B08_Section_J_Attachment_1_Specifications_6_26_23.pdf

PDF 6 MB Posted

Attached to
DRTO 244370/244372 Repair and Dredge Ft Jefferson
Solicitation number
140P2023R0033
Issued by

About this file

This document package includes technical specifications and appendices for a federal contract solicitation to perform repairs to Fort Jefferson Counterscarp and dredging of the Fort Jefferson Moat and waterfront areas at Dry Tortugas National Park. The solicitation number is 140P2023R0033 and was issued by the Department of the Interior National Park Service. The scope of work involves selective masonry repair to the historic Fort Jefferson Counterscarp, including reconstruction of a collapsed section, brick replacement, and repair of voids in the structure. It also includes dredging sediment deposits from the Fort Jefferson Moat and finger piers to design depths. The technical specifications provide requirements for masonry cleaning, concrete repair, underwater construction, and environmental compliance. Appendices include existing conditions assessments and testing reports to inform repair methods. The response due date is not stated.

View the file

Other files

File Type Posted
B09_Attachment_EVER_DRTO_2023_Hurricane_Plan_FINAL_Amendment06_0006.pdf PDF
B09_Attachment_01_27_00_Definition_Of_Contract_Line_Items_Rev001_Attachment06_0006.pdf PDF
B09_-_Amendment_0006_-_140P2023R0033_0006.pdf PDF
B09_Attachment_Price_Schedule_REV001_Amendment06_0006.xlsx XLSX spreadsheet
Sol_140P2023R0033_Amd_0006.pdf PDF
B09_Attachment_Fuel_Line_Relocation_Plan_Amendment06_0006.pdf PDF
Sol_140P2023R0033_Amd_0005.pdf PDF
B09_DRTO_244370-72_Contractor_RFI_Responses_Amend05_0005.pdf PDF
B09_-_Amendment_0005_-_140P2023R0033_0005.pdf PDF
Sol_140P2023R0033_Amd_0004.pdf PDF
B08_RFP_140P2023R0033_Amendment_0004_8_22_23_0004.pdf PDF
Sol_140P2023R0033_Amd_0003.pdf PDF
B09_Amendment_3_Sign_in_Sheet_Pg1_0003.PDF PDF
B09_Amendment_3_Sign_in_Sheet_Pg2_0003.PDF PDF
B08_RFP_140P2023R0033_Amendment_0002_Attachment_3_Presentation_0002.pptx PPTX presentation
Sol_140P2023R0033_Amd_0002.pdf PDF
B08_RFP_140P2023R0033_Amendment_0002_8_2_23_0002.pdf PDF
B08_RFP_140P2023R0033_Amendment_0002_Attachment_1_SF1442_Conformed_Copy_0002.pdf PDF
B08_RFP_140P2023R0033_Amendment_0002_Attachment_2_Attendance_List_and_Meeting_Minutes_0002.pdf PDF
Sol_140P2023R0033_Amd_0001.pdf PDF
B08_RFP_140P2023R0033_Amendment_0001_6_30_23_0001.pdf PDF
B08_Section_J_Attachment_9_Underwater_Inspection.pdf PDF
B08_Section_J_Attachment_14_General_Decision_Number_FL20230002.pdf PDF
B08_Section_J_Attachment_8_Waterfront_Inspection.pdf PDF
B08_Section_J_Attachment_13_Price_Schedule.xlsx XLSX spreadsheet
B08_Section_J_Attachment_16_Proposal_Submission_Package_Portfolio.pdf PDF
B08_Section_J_Attachment_6_Benthic_Survey.pdf PDF
B08_Section_J_Attachment_7_Sediment_Sampling.pdf PDF
B08_Section_J_Attachment_3_Geotechnical_Exploration.pdf PDF
B08_Section_J_Attachment_5_Petrographic_Investigation.pdf PDF
B08_Section_J_Attachment_10_Marine_Survey.pdf PDF
B08_Section_J_Attachment_4_Ft_Jeff_Counterscarp_Materials_Test.pdf PDF
B08_Section_J_Attachment_12_Topographic_Survey.pdf PDF
Sol_140P2023R0033.pdf PDF
B08_Section_J_Attachment_11_Coral_and_Seagrass_Survey.pdf PDF
B08_Section_J_Attachment_2_Drawings.pdf PDF
B08_Section_J_Attachment_15_General_Decision_Number_FL20230096.pdf PDF
B08_Solicitation_140P2023R0033_SF_1442_DRTO_244370_244372_6_26_23.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION J ATTACHMENT 1:

