This interoffice memorandum concerns the procurement timeline for RFP 250202, an Orange County Transportation Authority (OCTA) initiative to select a qualified consultant for an OC Bus Customer Satisfaction Survey. The RFP will be issued on February 23, 2026, with a second public notice and written question deadline of March 2, 2026 at 2:00 p.m. OCTA will respond to written questions by March 4, 2026. Proposals are due March 10, 2026 at 2:00 p.m., followed by a pre-evaluation meeting at 3:30 p.m. the same day. The evaluation committee will review proposals on March 17, 2026, with interviews tentatively scheduled for March 24, 2026, pending committee determination of necessity. Best and final offers, if required, are due March 25, 2026, with contract execution targeted for March 31, 2026. The project term is one year.
The contract budget is $150,000 for the one-year term. Internal communications indicate discussion between the section manager and contract administrator regarding whether formal interviews would be conducted; while interviews are standard for formal procurements, they may be cancelled if the evaluation committee determines them unnecessary after initial proposal reviews. The memorandum requests confirmation of the timeline from relevant stakeholders and requires project manager concurrence prior to finalization.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTEROFFICE MEMO
February 18, 2026
To: Ryan Maloney, Section Manager, Marketing and Customer Service
From: Rhea Aninzo, Contract Administrator, CAMM
| Subject: | Time Schedule for Release, Selection and Award |
| RFP 250202 “OC Bus Customer Satisfaction Survey” |
Please review the time schedule for the subject RFP. If there is an issue with any of the dates or timelines, kindly advise as soon as possible.
| February 23, 2026 | Issue RFP | |
| First Public Notice |
| March 2, 2026 | Second Public Notice | |
| Written Questions Due 2:00 p.m. |
March 4, 2026 OCTA’s Response
| March 10, 2026 | Offers Submitted 2:00 p.m. | |
| Pre-Evaluation Meeting 3:30 p.m. |
March 17, 2026 Evaluation Committee Reviews Proposals
March 24, 2026 Interviews (if needed) Comment by Rhea Aninzo: Could we remove this? Ryan said he didn’t need interviews. I let him know interviews are standard for formal procurements, but if the committee decides after evaluations that they aren’t needed, we can move forward without them. Comment by Georgia Martinez: We should leave them in and if not needed they can be cancelled.
March 25, 2026 Best and Final Offer (if needed)
March 31, 2026 Contract Executed
Project Manager Concurrence:
| _______________________________________________ | ______________ | |
| Ryan Maloney, Section Manager, Marketing and Customer Service | Date |