This solicitation requests proposals for repairs to the Fort Jefferson counter scarp wall and dredging at the Fort Jefferson Moat and finger slips at Garden Key in Dry Tortugas National Park. Proposals are due by August 25, 2023. The contract will be awarded as a firm fixed price contract valued at approximately $2.5 million. Small business participation goals include 44.8% for small business in general, with 5% each for small disadvantaged, women-owned, and HubZone businesses and 3% each for service-disabled veteran-owned small businesses and Alaska Native Corporation-owned firms. The National Park Service is the contracting agency. The scope of work involves rebuilding a collapsed section of the counter scarp wall, repairs to wall sections above and below water, addressing underwater voids and reinforcement of selected areas, as well as dredging and placement of approximately 3,000 cubic yards of material.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # 140P2023R0033
PARK/PMIS DRTO 244370/244372
Name Email Tim Pernsteiner tpernsteiner@michels.us Berg, Josiah Josiah.Berg@hdrinc.com Kyle Adkins kyle.adkins@ballardmc.com Ben Peterson bpeterson@michels.us Smith, Michael E michael_smith@contractor.nps.gov Graham Cofer graham.cofer@ballardmc.com Roe, Christine L Christine_Roe@nps.gov Andrew McFerrin amcferrin@michels.us Gottshall, Tree Tree_Gottshall@nps.gov Mike Henderson mhenderson@blm.gov Cole Fairey cfairey@michels.us Bobby Brown bbrown@chcmarine.com Christopher Dabek cdabek@stoneandlime.com Danielle May danielle.may@ballardmc.com Brice, Benjamin benjamin.brice@hdrinc.com David Cizek d.cizek@gatordredging.com Diaz, Sabrina L Sabrina_Diaz@nps.gov Dean, Tylan F tylan_dean@nps.gov Marybeth Petracone mpetracone@stoneandlime.com Hugh Murray hmurray@michels.us Eric Summers esummers@uwmechanix.com Shafer, Matthew W matthew_shafer@nps.gov
Virtual Industry Day Attendance List
Virtual Industry Day Meeting Minute Transcripts Solicitation # 140P2023R0033
PARK/PMIS: DRTO 244370/244372
0:0:0.0 --> 0:0:3.440
Smith, Michael E
Access to that recording, UM later as we go through the slides.
0:0:3.990 --> 0:0:5.420
Smith, Michael E
UMI.
0:0:5.600 --> 0:0:7.80
Smith, Michael E
You hold the questions until the end.
0:0:7.90 --> 0:0:9.900
Smith, Michael E
I do have a slide for questions on here.
0:0:10.860 --> 0:0:11.460
Smith, Michael E
Umm.
0:0:11.780 --> 0:0:13.410
Smith, Michael E
So yeah, let's go ahead and get started.
0:0:13.540 --> 0:0:15.960
Smith, Michael E
As I said, my name is uh Mike Smith.
0:0:16.640 --> 0:0:27.380
Smith, Michael E
Uh, today we're here for the virtual today, for the repairs to the Fort Jefferson counter scarp and some dredging at the Fort Jefferson Moat and finger slips at Garden Key at Draco Tugas National Park.
0:0:28.190 --> 0:0:48.460
Smith, Michael E
The solicitation was posted under uh solicitation #140P2023R0033 on sam.gov the park identifier or
Pmis identifier is DRT 0 or DRT O 244370 slash 244372.
0:0:48.630 --> 0:0:49.670
You often see these?
0:0:49.880 --> 0:0:54.10
Umm, these uh park identifiers on our projects.
0:0:54.20 --> 0:0:58.830
Smith, Michael E
If you're not familiar with working with the National Park Service, this is this how we identify our projects.
0:0:59.40 --> 0:1:1.10
Smith, Michael E
This is the part Dry Tortugas.
0:1:1.20 --> 0:1:6.10
Smith, Michael E
This is the projects, so this would be the counter scarf and this is going to be the dredging.
0:1:6.450 --> 0:1:8.340
Smith, Michael E
Let's go ahead and get into the slides so.
0:1:11.890 --> 0:1:13.100
Smith, Michael E
You slide mode as well.
0:1:13.290 --> 0:1:19.700
Smith, Michael E
So for the agenda I have, uh, today I'll go through the introductions.
0:1:20.10 --> 0:1:24.220
Smith, Michael E
I have our solicitation milestones and our solicitation requirements.
0:1:24.450 --> 0:1:34.980
Smith, Michael E
I'll go through our site layout and orientation, talk a little bit about our project background, our scope of work, our major areas of work and our key items.