Technical Specifications Solicitation # 140P2023R0033 Date: 06/26/2023

TABLE OF CONTENTS

DRTO 244370 & 244372 TOC - 1

051121

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

01 31 00 Project Management & Coordination

01 32 16 Construction Schedule

01 32 33 Photographic Documentation

01 33 23 Submittal Procedures

01 35 13.22 Archeological Protection

01 35 23 Safety Requirements

01 35 91 Historic Preservation Treatment Procedures

01 40 00 Quality Requirements

01 42 00 Reference Standards

01 50 00 Temporary Facilities and Controls

01 57 10 Moat Protection

01 57 19.12 Noise & Acoustics Management

01 57 23 Under-an-Acre Pollution Prevention

01 67 00 Product Requirements

01 71 23.16 Construction Surveying

01 73 40 Execution

01 74 19 Construction Waste Management and Disposal

01 77 00 Closeout Procedures

DIVISION 02 – EXISTING CONDITIONS

02 15 00 Bracing and Shoring

02 22 00 Existing Conditions Assessment

02 41 19 Selective Demolition

DIVISION 03 – CONCRETE

03 01 00.71 Rehabilitation of Concrete

03 15 23 Drilled-in Anchor Bolts and Reinforcing Bars

03 31 30 Marine Concrete

DIVISION 04 – MASONRY

04 05 00 Common Work Results for Masonry

04 05 10 Masonry Cleaning

04 05 16 Brick Unit Masonry Grouting and Re-pointing

04 21 13 Replacement Brick Masonry

DIVISION 05 – METALS

05 12 43 Metal Fabrications

DIVISION 06 – Wood, Plastics, and Composites

06 13 00 Heavy Timber Construction

06 74 13 Fiberglass Reinforced Plastic (FRP) Grating

TABLE OF CONTENTS

DRTO 244370 & 244372 TOC - 2

051121

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 19.13 Geotextiles for Exterior Improvements

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 24 00 Dredging

35 31 23 Riprap Revetment

DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT

44 22 50 Turbidity Control and Sediment Monitoring

APPENDIX

A Fort Jefferson Counterscarp Materials Tests Report, June 2022

B Petrographic Investigation of Mortar Sample from Fort Jefferson, June 2022

C Fort Jefferson Small Craft Dock Benthic Survey, January 2021

D Fort Jefferson Small Craft Dock Sediment Sampling, January 2021

E Waterfront Inspection Report Fort Jefferson South Coaling Dock, September 2020

F Underwater Inspection report Fort Jefferson Counterscarp, March 2019

G In-Situ Testing Report, June 2021

DRTO 244370 & 244372 01 11 00 - 1

051121 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Government-Furnished Materials

5. Contractor Use of Site

6. Public Use of Site

7. Occupancy Requirements for Buildings

8. Conduct of Operations

9. Work Restrictions

10. Special Construction Requirements

11. Soils Investigation Report

12. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Dry Tortugas National Park, Monroe County, Florida. Garden Key, located in the Gulf of Mexico, approximately 68 miles west of Key West. Garden Key is only accessible by boat or seaplane. The logistics of transporting personnel, supplies, materials and equipment to the Dry Tortugas and maintaining a productive construction site far from the mainland will require careful planning and coordination by the Contractor.

B. The Work consists of:

1. DRTO 244370 – Repairs to Fort Jefferson Counterscarp. The scope of this project involves selective repair to historic masonry. This project will include reconstruction of a collapsed section of counterscarp, replacing in-kind brick to match the historic fabric of the site, and repair of voids in the counterscarp.

2. DRTO 244372 – Dredging of Fort Jefferson Moat and Finger-slips and Piers at Garden Key Waterfront. The scope of this project involves the removal of hurricane accumulated sand deposits at Fort Jefferson. Dredging volume is approximately 3,000 CY and is located within the moat of the Fort and at the access finger slips. Dredged material will be stored/spread within the project boundaries.

