613727 BRAINTREE FAP No. STP/HPP-003S(904)X Reconstruction of Allen Street (MA285)
Solicitation number
BD-27-1030-0H100-0H002-133201
Issued by
Norfolk County, Boston City, Massachusetts

About this file

This is Addendum No. 1 issued by the Massachusetts Department of Transportation (MassDOT) Highway Division on September 16, 2026, for the Braintree Federal Aid Project No. STP/HPP-003S(904)X, which involves the reconstruction of Allen Street (MA285) in Braintree. The addendum transmits revisions to contract documents, including a revised page 2 of Document 00010, deletion and replacement of Document 00813 (4 pages), and insertion of new Document 00875 (2 pages). Bidders must acknowledge Addendum No. 1 in their Expedite Proposal file before submitting bids. The proposal opening is scheduled for Tuesday, October 6, 2026, at 2:00 p.m. The project encompasses approximately 0.54 miles of roadway reconstruction with multiple components including pavement milling and overlay, full-depth asphalt construction, cement concrete sidewalks with ADA-compliant curb ramps, drainage improvements, utility pole relocation involving seven utility providers, sanitary sewer and water main installation, retaining wall work, tree removal and protection, and electrical conduit and lighting installation. The estimated total contract value is $2.847 million, with Substantial Completion required within 665 calendar days and Contractor Completion within 712 calendar days from Notice to Proceed.

Document 00813 establishes price adjustment provisions for structural steel and reinforcing steel based on fluctuations in the U.S. Department of Labor Bureau of Labor Statistics Producer Price Index (PPI Series ID WPU101702), with adjustments applied only when variances between Base Prices and Period Prices exceed 5 percent. Base Prices are fixed and determined by MassDOT, while Period Prices are variable and calculated using the delivery date of materials to the fabricator. Price adjustments are paid separately under designated pay items for both positive adjustments to the contractor and negative adjustments (credits to MassDOT) for both structural and reinforcing steel. Document 00875 establishes trainee special provisions requiring the contractor to provide on-the-job training for four trainees aimed at developing full journeyworkers, with contractors reimbursed at 80 cents per hour of on-the-job training completed. Training priorities include minorities and women trainees, with apprenticeship programs registered with the U.S. Department of Labor or state-recognized apprenticeship agencies considered acceptable. The project is federally aided under STP/HPP funding and subject to prevailing wage requirements, Buy America provisions, and Massachusetts Department of Environmental Protection conditions.

View the file

Other files

File Type Posted
613727 - Notice to Contractors.pdf PDF
613727 - Plan Holders List 9-22-2026.pdf PDF
A00861-613727.pdf PDF
613727 Bid Items.txt TXT text file
A00820-613727.pdf PDF
A00801-613727.pdf PDF
A00808-613727.pdf PDF
A00802-613727.pdf PDF
A00875-613727.pdf PDF
A00844-613727.pdf PDF
A00804-613727.pdf PDF
A00863-613727.pdf PDF
A00860-613727.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ten Park Plaza, Suite 4160, Boston, MA 02116 Tel: 857-368-4636, TTY: 857-368-0655 mass.gov/massdot

September 16, 2026

613727-136651

ADDENDUM NO. 1

To Prospective Bidders and Others on:

BRAINTREE

Federal Aid Project No. STP/HPP-003S(904)X

Reconstruction of Allen Street (MA285)

THIS PROPOSAL TO BE OPENED AND READ: TUESDAY, OCTOBER 6, 2026 at 2:00 P.M.

Transmitting revisions to the Contract Documents as follows:

DOCUMENT 00010:

DOCUMENT 00813:

DOCUMENT 00875:

Revised page 2.

Deleted document in its entirety and inserted new document (4 pages).

Inserted new document (2 pages).

Take note of the above, substitute the revised page for the original, delete the document indicated, insert the new documents in proper order, and acknowledge Addendum No. 1 in your Expedite Proposal file before submitting your bid.

Very truly yours, Eric M. Cardone, P.E.