0:1:35.70 --> 0:1:40.0
Smith, Michael E
And then our upcoming formal site visit and the planning for that and then I'll open it up.
0:1:40.10 --> 0:1:49.70
Smith, Michael E
As I said before, for some industry day questions that we'll try to address and then we'll conclude on how we can get access to all this information.
0:1:50.950 --> 0:1:52.880
So as I said, I'll go through introductions.
0:1:52.890 --> 0:1:53.900
Smith, Michael E
My name is Mike Smith.
0:1:53.910 --> 0:1:55.360
Smith, Michael E
I'm the contract specialist.
0:1:55.610 --> 0:2:1.940
Smith, Michael E
UM, I have with me John Badcock, our contracting officer, our project manager Chrissy Rowe.
0:2:1.950 --> 0:2:9.660
Smith, Michael E
Our project specialist, Matt Schaefer, our designer of record HDR engineering, they're representative just Seiberg.
0:2:9.790 --> 0:2:18.470
Smith, Michael E
And then just for information purposes, we will have an on site construction management representative, which will be a third party company to be selected off the GSA.
0:2:21.820 --> 0:2:22.330
Smith, Michael E
Umm.
0:2:23.0 --> 0:2:26.610
Smith, Michael E
Are milestones that we you know that we're keeping for this solicitation.
0:2:26.620 --> 0:2:34.230
Smith, Michael E
We posted this solicitation back on June 26, so almost about a month ago today, we're holding the
Industry Day meeting.
0:2:34.240 --> 0:2:48.930
Smith, Michael E
This meeting is just, you know, gauge interest from the public and try to address as many questions as we can before we get to that formal site, visit our formal site visit is planned to be held on August 9th, 2023 at 11:00 AM.
0:2:49.180 --> 0:2:57.920
Smith, Michael E
I have another slide later in in these in this presentation discuss more of that because I know that will be a hot topic for getting out there.
0:2:58.770 --> 0:3:4.300
We're asking the pre bid request for information are all submitted by August 14th.
0:3:4.970 --> 0:3:19.600
Smith, Michael E
If you have you know pre bid rfis already ready, go ahead and start getting them in so we can get those addressed quickly because we're hoping we can turn those around in about four days time and get those posted via amendment August 18th.
0:3:20.450 --> 0:3:23.220
Smith, Michael E
Right now our proposal due date is August 25th.
0:3:23.230 --> 0:3:39.840
Smith, Michael E
We're hoping that hard due date and that does not need to be changed because we post we you know post this back in June 26, so roughly 60 days out there and we want to get this award at this fiscal year, although the funds do not expire.
0:3:40.50 --> 0:3:46.460
Smith, Michael E
We're just hoping we can get this awarded this fiscal year by September 15th as I had estimated up there on the slides.
0:3:46.850 --> 0:3:50.650
Smith, Michael E
This will be a 365 calendar day period of performance.
0:3:50.660 --> 0:3:56.370
Smith, Michael E
We're hoping we can issue that mobilization notice to proceed on numbers November 6, 2023.
0:3:56.700 --> 0:3:58.890
Smith, Michael E
This will be a firm fixed price contract.
0:3:59.260 --> 0:4:13.20
Smith, Michael E
It's being solicited under full and open competition reminder that if you are a large business, you must submit a subcontracting plan the next for this requirement is 237990 and the small business size standard for that is 45 million.
0:4:13.770 --> 0:4:18.960
Umm, just as you know, heads up the heads, the hub zone.
0:4:18.970 --> 0:4:23.210
Small business concern clause evaluation is included.
0:4:26.160 --> 0:4:40.730
Smith, Michael E
So some of the solicitation requirements that I wanna remind everyone when uh submitting a proposal is to ensure that you complete blocks 14 through 20 C and also acknowledge all amendments that we post.
0:4:40.740 --> 0:4:43.330
Smith, Michael E
I have already posted one amendment on sam.gov.
0:4:43.340 --> 0:4:48.330
Smith, Michael E
I'm probably going to be posting at least three or four more with the this industry day.
0:4:49.220 --> 0:4:54.380
Smith, Michael E
The site visit and the rfis and dependent on anything else that comes up.
0:4:54.460 --> 0:5:2.440
Smith, Michael E
Also remember to complete special requirements two and three for the key personnel and the key trades of the SF 1442.
0:5:3.10 --> 0:5:14.510
Smith, Michael E
Make sure you complete your section K of this 1442 and for the submission of the proposal, make sure you include a PDF copy separately for the technical proposal and the price proposal.
