This is a bid package for a construction project issued by the San Bernardino County Department of Public Works - Special Districts for the drilling and development of a new non-potable irrigation well at Prado Regional Park, located at 16700 Euclid Avenue in Chino, California (Project No. 30.30.0200). The scope of work encompasses mobilization and site preparation, drilling a 42-inch conductor borehole to 52 feet and a 17.5-inch pilot borehole to 515 feet, installing stainless steel casing and well screen, gravel packing, developing the well through surging and pumping, performing aquifer testing including step-drawdown and constant rate tests, conducting geophysical surveys and video inspections, and managing drill cuttings and wastewater disposal. The bid package contains 28 line items with quantities specified for each component. A mandatory pre-bid meeting is scheduled for September 15, 2026, at 10:30 AM at the project site, with attendance required for bid responsiveness. Bids are due on October 8, 2026, at 2:30 PM and will be opened virtually via GoToMeeting. The contract will be awarded to the lowest responsive and responsible bidder, with a project completion deadline of 120 calendar days from the Notice to Proceed.
Bidders must submit a bid bond or certified check equal to ten percent of the total base bid price and must possess a valid California Class A or C contractor's license. All bidders and subcontractors must be registered with the California Department of Industrial Relations prior to bid submission and must remain registered throughout contract performance. The project is subject to prevailing wage requirements established by the California Department of Industrial Relations, and contractors must comply with California Air Resources Board (CARB) In-Use Off-Road Diesel-Fueled Fleet regulations. The successful bidder must furnish performance and payment bonds each equal to 100 percent of the contract sum within ten calendar days of award. Liquidated damages are set at $1,200 per calendar day for work not completed within the 120-calendar-day contract period. Progress payments will not exceed 95 percent of the total contract value, with final payment processed 60 calendar days after filing of the Notice of Completion. Bids must remain valid for 60 days following the bid opening date, and the County reserves the right to reject any or all bids.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID REQUIREMENTS, CONTRACT DOCUMENTS,
GENERAL AND SPECIAL CONDITIONS,
TECHNICAL SPECIFICATIONS AND PROJECT PLANS
FOR THE
Prado Regional Park Drilling New Irrigation Well
FOR
16700 Euclid Ave, Chino, CA 91708
PROJECT NO.: 30.30.0200
SAN BERNARDINO COUNTY
DEPARTMENT OF PUBLIC WORKS - SPECIAL DISTRICTS
222 WEST HOSPITALITY LANE, 2
nd FLOOR
SAN BERNARDINO, CALIFORNIA 92415-0450
DATE: 10/08/2026
BID REQUIREMENTS, CONTRACT DOCUMENTS,
GENERAL AND SPECIAL CONDITIONS,
TECHNICAL SPECIFICATIONS AND PROJECT PLANS
FOR THE
Submitted By: Ashton Daneshmayeh, Project Manager Department of Public Works - Special Districts
Reviewed By: Mauricio Rodriguiez, Senior Project Manager
Approved By: David Doublet, Assistant Director
Approved as to form:
Approved By: Sophie Curtis, Deputy County Counsel
Contract Compliance Review:
Reviewed By: Noel Mondragon, Division Manager
TABLE OF CONTENTS
A. BIDDING REQUIREMENTS PAGE
Advertisement for Bid AB-1-2 Instructions to Bidders IB-1-11 Bidder Information Form BIF 1-7 Bid Proposal BP-1-9 Bid Bond Security Form BS-1 Non-Collusion Declaration NC-1 Contractor Certification CARB In-Use Off-Road Diesel Fueled Fleet Certification of Compliance CCC-1 List of Subcontractors Form SFC-1-2 Iran Contracting Act Certification ICC-1
B. CONTRACT AGREEMENTS AND BONDS
Sample Construction Contract Contract-1-38 Performance Bond PB-1-3 Payment Bond PLB-1-2 Contractor’s Affidavit and Final Release CAR-1
C. PREVAILING WAGES
D. GENERAL CONDITIONS (PROVISIONS)
E. SPECIAL CONDITIONS
F. TECHNICAL SPECIFICATIONS
G. CONTRACT DRAWINGS
H. GEOTECHNICAL REPORT
SECTION A
BIDDING REQUIREMENTS
Prado Regional Park Drilling New Irrigation Well
PROJECT NO.: 30.30.0200
Rev. 2/2026 Advertisement for Bids for County Projects – AB- 1
ADVERTISEMENT FOR BIDS
FOR PRADO REGIONAL PARK DRILLING NEW IRRIGATION WELL
Notice is hereby given that the Department of Public Works – Special Districts (Department), on behalf of the Board of Supervisors for San Bernardino County (County), will receive sealed bids for the Prado Regional Park Drilling New Irrigation Well on or before October 8, 2026 at 2:30PM at their office at 222 W. Hospitality Lane, 2nd Floor, San Bernardino, California, 92415-0450, at which time the bids will be opened [Virtual and In person] Bids received after this time will be returned unopened. Bids shall be valid for 60 calendar days after the bid opening date.