Construction Contracts Engineer

CS

cc: Yaseen Al Abdullah, Project Manager for

THIS PAGE IS INTENTIONALLY LEFT BLANK

Massachusetts Department Of Transportation Highway Division Proposal No. 613727-136651

00010 - 2

① Addendum No. 1 September 16, 2026 TABLE OF CONTENTS (Continued)

DOCUMENT 00860

COMMONWEALTH OF MASSACHUSETTS PUBLIC EMPLOYMENT LAWS ................ 00860-1 through 2

DOCUMENT 00861

STATE PREVAILING WAGE RATES ............................................................................... 00861-1 through 36

DOCUMENT 00870

STANDARD FEDERAL EQUAL EMPLOYMENT OPPORTUNITY

CONSTRUCTION CONTRACT SPECIFICATIONS ............................................................ 00870-1 through 8

① DOCUMENT 00875

TRAINEE SPECIAL PROVISIONS ...................................................................................... 00875-1 through 2

DOCUMENT 00880

MINIMUM WAGES FOR FEDERAL AND FEDERALLY

ASSISTED CONTRACTS .................................................................................................. 00880-1 through 50

DOCUMENT A00801

SPECIAL PROVISIONS ................................................................................................ A00801-1 through 140

DOCUMENT A00802

DETAIL SHEETS ............................................................................................................ A00802-1 through 10

DOCUMENT A00804

TOWN OF BRAINTREE MASSACHUSETTS WATER AND SEWER DEPARTMENT

RULES, REGULATIONS AND GUIDELINES ............................................................. A00804-1 through 102

DOCUMENT A00808

PROJECT UTILITY COORDINATION FORM ................................................................. A00808-1 through 4

DOCUMENT A00820

REQUEST FOR RELEASE OF MASSDOT AUTOCAD FILES FORM ............................ A00820-1 through 2

DOCUMENT A00844

US FISH AND WILDLIFE SERVICE

NLAA CONCURRENCE VERIFICATION LETTER ...................................................... A00844-1 through 16

DOCUMENT A00860

MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION

NOTICE OF INTENT ...................................................................................................... A00860-1 through 80

DOCUMENT A00861

MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION

ORDER OF CONDITIONS .............................................................................................. A00861-1 through 20

DOCUMENT A00863

THE COMMONWEALTH OF MASSACHUSETTS

OFFICE OF COASTAL ZONE MANAGEMENT (CZM) .................................................. A00863-1 through 4

DOCUMENT A00875

POLICY DIRECTIVE P-22-001 AND POLICY DIRECTIVE P-22-002 ............................. A00875-1 through 8

DOCUMENT B00420

PROPOSAL ..................................................................................................................... B00420-1 through 18

*** END OF DOCUMENT ***

Addendum No. 1, September 16, 2026

00813 - 1

DOCUMENT 00813

SPECIAL PROVISIONS

PRICE ADJUSTMENTS FOR STRUCTURAL STEEL AND REINFORCING STEEL

September 10, 2026

This special provision applies to all projects containing the use of structural steel and/or reinforcing steel as specified elsewhere in the Contract work. It applies to all structural steel and all reinforcing steel, as defined below, on the project. Compliance with this provision is mandatory, i.e., there are no “opt-in” or “opt-out” clauses. Price adjustments will be handled as described below and shall only apply to unfabricated reinforcing steel bars and unfabricated structural steel material, consisting of rolled shapes, plate steel, sheet piling, pipe piles, steel castings and steel forgings.

Price adjustments will be variances between Base Prices and Period Prices. Base Prices and Period Prices are defined below.

Price adjustments will only be made if the variances between Base Prices and Period Prices are 5% or more. A variance can result in the Period Price being either higher or lower than the Base Price. Once the 5% threshold has been achieved, the adjustment will apply to the full variance between the Base Price and the Period Price.

Price adjustments will be calculated by multiplying the number of pounds of unfabricated structural steel material or unfabricated reinforcing steel bars on a project by the index factor calculated as shown below under Example of a Period Price Calculation.

Price adjustments will not include guardrail panels or the costs of shop drawing preparation, handling, fabrication, coatings, transportation, storage, installation, profit, overhead, fuel costs, fuel surcharges, or other such charges not related to the cost of the unfabricated structural steel and unfabricated reinforcing steel.

The weight of steel subject to a price adjustment shall not exceed the final shipping weight of the fabricated part by more than 10%.

Base Prices and Period Prices are defined as follows:

Base Prices of unfabricated structural steel and unfabricated reinforcing steel on a project are fixed prices determined by the Department and found in the table below. While it is the intention of the Department to make this table comprehensive, some of a project’s unfabricated structural steel and/or unfabricated reinforcing steel may be inadvertently omitted. Should this occur, the Contractor shall bring the omission to the Department’s attention so that a contract alteration may be processed that adds the missing steel to the table and its price adjustments to the Contract.

The Base Price Date is the month and year of the most recent finalized period price index at the time that MassDOT opened bids for the project. The Base Price Index for this contract is the Steel PPI listed in the Notice to Contractors.