0:5:16.820 --> 0:5:32.620
Smith, Michael E
Are solicitation technical proposal requirements will be for the project, for the factors which are the project experience, key trade, technical approach, schedule management approach, past performance and then your small business participation.
0:5:34.830 --> 0:5:36.930
Smith, Michael E
Uh, I'm not going to read these slides verbatim.
0:5:36.940 --> 0:5:38.500
Smith, Michael E
This is what's in the solicitation.
0:5:38.510 --> 0:5:54.40
This is just a reminder for what the requirement for project experiences will be looking at anywhere from one to five projects that you're willing to submit from the past seven years that are similar in complexity and size of this current project.
0:5:54.50 --> 0:5:58.500
Smith, Michael E
Make sure they address your natural, cultural, or historic resources.
0:5:59.170 --> 0:6:13.160
Smith, Michael E
Your remote construction experience and your team experience with your subcontractors that you identify as key Subs, which is uh, and we are requesting that you are completing at least 30% of the cost of this contract excluding materials.
0:6:15.580 --> 0:6:20.770
Smith, Michael E
For the key trades, we're also accepting one to five projects from the last seven years.
0:6:20.780 --> 0:6:28.130
Smith, Michael E
We know there's gonna be a lot of complex requirements on this subcontracting's gonna most likely play a huge part.
0:6:29.180 --> 0:6:37.930
Smith, Michael E
So if you are subcontracting these projects, these sections, you may submit their project experience with the project experience forms.
0:6:37.940 --> 0:6:39.980
Smith, Michael E
It's included for these.
0:6:41.220 --> 0:6:46.210
Smith, Michael E
Reidentified sections of the work with the technical approach.
0:6:46.220 --> 0:6:46.670
Smith, Michael E
Please.
0:6:46.940 --> 0:7:7.510
Smith, Michael E
Identify your, you know, approach to the critical contract requirements that we've identified your means and methods for the masonary that you're reconstruction of the wall, the repairs of the undermined areas, the counter scarf damage, and make sure your technical approach really aligns with what your schedule was.
0:7:7.830 --> 0:7:10.900
I'm stating so you'll see coming up.
0:7:11.50 --> 0:7:18.920
We have schedule as another solicitation requirement, so make sure your technical approach and your schedule kind of complementing each other.
0:7:19.350 --> 0:7:28.750
Smith, Michael E
So there is also a narrative for your schedule where asking that your schedule requirements starts with the November 6th date that I estimated previously.
0:7:29.630 --> 0:7:45.400
Smith, Michael E
Umm for our mobilization, please provide an again chart for your schedule and then a A a schedule narrative that explains your approach to your contract, critical path items and your risk analysis.
0:7:45.410 --> 0:7:48.160
Smith, Michael E
So these are very important items for this project.
0:7:48.550 --> 0:7:52.670
Smith, Michael E
We know schedule and logistics is going to play a heavy part in completing this work.
0:7:54.680 --> 0:8:0.210
Smith, Michael E
Again, we are asking for a management approach as well, limited to 7 pages.
0:8:0.740 --> 0:8:18.960
Smith, Michael E
Logistic coordination process should be something you want to pay heavy attention to and spelling out in your management approach along with your roles and responsibilities and how you plan to gauge the owner, which is us, the SEC and the park and any other he member of the project.
0:8:22.390 --> 0:8:42.110
Smith, Michael E
Past performance for so for any of those projects, experience forms you complete for factors one and two, ensure that you're completing that past performance requirement or past Performance
Questionnaire as well for those projects or if you have a Peppers or CPARS for that already submitted in the system, you can just include the Peppers as backup for those experience forms.
0:8:44.940 --> 0:8:47.170
Smith, Michael E
Small business participation is required.
0:8:47.180 --> 0:8:55.880
Smith, Michael E
Small business participation will be given 100% for any small business concern that is submitting UM for those large business submitting.
0:8:55.890 --> 0:9:13.190
Ensure that you at least meet the 20% required to be submitted or be set aside for small business concerns on this project, and then anything meeting or above the standard of the UM subcontracting plan that is required.
0:9:13.200 --> 0:9:14.550
Smith, Michael E
We have goals in there.
0:9:14.600 --> 0:9:16.610
Smith, Michael E
Uh will be evaluated more favorably.
0:9:19.260 --> 0:9:23.910
Smith, Michael E
Uh, just require reminders for the price proposal and sure, you complete section B.
0:9:23.920 --> 0:9:32.510
Smith, Michael E
The contract price schedule and also provide a separate schedule of values for each line item of this section B contracts price schedule.