SCOPE OF WORK: The work consists of drilling and developing a new non-potable irrigation well within Prado Regional Park, located at 16700 Euclid Avenue in Chino, California. The Contractor shall provide all labor, materials, equipment, tools, and incidentals necessary to complete the drilling and development operations in accordance with the plans, specifications, and contract documents. Work includes mobilizing and preparing the site, installing temporary safety measures, drilling the well bore with conductor casing, maintaining a clean work area, collecting drill cuttings, and coordinating continuous lithologic and geologic logging with County staff. After drilling, the Contractor will conduct aquifer testing—such as water level measurements, water quality sampling, and limited pumping tests—and then fully develop the well using approved mechanical or pumping methods until production and water clarity meet specifications. The Contractor must manage purge water, assist with regulatory sampling, and comply with all environmental requirements related to dust, noise, stormwater, and waste disposal.
Bids can be submitted through the County Electronic Procurement Network (ePro) at ePro -
/view/login/login.xhtml (however, if the bid is submitted in ePro, the bidder’s security described herein must still be submitted in person in a sealed envelope prior to the proposal opening date and time) or in person at the Department. If the bid is submitted through ePro, the bidder acknowledges that its electronic signature is legally binding. All bidders must register with the ePro system prior to the date and time to receive sealed bids or they will be disqualified. Late or incomplete bids will be considered nonresponsive. A “complete” bid is defined as a bidder’s submittal that includes all bid documents (i.e., the bid / proposal, bidder’s security in a separately sealed envelope, and any other bid documents required for the project). System-related issues in ePro shall be directed to Vendor support at ePro.Vendors@buyspeed.com or at (855) 800-5046. For procurement questions involving ePro, please contact the Purchasing Department at (909) 387·2060.
PLEASE NOTE: All bidders and subcontractors must be registered with 1) the Department of Industrial Relations (with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)); and 2) the County’s ePro system prior to the date and time to receive sealed proposals or they will be disqualified. The lowest responsive and responsible bidder and its subcontractors must also be registered with the Department of Industrial Relations at the time of award of the contract and must remain registered throughout the term of the contract pursuant to Labor Code section 1771.1. For more information on the requirements of Labor Code section 1771.1, please see SB 854 – Important Information for Awarding Bodies.
https://epro.sbcounty.gov/bso/view/login/login.xhtml https://www.dir.ca.gov/Public-Works/SB854.html
Rev. 2/2026 Advertisement for Bids for County Projects – AB- 2
A Mandatory Pre-bid meeting will start at September 15 ,2026; 10:30 am at the project site located at 16700 Euclid Ave, Chino, California 91708. BIDS SUBMITTED BY FIRMS NOT
ATTENDING THE MANDATORY PRE-BID MEETING WILL BE REJECTED AS
NONRESPONSIVE.
Each bidder shall be a licensed contractor pursuant to the Business and Professions Code and shall be licensed in the following classification of contractor’s license, for the work bid upon, and must maintain the license throughout the duration of the contract: California Class A or C Contractor’s License. In order to be deemed responsive, the bidder must list, in the bid forms, at least three (3) projects of similar size and scope that it has completed over the last five years.
The Bid Documents, including final Plans and Specifications, are available at no cost to the bidder from the ePRO Website at ePro - /view/login/login.xhtml.
This Project is subject to California Prevailing Wage requirements. Copies of the prevailing wage rates are on file at the Department and shall be made available to any interested party on request.
Copies are also included in the Bid Documents. A copy of these rates shall be posted by the successful bidder at the job site.
Bids must be accompanied by cash, a certified or cashier’s check, or a bid bond in favor of the County in an amount not less than ten percent (10%) of the submitted total bid price.
The successful bidder will be required to furnish the Department with a Performance Bond and a Payment Bond, each equal to 100% of the successful bid, prior to execution of the contract. All bonds are to be secured from a surety that meets all of the State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and is admitted by the State of California.
Pursuant to Public Contract Code Section 22300, the successful bidder may substitute certain securities for funds withheld by the Department to ensure its performance under the Contract.
The County shall award the Contract for the Project to the lowest responsible bidder as determined from the base bid by the Department. The County reserves the right to reject any or all bids, to waive technical errors, discrepancies or informalities of a bid not affected by law, if to do so seems to best serve the public interest.
For information contact Ashton Daneshmayeh at (909)386-8827 or email Ashton.daneshmayeh@dpw.sbcounty.gov
By order of the Board of Supervisors for San Bernardino County, California.
Ashton Daneshmayeh, PMP, Project Manager
Published in the: ePro
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 1
INSTRUCTIONS TO BIDDERS
1. FORM AND PREPARATION OF BID PROPOSAL AND SIGNATURE
A. The bid proposal shall be submitted on the properly completed forms attached hereto and shall be enclosed in a sealed envelope marked and addressed as hereinafter directed. Bids can also be submitted through the San Bernardino County Electronic Procurement Network (ePro) ePro - /view/login/login.xhtml. However, if the bid is submitted in ePro, the bidder’s security described herein must still be submitted in person in a sealed envelope prior to the proposal opening date and time. All bidders must register with the ePro system prior to the date and time to receive sealed bids or they will be disqualified. System-related issues or procurement questions in ePro shall be directed to the Purchasing Department at (909) 387-2060.
B. The Opening Bid date is October 8, 2026 at 2:30 PM
A Mandatory Pre-bid meeting will start at 10:30AM on September 15, 2026 at the project site located at 16700 Euclid Ave, Chino, California 91708. BIDS
SUBMITTED BY FIRMS WHO HAVE NOT ATTENDED THE PRE-BID MEETING WILL
BE REJECTED.
