This document is a roofing specification for a section of the Central Administration building located at 4000 Cooper St. in the Southern Region. The document outlines three roofing system options for the approximately 6,000 square foot roof section 27: 1) a full roof replacement with a mechanically attached EPDM system, 2) a restoration specification to apply a coating over the existing EPDM roof, and 3) a full removal and replacement with a fully adhered EPDM system. The existing roof is identified as being in fair condition at approximately 15 years old. Replacement costs are estimated at $51,600, restoration costs at $6,000, and the alternate fully adhered system at $7,500. All specifications include a 15-year manufacturer's warranty.

The document provides detailed technical requirements for each roofing option, including insulation, flashing, drainage, and other roof components. It notes that the existing roof could not be fully inspected due to restricted access. The document is intended to provide budgetary cost information and technical specifications for the roofing project.

View the file

Other files

File Type Posted
Photos.pdf PDF
5-A-2.07.tif TIF image
Central Administration Sec 13.pdf PDF
RFP Billable Rate 24342.pdf PDF
DTMB-0414 (RFP Addendum) 01.pdf PDF
4-A-2.07.tif TIF image
SAMPLE Billable Rate Contract (Rev 221207).pdf PDF
6-A-2.08.tif TIF image
LEIN Request 24342.pdf PDF
4-block.pdf PDF
Sign-in sheet 08082024.pdf PDF
18-A-2.04.tif TIF image
Project Statement 24342.pdf PDF
Central Administration Sec 12.pdf PDF
Central Administration Sec 15.pdf PDF
Conference Note 08082024.pdf PDF
5-block.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D0035-21

01/07/2014

Central Administration - Section 27

Description

Created

Drawing Id a b c d e f g h i j k l m n o p q r s t u v w

Building Drawing

Legend Control Joint Expansion Joint

* Note: -U indicates an unused item

Roof Top Units

Drainage

Miscellaneous

Problem Indicators

Projections xxxxx

McDonald Roofing Co.

Project

Customer

DWG. By

Date Scale

This drawing is the property of McDonald Roofing Co.

It may not be reproduced without consent.

NTS

A. Kreichelt

HVAC on Curb

Roof Hatch

HVAC on Sleepers

Skylight

Unit on Curb

Unit on Sleepers

Plumbing Stack

Pitch Pan

Hot Stack

Metal Sleeve Stack

Drain (Existing)

Drain (New)

Scupper

Gas Line

Walkway

Paver Walkway

Satellite Dish

Antenna

Core Test

Blister

Ponding

Flashing Problem

Ridging

Bare Spot

Photo Indicator

3960 Ann Arbor Rd.

A

S L

C

Central Administration Sec 27

Southern Region

11/4/13

N

Sec 27

Legend Control Joint Expansion Joint

* Note: -U indicates an unused item

Roof Top Units

Drainage

Miscellaneous

Problem Indicators

Projections xxxxx

McDonald Roofing Co.

Project

Customer

DWG. By

Date Scale

This drawing is the property of McDonald Roofing Co.

It may not be reproduced without consent.

NTS

A. Kreichelt

HVAC on Curb

Roof Hatch

HVAC on Sleepers

Skylight

Unit on Curb

Unit on Sleepers

Plumbing Stack

Pitch Pan

Hot Stack

Metal Sleeve Stack

Drain (Existing)

Drain (New)

Scupper

Gas Line

Walkway

Paver Walkway

Satellite Dish

Antenna

Core Test

Blister

Ponding

Flashing Problem

Ridging

Bare Spot

Photo Indicator

3960 Ann Arbor Rd.

A

S L

C

Central Administration Sec 27

Southern Region

11/4/13

N

Sec 27

62'

20'

20'

28'

Section Composition

Section Condition Summary

Address - Section:

Section Summary

Roof System:

Manufacturer:

Age:

Area:

Replacement Cost $ :

Life:

Surface:

Membrane:

Insulation:

Prior Roof:

Vapor Barrier:

Deck:

Coping:

Base Flashing:

Counter Flash:

Drainage:

Construction:

Condition:

Restoration Cost $ :

Building Use:

Strategy:

Central Administration

Fair condition, do regular maintenance

Maintain yearly for longest serviceable life

EPDM MA

N/A

None

.045 mil reinforced EPDM

NO CORE TAKEN. RESTRICTED ROOF ACCESS.