3. This property is listed on the National Register of Historic Places (NR) and managed as a cultural resource asset. Historical significance extends to the entire site including all associated buildings, landscapes, engineering features and marine construction. This significance also extends to subterranean items including undiscovered or unexcavated

DRTO 244370 & 244372 01 11 00 - 2

archaeological resources. During construction care must be taken to protect all cultural and natural resources.

4. The site’s historical and environmental significance must be considered when planning and executing construction means and methods. All proposed work and modifications to historic features shall be in accordance with the Secretary of the Interior’s “Standards for the Treatment of Historic Properties with Guidelines for Preserving, Rehabilitating, Restoring and Reconstructing Historic Buildings.” Contractor shall proceed with care and attention to preservation concerns. Conservative and cautious approaches when working on or around this resource will be given precedence over radical and unproven methods.

Repair and retention of existing historic fabric is a priority. If potential exists for irreversible damage or loss of fabric, Contractor will cease work and seek guidance and approval from Contracting Officer (CO) before resuming work. Actions deemed detrimental to the resource or actions that place the resource at risk of damage or loss to its historic integrity, regardless of cause, will not be undertaken without prior review and approval by the Contracting Officer.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in phases to permit partial operation of the facility during construction and to accommodate allowable construction periods due to special conditions outlined in the environmental permits (TBD).

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.

B. Preceding Work: Government may award separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.

1. N/A (No separate contracts anticipated).

C. Concurrent Work: Government [may award] separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. N/A (No separate contracts anticipated).

DRTO 244370 & 244372 01 11 00 - 3

1.5 GOVERNMENT-FURNISHED MATERIALS (NOT USED)

1.6 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to work in areas indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to Contractor work area on the North Coaling Dock, work areas, approved travel/transit corridors, and designated staging areas shown on drawings.

B. While the Contractor Work Area shown on the drawings will be closed to the public during construction, the park needs to remain open to NPS personnel and the visiting public. If partial closure of is necessary for limited periods of time, the Contractor shall coordinate the details of this closure with the Contracting Officer. Use of the sally port will be restricted/limited by NPS from 10:30 am to 3:00 pm and when the sea plane is scheduled to be on site.

C. Contractor Barge Landing Area: The Contractor Barge Landing Area shown on the drawings will be available to Contractor vessels on a limited and temporary basis for loading and unloading of materials and equipment. The barge landing area may not be available to the Contractor when the concessionaire tour boat Yankee Freedom, NPS M/V Ft. Jefferson, or other official vessels (such as Coast Guard vessels) are scheduled to use the nearby main dock. Contractor vessels using the barge landing area will need to be relocated immediately following completion of their tasks. In order to provide temporary controls and limit public access to the area, the Contractor shall coordinate use of the barge landing area with the Contracting Office. Contractor shall provide a minimum of 48hrs notice of any Contractor vessel arriving at DRTO.

D. Limits on Number of Contractor Personnel: The Contractor’s crew (including Superintendent, foreman, laborers and subcontractor personnel) shall not exceed ten (10) individuals staying overnight on Garden Key and using water and sewage utilities during a 24-hour period.

E. Contractor Housing

1. There is one dormitory facility referred to as “The Crew’s Quarters” within the interior of

Front 2 with bunk beds (10 beds total) that the Contractor may use to accommodate its staff. The cost of these accommodations is $450.00 per night. If assigned different quarters, cost will be $45.00 per night per bed. Contractor shall include in its technical proposal the anticipated crew size. Further, during contract performance, the Contractor is responsible for tracking the number of beds used each month and making payment to Dry Tortugas National Park on a fixed payment schedule (every 3 months). The Contractor shall submit a report to the Government indicating the actual number of beds used by date with each payment. Facilities and supplies available in the Crew’s Quarters includes two toilets, two showers, one lavatory, one satellite television, three refrigerator/freezers, one freezer, one ice-maker, one microwave, two ranges/ovens, two coffee makers, pots, pans and tableware. The Contractor agrees that its staff shall not damage these accommodations and shall use reasonable amounts of electricity, water, and waste disposal. This requirement for conservation of electricity, water and waste disposal is required due to the remote location of the site and the Park’s schedule for waste and water management. No cleaning or other services are provided by the Government.

