This is an appendix to a timber sale contract for the "End of the World G-Z Long-Term IRSC" project on the Nez Perce-Clearwater National Forest, Salmon River Ranger District. The document establishes comprehensive road maintenance requirements and specifications for contractor performance across multiple road segments.
The contract identifies 18 pre-haul roads totaling approximately 51.92 miles, all designated as contractor performance items requiring maintenance under Specification T-101 (Surface Blading). During and post-haul operations, these roads require maintenance under multiple specifications including T-101, T-103 (water and magnesium chloride dust abatement), T-108 (slide removal), T-113 (surfacing repair), T-301 (ditch cleaning), T-310 (minor drainage structures), T-506 (clearing roadway vegetation), T-507 (cutting roadside vegetation), T-618 (major drainage structures), and T-710 (traffic services). Material sourcing requirements include aggregate from Twin Cabins Pit (885 cubic yards of surface course material), with provisions for alternate sources if designated sources prove insufficient. Additional contract requirements address dust abatement treatments, specifically magnesium chloride brine applications to Road 642 (Twin Cabins) at initial and subsequent application rates; snow removal; slide and slump repair; drainage structure maintenance; vegetation clearing; and traffic control sign maintenance. All work must comply with Forest Service specifications for road construction and traffic control devices, with quality testing and certification requirements for chemical dust abatement materials.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
End of the World G-Z Long-Term IRSC Nez Perce - Clearwater National Forest Page 1 of 17 Salmon River Ranger District
APPENDIX C
C5.31#– ROAD MAINTENANCE REQUIREMENTS. (7/01) Contractor shall maintain roads in accordance with the following Contract Road Maintenance Requirements Summary:
Contract Road Maintenance Requirements Summary Pre-Haul
Road Termini
Miles Applicable Pre-Haul Road Maintenance Specs
From To T-101 T-103 T-108 T-113 T-301 T-310 T-506 T-507 T-710 221 6.65 23.80 17.15 C N/A N/A N/A N/A N/A N/A N/A N/A 243 14.12 16.78 2.66 C N/A N/A N/A N/A N/A N/A N/A N/A
243B 0.00 1.10 1.10 C N/A N/A N/A N/A N/A N/A N/A N/A 642 1.53 7.25 5.72 C N/A N/A N/A N/A N/A N/A N/A N/A
642A 0.00 1.68 1.68 C N/A N/A N/A N/A N/A N/A N/A N/A 2026 0.00 4.96 4.96 C N/A N/A N/A N/A N/A N/A N/A N/A
2026A 0.00 0.99 0.99 C N/A N/A N/A N/A N/A N/A N/A N/A 9302 0.00 2.70 2.70 C N/A N/A N/A N/A N/A N/A N/A N/A
9302A 0.00 0.89 0.89 C N/A N/A N/A N/A N/A N/A N/A N/A 9302A1 0.00 0.17 0.17 C N/A N/A N/A N/A N/A N/A N/A N/A
9404 0.00 1.79 1.79 C N/A N/A N/A N/A N/A N/A N/A N/A 9424 0.00 3.86 3.86 C N/A N/A N/A N/A N/A N/A N/A N/A
9424B 0.00 1.03 1.03 C N/A N/A N/A N/A N/A N/A N/A N/A 9461 0.00 1.90 1.90 C N/A N/A N/A N/A N/A N/A N/A N/A 9465 0.00 0.61 0.61 C N/A N/A N/A N/A N/A N/A N/A N/A 9485 2.64 2.87 0.43 C N/A N/A N/A N/A N/A N/A N/A N/A
9485C 0.00 0.49 0.49 C N/A N/A N/A N/A N/A N/A N/A N/A 76479 0.00 0.37 0.37 C N/A N/A N/A N/A N/A N/A N/A N/A
C =Contractor Performance Item, D =Deposit to Forest Service, D3 =Deposit to Third Party
Page 2 of 17 Salmon River Ranger District
During/ Post-Haul
Road
Termini
Miles
Applicable During / Post-Haul Road Maintenance Specs From To T-101 T-103
H2O T103
MagCl T-108 T-113 T-301 T-310 T-506 T-507 T-618 T-710
221 6.65 23.80 17.15 N/A N/A N/A C C C C C C N/A N/A 243 14.12 16.78 2.66 C C N/A C C C C C C N/A N/A
243B 0.00 1.10 1.10 C C N/A C C C C C C N/A N/A 642 1.53 7.25 5.72 C N/A C C C C C C C N/A N/A