0:9:33.860 --> 0:9:42.290
Smith, Michael E
Also include as SF 24 bit bond along with general references and your small business subcontracting plan.
0:9:42.550 --> 0:9:52.180
Smith, Michael E
We've included a template for your subcontracting plan and the goals are included within and I'll talk a little bit more about those later or now.
0:9:52.270 --> 0:9:56.710
Smith, Michael E
Uh, our small business subcontracting plan is required for all large businesses.
0:9:56.720 --> 0:10:1.460
Smith, Michael E
You can kind of see what how we've laid out our goals to 44.8% is what we're aiming for.
0:10:1.520 --> 0:10:2.710
Smith, Michael E
Small business in general.
0:10:3.560 --> 0:10:21.910
Small disadvantage is 5% women owned is 5%, hub zone is 3%, service disabled veteran is 3% and then what we call SB or Indian Small Business Economic Enterprises or 3% our basis for the award for this contract will be as a best value.
0:10:21.920 --> 0:10:24.550
Smith, Michael E
So we're not using lowest price technically acceptable.
0:10:24.560 --> 0:10:35.60
Smith, Michael E
We are using best value based on those technical factors that just laid out and they are listed in just descending order from most important to least important.
0:10:37.460 --> 0:11:0.670
Smith, Michael E
Umm, we'll assemble a TEP uh after proposals are due or tap panel will evaluate you based on those factors we spelled out in the solicitation under L&M and then we will hopefully not have to enter into to discussion since we are getting our proposals and August 25th.
0:11:0.680 --> 0:11:2.890
Smith, Michael E
So we want to get that award out this fiscal year.
0:11:2.900 --> 0:11:6.640
Smith, Michael E
We wanna enter into a war without discussions.
0:11:10.440 --> 0:11:16.590
Smith, Michael E
Again, our technical factors are in descending order from one through 5 of order of importance.
0:11:16.960 --> 0:11:21.30
Smith, Michael E
Past performance is less important than all technical factors are combined.
0:11:21.940 --> 0:11:28.90
Smith, Michael E
Proposed pricing is significantly less important than the technical factors or is it's worded.
0:11:28.260 --> 0:11:32.650
Smith, Michael E
The technical factors combined are all significantly more important than the price.
0:11:33.650 --> 0:11:36.680
Smith, Michael E
Again, this will be rewarded under the best value, not lowest price.
0:11:36.690 --> 0:11:39.320
Technically acceptable are optional.
0:11:39.330 --> 0:11:53.190
Line items are line items 4 through 9 which are included to be unilaterally executed within 90 calendar days after award offers must provide at least 45 calendar days for government acceptance of their proposal.
0:11:56.740 --> 0:12:0.830
Smith, Michael E
Submit a minimum of an offer that conforms with the solicitation documents.
0:12:1.160 --> 0:12:5.810
Smith, Michael E
Proposals that have alternates will not be considered or accepted.
0:12:6.20 --> 0:12:10.550
Smith, Michael E
If you would like to propose an alternative, please do so in the form of a pre bid request.
0:12:10.560 --> 0:12:19.630
Smith, Michael E
For information prior to the formal submission in the proposal, just remind her any firm that participated in the design.
0:12:19.640 --> 0:12:27.980
Smith, Michael E
So any HDR engineering or any of their subcontractors who participated in this design cannot compete in the construction award.
0:12:30.210 --> 0:12:33.990
Smith, Michael E
I'm going to go ahead and actually turn it over to our project manager for this section.
0:12:34.0 --> 0:12:40.740
Smith, Michael E
They're going to walk us through our project logistics and uh, you know, our project background, Chrissy.
0:12:42.740 --> 0:12:45.540
Roe, Christine L
Thanks so here.
0:12:45.550 --> 0:12:51.560
Roe, Christine L
Umm, just orientation map for Jefferson is located on the island of garden.
0:12:51.570 --> 0:12:57.500
Roe, Christine L
Key you can see it there in red on both of the maps, which is about 70 miles West of Key West.
0:12:57.950 --> 0:12:58.450
Next slide.
0:13:1.450 --> 0:13:4.30
Roe, Christine L
The little project background orientation.
0:13:4.810 --> 0:13:9.680
Roe, Christine L
This view shows the East and SE fronts of felt of Fort Jefferson.
0:13:10.110 --> 0:13:16.260
Roe, Christine L
You see the South cooling dock and main dock on the left and then on the right you see the North cooling dock.
0:13:16.350 --> 0:13:20.230
Roe, Christine L
The large green area in front is called Bush Key, and that's not in the project.