DRTO 244370 & 244372 01 11 00 - 4

2. Provisions: The Contractor and or Contractor’s personnel shall provide their own food, condiments, drinks, toiletries, pillows, bed/bath linens, and any other personal items for the length of their stay. Recreation items desired such as fishing/snorkeling gear, beach accessories, or flashlights must likewise be brought to the site by the Contractor and/or its personnel.

3. All food and drink containers such as plastic (all types), glass, tin and aluminum is recycled.

All recycled containers that have been brought to the island must be carried back to the mainland at the Contractor’s expense. Contractor is responsible for all recyclable material.

4. Government-provided composters shall be used for fruit and vegetable waste.

5. Recyclable material and domestic waste must be removed from the island at regular intervals of no more than every three weeks.

6. All food must be removed upon departure.

7. Water shall be conserved by taking quick showers and consolidating dirty dishes to be washed only once a day.

8. Housing units must be thoroughly cleaned daily and upon departure.

9. Quiet hours are from 10:00 PM to 7:00 AM.

10. Contractor employees are restricted from using the NPS staff Recreation Room.

11. Contractor is restricted from using the Park’s laundry facilities. The Contractor must arrange to have laundry processed off-site at Contractor’s expense.

12. Contractor is restricted from using NPS boats without prior approval.

F. Conduct

1. All Park regulations must be followed. Park regulations can be found at the following website http://www.nps.gov/drto/planyourvisit/ and http://www.nps.gov/drto/learn/management/compendiumregulations.htm

2. Do not litter.

3. All natural, archaeological, and historical features and artifacts are protected. Do not take or collect anything without a permit.

4. Avoid interaction or interfering with protected, endangered species. Do not kill, harm or interact with any wildlife. Do not feed or approach any wildlife.

5. Do not enter posted closed areas.

6. Do not stand on any sea grass or coral.

7. Fishing is only allowed with a current Florida State saltwater fishing license and per the following guidelines: https://www.nps.gov/drto/planyourvisit/fishing.htm

8. Smoking will not be permitted inside the Fort walls.

G. Transportation to the Project Site

1. The Contractor shall be responsible for all transportation of personnel.

2. The Contractor shall be responsible for procuring, shipping and handling all construction materials.

3. The Contractor shall be responsible for packaging, transporting and disposal of all construction debris and personal trash. Due to limited space on site, debris and trash shall be removed from the island at regular intervals throughout the contract period.

4. Only USCG-approved vessels shall be used for transport of equipment, material and personnel. Contractor shall provide written verification that vessels used in the completion of this contract are USCG-approved.

5. Commercial Modes of Travel: The following schedules may be affected by weather conditions and are subject to cancellation or change.

DRTO 244370 & 244372 01 11 00 - 5

a. Yankee Freedom III Ferry/Tour Boat Daily Schedule: Boat departs Key West at 8:00 AM with a 6:00-6:30 AM check in time for passengers with luggage and 7:00 AM

– 7:30 AM check-in time for passengers with only carry-on type bags.. The amount of personal supplies/gear that can be carried on the vessel is limited to no more than 60lbs dry weight. All passengers with luggage are required to pass through a luggage screening check prior to boarding. The screening process may include a search of the luggage. Equipment and supplies for construction should be transported via the National Park Service’s tender, M/V Fort Jefferson or other Contractor secured vessel. Transportation of supplies/equipment other than personal gear aboard the Yankee Freedom requires prior approval of the Captain and is subject to availability of space and freight charges. Ferry arrives at Fort Jefferson at approximately 10:15 AM and departs at 3:00 PM – check in at 2:30 PM. Approximately 2 ½ hours of travel time (each-way).

1) As of January 17, 2023 the rate for Contractors is $99.00 each way. Breakfast and lunch is included on outbound trips. Lunch can be purchased separately for $7.00. The contractor is responsible for verifying all rules and rates and accounting for any differences in actual costs versus rates included in this document.