The individual attending the mandatory pre-bid meeting must comply with the following:
- Sign the individual’s name on the official sign in sheet at the beginning of the meeting.
- Write the name and address of the company the individual represents; and
- Only one company may be shown as being represented by the individual attending.
The Owner of this Project is San Bernardino County, hereinafter referred to as “County”.
The Project is administrated by the Department of Public Works - Special Districts, herein after referred to as “Department”.
No bid may be withdrawn for sixty (60) days following the bid opening.
For information regarding this Project, contact the Project Manager, Ashton Daneshmayeh at (909)386-8827 or email at Ashton.daneshmayeh@dpw.sbcounty.gov. DO NOT CONTACT THE DESIGN CONSULTANT. All technical questions may be submitted to the Project Manager in ePro, via e-mail and in writing. Last date to submit questions is October 5, 2026. No questions will be answered within 72 hours of the bid opening. Should any of the questions require changes to the plans, specifications or requirements, an addendum will be issued to clarify those changes. Bidders shall be responsible for ensuring that they have received all addenda issued by the Department and the submittal of a bid shall be deemed to be based on the Bid Documents, as modified and/or clarified by any and all addenda.
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 2
C. Bid proposals must be submitted on the forms prepared and furnished for that purpose and which may be obtained on ePro or at the Department of Public Works -
Special Districts office located at 222 W Hospitality Lane, 2 nd Floor, San Bernardino, CA 92415 (909-386-8818). All blank spaces in the bid proposal and bid sheet(s) shall be properly filled. The phraseology of the bid proposal must not be changed, and no additions shall be made to the items mentioned therein. Unauthorized conditions, limitations, or provisions attached to a bid proposal will render it unresponsive and may cause its rejection. Alterations by erasure or interlineations must be explained or noted in the bid proposal over the signature of the bidder. Alternative bid proposals will not be considered unless specifically provided for in the bid sheet(s).
D. In the event of a discrepancy between the unit price and the total amount bid for an item work, the unit price bid will be considered correct, and the total amount will be corrected to conform to the unit price. In the case of a discrepancy between the written bid or numerical bid set forth on the bid proposal, and the numerical bid set forth in the ePro system, the information on the bid proposal shall prevail.
E. If the bid proposal is made by an individual, it shall be signed with a full name and address; if it is made by a firm, it shall be signed with the partnership name by a member of the firm, who shall also sign their own name, and the name and address of each member shall be given; and if it is made by a corporation, the name of the corporation shall be signed by its duly authorized officer(s). If a bid proposal is a joint venture, it shall be signed by a member of the joint venture and the full names and addresses of all partners of the joint venture shall be given.
F. All the Work is to be done under contract to include the plans, specifications, and contract documents prepared for Prado Regional Park Drilling New Irrigation Well
G. Each bid shall be in accordance with the plans, specifications, and other bid documents, copies of which may be obtained at the Department of Public Works - Special Districts, Telephone No. (909) 386-8818. There is a non-refundable cost of $20.00 per Electronic CD. Plans and specifications will be mailed upon request if accompanied by check or money order and bidder's FED-X account number. The plans, specifications, and other bid documents are also available at no cost to the bidder in ePro.
2. ADDRESS AND MARKING OF HARD COPY SUBMISSIONS INCLUDING BID
PROPOSAL
A. The envelope enclosing the bid proposal shall be sealed and addressed to:
San Bernardino County
222 Hospitality Lane, 2 nd Floor
San Bernardino, CA 92415-0450
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 3
B. The envelope shall be plainly marked with the name and address of the bidder in the upper left-hand corner and labeled “Sealed Bids: Prado Regional Park Drilling New Irrigation Well
C. Bids can also be submitted through the San Bernardino County Electronic Procurement Network (ePro) ePro - /view/login/login.xhtml. However, hard copy documents that require separate submission will be delivered to the Department of Public Works - Special Districts Office prior to date and time set for the bid opening.
3. SUBMITTING THE BID PROPOSAL
A. Bid proposals submitted after the time set forth for receiving bid proposals at the place so named herein will returned unopened. It is the sole responsibility of the bidder to submit the bid proposal in accordance with all the provisions contained herein.
B. Bid proposals may be withdrawn upon the written request of the bidder prior to the time set forth for receiving and opening bid proposals without forfeiture of the bid security and/or bond. If a bid is submitted through ePro, then the bid may also be withdrawn in ePro prior to the scheduled time for receipt of bids. Bid proposals withdrawn after bid opening will cause the forfeiture of said bond and/or security as damages.
C. Opening of Bids: Due to the Covid-19 pandemic and to ensure compliance with social distancing requirements, the bid opening will be conducted virtually via GoToMeeting.
Bids (both paper and ePro) shall be opened and read aloud at the place and time set in the Advertisement For Bids. The Call in Number, Access Code, and link information for this bid opening will be posted as an amendment on ePro prior to Bid Opening.