0:13:21.390 --> 0:13:28.560
Roe, Christine L
Uh for Jefferson is listed on the National Register of Historic Places and it is managed as a cultural resource for the MPs.
0:13:28.970 --> 0:13:37.650
Roe, Christine L
This historic significance extends for the entire site that includes buildings engineering features, landscape marine construction next.
0:13:41.990 --> 0:13:46.700
Roe, Christine L
So this photo it's a good view of the Fort and interior parade grounds.
0:13:47.30 --> 0:13:53.20
Roe, Christine L
We're looking at the West and southwest sides, which is front two and 3/4 Jefferson.
0:13:53.510 --> 0:14:5.880
Roe, Christine L
The main doc finger slips and peers and South cooling dock are located on the right hand side on the front, so the outer brick wall of the mote the counter scarp is the sea wall surrounding the Fort.
0:14:6.310 --> 0:14:16.930
Roe, Christine L
It both protects the Fort from the Ocean's energy, and it's very popular feature for visitors with The
Walking and snorkeling, and we'll be focusing a lot on that on this project.
0:14:17.540 --> 0:14:22.650
As you can see, the section of the collapsed counter score of wall is in the front left.
0:14:22.940 --> 0:14:24.190
Roe, Christine L
There's a breach in the wall.
0:14:24.200 --> 0:14:25.550
Roe, Christine L
Yeah, right there.
0:14:25.680 --> 0:14:35.940
Roe, Christine L
And then you can see one of the main dredging areas on the right hand side, it's all that sand that's in the mode in the front right next.
0:14:38.990 --> 0:14:46.40
Roe, Christine L
So here's a plan view of Port Jefferson, and one indicates the main doc.
0:14:46.50 --> 0:14:54.200
Roe, Christine L
It's on the lower right side on the southeast, area 2 is the proposed barge landing access area, again in the southeast.
0:14:54.870 --> 0:14:58.760
Roe, Christine L
Section 3 is the North cooling dock.
0:14:58.810 --> 0:15:6.680
Roe, Christine L
That's a staging area, or half of it is a stationary will be a staging area, 4 on the left side.
0:15:6.750 --> 0:15:10.0
Roe, Christine L
That's the breached wall section that's on front 3.
0:15:11.30 --> 0:15:14.220
Roe, Christine L
5 indicates dredging areas.
0:15:14.410 --> 0:15:14.830
Roe, Christine L
There is that.
0:15:14.840 --> 0:15:16.700
That's the north up there.
0:15:16.790 --> 0:15:22.0
Then on the bottom, there's the other two fives that there's the.
0:15:22.70 --> 0:15:24.640
Roe, Christine L
Yeah, right there are the finger Piers and slips.
0:15:24.650 --> 0:15:32.980
Roe, Christine L
And then the other area in the mode U and then let's see what we have 6 and there's four, you know?
0:15:33.290 --> 0:15:37.300
Roe, Christine L
Yeah, there's four main fronts or there are four fronts that we're doing.
0:15:37.410 --> 0:15:39.620
Roe, Christine L
Repairs to the counter scarf wall.
0:15:41.60 --> 0:15:48.730
Roe, Christine L
That's France, two to five that mikes pointing to, and then just seven in the center is the pre grounds in the center of the Fort.
0:15:50.720 --> 0:15:51.200
Roe, Christine L
Next slide.
0:15:54.370 --> 0:15:58.780
Roe, Christine L
So scope of work, you know, they're really like 2 main scopes of work.
0:15:58.790 --> 0:16:9.900
Roe, Christine L
One is repairs to the Fort Jefferson counter scope wall, which includes rebuilding the clap section while repairs to the counter scarp on all four fronts or on forefronts.
0:16:9.910 --> 0:16:25.510
Roe, Christine L
Of the six, it's the top of the wall interior remote side of the wall exterior ocean side of the wall, and the core in a few areas, as well as addressing underwater voids and rip rap to reinforce a few selected areas.
0:16:26.30 --> 0:16:38.210
Roe, Christine L
And then the other main work is dredging, sifting and placement of the dredging material, and the volume is about 3000 cubic yards.
0:16:41.50 --> 0:16:41.810
Next slide.
0:16:43.500 --> 0:16:55.100
Roe, Christine L
Ohh and now I was gonna hand over the next two slides to just Siah who is from HDR, just to talk about a little more technical on some of the repairs to the counter scarp wall.
0:16:58.100 --> 0:16:58.510
Berg, Josiah
OK, great.
