A00808-613727.pdf
PDF 2 MB Posted
- Solicitation number
- BD-27-1030-0H100-0H002-133201
- Issued by
- Norfolk County, Boston City, Massachusetts
About this file
This is a Project Utility Coordination Form submitted by the Massachusetts Department of Transportation Highway Division for Proposal No. 613727-136651, detailing utility relocation requirements for the reconstruction of Allen Street (MA285) in Braintree, Massachusetts. The project involves coordinating relocations for seven utility poles and related infrastructure managed by multiple utility providers including Braintree Electric Light Department (BELD), Comcast, Verizon, National Grid Gas, Enbridge, AT&T, Eversource Gas, MWRA Sewer, and others. The utility coordination work is organized into nine sequential tasks spanning two phases, with estimated durations totaling approximately 92 work days for utility operations excluding lead times. Key activities include temporary fiber relocation, pole repositioning, conduit system installation, guy wire installation for utility pole #7, and final utility structure adjustments. The contractor must provide seven calendar days advance notification to the District Construction Office to enable 30 days advance notice-to-proceed for each utility relocation sequence, with the scheduled advertisement date of August 15, 2026.
The contractor is responsible for all enabling work including site preparation, environmental controls, digsafe marking, and providing safe unimpeded access to utilities for trucks, lifts, and cranes. Seasonal restrictions apply to gas line work, which cannot be installed between November 15 and April 15, with the same restrictions applying to municipally owned electric and gas utilities. The form identifies specific utilities working concurrently on-site and notes that BELD requires 30 days advance notice for utility disconnections. Special provisions address potential access restraints, contractor coordination responsibilities, and the integration of utility work into the project's baseline schedule, with all costs associated with access provision deemed incidental to the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 613727 - Notice to Contractors.pdf | ||
| 613727 - Plan Holders List 9-22-2026.pdf | ||
| A00861-613727.pdf | ||
| 613727 Bid Items.txt | TXT text file | |
| A00820-613727.pdf | ||
| A00801-613727.pdf | ||
| A00802-613727.pdf | ||
| A00875-613727.pdf | ||
| A00844-613727.pdf | ||
| A00804-613727.pdf | ||
| BRAINTREE-613727-136651-A-1.pdf | ||
| A00863-613727.pdf | ||
| A00860-613727.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Massachusetts Department Of Transportation Highway Division Proposal No. 613727-136651
A00808 - 1
DOCUMENT A00808
PROJECT UTILITY COORDINATION FORM
Massachusetts Department Of Transportation Highway Division
A00808 - 2
THIS PAGE IS INTENTIONALLY LEFT BLANK
7/20/2026
Revision
Date:
Mass DOT PM: Total Poles Relocated: 7/23/2026
PRINTED
Yes No Agreement YES NO YES NO UG OH
Braintree Electric Light Dept
Darron MacDonald David McGillicuddy
Dan Ohlman RJ O'Neill
781-348-1072 781-348-1070 781-964-6207 617-653-8397 dmacdonald@beld.com dmcgillicuddy@beld.com dohlman@beld.com roneill@beld.com x x x x x x
Comcast Michael Cook
Patrick MacAllister Jeff Machado
508-962-3873
Michael_Cook7@comcast.com patrick_macallister@cable.comcast.com Jeff_Machado@comcast.com x x x x x x
Verizon Stacey Manseau
Eugene Butterfield 978-501-3967 781-917-2054 smanseau@pike.com eugene.butterfield.jr@verizon.com x x x x x x
Braintree Fire alarm Frederick Warren 781-843-3600 wfrederick@braintreema.gov x x x x
National Grid Gas Melissa Owens Katherine Joy
781-907-2845 781–864–8219 melissa.owens@nationalgrid.com Katherine.Joy@nationalgrid.com x x x
Enbridge Kathleen Aruda 508-938-7728 Kathleen.Aruda@enbridge.com x x x
Braintree DPW Water & Sewer
Braintree DPW Mark Thompson
781-843-8097 781-831-4058 mthompson@braintreema.gov x x x
Zayo (Formerly Crown
Castle) Mark Vegnani mark.vegnani@crowncastle.com
AT&T
Erica Hudson Bob Jordan
781-221-8400 erica.hudson@sienaengineeringgroup.com bob.jordan@sienaengineeringgroup.com
Braintree DPW - Engineering
Ryan Matheson rmatheson@braintreema.gov
MCI - Verizon Business
Stephen Parretti Kewsi King
Tremain Fernandes
508-248-1305 stephen.parretti@verizon.com kwesi.king@verizon.com tremain.k.fernandes@verizon.com
Eversource Gas Brendan Pitts (508) 895-4818 brendan.pitts@eversource.com
MWRA Sewer Kevin McKenna (617) 305-5956 kevin.mckenna@mwra.com
Extenet Chad Wagner 617-529-0973 cwagner1@extenetsystems.com
Verizon small cell Elizabeth Glidden
Sean Conway elizabeth.glidden@vzw.com sean.conway@verizonwireless.com
MBTA Archives Sylvia Welsh archives@mbta.com
Suggested Sequence of Relocation ( Based on Consultant proposed construction staging)
2026-01-23 No Facilities
Consultant: Contact: Office # Cell #
The sequence as detailed on the following pages is based on the consultants proposed staging plan. This information was compiled through meetings that included all of the utilities listed below along with the designer and the Braintree. The information provided is the best available information prior to project advertisement.