642A 0.00 1.68 1.68 C C N/A C C C C C C N/A N/A 2026 0.00 4.96 4.96 C C N/A C C C C C C N/A N/A
2026A 0.00 0.99 0.99 C C N/A C C C C C C N/A N/A 9302 0.00 2.70 2.70 C C N/A C C C C C C N/A N/A
9302A 0.00 0.89 0.89 C C N/A C C C C C C N/A N/A 9302A1 0.00 0.17 0.17 C C N/A C C C C C C N/A N/A
9404 0.00 1.79 1.79 C C N/A C C C C C C N/A N/A 9424 0.00 3.86 3.86 C C N/A C C C C C C N/A N/A
9424B 0.00 1.03 1.03 C C N/A C C C C C C N/A N/A 9461 0.00 1.90 1.90 C C N/A C C C C C C N/A N/A 9465 0.00 0.61 0.61 C C N/A C C C C C C N/A N/A 9485 2.64 2.87 0.43 C C N/A C C C C C C N/A N/A
9485C 0.00 0.49 0.49 C C N/A C C C C C C N/A N/A 76479 0.00 0.37 0.37 C C N/A C C C C C C N/A N/A
C =Contractor Performance Item, D =Deposit to Forest Service, D3 =Deposit to Third Party
Page 3 of 17 Salmon River Ranger District
C5.221# – MATERIAL SOURCES. (4/04) Sources of local materials are designated on Plans and Sale Area Map.
Forest Service assumes responsibility for the quality and quantity of material in designated sources. Contractor shall determine the equipment and work required to produce the specified product, including the selection of acceptable material that is reasonably available in the source that meets specifications. The designation of source includes the rights of Contractor to use certain area(s) for plant site, stockpiles, and haul roads.
Should the designated source, due to causes beyond the control of Contractor, contain insufficient acceptable material, Forest Service will provide another source with adjustment in accordance with B5.253.
When Contractor elects not to use designated sources, Contractor shall furnish the specified product with no adjustment in unit rates. Quality testing shall be the responsibility of Contractor. Test results shall be furnished to Forest Service.
When Contractor elects not to use designated sources and the Schedule of Items lists pit development separately, cost allowance will be reduced under B5.253 when Forest Service determines the work will not be required.
When materials are subject to a weight measurement, the specific gravity or weight/volume relationship used as a basis for determination of estimated quantities shall be:
Source I , Source II and Source III
Contractor may, when agreed in writing, use on the project such suitable stone, gravel, and sand, or other material found in the excavation, and will earn a cost allowance for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. Contractor shall replace, without additional cost allowance, sufficient suitable materials to complete the portion of the work that was originally contemplated to be constructed with such material. Contractor shall not excavate or remove any material, except that which is within the excavation limits, without written authorization from Forest Service.
When material is appraised from non-National Forest designated sources, owner charges for the material in terms of unit cost for royalties, purchase of raw materials, or finished products shall be as follows- N/A.
Material
Type of
Purchase Owner(s)
Unit of
Measure
Unit
Price
Estimated
Quantity Total
Should quantity vary from that estimated, payment to owners shall be for units actually obtained. Contractor shall make arrangements with owner(s) for measurement and payment for royalties, purchase of raw materials, or finished products, as shown above.
Materials produced or processed from National Forest lands in excess of the quantities required for performance of this contract are the property of Forest Service, unless prior written agreement has been obtained to use excess material on other National Forest sales. Forest Service is not obligated to reimburse Contractor for the cost of their production.
