This document provides guidance on calculating self-performance for a solicitation responding to Request for Proposal 36C10F-20-R-0091 from the Department of Veterans Affairs for the Central Utility Plant construction project located at the Dallas VA Medical Center campus. Contractors must clearly describe the work to be self-performed and show the calculation, which includes materials purchased and installed by the contractor's own forces, labor for those materials, supplies directly supporting the contractor's work, mobilization and use of owned or rented equipment operated by the contractor's employees, and own job overhead costs. The calculation requires identifying the total offer price, subtracting any specialty trades work not self-performed, and general and administrative costs to determine the total amount of work under the contract. The self-performance amount must then be provided and calculated as a percentage of the total contract work.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED WORK (SDVOSB only)
SUBMITTED IN RESPONSE TO RFP 36C10F-20-R-0091
Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
Clearly describe the work to be self-performed:
Show Calculation of Self-Performed work: __________________________________
B.1 Total Offer Price: $_________________
B.2 If applying for consideration as a General Contractor (multi-discipline projects) subtract Specialty Trades
(Unless being self-performed) $_____________
B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc.
B.4 Remainder is “Total amount of work to be performed under the Contract” = $__________________
B.5 “Work to be self-performed”: = $ _________________________________ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”?
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
B.6 % Self-performed Work = Line B.5 / B.4 X 100% = ________________________%