• Call In Number: +1 661-568-6806,,716759150#
• Access Code: 716 759 150#
• Link:
https://teams.microsoft.com/meet/231060899966700?p=7EpC17pu4RbL3McVBj
• Passcode: LQ6MH6to
D. The County reserves the right to reject any or all bids, and to waive technical errors, discrepancies or informalities of a bid not affected by law, if to do so is in the best interest of the County.
E. Submitting via ePro – Once the contractor is registered in ePro and logged into the project for which contractor is submitting a bid on, contractor can enter the quote in the “Quote Tab” and then click Save and Continue. Contractor then must acknowledge and click yes on the terms and conditions in the “Terms and Conditions” tab. To submit and send the bid, contractor needs to access the “Summary Tab”, scroll to the bottom of the page and then click the “Submit Quote” button prior to date/time set for bid opening.
Failure to complete all tabs may result in the bid not being submitted electronically. If contractor has any questions, they may contact the County’s Project Manager to get further directions.
https://epro.sbcounty.gov/epro/ https://epro.sbcounty.gov/epro/ tel:+16615686806,,716759150 https://teams.microsoft.com/meet/231060899966700?p=7EpC17pu4RbL3McVBj
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 4
4. BID BOND OR CHECK
The bid must be accompanied by a certified or cashier’s check or bidder’s bond issued by a surety company acceptable to the County, for not less than ten percent (10%) of the amount of the TOTAL BASE BID, made payable to the order of the County, given as a guarantee the bidder will secure the requisite insurance and bonds and enter into contract within ten
(10) calendar days after being requested to do so by the County. If the bid is submitted to the Department of Public Works - Special Districts, the bid security shall be enclosed in the sealed and marked envelope along with the bid proposal. If the bid is submitted through the San Bernardino County Electronic Procurement Network (ePro) then scan the bid security (bid bond/check) and submit the scanned copy with your bid submittal in ePro, additionally, mail or submit the original bid security, in a separate sealed envelope labeled “Bid Bond” with the title of the work and the name of the bidder clearly marked on the outside to: Department of Public Works - Special Districts, 222 Hospitality Lane, Second Floor, San Bernardino, California, 92415-0450. Any mailed or submitted bid security must be received on or before the time set for the opening of the bids.
Within sixty (60) calendar days after the award of the Contract, the County will return to each bidder the bid proposal security submitted with the bid proposal in the form of cash, cashier’s check or certified check, except such security that may have been forfeited in accordance with the provisions stated herein. Bid bonds will be returned within sixty (60) calendar days after the award of the Contract, upon bidder’s written request to the County, except such bid bonds which may have been forfeited in accordance with the provisions stated herein.
5. REGISTRATION OF CONTRACTORS
All bidders shall be licensed in accordance with the provisions of Chapter 9, Division 3, of the Business and Professions Code of the State of California and possess a California Class A or C Contractor’s License at the time of the scheduled bid opening.
6. LIST OF SUBCONTRACTORS FILED WITH BID AND REGISTERED
CONTRACTORS/SUBCONTRACTORS
In accordance with the provisions of Section 4100 through 4113 inclusive of the Public Contract Code of the State of California, each bidder shall submit with their bid proposal the name, location of place of business, and California contractor’s license number of each proposed subcontractor who will perform work or labor or render service to the principal Contractor in an amount in excess of ½ of one percent (.5%) of the principal Contractor’s bid, and shall state the portions of the work which will be done by each such subcontractor.
Contractor and all listed subcontractor(s) must be registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. Contractor agrees that no contractor or subcontractor may be awarded a contract for public work or perform work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
7. LOWEST RESPONSIBLE BIDDER
The contract shall be awarded to the lowest responsive, responsible bidder based upon the
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 5
BASE BID. To be deemed responsive, the bidder must list in the bid forms at least three (3) projects of similar size and scope completed within the last five(5) years.
The low bid shall be determined pursuant to Public Contract Code Section 20103.8(b), considering the total of the base bid and any additive or deductive items specifically identified for determining the lowest bid. The responsible bidder submitting the lowest bid as determined under this section shall be awarded the contract, and this does not preclude adding or deducting any identified additive or deductive items after award.
8. INTERPRETATION OF DRAWINGS AND SPECIFICATIONS
If any bidder is in doubt as to the true meaning of any requirements of drawings or specifications, or finds any discrepancies in, or omissions from the drawings or specifications, the bidder may submit to the engineer a written request for an interpretation or correction thereof. The written request must be received by October 1, 2026. The person making the request will be responsible for its prompt delivery. Interpretations or corrections will be made only by addenda to specifications or by dated revisions or drawings with a copy of each addition or change being furnished through the County to each prospective bidder.
Only a written interpretation or correction by Addendum shall be binding.
Bidders shall examine all the bid documents, including the drawings, perform their own estimates for the proposed work, taking into account local conditions, uncertainty of weather, and all laws, ordinances, rules and regulations of any federal, state, County, municipal or other governmental agency that has jurisdiction over the work. The more stringent requirement shall always prevail.
9. LOCAL AND SITE CONDITIONS
A. Bidders shall read the specifications, examine the drawings and the bid documents, and make their own estimates of the existing conditions and the difficulties that will attend the execution of the work called for by the proposed contract, including uncertainty of weather and other contingencies prior to submitting bid proposals for the work.