Materials shall be stored to assure the preservation of their quality and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by Forest Service, may be used for storage purposes and for the placing of Contractor’s plant equipment. All storage sites provided by Forest Service shall be restored at Contractor’s expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered lands.
Page 4 of 17 Salmon River Ranger District
When the construction of the portion of the project for which Temporary Roads used for hauling materials is completed, all such Temporary Roads shall be restored as nearly as practicable to their original ground profile, unless otherwise agreed in writing.
C5.222# - STOCKPILED MATERIAL SOURCES (1/02). Material is appraised from National Forest stockpiles designated on the Sale Area Map. Payment to the Forest Service for such material shall be made prior to removal of any material and at the following rates:
Source/Stockpile
Type of Material
Unit of Measure
Unit Price
Estimated Quantity
Total Price
Twin Cabins Pit Aggregate Surface Course (Gradation F)
CY N/A 885 CY N/A
When agreed to in writing, Contractor may elect to crush material at the above sources in lieu of purchasing stockpiled material; however, there will be no adjustment in cost allowance.
When agreed to in writing, Contractor may elect to obtain material from other sources, with no adjustment in cost allowances, unless such adjustment results in a savings to the Forest Service. Such adjustment will be in accordance with B5.253.
Forest Service assumes responsibility for the quality and quantity of material in the sources designated above.
Should a designated source, due to causes beyond the control of the Contractor, contain insufficient acceptable material, the Forest Service will provide another source with adjustment in accordance with B5.253.
C5.314# - DUST ABATEMENT TREATMENT (02/02). When conditions are such that dusting would result in hazardous driving conditions or there would be an appreciable loss of road surface binder material, Contractor shall control such dusting by application of a dust abatement treatment to the surface of roadways and other traveled areas according to referenced or attached specifications or other specifications agreed to in writing. This treatment will provide a surface which can be bladed and retreated when necessary. It is not intended to produce a permanent waterproof wearing surface or dust control for more than one year, even though some residual value may be retained. It is intended to be compatible with the physical characteristics of the road surface, such as parent material, percent fines, relative humidity, or possibly some residual dust abatement material.
Dust abatement treatment shall apply only to the roads listed below. The provisions of Specification T-103 of C5.31# shall apply to all other roads when required under C5.31#. T-103 of C5.31# may be used in lieu of C5.314# to perform dust abatement during hauling of timber cut within the clearing limits of roads constructed under this timber sale unless otherwise agreed.
C5.314# Attachment (6/23)
SURFACE PREPARATION
Prior to application of chlorides, the roadway shall be prepared by T-101 Surface Blading and watered as necessary to achieve adequate penetration of the chlorides without runoff. If flakes are used, water will be added after placing the flakes to facilitate penetration of the chlorides into the roadway.
APPLICATION
(a) The Distribution Equipment shall be so designed, equipped, maintained, and operated such that the dust abatement material may be applied uniformly on variable widths of surface.
Page 5 of 17 Salmon River Ranger District
For liquid products the following requirements shall apply: (1) The spray pattern from each nozzle on the spray bar shall be uniform across the spray bar; (2) Distribution equipment shall include accurate volume measuring devices or a calibrated tank, a thermometer for measuring temperatures of tank contents, and a hose and nozzle attachment for applying material to areas inaccessible to the spray bar.
Calcium Chloride Flake shall be spread with equipment that evenly distributes the material across the required road width. The relative weight of material placed shall be easily determined during application.
(b) Application Rate. Application rates will be as follows:
Road Number
Road Name Termini Application
Type
Abatement Treatment
Application Rate **
Width of Application
(Feet) 642 Twin Cabins MP 1.53 –
MP 7.25
Initial Mag Cl Brine 0.50
Gal./Sq. Yd.
642 Twin Cabins MP 1.53 –
MP 7.25
Subsequent Mag Cl Brine 0.25 Gal. / Sq. Yd.
