021

06/30/2022

06/30/2022

06/29/2023

Diane Langston Diane Langston Digitally signed by Diane Langston Date: 2022.05.31 08:00:36 -04'00'

Andrew Lippens Andrew Lippens Digitally signed by Andrew Lippens Date: 2022.05.31 08:58:03 -04'00'

Ralph M Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.06.28 15:47:44 -04'00'

Jeffrey Parzych, P.E. Jeffrey Parzych Digitally signed by Jeffrey Parzych Date: 2022.06.28 16:19:21 -04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2022.06.29 09:04:16 -04'00'