B. Bidders shall satisfy themselves by personal examination of the location of the proposed work and by such means as they may choose as to actual conditions, limitations and requirements that may affect the execution of the work and as to the accuracy of the quantities stated in the Bid Sheet(s). The submission of a bid proposal shall be conclusive evidence that the Bidder has investigated the Project site and is aware and acknowledges the conditions to be encountered.
Information derived from the maps, plans, specifications, profiles, drawings or from the Engineer or the Engineer’s assistants shall not relieve the bidder of this responsibility.
C. The failure or omission of any bidder to receive or examine any form, instrument, addendum or other document, or failure to visit and to be acquainted with the conditions at the proposed project site, shall in no respect relieve the bidder from any obligation imposed by the bid or by the contract. The submittal of a bid shall be taken as prima facie evidence of compliance with all instruction contained herein. Any or all addenda issued during the bid process must be submitted with the bid document or the
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 6 bidder will be disqualified.
D. The quantities of work or material stated in the unit price items of the Bid Sheet(s) are supplied only to give an indication of the general scope of work; the County does not expressly or by implication agree that the actual amount of work or material will correspond therewith but reserves the right to increase or decrease the amount of any unit price item or to omit portions of such work as may be deemed necessary or expedient by the Engineer without a change in the unit price.
E. Bidders shall not at any time after the submittal of a bid make or have any claim for damages or anticipated profits or loss of profit or otherwise because of any difference between the quantities of work actually done and material furnished and those stated in said unit price items of the Bid Sheet(s).
10. GEOLOGIC AND SOILS CONDITIONS
Geologic conditions to be referenced in Section H of the Bid Package. It shall be the bidder’s responsibility to make all examinations borings, and the field studies necessary for required excavation and embankment construction operations and to fully determine all cost factors related thereto which shall be included in the bid price for the work. The submittal of a bid will be accepted as prima facie evidence that in compliance herewith the bidder accurately and fully informed itself of all geological and soil conditions that will influence the cost of performing the work and that due consideration of all such factors was taken prior to making the bid.
The Contractor shall promptly notify the County, in writing, if any subsurface or latent physical conditions are encountered at the site differing from those indicated, if material is found that the contractor believes may be hazardous waste, or if unknown physical conditions are encountered of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this contract.
11. EXECUTION OF CONTRACT AND BONDS
The successful bidder shall execute a written contract with the County in the form attached hereto and shall secure the payment of Workers’ Compensation and the successful bidder shall also furnish a certificate of insurance evidencing the contractor has the required insurance at the time contractor executes the agreement, and approved bonds as required in the following paragraphs, all in accordance with the provisions hereof within ten (10) calendar days or such additional time as may be allowed by the Engineer from the date of the mailing of a notice from the County to the bidder according to the address given, of the acceptance of the bid proposal. If a bidder to whom award is made fails or refuses to enter into Contract as herein provided, or to conform to any of the stipulated requirements in connection therewith, the money represented by the cashier’s check or Bidder’s Bond shall become the property of the County as provided in Section 4, hereof, the award will be annulled and at the discretion of the County, the contract may be awarded to the next lowest qualified bidder. Such bidders shall fulfill every stipulation embraced herein as if the parties to whom the first award was made. A corporation to which an award is made may be required before the contract is finally executed to furnish evidence of its corporate existence, of its
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 7 right to do business in California and of the authority of the officer signing the contract and bonds for the corporation.
A. The successful bidder shall furnish a bond with a responsible corporate surety or corporate sureties authorized to do business in California conditioned upon the faithful performance of the said bidder of all covenants and stipulations in the contract. Said bond, hereinafter referred to as the Faithful Performance Bond, shall be in the form approved by the County and shall not be less than one hundred percent (100%) of the total amount of the Contract Sum named in the contract.
B. The bidder to whom the contract is awarded shall also furnish a Labor and Material
Payment Bond, approved by the County, in accordance with the provisions of Civil Code Sections 8150-8154 inclusive, and Sections 9550- 9566 inclusive. Said labor and material bond shall not be less than one hundred percent (100%) of the total amount of the Contract Sum named in the contract.
C. The surety on all bonds furnished must be satisfactory to the County. The party required to furnish bonds pursuant to these instructions shall furnish such bonds at their own cost and expense. The County shall reject any bond if the surety’s acknowledgment is not in the form included in the Contract documents.
D. Permits – The Contractor shall meet the San Bernardino County Department of Public
Health well installation requirements for placing a sanitary seal. Comply with applicable permits, laws, and regulations in placing a sanitary seal for water production well. The permits, laws and regulations shall include, but not be limited to, the following: Federal, State and Local laws, Regulations, and Ordinances related to constructing a sanitary seal in water wells. The Contractor shall secure at his/her own expense, all permits and/or licenses necessary for the prosecution of the contract work, except for any permits and/or licenses that have been secured and paid for by the County. The Contractor shall obtain and pay for all licenses required by cities, San Bernardino County, State or Federal laws. The Contractor shall also be liable for any expense, of any kind, associated with any permit or license for any expense, of any kind, associated with any permit or license, including those obtained by the County, in excess of payments made by County prior to Contract Award.
The Contractor shall comply with the applicable requirements of all necessary permits and/or licenses, all at no additional cost to the County. Any inspection and/or testing fees required in connection with any governing permit and/or license shall be responsibility of the contractor, at no additional cost to the County.
