About this file
This document is Addendum Number 1 for Invitation to Bid #2025-46 issued by Clackamas County, Oregon, dated May 29, 2025. The addendum modifies the original bid documents for the SE Johnson Creek Blvd: 79th Place – 82nd Ave Project, specifically addressing changes to the Project Special Provisions related to asphalt cement material price escalation and de-escalation. The amendment provides a detailed mechanism for monthly adjustments to asphalt cement pricing based on published market rates from Poten & Partners, Inc., with pricing calculations using monthly material prices from either the Portland, Oregon or Boise, Idaho areas.
The addendum outlines a specific price adjustment methodology where contractors will receive price modifications for two specific pay items: Emulsified Asphalt in Fog Coat and Level 3, 1/2 Inch ACP Mixture. The adjustment factor will be calculated monthly, with no adjustments made if the Monthly Asphalt Cement Material Price (MACMP) remains within ±5% of the base price. If the MACMP varies more than 5% from the base price, a corresponding adjustment will be applied. The County reserves its rights under the contract, including suspension and termination options, and the contractor must select and adhere to either the Portland or Boise pricing area for the entire contract duration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID #2025-46
SE Johnson Creek Blvd: 79th Place – 82nd Ave Project
ADDENDUM NUMBER 1
May 29, 2025
On May 14, 2025, Clackamas County (“County”) published Invitation to Bid #2025-46 (“BID”).
The County has found that it is in its interest to amend the BID through the issuance of this Addendum #1. Except as expressly amended below, all other terms and conditions of the original BID and subsequent Addenda shall remain unchanged.
The following changes are made to the Project Special Provisions:
1. Subsection 00195.10 Payment for Changes in Materials Costs – Replace this subsection with the following subsection:
00195.10 Asphalt Cement Material Price Escalation/De-escalation - An asphalt cement escalation/de-escalation clause will be in effect during the life of the Contract.
The Agency reserves all of its rights under the Contract, including, but not limited to, its rights for suspension of the Work under 00180.70 and its rights for termination of the Contract under 00180.90, and this escalation/de-escalation provision shall not limit those rights.
(a) Monthly Asphalt Cement Material Price (MACMP) - The Monthly Asphalt Cement Material Price (MACMP) is established by the Agency each month. For the actual MACMP, go to the Agency website at:
https://www.oregon.gov/ODOT/Business/Pages/Asphalt-Fuel-Price.aspx
The MACMP is based on selling prices of asphalt cement published by Poten & Partners, Inc.
for primarily PG 64-22 paving grades in the Portland, Oregon area and typical non-modified paving grades in the Boise, Idaho area. The MACMP for a given month is the average of the weekly published prices for each area reported each Friday in that month. If any portion of the Project Site is located within the boundaries of ODOT Maintenance District 13 or 14, the MACMP will be based on the prices for the Boise, Idaho area. If no portion of the Project Site is within the boundaries of ODOT Maintenance District 13 or 14, the Contractor may elect to have the MACMP based on the prices of either the Portland, Oregon area or the Boise, Idaho area. If electing to use Boise, Idaho area prices for determination of the MACMP, the Contractor shall notify the Engineer in writing of the Contractor’s election before or within 7 Calendar Days after the date of the preconstruction conference. This election, once acknowledged by the Engineer, will be binding for the entire duration of the Contract. If no such written notification is made, the Portland, Oregon area prices will be used as the basis of the MACMP. The area selected as the basis of the MACMP, once chosen, will become the sole area to be used as the basis for all asphalt cement used on the Project.
https://www.oregon.gov/ODOT/Business/Pages/Asphalt-Fuel-Price.aspx
If the weekly prices cease to be available from Poten & Partners, Inc. for any reason, the Agency, in its discretion will select and begin using a substitute price source or index to establish the MACMP each month. The Agency does not guarantee that asphalt cement will be available at the MACMP.
(b) Base Asphalt Cement Material Price (Base) - The base asphalt cement material price for this Project is the MACMP published on the Agency website for the month immediately preceding the Bid Opening date.
(c) Monthly Asphalt Cement Adjustment Factor - The monthly asphalt cement adjustment factor will be determined each month as follows:
• If the MACMP is within ± 5% of the Base, there will be no adjustment.
• If the MACMP is more than 105% of the Base, then:
Adjustment Factor = (MACMP) - (1.05 x Base)
• If the MACMP is less than 95% of the Base, then:
Adjustment Factor = (MACMP) - (0.95 x Base)
(d) Asphalt Cement Price Adjustment - A price adjustment will be made for the items containing asphalt cement listed below. The price adjustment as calculated in (c) above will use the MACMP for the month the asphalt is incorporated into the Project. The price adjustment will be determined by multiplying the asphalt incorporated during the month for subject Pay Items by the Adjustment Factor.
The Pay Items for which price adjustments will be made are:
Pay Items
EMULSIFIED ASPHALT IN FOG COAT
Level 3, 1/2 INCH ACP MIXTURE
These changes will be included in the Contract for this Project. It is understood that your Bid will be submitted accordingly.
End of Addendum #1