The Forest Service may field test Chloride brines prior to application to make sure that the products meet the minimum concentrations specified. Acceptance of the material will be based on the concentration shown on the manufacturer's certificate, or on results of laboratory quality assurance tests done by the Forest Service on samples taken from distribution or hauling vehicles.
Uniform distribution shall be obtained at all points. For liquid products the spray pattern from each nozzle on the spray bar shall be uniform across the spray bar. For flake products, the coverage will be uniform on the road surface. Overlapping or skipping between spread sections shall be corrected. Accidental spillage and areas with excess dust palliative that are hazardous to traffic shall be covered with additional road surfacing material. The surface of adjacent structures and trees shall be protected from spattering or marring. Dust palliative material shall be discharged only in approved areas and shall not be allowed to flow into ditches or stream courses. All products may be placed in one application.
All spreading and hauling equipment shall comply with applicable State and Federal requirements including GVW limitations.
(c) Certification with Shipment. When each load of chloride material is delivered, the Contractor shall furnish one copy of the Bill of Lading, and a fully executed Certificate of Compliance indicating, as a minimum, the following information: Date, Material composition by weight of MgCL and CaCl, Net weight of shipment, Net gallons at 60 degrees F, Specific Gravity of brine at 60 degrees F. A separate Certificate of Compliance will not be required if the standard Bill of Lading contains the essential information required by the certificate.
(c) Sampling. Sampling of chloride material may be required to validate certifications furnished by the Contractor. When sampling is directed by the Forest Service, the actual samples will be taken by the Contractor in the presence of the Forest Service representative. All delivery and distribution equipment shall be constructed to permit sampling in conformance with AASHTO T-40 test procedure. Samples shall be obtained from hauling units just prior to application of the material.
Page 6 of 17 Salmon River Ranger District
C5.316 – SNOW REMOVAL (4/13). Snow removal shall be done in a manner to preserve and protect the roads, to insure safe and efficient transportation and to prevent unacceptable damage to roads, streams, and adjacent lands.
A. Description. Snow removal work by Contractor shall include:
1. Removal of snow from entire width of road surface including turnouts.
2. Removal of snow slides, minor earth slides, fallen timber and boulders that obstruct normal road surface width including turnouts.
3. Maintenance of drainage so that the drainage system will function efficiently and prevent erosion damage.
B. Performance. Snow removal shall be kept current and performed as often as necessary to insure safe and efficient transportation. Work shall be done in accordance with the following minimum standards of performance.
1. All debris, except snow and ice, that is removed from the road surface and ditches shall be deposited away from stream channels at agreed locations.
2. During snow removal operations, banks shall not be undercut nor shall gravel or other surfacing material be bladed off the roadway surface.
3. Ditches and culverts shall be kept functional during and following road use.
4. Snow berms shall not be left on the running surface of the road. Berms left on the shoulder of road shall be removed and/or drainage holes shall be opened and maintained in them. Drainage holes shall be spaced as needed to obtain satisfactory surface drainage without discharge on erodible fills.
5. Dozers or skidders shall not be used to plow snow on system roads without written approval of Forest Service. If approved, dozers and skidders must be equipped with shoes or runners to keep the plow blade a minimum of two inches above the road surface.
6. Snow removal must be done in such a way as to protect surface water drainage structures and the road surface. Any damage from, or as a result of, Contractor's snow removal work shall be restored in a timely manner at Contractor’s expense.
Page 7 of 17 Salmon River Ranger District
SPECIFICATION T-101 SURFACE BLADING
DESCRIPTION
1.1 Surface blading is keeping the native or aggregate surfaced road in a condition to facilitate traffic, minimize additional future maintenance, reduce erosion, and provide proper drainage. It includes maintaining the crown, in slope or out slope of the traveled way and shoulders, drainage dips, leadoff ditches, berms, turnouts, removal of minor slides and slumps, and other irregularities that prevent normal runoff from the road surface.
REQUIREMENTS
3.1 Surface blading shall be performed as often as necessary and to the standards required to facilitate traffic and proper drainage.
