This document provides guidance on calculating self-performance for a solicitation responding to Request for Proposal 36C10F-20-R-0091 from the Department of Veterans Affairs for the Central Utility Plant construction project located at the Dallas VA Medical Center campus. Contractors must clearly describe the work to be self-performed and show the calculation, which includes materials purchased and installed by the contractor's own forces, labor for those materials, supplies directly supporting the contractor's work, mobilization and use of owned or rented equipment operated by the contractor's employees, and own job overhead costs. The calculation requires identifying the total offer price, subtracting any specialty trades work not self-performed, and general and administrative costs to determine the total amount of work under the contract. The self-performance amount must then be provided and calculated as a percentage of the total contract work.

View the file

Other files

File Type Posted
36C10F20R0091 0012.docx DOCX document
36C10F20R0091 0011.zip ZIP file
Part I RFIs combined Responses CUP Bid Package KW Reviewed.pdf PDF
Part II RFIs combined Responses CUP Bid Package KW Reviewed.pdf PDF
Part IV RFIs combined Responses CUP Bid Package KW Reviewed.pdf PDF
36C10F20R0091 0010.docx DOCX document
Part III RFIs combined Responses CUP Bid Package KW Reviewed.pdf PDF
36C10F20R0091 0009.docx DOCX document
36C10F20R0091 0008.docx DOCX document
36C10F20R0091 0007.docx DOCX document
CUP Preposal Mtg Notice of Attendance -Jan62020.pdf PDF
Onsite Sign in CUP Preproposal Mtg 20210106.pdf PDF
36C10F20R0091 0006.docx DOCX document
36C10F20R0091 0005.docx DOCX document
36C10F20R0091 0004.docx DOCX document
Dallas Campus Site Plan 2018 - Bldg. 9 Engineering.pdf PDF
36C10F20R0091 0003.docx DOCX document
23 65 00 Cooling Towers ADD1.pdf PDF
00 00 01 - Table of Contents ADD1.pdf PDF
36C10F20R0091 0002.docx DOCX document
36C10F20R0091 0001.docx DOCX document
repost-70-08 Structural DWGs BP E rev.pdf PDF
70-01 Civil Dwgs BP E rev part 2of2.pdf PDF
S05 REGULATED BUILDING MATERIALS SURVEY REPORT.pdf PDF
70-23 Mechl Dwgs BP-E rev.pdf PDF
70-22 Plumbg Dwg BP-E.pdf PDF
70-09 Architectural Dwgs BP E rv.pdf PDF
70-02 Land Irrigatn Dwgs BP E rv.pdf PDF
70-08 Structural DWGs BP E rev.pdf PDF
70-26 Elecl Dwgs BP-E rev.pdf PDF
70-00 General Dwgs BP-E rv.pdf PDF
36C10F20R0091_1.docx DOCX document
Supplemental Info Bid Pack E part-1of2.pdf PDF
Contractor Evaluation Safety Guide OSHA-EMR.pdf PDF
WD-Dallas TX-TX20190241 02142020.pdf PDF
ProjMan-VA-LTSCIF-D-20200602_Vol2 r4.pdf PDF
Supplemental Info Bid Pack E part-2of2.pdf PDF
70-01 Civil Dwgs BP E rev part 1of2.pdf PDF
VAMC-D 2020-1119r JOFOC notice w-attachments.pdf PDF
ProjMan-VA-LTSCIF-D-20200602_Vol1 r4.pdf PDF
Notification of Attendance-PreProposal Site Visit.pdf PDF
Contractors Reference Form.pdf PDF
Request for Information Doc.pdf PDF
PPQ-Attachment.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CALCULATION OF SELF-PERFORMED WORK (SDVOSB only)

SUBMITTED IN RESPONSE TO RFP 36C10F-20-R-0091

Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.

(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)

Clearly describe the work to be self-performed:

Show Calculation of Self-Performed work: __________________________________

B.1 Total Offer Price: $_________________

B.2 If applying for consideration as a General Contractor (multi-discipline projects) subtract Specialty Trades

(Unless being self-performed) $_____________

B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc.

B.4 Remainder is “Total amount of work to be performed under the Contract” = $__________________

B.5 “Work to be self-performed”: = $ _________________________________ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”?

(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)

B.6 % Self-performed Work = Line B.5 / B.4 X 100% = ________________________%