12. INDEMNIFICATION, INSURANCE
Any reference “County” in this Section 12 refers to San Bernardino County. The Contractor agrees to and shall comply with the following indemnification and insurance requirements:
A. Indemnification: To the fullest extent possible permitted by law, Contractor assumes liability for and agrees, at the Contractor’s sole cost and expense, to promptly and fully indemnify, defend (with counsel reasonably approved by the County) (even if the allegations are false, fraudulent, or groundless), and hold harmless the County, and their
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 8 authorized officers, employees, agents and volunteers (Indemnitees) from and against any and all claims (including claims against the County seeking compensation for labor performed or materials used or furnished to be used in the work or alleged to have been furnished on the project, including all incidental or consequential damages resulting to the County from such claims), allegations, actions, suits, arbitrations, administrative proceedings, regulatory proceedings, or other legal proceedings, demands, losses, costs, damages, judgments, liens, stop notices, penalties, anticipated losses of revenue and/or liability, and expenses (including, but not limited to, any fees of accountants, attorneys, experts or other professionals, or investigation expenses) arising out of, resulting from, or in any way (either directly or indirectly) related to the contract, the work, the project or any breach of the Contract by Contractor (or any of its officers, agents, employees, subcontractors, or any person performing any of the work, or from any cause whatsoever, including the acts, errors or omissions of any person and for any costs or expenses incurred by the Indemnitees on account of any claim except where such indemnification is prohibited by law. This indemnification provision shall apply regardless of the existence or degree of fault of indemnitees. The Contractor’s indemnification obligation applies to the Indemnitee’s “passive” negligence but does not apply to the Indemnitee’s “sole” or “active” negligence or “willful misconduct” within the meaning of Civil Code section 2782 provided such “active” negligence or “willful misconduct” is determined by agreement of the parties or by findings of a court. In instances where an Indemnitee’s “active” negligence accounts for only a percentage of the liability for the claim involved, the obligation of the Contractor will be for that entire percentage of liability for the claim not attributable to the “active” negligence or “willful misconduct” of the Indemnitees. The County shall be consulted with regard to any proposed settlement.
The duty of the Contractor to indemnify and hold harmless the Indemnitees includes the separate and independent duty to defend the Indemnitees, which duty arises immediately upon receipt by Contractor of the tender of any claim from the County. The Contractor’s obligation to defend the County shall be at Contractor’s sole expense and not be excused because of the Contractor’s inability to evaluate liability or because the Contractor evaluates liability and determines that the Contractor is not liable. The duty to defend shall apply whether or not a claim has merit or is meritless, or which involves claims or allegations that any or all of the Indemnitees were actively, passively, or concurrently negligent, or which otherwise asserts that the Indemnitees are responsible, in whole or in part, for any claim. The Contractor shall respond within thirty (30) calendar days to the tender of any claim for defense and/or indemnity by the County, unless the County agree in writing to an extension of this time. The defense provided to the Indemnitees by Contractor shall be by well qualified, adequately insured, and experienced legal counsel acceptable to the County Counsel.
It is the intent of the parties to the Contract that the Contractor and its subcontractors of all tiers shall provide the Indemnitees with the broadest defense and indemnity permitted by law. In the event that any of the defense, indemnity, or hold harmless provisions are found to be ambiguous, or in conflict with one another, it is the parties’ intent that the broadest and most expansive interpretation in favor of providing defense and/or indemnity to the Indemnitees be given effect.
Contractor shall ensure, by written subcontract agreement, that each of Contractor’s
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 9 subcontractors of every tier shall protect, defend, indemnify and hold harmless the Indemnitees with respect to all claims arising out, in connection with, or in any way related to each such subcontractor’s work in the same manner in which Contractor is required to protect, defend, indemnify, and hold the Indemnitees harmless. In the event Contractor fails to obtain such defense and indemnity obligations from its subcontractors as required herein, Contractor agrees to be fully responsible to the Indemnitees according to the terms of this Section.
Contractor’s indemnification and defense obligations set for in this Section are separate and independent from the insurance requirements and do not limit, in any way, the applicability, scope, or obligations set forth in such insurance requirements. The purchase of insurance by the Contractor with respect to the obligations required herein shall in no event be construed as fulfillment or discharge of such obligations.
Contractor’s obligations under this Section are binding on Contractor’s and its subcontractors’ successors, heirs and assigns and shall survive the completion of the work or termination of the Contractor’s performance of the work.
B. Insurance: The Contractor agrees to furnish certified copies of all insurance policies and endorsements; all certificates of comprehensive, general and auto liability insurance;
Workers' Compensation insurance; builder’s risk insurance; and such other insurance that will protect it from claims for damages and personal injury, including death, which may arise from operations under the contract, whether such operation be by the Contractor or by any subcontractor of the Contractor, or anyone directly or indirectly employed by the Contractor or any subcontractor of the Contractor in accordance with Section 11.2 of the General Conditions and the Construction Contract. The Contractor agrees to provide the Department of Public Works - Special Districts with Certificates of Insurance evidencing the required insurance coverage at the time Contractor executes the contract with the County. All policies (excluding Workers' Compensation) shall name San Bernardino County, and their officers, employees, agents and volunteers as additional insureds. All coverages shall be subject to approval by the County for adequacy of protection.