3.2 The blading shall be performed in such a manner as to preserve the existing cross section and to conserve surface materials. On gravel surfaced roads, the base must not be disturbed and no surface material may be bladed into the ditch or over the road shoulders. Blading of native surface roads shall be performed so no base material under four (4) inches in the greatest dimension is lost. All ruts, holes, etc., shall be removed by scarifying and/or cutting to the bottom of any surface irregularities. Oversize material brought to the surface in the scarification process shall be removed from the roadway. Surface material which has been displaced to the shoulders, turnouts, outside of curves, etc., shall be brought back so as to leave a uniform depth on the traveled way at completion of blading. Water shall be applied during blading if sufficient moisture is not present to prevent segregation.
3.3 Roadside cut slopes or berms shall not be undercut.
3.4 At intersections, the roadbeds of side roads shall be graded for a reasonable distance to assure proper blending of the two riding surfaces.
3.5 Drainage dips and leadoff ditches shall be cleaned and continually maintained to conform reasonably to their original constructed lines, grade, and cross section.
3.6 Berms shall be repaired promptly by placing selected material as needed to restore the berm to its original condition.
3.7 Surface blading of native surface roads also includes ditch cleaning, which shall be done in accordance with T- 301, Ditch Cleaning.
3.8 All blading operations shall be properly signed in accordance with B (T) 6.33# and all applicable State Laws.
Page 8 of 17 Salmon River Ranger District
SPECIFICATION T-103 DUST ABATEMENT
1.1 Dust abatement consists of road surface preparation and application of materials.
MATERIALS
2.1 Water, bituminous products, lignin sulfonates, chloride products, and other materials may be used for dust abatement. Materials other than water will require approval of the Forest Service and shall meet specifications furnished by the Forest Service.
REQUIREMENTS
3.1 Dust abatement materials shall be applied to the road surface as necessary to control surface loss and provide that vehicles are always inter-visible within their stopping sight distance. The average user speed on the road shall be used to determine stopping sight distance. Preparation shall be in accordance with Specification T- 101, Surface Blading.
3.2 The rate of application shall be such that the selected material will not run off the surface and cause pollution or unnecessary waste.
3.3 When water is the selected material, it shall be applied as often as necessary to abate dust from all Contractor operations.
Dust abatement shall be maintained as needed throughout the duration of operations.
Page 9 of 17 Salmon River Ranger District
SPECIFICATION T-108 SLIDE REMOVAL AND SLUMP REPAIR
1.1 Slide removal and slump repair consists of all work necessary to restore the road to its original cross section as necessary to facilitate use and provide drainage. This work is such that it cannot be handled by a grader during surface blading and ditch cleaning operations.
Slump repair is the filling with selected material of depressions or washouts in roadway which cannot be routinely filled by a motor grader.
Slide removal and slump repair includes excavation, loading, hauling, placing, and compacting of replacement material and the removal and disposal of waste material. This includes the development of disposal or borrow areas at locations approved by the Forest Service.
REQUIREMENTS
3.1 Contractor shall deposit slide material in an approved manner at designated locations.
Material shall not be disposed of on road fills unless otherwise agreed.
The slope which contributed the slide material shall be reshaped as practicable to reduce future sliding unless otherwise agreed.
3.2 When filling slumps and depressions, select material shall be used, placed in layers, and compacted to conform with or exceed the density of existing subgrade.
Existing aggregate surfacing shall be salvaged and relayed or replaced after slumps have been filled.
Damaged aggregate base, aggregate surfacing, and asphalt surfacing shall be repaired under Specification T-113, Surfacing Repair.
3.3 Following slide removal, roadway shall be shaped so as to reasonably conform to its original subgrade template.
3.4 Slump, waste, and borrow areas shall be seeded as required under T-508.
Page 10 of 17 Salmon River Ranger District
SPECIFICATION T-113 SURFACING REPAIR
1.1 Surfacing repair is patching potholes or small areas of broken asphalt or imported aggregate surfaces and asphalt dikes. It includes preparing the area to be patched and furnishing and placing all necessary materials, including base, and other work necessary to patch the surfacing, including paved shoulders. Sections requiring repair work shall be limited in area not to exceed 20 square feet for paved surfaces or 200 square feet for aggregate surfaces and not more than 10 areas per mile per year.