Period Prices of unfabricated structural steel and unfabricated reinforcing steel on a project are variable prices that have been calculated using the Period Price Date and an index of steel prices to adjust the Base Price.

The Period Price Date is the date the steel was delivered to the fabricator as evidenced by an official bill of lading submitted to the Department containing a description of the shipped materials, weights of the shipped materials and the date of shipment. This date is used to select the Period Price Index.

The index used for the calculation of Period Prices is the U.S. Department of Labor Bureau of Labor Statistics Producer Price Index (PPI) Series ID WPU101702 (Not Seasonally Adjusted, Group: Metals and Metal Products, Item: Semi-finished Steel Mill Products.) As this index is subject to revision for a period of up to four (4) months after its original publication, no price adjustments will be made until the index for the period is finalized, i.e., the index is no longer suffixed with a “(P)”.

Addendum No. 1, September 16, 2026

00813 - 2

Period Prices are determined as follows:

Period Price = Base Price X Index Factor Index Factor = Period Price Index / Base Price Index

Example of a Period Price Calculation:

Calculate the Period Price for December 2009 using a Base Price from March 2009 of $0.82/Pound for 1,000 Pounds of ASTM A709 (AASHTO M270) Grade A36 Structural Steel Plate.

The Period Price Date is December 2009. From the PPI website*, the Period Price Index = 218.0.

The Base Price Date is March 2009. From the PPI website*, the Base Price Index = 229.4.

Index Factor = Period Price Index / Base Price Index = 218.0 / 229.4 = 0.950 Period Price = Base Price X Index Factor = $0.82/Pound X 0.950 = $0.78/Pound

Since $0.82 - $0.78 = $0.04 is less than 5% of $0.82, no price adjustment is required.

If the $0.04 difference shown above was greater than 5% of the Base Price, then the price adjustment would be 1,000 Pounds X $0.04/Pound = $40.00. Since the Period Price of $0.78/Pound is less than the Base Price of $0.82/Pound, indicating a drop in the price of steel between the bid and the delivery of material, a credit of $40.00 would be owed to MassDOT. When the Period Price is higher than the Base Price, the price adjustment is owed to the Contractor.

* To access the PPI website and obtain a Base Price Index or a Period Price Index, go to http://data.bls.gov/cgi-bin/srgate

End of example.

The Contractor will be paid for unfabricated structural steel and unfabricated reinforcing steel under the respective contract pay items for all components constructed of either structural steel or reinforced Portland cement concrete under their respective Contract Pay Items.

Price adjustments, as herein provided for, will be paid separately as follows:

Structural Steel Pay Item Number 999.449 for positive (+) pay adjustments (payments to the Contractor)

Pay Item Number 999.457 for negative (-) pay adjustments (credits to MassDOT Highway Division)

Reinforcing Steel Pay Item Number 999.466 for positive (+) pay adjustments (payments to the Contractor)

Pay Item Number 999.467 for negative (-) pay adjustments (credits to MassDOT Highway Division)

No price adjustment will be made for price changes after the Contract Completion Date, unless the MassDOT Highway Division has approved an extension of Contract Time for the Contract.