2) Contractor reservations must be made online using the NPS Contractor/Cooperator dedicated website. This web address will be provided to the Contractor after award. Cancellations or changes to reservations may be made by telephone at 305-294-7009 or 1-800-634- 0939.

b. Key West Seaplane Adventures Daily Schedule: Flight times are subject to availability. Flights leave Key West Airport at 8:00 AM, 10:00 AM, 12:00 PM and 2:00 PM. Flights leave the Fort at 11:00 AM, 1:00 PM, 3:00 PM and 5:00 PM.

Approximately 45 min. flight time each way.

1) As of January 17, 2023, Contractor rates for traveling on the seaplane are

$371 for a 4 hour round trip. A full day (8 hour round trip) will cost $644 Contractor is responsible for verifying all rules and rates and accounting for any differences in actual costs versus rates included in this document.

2) Contact Key West Seaplane Adventures for weight limitations and lists of items that can and cannot be transported by air.

3) Contact Information: By phone: 1-305-293-9300, by website https://keywestseaplanecharters.com, and by email:

info@keywestseaplanecharters.com,

4) Key West Seaplane Adventures is not contractually obligated to transport persons other than park visitors and may refuse transportation of any individual not traveling to the park for public visitation.

6. National Park Service Crew Boat (Motor Vessel Fort Jefferson): The Government has a crew boat that may be available for the Contractor to arrange transportation for its construction personnel to the site rather than relying only on commercial modes of transportation. While the Contractor may make arrangements for its personnel to be transported to the construction site based on the Government crew boat’s availability and schedule, the Government crew boat’s schedule and availability is uncertain and subject to weather conditions and other operational requirements such as staff availability, boat repairs, etc. Since this alternative method of transportation might be available but is not being provided as Government-furnished property/services, the Contractor shall be responsible for determining what method to use to transport its personnel to the construction site. If the Contractor chooses to use the Government crew boat and the crew boat is unable to make a trip, the Contractor shall bear all responsibility and expense for transporting its crew to the site; and this shall not be recognized as a Government delay

DRTO 244370 & 244372 01 11 00 - 6

of work or be an acceptable reason for the Contractor to make a request for equitable adjustment or additional time under the contract. The Contractor shall be responsible for making arrangements for the Government crew boat with the park personnel.

Information and restrictions that apply to passengers on the Government crew boat include the following:

a. All food items must be placed in cardboard boxes or coolers labeled with the owner’s name.

b. All other cargo must be labeled and easily identifiable as to the owner of the property.

c. Prior Park (and USCG) approval must be obtained in order to gain access to the docking facilities at the West Trumbo Point Naval Annex main gate. NPS staff (crew of M/V Fort Jefferson) must escort passengers through the USN main gate and USCG gate. Truck deliveries require a driver with a TWIC card and inspection of the vehicle at the USN Key West Naval Air Station Boca Chica entrance station.

d. The trip is approximately 5-1/2 hours of travel time from Key West to Dry Tortugas.

The Government crew boat typically departs at 9:00 am from Key West Trumbo Point Naval Annex every other Tuesday. Return trips to Key West are generally the following Thursday, departing at 7:00 am from Dry Tortugas. There would be no charge for use of the Government crew boat when used with the normal operational schedule and solely for the transportation of Contractor personnel, groceries and personal items. Scheduled trips are generally every other week. The Government crew boat is unavailable when the crew have scheduled leave, training, scheduled maintenance at a shipyard or have chartered trips supporting research. On an annual average basis, the Government crew boat will make approximately 18 resupply trips to Dry Tortugas.

e. Arrangements for use of the Government crew boat shall be made at least two weeks in advance of travel.

f. All Contractor personnel cargo must be loaded, secured and unloaded by the Contractor or its personnel with guidance from the motor vessel Fort Jefferson crew.