MATERIAL
2.1 Materials used for repair of aggregate surfacing shall conform to these specifications: Section 300 of Forest Service Specifications for Construction of Roads.
2.2 Materials used for asphalt patching shall conform to or exceed the requirements of these specifications:
Section 400 of Forest Service Specifications for Construction of Roads.
REQUIREMENTS
3.1 Aggregate Surfacing Repair. Aggregate material shall be placed in accordance with the applicable specification used in paragraph 2.1 above. Work under this specification shall be performed in a timely manner to reduce further deterioration of the surface.
3.2 Asphalt Surfacing Repair.
A. Potholes (deep patch). Remove the surface course and base course as deep as necessary to reach firm support; extend horizontally at least six (6) inches into good asphalt surfacing surrounding the cracked area. Make the cut square or rectangular with faces straight and vertical. Prime the bottom and faces using MC70, MC250, MC800, or emulsified asphalt (penetration type). Backfill the hole with asphalt mix and compact. Use 2-inch layers if the hole is more than four (4) inches deep. Compact each layer thoroughly with mechanical tampers or rollers. Compaction shall not be done with equipment wheels without prior approval. The patch when completed and compacted shall be flush with surrounding surface.
B. Skin Patches. Minor depressions, light raveling, or surface checking at scattered locations shall be treated by applying a skin patch. Carefully broom the surface of all loose material and apply a tack coat of MC70, MC250, or emulsified asphalt (penetration type) at the rate of 1/10-gallon per square yard. Place asphalt mix, distribute uniformly, and feather edges with asphalt rakes so the patch when compacted shall be flush with the adjoining surface. Roll thoroughly with a portable roller.
3.3 Asphalt Dikes. Asphalt material in the damaged length of dike shall be removed. Clean and repair asphalt foundation as necessary. Level exposed ends of existing dike. Prime all surfaces with bituminous material.
Asphalt mix shall be placed and compacted to conform with the shape of the original dike.
All asphalt material removed from potholes, patches, and dikes shall be disposed of in designated area.
Page 11 of 17 Salmon River Ranger District
SPECIFICATION T-301 DITCH CLEANING
1.1 Ditch cleaning is removing and disposing of all slough material from roadside ditches to provide an unobstructed waterway conforming reasonably to previous line, grade, and cross section.
REQUIREMENTS
3.1 Slough Material.
A. Native Surfaced Roads. Slough material from ditch cleaning, if suitable, may be placed and blended into the existing road surface or shoulders or placed in a designed berm during surface blading.
B. Aggregate Surface Roads. Slough material from ditch cleaning shall not be mixed with aggregate surfacing or left on the road surface unless otherwise agreed. Material shall be disposed of in an agreed manner at designated locations.
C. Asphalt Surfaced Roads. Equipment, methods, and timing shall be agreed to before start of ditch cleaning operations so as to protect the asphalt pavement. Material shall be disposed of in an agreed manner at designated locations.
Page 12 of 17 Salmon River Ranger District
SPECIFICATION T-310 MINOR DRAINAGE STRUCTURES
1.1 Minor drainage structures are single passages with maximum waterway opening equivalent to a 78-inch round pipe (87- by 63-inch arch) or multiple passages with maximum, single waterway opening equivalent to a 60-inch round pipe (66- by 51-inch arch). They include over side drains. Maintenance is work performed on inlets, outlets, related channels, existing riprap, trash racks, and drop inlets.
MATERIALS
2.1 All materials used in the maintenance of minor drainage structures shall conform by type and specification to the material in the structure being maintained.
REQUIREMENTS
3.1 All minor drainage structures are to be maintained in accordance with these specifications in the spring following any significant runoff and prior to the beginning of winter storms.
