This is a Procurement Plan (RFP 250236) issued by the Orange County Transportation Authority (OCTA) for the acquisition of hydrogen mobile fuelers to support 40-foot hydrogen fuel cell buses. The procurement is structured as a Request for Proposals, indicating that evaluation criteria beyond price will be used in vendor selection. The contract will be awarded for an initial one-year term with two optional one-year renewal periods. The procurement plan identifies Ellis Hoskin as the Senior Contract Administrator overseeing the process and Sunil Chettiar as the Senior Section Manager for Transit Technical Services providing project management oversight.
The evaluation criteria are weighted as follows: Qualifications of the Firm (30%), Staffing/Project Organization (20%), Work Plan (25%), and Cost (25%). The contract will be structured as a Time and Expense agreement with firm-fixed rates, allowing services to be provided on an as-needed basis. The total budget is $6,779,429 per year for each contract term, with identical amounts allocated for the initial term and both optional renewal periods, totaling potential funding of $20,338,287 across all three years. Funding is sourced from local revenues. The procurement does not include prevailing wage requirements, liquidated damages provisions, DBE goals, or a retention requirement. An independent cost estimate has been received, and Requisition R001397 has been submitted to support the procurement.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTEROFFICE MEMO
Procurement Plan, RFP 250236
Date: February 17, 2026
To: Sunil Chettiar, Senior Section Manager, Transit Technical Services
From: Ellis Hoskin, Senior Contract Administrator, CAMM
Subject: Procurement Plan for Release, Selection and Award RFP 250236 “Hydrogen Mobile Fueler for 40-Foot Hydrogen Fuel Cell Buses”
Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments. Thanks.
Procurement Type: |X| RFP |_| IFB
A Request for Proposals (RFP) is issued as the nature of the procurement demands that evaluation criteria, in addition to price, be used to select a firm.
Evaluation Criteria:
| PROPOSAL |
| WEIGHT |
| Qualifications of the Firm |
| 30% |
| Staffing/Project Organization |
| 20% |
| Work Plan |
| 25% |
| Cost |
| 25% |
Justification:
Qualifications of the firm criterion is weighted at 30 percent as the proposing firms must demonstrate a proven history in successfully completing similar projects. Staffing and project organization criterion is weighted at 20 percent as the firm must demonstrate the proposed key personnel have specific skillsets in order to complete the services required in the scope of work. Work Plan is weighted at 25 percent to ensure proposals address each section of the work plan in sufficient detail to demonstrate a clear understanding of the scope of work. Cost and price criterion is weighted at 25 percent to ensure OCTA receives fair and competitive pricing for the services provided.
Contract Type: |X| Time & Expense |_| CTO-Based |_| Firm Fixed Price
Justification (Explain the rationale for using the particular contract type):
A time and expense contract is appropriate for this procurement as firms are required to provide services on an as-needed basis at a firm-fixed rate.
| Retention: |
| |_| Yes |
| |X| No |
| |_| N/A |
| Prevailing Wages: |
| |_| Yes |
| $ |
| |X| No |
| |_| N/A |
| Liquidated Damages: |
| |_| Yes |
| $ |
| |X| No |
| |_| N/A |
Procurement Schedule: |X| Attached
Internal Evaluators:
Ellis Hoskin, Senior Contractor Administrator, Contracts Administration and Materials Management
Olivia Salters, Senior Health, Safety and Environmental Compliance (HSEC) Specialist, HSEC
Robert Fernandez, Department Manager, Maintenance Administration
Sunil Chettiar, Senior Section Manager, Transit Technical Services
Trevor Johnson, Section Manager III, Facilities Maintenance Administration
Contract Term: One (1) year initial term with two, one (1)-year option term
Funding Source: |X| Local |_| Measure M |_| Federal (CMAQ)
Dollar Amount: |X| Initial Term $6,779,429.00 |X| First Option Term $6,779,429.00 |X| Second Option Term $6,779,429.00
Independent Cost Estimate Received: |X| Yes |_| No
Requisition Received: |X| Yes Req. R001397
DBE Goal: |_| Yes |X| No
Project Manager Concurrence:
| __________________________________________ | ______________ | |
| Sunil Chettiar, Senior Section Manager, Transit Technical Services | Date |
CAMM Section/Department Manager Concurrence:
| __________________________________________ | ______________ | |
| Georgia Martinez, Department Manager, Contracts and Procurement | Date |