Contractor is not permitted to use crane on vessel. Crane shall be operated by ship’s crew. The Government is not responsible for lost or damaged goods.

g. The Contractor and Contractor’s personnel or subcontractors’ personnel must present proper identification at the naval base gate and be escorted to the boat by a crew member of the M/V Fort Jefferson. The Government will not be responsible for personnel unable to access the boat prior to departure.

h. Private vehicles may not be parked overnight on the base. A small parking area is located directly outside the main gate and can be used to park privately owned vehicles. The Government shall not be liable for vehicle damage or theft if the Contractor’s or subcontractor’s personnel park their vehicle at this site.

i. Entry to the naval base may be denied anytime the national security level is elevated to orange or red or the naval base determines the individual(s) may not enter.

j. The Contractor shall be responsible for completing liability waivers for each person traveling on the Government crew boat. These waivers must be presented to the captain prior to the Government crew boat getting underway.

H. Storage of Materials: Confine storage and stockpiling of materials to staging and storage area shown on plans.

I. Parking: Site is not accessible by over-land vehicles. Contractor is to confine any vehicles or equipment to the staging areas shown on plans. Contractor shall prepare a Storage Plan that

DRTO 244370 & 244372 01 11 00 - 7

describes what equipment and materials will be housed on the island and where it will be stored during regular working conditions as well as during major weather events.

J. Preservation of Natural Features: The Contractor will take special care to protect areas and features of the site and surrounding water/marine environment that are not to be disturbed from the work in progress.

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

6. Position scaffolding, formwork, equipment, and temporary staging so as to avoid impacts to sessile marine organisms such as coral and sponges. National Park Service will provide a qualified biologist to identify State-listed plant species that could be affected by the project and investigate the potential for relocating individual plants. Notify the Contracting Officer if impacts are anticipated.

7. In the event that natural features are inadvertently damaged, Contractor shall notify Construction Management Representative immediately.

K. Preservation of Cultural Resources

1. Due to the elevated historic status of this resource, preservation treatment approaches must concur with The Secretary of the Interior’s “Standards for the Treatment of Historic Properties,” along with The Secretary of the Interior’s Guidelines for Treatment of Cultural Landscapes.”

2. This property is a National Historic Landmark and it will continue to be managed as an important resource. It may contain historic features that include buildings, structures, landscapes and associated landscape features (sidewalk, planters culverts, fences, site walls, retaining walls, etc. and engineering features such as bridges, towers, lighthouses, etc.) It is also possible that certain site features within the project boundary are not mentioned in the NR document, but those unnamed items are considered potentially eligible and are treated with the same level of concern.

3. During construction, care must be taken to protect cultural resources. When planning construction means and methods, preservation and protection of this resource is paramount. Contractor will proceed with care, using conservative and cautious approaches when working on and around historic fabric. Recognized and approved methods, favoring hand tools over power tools along with demonstrated experience and skill, will take precedence over radical and unproven procedures. If potential exists for irreversible damage or loss of fabric, contractor will cease work and seek guidance and approval from CO (Contracting Officer) before resuming work. Actions deemed detrimental to the resource, that would otherwise place the resource at jeopardy of loss to its historical integrity, regardless of cause, will not be undertaken without prior review and approval by CO.

DRTO 244370 & 244372 01 11 00 - 8

L. Driveways and Entrances: Keep walkways, boardwalks, sally port and counterscarp clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries, pick-ups/removals to minimize use of docks, seaplane ramp, counterscarp and sally port. Major delivery or pick-up of material shall not take place during peak visitor use times (10:00 am – 3:00 pm).

2. Schedule deliveries, pick-ups/removals to minimize space and time requirements for storage of materials and equipment on-site.

M. Construction Camp: Establishment of a camp within park will not be permitted. Contractor will have access to on-site living quarters for the duration of the work. The Contractor may propose to house its staff or subcontractors on boats in the harbor as long as the boats are self-contained and the contractor does not use the park’s facilities to dispose of sewage/gray water. If the

Contractor proposes to house staff or subcontractors on boats in the harbor, the Contractor shall be responsible for storing and hauling out of the park, and surrounding waterways, the sewage/gray water to an appropriate treatment facility.

N. Telephone/Internet Communications Systems: There is no hard line on site for telephone/internet communications. Contractor shall be responsible for their own telephone and internet communications systems. Close coordination with Park personnel will be necessary to establish where equipment components can or cannot be located. Contractor shall receive approval from the Contracting Officer before installing any communications equipment.