3.2 Clear inlet and outlet channels, inlet trash racks, and drop inlets of loose material that could cause plugging or prevent the free flow of water. Debris shall be disposed of in agreed manner at designated locations.
3.3 If outlet riprap was originally placed to dissipate water energy, it shall be maintained in good condition including the replacement of riprap if necessary.
4.1 Make whatever minor repairs are necessary to ensure the proper functioning of the head walls, aprons, inlet assemblies, over side drains, riprap, trash racks, and other facilities related to the drainage structure.
Page 13 of 17 Salmon River Ranger District
SPECIFICATION T-506 CLEARING ROADWAY VEGETATION
1.1 This work consists of cutting and disposing of all vegetative growth including trees from the road surface that reduces the operational capability of the road. Vegetation removal is required if the growth of the vegetation during the contract period causes unacceptable reduction of sight distance and operation capability.
REQUIREMENTS
3.1 Vegetative matter on the road surface which reduces sight distance, impedes vehicular travel, or interferes with road maintenance operations such as surface blading and ditch and culvert cleaning shall be removed. Downed timber meeting utilization standards shall be cut in appropriate lengths and decked along the roadside in locations where the traveled way or sight distance will not be impaired.
3.2 Low shrubs and brush which do not restrict sight distance, do not impede road maintenance, and reduce erosion need not be removed if the road surface can be adequately maintained without doing so. Vegetation and nonmerchantable timber removed shall be disposed of by scattering, chipping, hauling to designated disposal areas, or as otherwise agreed upon.
Page 14 of 17 Salmon River Ranger District
SPECIFICATION T-507 CUTTING ROADSIDE VEGETATION
1.1 This work consists of cutting and disposing of all vegetative growth, including trees from within the roadway that reduce sight distance and operational capability of the road. Vegetation removal is required if the growth of the vegetation during the contract period causes unacceptable reduction of sight distance and operation capability.
REQUIREMENTS
3.1 Vegetative matter within the roadway which reduces sight distance, impedes vehicular travel, or interferes with road maintenance operations such as surface blading and ditch and culvert cleaning shall be removed. Downed timber meeting utilization standards shall be cut in appropriate lengths and decked along the roadside in locations where the traveled way or sight distance will not be impaired.
3.2 Low shrubs and brush which do not restrict sight distance, do not impede road maintenance, and reduce erosion shall not be removed. Vegetation removed shall be disposed of by scattering, chipping, hauling to designated disposal areas, or as otherwise agreed upon.
Page 15 of 17 Salmon River Ranger District
SPECIFICATION T-618 MAJOR DRAINAGE STRUCTURES
1.1 Major drainage structures are culverts, bridges, and other structures with a minimum waterway opening equivalent to an 84-inch round pipe (95- by 67-inch arch) or multiple passages where the smallest single waterway opening is 66 inches (73- by 55-inch arch). All low water structures are major drainage structures.
Maintenance of these structures includes cleaning inlets, outlets, and related channels, trash racks, delineators, object markers, rails, timber or asphalt running surfaces, bridge inspections, and other work incidental to maintenance of the structure.
MATERIALS
2.1 All materials used in the maintenance of large drainage structures shall conform by type and specification to the material in the structure being maintained.
REQUIREMENTS
3.1 All major drainage structures and related channels except stream channels shall be maintained as early as possible in the spring following any significant runoff and prior to the beginning of winter storms.
3.2 The items listed below shall be accomplished within the scope of bridge maintenance and where applicable to the maintenance of other large drainage structures.
A. Ditch Cleaning, T-301, and Surface Blading, T-101, shall be performed to direct drainage away from the approaches to the structure.
B. Trash racks shall be cleaned, and any logs or drift lodged against piers and abutments shall be removed without causing damage to the structure. Vegetative debris removed shall be treated as agreed.
C. Debris shall be removed from the bridge deck, and deck drains shall be opened.
a. Loose bolts and nuts shall be tightened.