Addendum No. 1, September 16, 2026

00813 - 3

TABLE

Price per Steel Type Pound

1 ASTM A615/A615M Grade 60 (AASHTO M31 Grade 60 or 420) Reinforcing Steel $0.59

2 ASTM A27 (AASHTO M103) Steel Castings, H-Pile Points & Pipe Pile Shoes (See Note below.)

$0.83

3 ASTM A668 / A668M (AASHTO M102) Steel Forgings $0.83

4 ASTM A108 (AASHTO M169) Steel Forgings for Shear Studs $0.85

5 ASTM A709/A709M Grade 36 / AASHTO M270M/M270 Grade 36 or 250 Structural Steel Plate

$0.89

6 ASTM A709/A709M Grade 36 / AASHTO M270M/M270 Grade 36 or 250 Structural Steel Shapes

$0.84

7 ASTM A709/A709M Grade 50 / AASHTO M270M/M270 Grade 50 or 345 Structural Steel Plate

$0.89

8 ASTM A709/A709M Grade 50 / AASHTO M270M/M270 Grade 50 or 345 Structural Steel Shapes

$0.84

9 ASTM A709/A709M Grade 50WT / AASHTO M270M/M270 Grade 50WT or 345WT Structural Steel Plate

$0.92

10 ASTM A709/A709M Grade 50WT / AASHTO M270M/M270 Grade 50WT or 345WT Structural Steel Shapes

$0.85

11 ASTM A709/A709M Grade 50W / AASHTO M270M/M270 Grade 50W 345W Structural Steel Plate

$0.92

12 ASTM A709/A709M Grade 50W / AASHTO M270M/M270 Grade 50W or 345W Structural Steel Shapes

$0.85

13 ASTM A709/A709M Grade HPS 50W / AASHTO M270M/M270 Grade HPS 50W or 345W Structural Steel Plate

$0.97

14 ASTM A709/A709M Grade HPS 70W / AASHTO M270M/M270 Grade HPS 70W or 485W Structural Steel Plate

$1.04

15 ASTM A514/A514M-05 Grade HPS 100W / AASHTO M270M/M270 Grade HPS 100W or 690W Structural Steel Plate

$1.59

16 ASTM A992/A992M Grade 50S / AASHTO M270M/M270 Grade 50S or 345S Structural Steel Plate

$0.92

17 ASTM A992/A992M Grade 50S / AASHTO M270M/M270 Grade 50S or 345S Structural Steel Shapes

$0.85

18 ASTM A276 Type 316 Stainless Steel $4.78 19 ASTM A240 Type 316 Stainless Steel $4.78 20 ASTM A148 Grade 80/50 Steel Castings (See Note below.) $1.64 21 ASTM A53 Grade B Structural Steel Pipe $1.04 22 ASTM A500 Grades A, B, 36 & 50 Structural Steel Pipe $1.04 23 ASTM A252, Grades 240 (36 KSI) & 414 (60 KSI) Pipe Pile $0.83 24 ASTM 252, Grade 2 Permanent Steel Casing $0.83 25 ASTM A36 (AASHTO M183) for H-piles, steel supports and sign supports $0.87 26 ASTM A328 / A328M, Grade 50 (AASHTO M202) Steel Sheetpiling $1.57 27 ASTM A572 / A572M, Grade 50 Sheetpiling $1.57 28 ASTM A36/36M, Grade 50 $0.89 29 ASTM A570, Grade 50 $0.87 30 ASTM A572 (AASHTO M223), Grade 50 H-Piles $0.89 31 ASTM A1085 Grade A (50 KSI) Steel Hollow Structural Sections (HSS), heat-treated per

ASTM A1085 Supplement S1 $1.04

32 AREA 140 LB Rail and Track Accessories $0.54 NOTE: Steel Castings are generally used only on moveable bridges. Cast iron frames, grates and pipe are not “steel” castings and will not be considered for price adjustments.

END OF DOCUMENT

Addendum No. 1, September 16, 2026

00813 - 4

THIS PAGE IS INTENTIONALLY LEFT BLANK

Addendum No. 1, September 16, 2026

00875 - 1

DOCUMENT 00875

TRAINEE SPECIAL PROVISIONS

Revised October, 2016

THE REQUIRED NUMBER OF TRAINEES TO BE TRAINED UNDER THIS CONTRACT WILL BE 4

The contractor shall provide on-the job training aimed at developing full journeyworkers in the type of trade of job classification involved.

In the event that a contractor subcontracts a portion of the contract work, the General Contractor shall determine how many, if any, of the trainees are to be trained by the subcontractor, provided, however, that the contractor shall retain the primary responsibility for meeting the training requirements imposed by this special provision. The contractor shall also insure that this training special provision is made applicable to such subcontract. Where feasible, 25 percent of apprentices or trainees in each occupation shall be in their first year of apprenticeship or training.

The number of trainees shall be distributed among the work classifications on the basis of the contractor's needs and the availability of journeyworkers in the various classifications within a reasonable area of recruitment. Prior to commencing construction, the contractor shall submit to the Massachusetts Department Of Transportation (MassDOT) for approval the number of trainees to be trained in each selected classification and training program to be used. Furthermore, the contractor shall specify the starting time for training in each of the classifications. The contractor will be credited for each trainee employed on the contract work who is currently enrolled or becomes enrolled in an approved program and will be reimbursed for such trainees as provided hereinafter.

Training and upgrading of minorities and women toward journeyworker status is a primary objective of the Training Special Provision. Accordingly, the contractor shall make every effort to enroll minority and women trainees (e.g., by conducting systematic and direct recruitment through public and private sources likely to yield minority and women trainees) to the extent that such persons are available within a reasonable area of recruitment. The contractor will be responsible for demonstrating the steps that have been taken in pursuance thereof, prior to a determination as to whether the contractor is in compliance with this Training Special Provision. This training commitment is not intended, and shall not be used, to discriminate against any applicant for training.