Utility Relocation Notes for MassDOT Contractor Unless otherwise noted by Contract, the MassDOT Contractor is to provide the District Construction Office with 7 Calendar Days advance notification in order to validate the current progress and provide the required 30 Days advance notice-to-proceed for the first Utility - and each subsequent Utility. These advance notifications are to be identified in the Contractor's Schedules (Pre-Con preparation, Baseline, Subnets, and Updated/Monthly Schedules) as specified in Subsection 8.02 (for DBB Contracts) and/or Section 9 (of DB Contracts). Note: The durations included below do not include these lead-times. See Additional 'Important Basis notes for Contractor' - on last PUC Form page.
Additional notes:
1/28/26 Mark V says Crown castle does not own fiber and they belong to BELD
2026-01-28 No Facilities
2024-10-03 No Facilities
Office # Cell # Email
PARE Greg Berube
Utility Company Contact
RECONSTRUCTION OF ALLEN STREET (MA285) TBD Thomas Currier 8/15/2026
Braintree 613727 Elijah Doubleday Braintree Electric Light/ Verizon Route/Street: Resident Engineer: Scheduled Ad Date:
City/Town: PUC Completed by:Project File #: Utility Pole Set:
CONTACTS AND GENERAL UTILITY INFORMATION
Project Utilities Coordination (PUC) Form
Scope, Budget, Duration Submitted Reimbursement
Non-Reimb'le Notes gberube@parecorp.com401-414-5237 401-480-3519
2024-10-03 No Facilities
Utilities On Bridge/Structure
6/12/26 ED reaches out 7/1/26 No response, presume no conflict
High pressure gas main under Shaw Street.
Notify Enbridge when working in area as they may want to have a representative on-site when working near their main.
Water main abandoned on south side of Allen Street.
Verizon bottom wire on poles.
Has riser on UP 1 and up 2 they will be relocating under their force account.
Gate valve and gas service potentially in moment slab. Contact Ngrid gas Katherine Joy to relocate if necessary.
No Facilities or No Conflicts
Contractor must notify BELD when contruction will begin at NTP.
BELD to pull wires, set poles, transfer cobra head lights, transfer wires, remove poles, and run wires into new conduit system.
Poles will be placed on active road initially and will require protection.
Guy anchor for utility pole #7 to be installed prior to moment slab contruction and guy wire for utility pole #7 to be installed after moment slab construction.
For Information Only
BELD to de-commission old fire alarm system
Prior to this project Comcast to run new OHW fiber coming from west of project and terminating at UP 2.
Comcast to install riser and HH within sidewalk on UP 2.
Comcast will perform work to relocate riser as part of their FA work.
1/15/26 Erica Hudson says AT&T has leased fiber in cable owned by crown castle
Utilities Underground (UG)
/Aerial (OH)
Potential for District Initiated Early Relocation *
A00808 - 3
Is 'enabling' (prep) work, by the Contractor, necessary prior to the start of the first series of utility relocations: Yes No 7/23/2026 x Project File #: 613727 PRINTED
Has any of the Utility work been identified to work concurrently Yes No City/Town: Braintree x Route/Street: RECONSTRUCTION OF ALLEN STREET (MA285)
Exclusive Utility on site
Concurrent Utilities
Contractor Off-Site
Contractor Concurrent
C
Co nt ra ct or U
U til ity
C o.
U til ity w or ki ng w ith n o ot he r
U til iti es in v ic in ity
U til ity w or ki ng w ith o th er
U til iti es on si te
N o
Co nt ra ct or p hy si ca l c on st ru ct io n op er at io ns o n-si te (w hi le
U til ity is w or ki ng
Co nt ra ct or a nd U til ity a re w or ki ng on
-s ite bu t N O
T in th e sa m e vi ci ni ty
Stage : 1 Phase : A
UTILITY OPERATIONS - Temporary BELD fiber relocation Task: 1 Braintree Electric & Lighting Department
U 3 X X NO
Sub-Total 3
UTILITY OPERATIONS - Pole relocations Task: 2 Braintree Electric & Lighting Department
C C U
U 8 X X NO
U 1 X X NO DUCE Estimate
U 3 X X NO
C
Task: 3 Comcast
U 1 X X NO
U 1 X X NO
U 1 X X NO
U 1 X X NO
U 1 X X NO
U 1 X X NO
Task: 4 Verizon
U 2 X X NO
U 4 X X NO
U 3 X X NO
U 23 X X NO
U 19 X X NO
U 1 X X NO
Task: 5 Braintree Electric & Lighting Department
7 X X NO DUCE Estimate
UTILITY OPERATIONS - BELD Conduit System Task: 6 Braintree Electric & Lighting Department
C
U 3 X X NO
UTILITY OPERATIONS - Guy wire moment slab solution
Task: 7 Braintree Electric & Lighting Department C
U 1 X X NO DUCE Estimate
Task: 8 Verizon U 1 X X NO DUCE Estimate
UTILITY OPERATIONS - Adjustment utility structures for final paving
Task: 9 National Grid Gas
U X X NO
U X X NO
IMPORTANT BASIS NOTES - FOR CONTRACTOR
Enabling' work by the Contractor - Prep site (clearing, grubbing, guard rail removal) as required. Contractor will also install project environmental controls (hay bales, silt fence, etc.) as required per the project plans prior to the start of any work. Digsafe paint and pole markout with proposed curb marked out.
