Diversion Chamber C Inlet Pipe Modifications -WPCF
Solicitation number
BID 2027-08
Issued by
Fairfield County, Connecticut

About this file

This is a solicitation document and invitation to bid (ITB) issued by the Town of Stratford, Connecticut for Diversion Chamber C Inlet Pipe Modifications at the Water Pollution Control Facility (WPCF). The project encompasses dewatering, cleaning, groundwater control, closed-circuit television (CCTV) inspection, and Cured-in-Place (CIPP) lining services on approximately 225 linear feet of 54-inch corrugated metal pipe (CMP) stormwater pipe and approximately 105 linear feet of 12-inch reinforced concrete pipe (RCP) stormwater pipe. A mandatory prebid meeting is scheduled for September 29, 2026 at 10:00 a.m. The vendor question and answer period runs from September 17, 2026 at 1:15 p.m. EDT through October 7, 2026 at 12:00 p.m. EDT, with all inquiries to be submitted in writing to Purchasing Agent Phillip Ryan at pryan@townofstratford.com. Bids are due on October 16, 2026 at 10:00 a.m. EDT. Physical bid submission is mandatory; electronic submission is prohibited.

The work scope includes removal and disposal of sediment estimated at 12-24 inches, retrieval of equipment stuck approximately 70 feet from the inlet, excavation of a buried 12-inch RCP inlet headwall, and plugging the pipe to prevent river water or wetland flow during construction. CIPP lining must be completed during dry weather and low river conditions, with the contractor responsible for monitoring rainfall and river levels throughout installation, curing, and testing. Groundwater control is required due to groundwater observed 5 feet below grade. The contractor assumes responsibility for all site safety, utility protection, traffic control, erosion control, and regulatory compliance. Payment terms are Net 30 Days upon approval by all Town boards. No estimated contract value is disclosed in the solicitation. All vendors are eligible to respond.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: BID 2027-08

Diversion Chamber C Inlet Pipe Modifications -WPCF

Invitation to Bid (ITB)

Stratford, Town of

September 17, 2026 - October 16, 2026

Page:2

General Header Information

This bid has no questions defined.

BID 2027-08

No. BID 2027-08 Title: Diversion Chamber C Inlet Pipe Modifications -WPCF Start Date: September 17, 2026 at 1:00:00 PM EDT End Date: October 16, 2026 at 10:00:00 AM EDT Vendor Q&A Start Date: September 17, 2026 at 1:15:00 PM EDT Vendor Q&A End Date: October 07, 2026 at 12:00:00 PM EDT Estimated Total Value:

Who can respond to this bid? : All Vendors Description: Dewatering, cleaning, ground water control, CCTV, Cured-in-Place

(CIPP) lining of located on the Water Pollution Control Facility (WPCF).

Approximately 225 linear feet of 54-inch corrugated metal pipe (CMP) stormwater pipe. Approximately 105 linear feet of 12-inch reinforced concrete pipe (RCP) stormwater pipe. PREBID MEETING: 09/29/2026 -

10:00AM. ***DO NOT SUBMIT BIDS ELECTRONICALLY***

Delivery Terms: N/A: Not Applicable Payment Terms: Net 30 Days Payment Notes: Upon approval by all Town boards.

Contact Information: Stratford, Town of

Phillip Ryan, Purchasing Agent Email: pryan@townofstratford.com Submit all requests for information (RFI) to email address above.

Verbal communication will NOT be accepted.

Contact Details: If you have any questions, please contact:

Phillip Ryan, Purchasing Agent Email: pryan@townofstratford.com Submit all requests for information (RFI) to email address above.

Verbal communication will NOT be accepted.

Selected Categories:

Page:3

Documents:

2027-08 Inlet Pipe Modifications - WPCF - Drawings.pdf

2027-08 Inlet Pipe Modifications - WPCF - Specifications.pdf

2027-08 Sign-in Sheet.pdf

Page:4

Item Specifications Solicitation has been designated as having no line items.

Page:5

File details come from the government source that posted it. Updated .