C250202_PS_02-18-26.docx

DOCX document 41 KB Posted

Attached to
OC Bus Customer Satisfaction Survey
Solicitation number
250202
Issued by
Orange County, California

About this file

This is an interoffice memorandum from the Orange County Transportation Authority (OCTA) outlining the procurement timeline for RFP 250202, an OC Bus Customer Satisfaction Survey project. The RFP will be issued on February 23, 2026, with a second public notice and written questions deadline of March 2, 2026 at 2:00 p.m. OCTA will respond to written questions by March 4, 2026. Proposals are due on March 10, 2026 at 2:00 p.m., followed by a pre-evaluation meeting at 3:30 p.m. the same day. The evaluation committee will review proposals on March 17, 2026. Interviews are tentatively scheduled for March 24, 2026 but may be eliminated if the evaluation committee determines they are unnecessary; a best and final offer phase is scheduled for March 25, 2026 if needed. The contract is expected to be executed by March 31, 2026. The project involves developing, conducting, analyzing, and reporting on a customer satisfaction survey for OC Bus services over a one-year term.

The budget allocated for this procurement is $150,000 for the one-year contract period. The memorandum includes a comment from Contract Administrator Rhea Aninzo noting that while interviews are standard for formal procurements, the Section Manager indicated they may not be necessary for this project. The memorandum requires project manager concurrence from Ryan Maloney, Section Manager of Marketing and Customer Service, confirming approval of the proposed timeline before proceeding with the RFP release.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

February 18, 2026

To: Ryan Maloney, Section Manager, Marketing and Customer Service

From: Rhea Aninzo, Contract Administrator, CAMM

Subject:Time Schedule for Release, Selection and Award
RFP 250202 “OC Bus Customer Satisfaction Survey”

Please review the time schedule for the subject RFP. If there is an issue with any of the dates or timelines, kindly advise as soon as possible.

February 23, 2026Issue RFP
First Public Notice
March 2, 2026Second Public Notice
Written Questions Due 2:00 p.m.

March 4, 2026 OCTA’s Response

March 10, 2026Offers Submitted 2:00 p.m.
Pre-Evaluation Meeting 3:30 p.m.

March 17, 2026 Evaluation Committee Reviews Proposals

March 24, 2026 Interviews (if needed) Comment by Rhea Aninzo: Could we remove this? Ryan said he didn’t need interviews. I let him know interviews are standard for formal procurements, but if the committee decides after evaluations that they aren’t needed, we can move forward without them.

March 25, 2026 Best and Final Offer (if needed)

March 31, 2026 Contract Executed

Project Manager Concurrence:

_____________________________________________________________
Ryan Maloney, Section Manager, Marketing and Customer ServiceDate

Revised: 03/03/2010 image1.png