Pre-Walk with all utilities, DE, DURE, RE, and Contractor.
"Concurrent Utilities" operations noted herein, are to signify those Utility Company operations that can be worked concurrently (e.g. Utility A and Utility B work on-site together) - MassDOT and the Contractor are to prepare NTPs to Utilities accordingly.
Sub-Total
VZ contractor to relocate conduit risers VZ Line to place strand and guying VZ Line to place new cables VZ Splice to cut over cables and terminals VZ Line to transfer/remove cables and terminals
'Enabling' work by contractor - set grade at utility pole #15
** Assumed Duration, Not Provided By Utility Company.
Unless otherwise specified in the MassDOT Construction Contract, or unless specifically noted within this PUC Form, these durations (herein) are based upon the Contractor providing unimpeded access to the Utility company to perform Utility relocations (see Note 5 - Access).
Access - Unless otherwise noted in the Contract, and in addition to the 'enabling' notes above, the Contractor must provide safe and unimpeded access (for trucks, lifts, cranes, etc.) to the Utilities, to allow for the proposed relocation(s) - including but not limited to snow removal, clearing and grubbing, guard rail removal, barrier removal, tree removal, and grading. Any costs associated with these tasks are deemed to be incidental to the project.
For all MassDOT construction contracts issued after January 2014, the new Utility Coordination/documentation specification is required. This is Section 8.14 in Design-Bid-Build Contracts (see Design-Build index reference for applicable section #).
Prior to starting any and all enabling work for Utilities, the Contractor is to plan in advance with submittals and approved durations.
* Potential District Initiated Early Utility Relocation - if noted herein, the District reserves the right to initiate early utility relocation in advance of the Contract NTP. In submitting a bid price and in the development/basis of the Baseline Schedule, the Contractor shall not plan the Work with the potential benefit of any form of 'early utility relocation.' As a requirement of the Baseline submission, unless otherwise noted in this Specification, the earliest that the first Utility company is to receive the 30 days advance notification to mobilize to the site, will be 7 calendar days after the pre-construction meeting and never sooner than 7 days after the Contract NTP.
RE
SP
O N
SI
BL
E
PA
RT
Y Concurrent / Exclusive Utility Work
Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.
Access Restraint & Limitations of Operations Notes
Should an AR be considered for the Contractor ?
Po te nt ia l A cc es s R es tr ai nt
(Y es
/N o)
Re as on /N ot e
(o pt io na l)
DESCRIPTION - Utility Relocation Phases, Tasks and Activities
Es tim at ed
D ur at io n (W or k
D ay
s) b y U til iti es (L ea d tim e no t in cl ud ed
PUC FORM - CONTINUED
"Potential Access Restraints" noted within this PUC Form are for planning purposes. See MassDOT Contract for Contractual Access Restraints (refer to Subsections 8.02, 8.03, and/or 8.06 for Design Bid Build Contracts and Volume II Section 9 for Design Build Contracts).
Utility non-work periods - For planning purposes, the durations above contain some non work days (contingency) for New England conditions (precipitation, high temperatures, low temperatures, snow, ice). Gas line work however, typically has a seasonal restriction and can NOT be installed from 15-November to 15-April. Municipally Owned Electric and Gas Utilities are also restricted from proceeding from 15-November to 15-April. The Contractor shall (and the CTD plan) reflect this calendar restriction within the schedule (unless otherwise note).
BELD UG - Removal and temporary relocation and splicing of existing UG Fiber Optic Network
**BELD - 30 day heads up for utility disconections BELD OH to install 7 new poles. Move primary,secondary transformet and re-attach secondary's to dwellings.
**BELD Place guy anchor for utility pole #7 BELD UG to DEMO and de-commission old fire alarm system and re-pipe and feed the bridge street lights.
'Enabling' work by the Contractor - Protect Utility poles on roadway
Sub-Total
Frame poles, construct support strand Pull + lash coax Splice +activate coax Delash + swing fiber Lash fiber Wreckout old plant, remove from old poles
VZ Line to remove guying Sub-Total
** BELD - Remove existing utility poles Sub-Total
'Enabling' work by the Contractor - Complete new conduit system BELD UG - Replacement in Kind of the temporary relocated UG Fiber Optic Network
Sub-Total
'Enabling' work by the Contractor - Complete Moment Slab ** BELD - Install Guy wire for utilty pole #7 to previously installed guy anchor.
Sub-Total
** VZ - Install Guy wire for utilty pole #7 to previously installed guy anchor.
Sub-Total
Verizon National Grid Gas
Sub-Total
A00808 - 4