0:16:58.520 --> 0:16:59.130
Berg, Josiah
Thank you, Chrissy.
0:17:0.100 --> 0:17:0.520
Berg, Josiah
Umm.
0:17:0.840 --> 0:17:3.960
Berg, Josiah
So as mentioned, there's potentially 2.
0:17:5.200 --> 0:17:10.60
Berg, Josiah
I mean portions of work on the project.
0:17:10.300 --> 0:17:19.110
Berg, Josiah
I'll talk about the first one, which which comprises of repairs to the counter scarf structure.
0:17:20.160 --> 0:17:27.130
Berg, Josiah
There's a number of deep texts that were identified in previous, umm inspections investigations.
0:17:28.180 --> 0:17:28.730
Berg, Josiah
Umm.
0:17:29.100 --> 0:17:38.840
Berg, Josiah
And listen those out here and on this sheet, which is actually part of the construction drawing package, you guys like they downloaded by now.
0:17:39.670 --> 0:17:48.740
Berg, Josiah
I'm first defect type is a loss of walkway for surface concrete surface on the counter scarf.
0:17:50.210 --> 0:17:52.960
This is not a defect.
0:17:52.970 --> 0:18:1.730
Berg, Josiah
That's because consistent through all the entire color script, but there are areas where where there are sections that have that we're lost.
0:18:2.280 --> 0:18:3.580
Berg, Josiah
And need to get repaired or replaced.
0:18:4.430 --> 0:18:6.630
Berg, Josiah
Umm, next to you that time?
0:18:7.260 --> 0:18:17.540
Berg, Josiah
Uh, actually, the two two next week that types, umm, are essentially repairs to the brick facade of both
Bove and below the water.
0:18:19.70 --> 0:18:21.630
Berg, Josiah
And I think that is you 2 examples of that right here.
0:18:23.990 --> 0:18:35.420
Berg, Josiah
The obviously the the the repairs to to masonry above water are fairly straightforward, but there's gonna be a good bit more technical.
0:18:37.730 --> 0:18:42.710
Berg, Josiah
Requirements here for the blow water as far as how that work gets completed.
0:18:45.130 --> 0:18:53.540
Berg, Josiah
Umm, the next feedback type, which involves some existing scar pits or undermining them in the structure.
0:18:53.790 --> 0:18:54.280
Berg, Josiah
Connor square.
0:18:55.520 --> 0:19:8.320
Berg, Josiah
Those have been identified in the construction, drawings and plan view area umm, and that that will require replacement of that feel beneath the college group.
0:19:11.330 --> 0:19:32.930
Umm, the last defect you identified on on this sheet is what what we're referring to as core damage and what what it appears is that the counter scarp is starting to it's starting to fracture and and split down the center.
0:19:32.940 --> 0:19:41.970
Berg, Josiah
So we consider that the the core of this structure and some bracing will be required to to shore that up and and maintain stability.
0:19:44.40 --> 0:19:44.480
Berg, Josiah
Umm.
0:19:45.100 --> 0:20:0.570
Berg, Josiah
Last but not least, at the top rate photo, this slide is is Christy mentioned earlier, there is a structure that that actually has completely failed and collapsed that will require removal of the debris and reconstruction of that of that section terribly.
0:20:2.210 --> 0:20:7.760
Berg, Josiah
And then the last best bottom slide here is to view the counter scarf and some of the varying conditions.
0:20:7.820 --> 0:20:9.740
Berg, Josiah
It's next slide.
0:20:13.840 --> 0:20:23.150
Berg, Josiah
As mentioned, the kind of second bucket of work on the project is is the maintenance stretching and there's kind of three narrative 3 main errors that need to get addressed.
0:20:24.60 --> 0:20:50.180
Berg, Josiah
The North and South portions of the Mote, and if you can manage your back on the plan view of the of the site, the North mode is essentially the North East corner of the site or bastion to five, and the South
Note is the southwest corner probation number. Fashion #1.
0:20:51.380 --> 0:20:53.640
Berg, Josiah
Umm, the finger pears?
0:20:55.140 --> 0:21:1.280
Of course it as they, as they suggest, are our docs, existing docs on site.
0:21:2.120 --> 0:21:13.960
Umm that some of the areas between them have have showed in and those require said maintenance dredging to restore birth access to Park Service and and visitors.
0:21:16.210 --> 0:21:41.960
Berg, Josiah
Umm, as described in the construction drawings and specifications, the intent removal of all this material has been has been fairly easily laid out and as far as where specific locations need to get get placed and filled and how that material is is sorted, sifted clean.
