About this file
This is an email chain documenting confirmation from the Orange County Transportation Authority (OCTA) regarding prevailing wage applicability to RFP 260451 for hydrogen mobile fuelers for 40-foot hydrogen fuel cell buses. The project involves the procurement of two hydrogen mobile fuelers, with a total budget of $5,872,800 for a one-year initial term. The email correspondence dated August 12, 2026, between Ellis Hoskin, Senior Contract Administrator at OCTA's Contracts Administration and Materials Management division, and Sunil Chettiar addresses clarifications on project requirements and cost calculations. Ellis Hoskin requested confirmation of prevailing wage applicability and updates to liquidated damages calculations in the associated scope of work memorandum.
In response to prevailing wage inquiries, Sunil Chettiar confirmed that prevailing wages should not apply to this project as it does not constitute a public works project. The pricing discussion referenced labor costs of $100 per hour as an average rate for 2.5 hours of work, which was stated to account for combined mechanic and supervisor time. Ellis Hoskin emphasized that the prevailing wage determination was required based on the applicable scope of work and requested that Chettiar provide documented calculations for liquidated damages to support the project documentation. The email chain reflects internal coordination between procurement and project management to ensure compliance with contractual requirements prior to finalizing the RFP.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ellis Hoskin
From: Sunil Chettiar Sent: Wednesday, August 12, 2026 3:30 PM To: Ellis Hoskin Subject: RE: RFP 260451 Hydrogen Mobile Fuelers for 40-Foot Hydrogen Fuel Cell Buses
Ellis, Prevailing wages should not apply here as this is not a public works project.
Thanks
From: Ellis Hoskin <ehoskin@octa.net> Sent: Wednesday, August 12, 2026 1:56 PM To: Sunil Chettiar <schettiar@octa.net> Subject: RE: RFP 260451 Hydrogen Mobile Fuelers for 40-Foot Hydrogen Fuel Cell Buses
Hi Sunil, See below link:
Prevailing Wage
Prevailing wage determinaƟon is required by the project manager based on the applicable scope of work.
Thank you, Ellis Hoskin | Senior Contract Administrator Contracts Administration and Materials Management Orange County Transportation Authority
(714) 560-5551 550 South Main Street | PO Box 14184 | Orange, CA 92863-1584 CAMM - Procurement with Integrity
From: Sunil Chettiar <schettiar@octa.net> Sent: Wednesday, August 12, 2026 11:50 AM To: Ellis Hoskin <ehoskin@octa.net> Subject: RE: RFP 260451 Hydrogen Mobile Fuelers for 40-Foot Hydrogen Fuel Cell Buses
Ellis, Please see updated. Prevailing wages not sure what you mean by that?
I just kept $100/hour as 2.5 hours include mechanic and supervisor time. So, avg. $100 should be good.
Thanks From: Ellis Hoskin <ehoskin@octa.net> Sent: Wednesday, August 12, 2026 11:35 AM To: Sunil Chettiar <schettiar@octa.net> Subject: RFP 260451 Hydrogen Mobile Fuelers for 40-Foot Hydrogen Fuel Cell Buses
Hi Sunil, Please confirm if prevailing wages are applicable to the subject referenced Scope of Work.
AddiƟonally, please update the aƩached memo with the calculaƟon for the LD’s.
I understand we have discussed this previously, the calculaƟon is required.
Thank you, Ellis Hoskin | Senior Contract Administrator Contracts Administration and Materials Management Orange County Transportation Authority
(714) 560-5551
550 South Main Street | PO Box 14184 | Orange, CA 92863-1584 CAMM - Procurement with Integrity