N/A

None

Metal

Limestone

EPDM

2pc. Stainless Steel

Drains

Block

6,000

5,100

DEPTCOR

The roof and its components were inspected on section 27 of the building known as Central Administration. The mechanically attached EPDM roof appears to be in near fair condition at approximately 15 years of age. The roof was not cored or was able to be thoroughly inspected due to restricted roof access. The roof should last up to 5 years with routine roof inspections and maintenance performed annually.

The costs shown for the roof replacement, restoration and alternate specifications are for the purpose of budgeting only and may be subject to change.

The replacement specification is to remove the existing roof and replace with like system.

The restoration specification is to apply Andek restorative coating over the existing roof surface.

The alternate specification is to remove the existing roofing and replace with a fully adhered EPDM roof system at a cost of: $7,500

4000 Cooper St. C.Admin.27

01/23/2014

Drawing

Warranty Number

Warranty Expires

D0035-21

Squares (100 sft.)

03/03/2014

Restoration or Replacement Cost Specification

Address - Section ID: 4000 Cooper St. C.Admin.27

1. Replacement Specification

Remove the existing roof and replace with like system.

Remove existing roof system and properly dispose of.

Inspect the metal decking for damage or deterioration and repair or replace as needed at an extra cost based on unit sf pricing determined at the time of the project.

Mechanically attach 2 layers of 2" isocyanurate insulation to the metal decking in a staggered fashion.

Mechanically attach 1/8" tapered sloped insulation to properly guide moisture to roof drains.

Mechanically attach .060 mil EPDM reinforced membrane over insulation.

Seal all seam of the field membrane with 3" tape and q.s. primer.

Properly flash all roof drains, support curbing, perimeter flashing and roof penetrations in accordance with manufactures specifications.

Install new pre finished steel coping at perimeter walls as needed.

Install new pre finished steel counter flashing as needed.

This project comes with a 15 year manufacture warranty.

Specification

2. Restoration Specification

EPDM specification to cover over the existing roof system.

Remove existing roof membrane, metal coping and flashing trim, curb and penetration flashings and properly dispose of.

Inspect the existing roof insulation for damage or deterioration and repair or replace as needed at an extra cost based on unit sf pricing determined at the time of the project.

Mechanically attach 1 layer of 1" isocyanurate insulation over the existing roof system.

Mechanically attach 1/8" tapered sloped insulation to properly guide moisture to roof drains.

Fully adhere .060 mil EPDM membrane over new insulation.

Seal all seam of the field membrane with 3" tape and q.s. primer.

Properly flash all roof drains, support curbing, perimeter flashing and roof penetrations in accordance with manufactures specifications.

Fabricate and install new metal copings and trim from pre-finished steel.

This project shall include a 15 year manufactures warranty.

3. Alternate Specification

Remove the existing roof and replace with a fully adhered EPDM system.

-Remove the existing roofing membrane, all flashings, metal copings and metal trim and properly dispose of.

-Inspect the decking for damage or deterioration and repair or replace as needed. This will be an extra cost based unit sf pricing determined at the time of the inspection.

-Mechanically attach 2 layers of 2" isocyanurate.

-Install tapered insulation as needed to guide water to roof drains or scuppers.

-Mechanically attach RFPS strip to the base of all walls and support curbing.

-Fully adhere .060 mil EPDM to the insulation with bonding adhesive.

-Properly flash all roof penetrations, support curbing, roof drains and walls to manufacturers specifications.

-Fabricate and install new metal copings and trim metal from 24 gauge pre-finished steel.

-This project shall include a 15 year manufacturers material warranty.