0:21:42.150 --> 0:21:42.660
Berg, Josiah
What have you?
0:21:44.170 --> 0:21:47.50
Berg, Josiah
Of course, if you have any questions with that, you know it's Christy mentioned earlier.
0:21:48.430 --> 0:21:50.350
Berg, Josiah
Pleased to submit that in the RFI process.
0:21:56.940 --> 0:21:57.180
Roe, Christine L
Yep.
0:21:52.840 --> 0:21:57.340
Berg, Josiah
Umm, Chris, I believe I'm done with this slide, so if you wanna take over.
0:21:58.70 --> 0:21:58.940
Roe, Christine L
I'll take over now.
0:21:58.950 --> 0:22:4.560
Roe, Christine L
So I'm just wanna hit on a few key items.
0:22:5.150 --> 0:22:8.380
Roe, Christine L
You know, schedules always very important.
0:22:8.470 --> 0:22:16.750
Roe, Christine L
Wanna point out some of the compliance and environmental restrictions that we have on site one, we have the city turn nesting season.
0:22:16.760 --> 0:22:18.660
That's February 1st through 30th.
0:22:18.990 --> 0:22:21.200
Roe, Christine L
No work may take place on Isthmus.
0:22:21.210 --> 0:22:23.170
Roe, Christine L
Connecting garden and Bush keys.
0:22:23.940 --> 0:22:27.210
Roe, Christine L
Then there's the loggerhead turtle nesting season.
0:22:27.280 --> 0:22:31.0
Roe, Christine L
Really important to know about May 1st is September 30th.
0:22:31.50 --> 0:22:51.540
Roe, Christine L
No work may take place on or near the indicative beaches, including excavation, material handling, storage, vessel landing, any activities that disturb the beach, and so you know this one really associates with dredging, no dredging can take or dredging needs to take place out of this period.
0:22:52.420 --> 0:22:58.810
Roe, Christine L
Then we have the Atlantic hurricane season, typically June 1st to November 30th.
0:22:58.820 --> 0:23:6.280
Roe, Christine L
You know, I'm sure everyone's aware of that, but just contractors do need to be prepared to comply with park emergency storm procedures.
0:23:7.240 --> 0:23:20.730
Roe, Christine L
And one other thing, that's not a requirement, and it's not a compliance issue that relates to schedule as, but it is an MPs preference to have repairs to that breached wall completed in the first half of the schedule.
0:23:21.200 --> 0:23:28.590
Roe, Christine L
And you know what kind of hitting items right here that are that environmental ones we know schedules's gonna be critical.
0:23:28.700 --> 0:23:35.550
You know, logistics for the island is difficult and tricky and we do have all of these compliance issues.
0:23:35.560 --> 0:23:44.840
So just schedule is going to be a big part of this project and then jumping to coordination there is limited housing.
0:23:45.110 --> 0:23:46.740
Roe, Christine L
It's the cruise quarters.
0:23:46.750 --> 0:23:48.520
Roe, Christine L
It's sleeps 10 people.
0:23:48.770 --> 0:24:4.580
Roe, Christine L
That is in the specifications with all the details and we just wanna make contractors aware that, you know, there's always challenges maintaining a historic Fort and utility systems, sometimes they can't breakdown, then they get fixed.
0:24:5.330 --> 0:24:6.810
Roe, Christine L
Just wanna throw it out there.
0:24:6.820 --> 0:24:8.140
Roe, Christine L
That that's there.
0:24:8.790 --> 0:24:12.150
Roe, Christine L
They're available and typically used for construction projects.
0:24:12.860 --> 0:24:15.250
Roe, Christine L
There is limited use of the main dock.
0:24:15.920 --> 0:24:19.730
Roe, Christine L
You need to coordinate with the park unavailability and times a use.
0:24:19.740 --> 0:24:22.620
Roe, Christine L
It's a busy doc through the Yankee freedom.
0:24:22.630 --> 0:24:31.430
Roe, Christine L
We have the park, we have the Coast Guard, even though a lot of vessels using that space, there's limited areas for mooring and anchoring of vessels.
0:24:31.730 --> 0:24:48.580
So again, there's, you know, the need for coordinating with the park and reference the benthic survey for areas their own won't be any groundbreaking activities that will take place until all the government provided permanent seeing.
0:24:48.640 --> 0:24:57.150
Roe, Christine L
As in hand to the contractor right now, we have two final permits, the core and FDP.
0:24:57.500 --> 0:25:5.590
Roe, Christine L
We expect to get those back late September, but those need to be in hand before any construction starts.