13. PREVAILING WAGES
Bidders are hereby notified that this Project is subject to state prevailing wage guidelines.
The prime Contractor and all subcontractors are required to pay their laborers and mechanics employed under this Contract a wage not less than the wage applicable for their work classification, as specified in the wage guidelines. The County has obtained the general prevailing rate of per diem wages in accordance with the law to be paid for the construction of the above Project. The schedules have been obtained from the Director of the California Department of Industrial Relations (DIR), and reference is hereby made to copies thereof on file with the Special District Department at 222 Hospitality Lane, 2nd Floor, Street, San Bernardino. CA 92415-0450, which said copies are available to any interested party upon request and included in these bid documents. Further, a copy shall be posted at each job site during the course of construction.
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 10
Contractor shall be registered with the DIR at time of bid submission and shall indicate its registration number as well as the registration number for all of its subcontractors that will be working on the project. Contractor acknowledges that the project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
As required by Labor Code section 1771.1(a) “A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”
14. NON-COLLUSION DECLARATION
The County requires all bidders to execute a Non-collusion Declaration in the form attached hereto. The County also reserves the right to require that the principal Contractor shall, before awarding any subcontract, secure from the proposed subcontractor(s) a Non-collusion Declaration in the form also attached.
15. SCHEDULE
Prior to signing the Construction Contract, the Contractor shall submit on a form acceptable to the County and representative of an overall construction schedule for the work. The construction start date will begin when the "Notice to Proceed" is issued and the completion date will be 120 calendar days after the "Notice to Proceed" is issued by the Department of Public Works - Special Districts.
16. ASSIGNMENT OF CONTRACT AND SUBSTITUTION OF SUBCONTRACTORS
No assignment by the Contractor of any Contract, or any part thereof, to be entered into in accordance with the Bid Documents and these Instruction to Bidders, or of funds to be received thereunder, will be recognized by the awarding authority unless such assignment has had the prior written approval of the awarding authority and the surety has had notice of such assignment in writing and has given written consent thereto.
No contractor shall substitute any person as a subcontractor in place of the subcontractor designated in the original bid; or permit any such subcontract to be assigned or transferred or allow it to be performed by anyone other than the original subcontractor listed in the bid;
or sublet or subcontract any portion of the work in excess of one-half of one percent (0.5%) of the contractor’s total bid in which the original bid did not designate a subcontractor; except as provided by Section 4100 et. seq. of the Public Contract Code of the State of California.
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 11
17. PAYMENTS
Payments will be made as outlined in the General Conditions. The Contractor must sign and submit the Affidavit of Completion prior to the Notice of Completion being recorded and retention paid. Progress payments shall be made no more than once every thirty (30) calendar days, nor shall the amount paid be in excess of ninety-five percent (95%) of the total contract at the time of completion. At the request and expense of the successful Bidder, the County will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300. Final payment shall be processed sixty (60) calendar days after the filing of the Notice of Completion. In addition, all payments shall be approved by the Division Engineer for the Department of Public Works - Special Districts.
18. TIME LIMITS OF WORK
The contract work shall be completed within 120 calendar days after the Notice to Proceed.
In case all the work called for under the Contract is not finished or completed within the number of calendar days as set forth in the bid proposal, the Contractor shall forfeit to the County a specified sum of money, to be deducted from any payments due to the Contractor.
The sum of money shall be $1,200 per calendar day more than the Contract Time as Liquidated Damages per Section 8.5 of the General Conditions.
19. GOVERNING DOCUMENTS
Where a conflict of requirements exists between the various conditions of these documents, the more restrictive of the requirements shall apply.
20. EXPLANATION OF BID ITEMS
The monies to be paid for the various items of work included in the Bid Sheet(s) shall constitute the total obligation of the County as described in the Contract Documents, with the exception of costs specifically delegated to the County by the Contract Documents and no additional compensation will be allowed therefore.
21. SUBCONTRACTOR ELIGIBILITY
Ineligible Subcontractors – Pursuant to the provisions of Section 1777.1 of the California Labor Code, the Labor Commissioner publishes and distributes a list of contractors’ ineligible to perform work as a subcontractor on a public works project. This list of debarred contractors is available from the DIR website at http://www.dir.ca.gov/dlse/debar.html. Any contract entered into between a contractor and a debarred contractor subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract, and any public money that may have been paid to a debarred subcontractor by a contractor on the project shall be returned to the County. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the project.
http://www.dir.ca.gov/dlse/debar.html
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 12
22. BID PROTEST
Any Bidder submitting a Bid to the County for this Project may file a protest of the County’s proposed award of a construction contract for this Project, provided that each and all of the following are complied with:
1. The bid protest is in writing.
2. The bid protest is submitted to and received by the Department of Public Works - Special
Districts, 222 Hospitality Lane, Second Floor, San Bernardino, CA, 92415- 0450 before 4:00p.m. of the fifth business day following the bid opening. Failure to timely submit a written protest shall constitute grounds for the County’s denial of the bid protest without consideration of the grounds stated in the bid protest and a waiver of the right to protest.
Untimely protests will not be accepted or considered.