No employee shall be trained under this Special Provision in any classification in which he or she has successfully completed a training course leading to journeyworker status or in which he or she has been employed as a journeyworker. The contractor should satisfy this requirement by including appropriate questions in the employee application or by other suitable means. Regardless of the method used the contractor's records should document the finding in each case.

The minimum length and type of training for each classification will be as established in the training program selected by the contractor and approved by the Massachusetts Department Of Transportation and the Federal Highway Administration. The Massachusetts Department Of Transportation and the Federal Highway Administration shall approve a program if it is reasonably calculated to meet the equal employment opportunity obligations of the contractor and to qualify the average trainee for journeyworker status in the classification concerned by the end of the training period. Furthermore, apprenticeship programs registered with the U.S.

Department of Labor, Bureau of Apprenticeship and Training, or with a State apprenticeship agency recognized by the Bureau and training programs approved but not necessarily sponsored by the U.S. Department of Labor, Manpower Administration, Bureau of Apprenticeship and Training shall also be considered acceptable provided it is being administered in a manner consistent with the equal employment obligations of Federal-aid highway construction contracts. Approval or acceptance of a training program shall be obtained from the State prior to commencing work on the classification covered by the program. It is the intention of these provisions that training is to be provided in the construction crafts rather that clerk-typist or secretarial-type positions. Training is permissible in lower level management positions such as office engineers, estimators, timekeepers, etc. where the training is oriented toward construction applications. Training in the laborer classification may be permitted provided that significant and meaningful training is provided and approved by the Federal Highway Administration division office. Some offsite training is permissible as long as the training is an integral part of an approved training program and does not comprise a significant part of the overall training.

Addendum No. 1, September 16, 2026

00875 - 2

Reimbursement

Under these Training Special Provisions, reimbursement will be as follows:

The Contractor will only be reimbursed 80 cents for each hour of on the job training as specified in the approved Training Program.

The Contractor is advised and encouraged that it may train additional persons in excess of the number specified and will be reimbursed as stated above. Reimbursement will be made even though the contractor receives additional training program funds from other sources, provided such other source does not specifically prohibit the contractor from receiving other reimbursement.

If less than full training specified in the approved training programs is provided, payment to the contractor will be made at a rate of 80 cents for each hour of training completed under this contract. However, no payment shall be made to the contractor if either the failure to provide the required training, or the failure to hire the trainee as a journeyworker, is caused by the contractor and evidences a lack of good faith on the part of the contractor in meeting the requirements of this Training Special Provision.

Payment

Trainees will be paid:

1. Percentage (%) of the journeyworker's rate as provided in the existing programs approved by the Department of Labor or Transportation as of September 15, 1970.

2. For journeyworker programs submitted by the Contractor and approved by Massachusetts Department Of

Transportation and the Federal Highway Administration at least 60 percent of the appropriate minimum journeyworker's rate specified in the contract for the first half of the training period, 75 percent for the third quarter if the training period, and 90 percent for the last quarter of the training period.

3. For skilled laborer programs, the minimum starting wage rate of unskilled laborer. At the conclusion of training, he or she will be paid the minimum wage rate of the Classification for programs submitted by the Contractor and approved by the Massachusetts Department Of Transportation and the Federal Highway Administration.

4. For the purposes of meeting the legal requirements of State Prevailing Wage Law, please be advised that no person may be paid the Apprentice wage rate as listed on a MA Prevailing Wage Rates schedule, unless that person and program is registered with the Department of Labor Standards/Division of Apprentice Standards (DLS/DAS). Any person or program not registered with DLS/DAS, regardless of whether or not they are registered with any other federal, state, local, or private entity must be paid the journeyworker’s rate for the trade.

The contractor shall provide each trainee with a certification showing the type and length of training satisfactorily complete.

The contractor will provide for the maintenance of records and furnish periodic reports documenting his performance under this Training Special Provision.

Form FHWA-1409, Federal-aid Highway Construction Contracting Semi Annual Training Report, shall be submitted as per instructions on the Form.

*** END OF DOCUMENT ***

Addendum Letter-A1
00010 TOC - 7-16-26-A1
00813 Steel Price Adj. w Base Prices 09-10-2026-A1
00875 FED Trainee 10-27-16-A1
DOCUMENT 00875
TRAINEE SPECIAL PROVISIONS
Reimbursement