O. Hauling Restrictions: Vehicles shall not be driven inside the Fort unless moving materials or debris. Comply with all legal load restrictions in the hauling of materials. (Dimensions of bridge and counterscarp and associated load restrictions are indicated on drawings). Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

P. Contractor shall install temporary roadway surface or protective mats along haul route within the fortification between parade ground and Sally Port to minimize damage to existing turf and protect significant archeological deposits known to exist in the area.

Q. Hurricane Plan: A copy of the most recent version of the Everglades/Dry Tortugas Hurricane Plan will be provided to the awarded Contractor. The hurricane plan shall be provided as reference for the development of safety and storm preparation plans by the Contractor.

1.7 PUBLIC USE OF SITE

A. The facility will not be fully closed to the public during construction.

B. Contractor shall conduct his operations to ensure the least inconvenience to public. Sally Port closures to facilitate the work will be permitted, when required, before 10:00 am and after 3:00pm, upon specific approval of the Contracting Officer.

C. At any given time, no less than four [4] vessel slips at the finger piers shall be operational/available for Government, administrative, and public use.

DRTO 244370 & 244372 01 11 00 - 9

1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings and Facilities

1. Partial Government Occupancy: Government will occupy premises during entire construction period, with exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government’s operations.

Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. Repair damage caused by construction operations. Protect building and its occupants during construction period.

1.9 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work at night (after 6:00pm) may not be performed without prior consent from the Contracting Officer. Submit requests 3 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

D. Contractor is permitted to work on Federal and State holidays.

1.10 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 6:00 p.m., seven days a week, except when otherwise indicated or approved by the Contracting Officer.

1. Noisy activities (use of jackhammers, heavy equipment, etc.) shall occur between 8:00 a.m.

and 5:00 p.m.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and Park Facilities Maintenance Supervisor of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, consult Contracting Officer and Park Point of Contact prior to repairs being made.

DRTO 244370 & 244372 01 11 00 - 10

3. If damage occurs to an unknown utility, consult Contracting Officer and Park Point of Contact prior to repairs being made. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within walls of Fort Jefferson or within 25 feet of entrances, operable windows, or outdoor air intakes. Debris/waste shall be collected and not enter the waterway. Smoking is not permitted within the Fort walls.

1.11 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by NPS or contracted construction management firm will be used for purposes of managing communication and documents during construction stage.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using Project Website.

B. Restricted Work Periods: The following periods are subject to additional work/site access restrictions:

1. Sooty Tern Nesting Season; February 01 to September 30 – no work may take place on the isthmus connecting Garden and Bush Keys

2. Loggerhead Turtle Nesting Season: May 01 to September 30 – no work may take place on or near the indicated beaches. This includes excavation, material handling, storage, vessel landing, or any activity that may disturb the beach in any way.

3. Atlantic Hurricane Season: June 01 to November 30 – Contractor shall be prepared to comply with Park emergency storm preparedness procedures which will include securing all equipment, materials, and work and evacuating the site if required/directed by the Contracting Officer.

a. Contractor shall develop and maintain a severe weather/hurricane plan that enables them to secure all resources and materials within 72 hours of projected landfall and be able to demobilize all personnel from Garden Key no later than 48 hours from projected landfall.

4. Contractor to develop a vessel landing/access plan and submit for approval.

C. No off-season temporary storage will be provided at Garden Key.

D. Contractor is solely responsible for all contents on site during the construction period and temporary barriers shall be designed to withstand extreme weather events.

DRTO 244370 & 244372 01 11 00 - 11

1.12 SOILS INVESTIGATION REPORT

A. The report Geotechnical Exploration and Remediation Recommendations, May 2022, prepared by Bhate Geosciences, Inc. is available as an appendix with this package.

B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.

1.13 ADDITIONAL REPORTS

A. The report Ft. Jefferson Counterscarp Materials Tests, June 2022 prepared by Atkinson-Noland & Associates is an appendix with this package.

B. The report Petrographic Investigation of One Mortar Sample From Fort Jefferson National Monument Located in Dry Tortugas National Park, Florida, June 2022 prepared by DRP Petrographic & Materials Investigations is an appendix with this package.