3. The written bid protest shall set forth, in detail, all grounds for the bid protest (including without limitation all facts, supporting documentation, legal authorities and argument in support of the grounds for the bid protest), the form of relief required and the legal basis for such relief. Any grounds not set forth in the bid protest shall be deemed waived. All factual contentions must be supported by competent, admissible and credible evidence.
The bid protests shall include the name of the project manager and the name and number of the bid Project. Any bid protest not conforming to the foregoing shall be rejected as invalid.
If a valid protest is timely filed and complies with the above requirements, the Department shall review and evaluate the bid protest. All bidders, including the protesting bidder, shall have three business days to respond to the Department and to provide any information requested by the Department. The Department shall respond to the protesting bidder and state the Department’s findings regarding the bid protest. The Department Director’s decision shall be final, unless overturned by the San Bernardino County, Board of Supervisors.
23. CALIFORNIA AIR RESOURCES BOARD (CARB) IN-USE OFF-ROAD DIESEL-FUELED
FLEETS REGULATION COMPLIANCE CERTIFICATION
This Project is subject to the California Air Resources Board (CARB) approved amendments relating to In-Use Off Road Diesel-Fueled Fleets found at California Code of Regulations Title 13, sections 2449, 2449.1, and 2449.2 (the “Regulations”). The Regulations require a Prime Contractor (Contractor), bidding on a public works project to be awarded by any public works awarding body, to certify that the Contractors off-road diesel-fueled fleets comply with CARB regulations. Section 2249(b) includes a list of off-road diesel-fueled fleets subject to these regulations. It is the responsibility of the Contractor to verify if their fleet is subject to these regulations.
Contractor is required to obtain and submit Certificates of Reported Compliance from all subcontractors that are listed in the bid submission. Failure to provide Contractor’s CARB compliance number may constitute a material irregularity rendering their bid non-responsive and subject to rejection for non-responsiveness.
Rev. 2/2026 Instructions for Bidders for County Projects – IB- 13
No award shall be made to a Contractor that has failed to provide its CARB compliance certificates, unless the Contractor confirms that no equipment subject to the regulation will be used to execute the Contract Work. By submitting a bid, the Bidder hereby certifies that it is aware of the requirements set forth in Sections 2449, 2449.1, and 2449.2, Title 13, California Code of Regulations and any successful Bidder and its subcontractors shall comply with sections 2449, 2449.1, 2449.2 of Title 13 of the California Code of Regulations, including by providing Certificate(s) of Reported Compliance for In-Use Off-Road Diesel- Fueled Fleets for the fleet selected for the contract and their listed subcontractors, if applicable, with its bid.
Contractor shall not enter into a contract with a fleet for which it does not have a valid Certificate of Reported Compliance for the fleet and Contractor’s listed subcontractors, if applicable, prior to entering into a new or renewed contract with that fleet. Contractor shall only allow fleets with valid Certificates of Reported Compliance on Contractor’s job sites.
The Certificates of Reported Compliance received by the Contractor for this Project must be retained for three (3) years after the Project’s completion. Upon request by CARB, these records must be provided to CARB within five (5) business days of the request. Between March 1 and June 1 of each year, Contractor must collect new valid Certificates of Reported Compliance for the current compliance year, as defined in Regulation Section 2449(n), from all fleets that have an ongoing contract with the Contractor as of March 1 of that year.
Contractor must not write contracts to evade this requirement.
If Contractor discovers that any fleet intending to operate vehicles subject to the Regulation for Contractor does not have a valid Certificate of Reported Compliance, as defined in Regulation section 2449(n), or if Contractor observes any noncompliant vehicles subject to the Regulation on Contractor’s job site, then Contractor must report the required information to CARB within the time period contained in in the Regulations.
Upon request by CARB, Contractor must immediately disclose to CARB the name and contact information of each responsible party for all vehicles subject to the Regulation operating at the job site or for Contractor. If applicable, Contractor shall prominently display signage for any project where vehicles subject to the Regulation as provided and within the time period contained in the Regulation.
Situations in which prime contractors or public works awarding bodies, as applicable, are contracting for projects that are considered emergency operations, as defined in section 2449(c)(18), are exempt from the requirements in section 2449(i)(1)-(3), but must still retain records verifying vehicles subject to the regulation that are operating on the emergency operations project are actually being operated on the project for emergency operations only.
These records must include a description of the emergency, the address or a description of the specific location of the emergency, the dates on which the emergency operations were performed, and an attestation by the fleet that the vehicles are operated on the project for emergency operations only.
Contractor shall complete and return the “California Air Resources Board (CARB) In-Use Off-Road Diesel-Fueled Fleets Certification of Compliance” form attached hereto as a condition to bidding this Project.
Rev. 2/2026 Bidder Informatino Form for County Projects – BIF- 1
BIDDER INFORMATION FORM
(TO BE COMPLETED AND SUBMITTED WITH BID)
A. INFORMATION ABOUT BIDDER
Failure to complete all information may render your bid non-responsive. [**Indicate not applicable (“N/A”) where appropriate.**]
NOTE: Where Bidder is a joint venture, pages shall be duplicated and information provided for all parties to the joint venture.
1.0 Name of Bidder:
2.0 Type, if Entity:
3.0 Bidder Address:
Email Address Telephone Number
4.0 How many years has Bidder’s organization been in business as a Contractor?
5.0 How many years has Bidder’s…