Page 16 of 17 Salmon River Ranger District
SPECIFICATION T-619 MISCELLANEOUS STRUCTURES
1.1 Maintenance of miscellaneous structures include the maintenance of retaining walls, guard rails, cattleguards, fences, gates, and any other similar structures that have been previously installed to insure the safe and efficient operation of the road.
MATERIALS
2.1 Any materials needed in the maintenance of miscellaneous structures shall be similar in type and quality to he material in the structure being maintained.
REQUIREMENTS
3.1 Guard Rails. Anchors shall be tightened.
3.2 Cattleguards. Tie-in fences shall be sound and secured to the wings. Loose rails shall be welded or bolted back in place. Material deposited into the cattleguard well during operations shall be removed. Drainage into and out of cattleguards shall be maintained.
3.3 Fences. Wire fences shall be tightened if loose. Broken strands of wire or wood railings shall be replaced.
3.4 Gates. Gates shall be properly signed, kept in good repair, and made to swing easily. Hinges or latches shall be repaired if not operating properly. Hinges shall be oiled.
Page 17 of 17 Salmon River Ranger District
SPECIFICATION T-710 TRAFFIC SERVICES
1.1 Traffic service maintenance includes the maintenance of traffic-related regulatory, warning, and directional signs as well as devices such as roadside delineators or markers. It also includes restriping paved surfaces.
MATERIALS
2.1 All sign faces shall be retroflective sheeting. Sign posts shall be treated. Materials for delineators and markers shall be similar to those in the devices being replaced unless in conflict with the Manual on Uniform Traffic Control Devices. Pavement striping shall be retroflective and meet the material requirements of specification 634 in "Forest Service Standard Specifications for Construction of Roads and Bridges."
REQUIREMENTS
3.1 A minimum area six (6) feet in diameter around any traffic sign or device shall be kept free of weeds, brush, and limbs. Greater dimensions may be necessary depending on viewing direction.
3.2 Defaced signs shall be repaired using materials in accordance with the Manual on Uniform Traffic Control Devices.
3.3 All traffic control signs and devices that are replaced shall be installed in accordance with the Manual on Uniform Traffic Control Devices.
3.4 All pavement striping shall conform to attached specifications. Pavement striping shall be required when the existing striping is not readily visible both by day and night.
| C5.31#– ROAD MAINTENANCE REQUIREMENTS. (7/01) Contractor shall maintain roads in accordance with the following Contract Road Maintenance Requirements Summary: |
| C5.221# – MATERIAL SOURCES. (4/04) Sources of local materials are designated on Plans and Sale Area Map. Forest Service assumes responsibility for the quality and quantity of material in designated sources. Contractor shall determine the equipment and... |
| C5.222# - STOCKPILED MATERIAL SOURCES (1/02). Material is appraised from National Forest stockpiles designated on the Sale Area Map. Payment to the Forest Service for such material shall be made prior to removal of any material and at the following ra... |
| C5.314# - DUST ABATEMENT TREATMENT (02/02). When conditions are such that dusting would result in hazardous driving conditions or there would be an appreciable loss of road surface binder material, Contractor shall control such dusting by application... |
| C5.316 – SNOW REMOVAL (4/13). Snow removal shall be done in a manner to preserve and protect the roads, to insure safe and efficient transportation and to prevent unacceptable damage to roads, streams, and adjacent lands. |
| SPECIFICATION T-101 SURFACE BLADING |
| SPECIFICATION T-103 DUST ABATEMENT |
| SPECIFICATION T-108 SLIDE REMOVAL AND SLUMP REPAIR |
| SPECIFICATION T-113 SURFACING REPAIR |
| SPECIFICATION T-301 DITCH CLEANING |
| SPECIFICATION T-310 MINOR DRAINAGE STRUCTURES |
| SPECIFICATION T-506 CLEARING ROADWAY VEGETATION |
| SPECIFICATION T-507 CUTTING ROADSIDE VEGETATION |
| SPECIFICATION T-618 MAJOR DRAINAGE STRUCTURES |