C. The report Fort Jefferson Small Craft Dock Benthic Survey, January 2021 prepared by Schneider Engineering & Consulting is an appendix with this package.

D. The report Fort Jefferson Small Craft Dock Sediment Sampling, January 2021 prepared by Schneider Engineering & Consulting is an appendix with this package.

E. The report Waterfront Inspection Report Fort Jefferson South Coaling Dock, September 2020 prepared by Collins Engineers, Inc. is an appendix with this package.

F. The report Underwater Inspection Report Fort Jefferson Counterscarp, March 2019 prepared by Collins Engineers, Inc. is an appendix with this package.

G. The report In-situ Testing Report, June 2021 prepared by Atkinson-Noland & Associates, Inc. is an appendix with this package.

H. In case of conflict between a report and drawings or specifications, drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

DRTO 244370 & 244372 01 26 01 - 1

012721 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

DRTO 244370 & 244372 01 26 01 - 2

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

DRTO 244370 & 244372 01 26 01 - 3

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

DRTO 244370 & 244372 01 26 01 - 4

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

DRTO 244370 & 244372 01 26 01 - 5

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit……………...……8%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

DRTO 244370 & 244372 01 26 01 - 6

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 26 01

DRTO 244370 & 244372 01 27 00 - 1

012721 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

C. The contract line items listed below relate to two PMIS, to be lumped under one contract:

1. DRTO 244370 – Repairs to the Fort Jefferson Counterscarp

2. DRTO 244372 – Perform Dredging of Fort Jefferson Moat and Finger-Slips and Piers at

Garden Key Waterfront

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEM NUMBER (CLIN)

A. Contract Line Item Number 1, BASE – Mobilization, Demobilization & Temporary Facilities for work related to repairs of the Fort Jefferson Counterscarp

1. This item consists of mobilization and demobilization of all required personnel, equipment, and materials to and from Garden Key and housing of personnel at Fort Jefferson for the completion of the work under DRTO 244370 – Repairs to Fort Jefferson Counterscarp.

2. Measurement for payment: No measurement required.

3. Payment will be made based on review of updated schedule of values submitted with progress payments, totaling the contract lump sum price.

B. Contract Line Item Number 2, BASE – Repairs to Fort Jefferson Counterscarp

1. This CLIN includes, but is not limited to, costs for project management, home office support, quality control related tasks throughout the duration of the Project, costs for compliance with environmental permit requirements and environmental monitoring and protection measurements, all labor, materials, and equipment to complete the repairs to the

Fort Jefferson Counterscarp.

The work covered under this CLIN includes repairs to the concrete walkway, masonry brick repair, underwater concrete void repair, sluice gate pedestrian walkway, foundation and void repair under the counterscarp, and discrete counterscarp reconstruction. Base quantities and work items are outlined in the table of “Summary of Irma Repairs” on Sheet

S6.1 of the Contract Drawings.

DRTO 244370 & 244372 01 27 00 - 2

2. Measurement for payment: Contractor will submit a cost loaded schedule in accordance with Section 01 32 16 outlining percent complete during the billing period.

3. Payment will be made based on monthly invoices.

C. Contract Line Item Number 3, BASE – Mobilization, Demobilization & Temporary Facilities for

Dredging of Fort Jefferson Moat and Finger Slips and Piers at Garden Key Waterfront

1. This CLIN item consists of mobilization and demobilization of all required personnel, equipment, and materials to and from Garden Key and housing of personnel at Fort

Jefferson for the completion of the work under DRTO 244372 – Dredging of Fort Jefferson

Moat and Finger Slips and Piers at Garden Key Waterfront.

2. Measurement for payment: No measurement required.

3. Payment will be made based on review of updated schedule of values submitted with progress payments, totaling the contract lump sum price.

D. Contract Line Item Number 4, BASE - Dredging of Fort Jefferson Moat and Finger Slips and

Piers at Garden Key Waterfront

1. This CLIN includes, but is not limited to, costs for project management, home office support, quality control related tasks throughout the duration of the Project, costs for compliance with environmental permit requirements and environmental monitoring and protection measurements, all labor, materials, and equipment to complete the dredging work.