0:25:6.360 --> 0:25:9.710
Roe, Christine L
Umm, just pointing out for specifications.
0:25:9.720 --> 0:25:12.470
Roe, Christine L
There's preconstruction assessment and survey required.
0:25:12.980 --> 0:25:24.10
Roe, Christine L
And lastly, we have this on all of our projects, just contractors shall conduct operations to ensure the least inconvenience to the public and the park we all expect to work together as a team.
0:25:24.70 --> 0:25:32.340
Roe, Christine L
You know, lots of moving pieces on every construction project and the best projects are the ones with full coordination with everyone.
0:25:33.800 --> 0:25:35.470
Roe, Christine L
No, I think we're going back to you, Mike.
0:25:36.530 --> 0:25:37.20
Smith, Michael E
Yep.
0:25:37.390 --> 0:25:37.660
Smith, Michael E
Yeah.
0:25:37.670 --> 0:25:38.200
Thanks Christy.
0:25:38.210 --> 0:25:38.890
Thanks Josiah.
0:25:39.890 --> 0:25:44.310
Smith, Michael E
I I wanna talk a little bit about the the formal site visit.
0:25:44.400 --> 0:25:48.330
Smith, Michael E
Most of the pre bid RFI I've gotten so far have been about the uh.
0:25:48.380 --> 0:25:57.890
Smith, Michael E
The formal site visit, so I I wanted to put a few slides in here to address some of those questions and hopefully points you guys in the right direction.
0:25:57.900 --> 0:26:9.770
Smith, Michael E
So the formal site visit will be held on August 9th is starting at 11:00 AM Eastern Time meet no earlier than 10:45 Eastern Time at the Garden Key Main Doc.
0:26:10.630 --> 0:26:11.0
Smith, Michael E
Umm.
0:26:11.10 --> 0:26:18.760
Smith, Michael E
If you're interested in coming to the formal site, visit, please register to me by August 4th, 2023.
0:26:19.480 --> 0:26:27.920
Smith, Michael E
Umm, you're limited to two participants per the visit, and I'll talk a little bit more about the logistics of getting out there.
0:26:28.830 --> 0:26:34.990
Smith, Michael E
Uh, understand that transportation to and from the site location must be self provided.
0:26:36.450 --> 0:26:45.240
Smith, Michael E
The park and the Park Service will not be transporting UM anybody for the site visit uh, even ourselves, going out for the site visit.
0:26:45.250 --> 0:26:46.340
We're taking the ferry.
0:26:46.730 --> 0:26:56.680
We did share the Yankee Freedom ferry information, but now it is our understanding that the Yankee
Freedom Fairy is full for the date August 9th.
0:26:57.430 --> 0:26:59.480
Smith, Michael E
I don't know if you can.
0:26:59.580 --> 0:27:5.620
Smith, Michael E
You know, if someone cancels, if you can put yourself on standby or anything like that and keep freedoms operated by it.
0:27:6.0 --> 0:27:11.60
Smith, Michael E
But a third party that we don't have control over, so you can reach out and contact them.
0:27:11.70 --> 0:27:12.510
Smith, Michael E
I've provided their information.
0:27:12.520 --> 0:27:13.770
Smith, Michael E
I have their information as well.
0:27:13.780 --> 0:27:20.490
Smith, Michael E
Further down, we're also providing information for the Key West C plane that does charters out to the island.
0:27:21.260 --> 0:27:28.830
Smith, Michael E
Uh, you can find their website here and I'll this these slides will be shared and this information will also be provided in the updated amendment.
0:27:28.840 --> 0:27:34.650
Smith, Michael E
I'm planning on probably tomorrow or no later than Thursday.
0:27:36.10 --> 0:27:38.580
Smith, Michael E
Well, you may also provide your own private charters.
0:27:39.60 --> 0:27:58.220
Smith, Michael E
UM and I believe if you have, you know, a of your own, or if you're a company owns about you can you can go out there yourself and anchor or more and attend the site visit like that we are asking and umm for those who have already registered, I'll be sending this out.
0:27:58.540 --> 0:28:4.370
If you are gonna be sent attending the site visit, we're asking that you complete the form.
0:28:5.220 --> 0:28:6.770
Smith, Michael E
The website will be provided.
0:28:7.100 --> 0:28:21.650
Smith, Michael E
It has like 6 or 7 questions on the purpose of your visit, I should go back umm but uh, this complete the form that you're coming out there for the site visit for August 9th.
0:28:22.180 --> 0:28:26.110
Smith, Michael E
If you have any questions when going through the form, don't hesitate to ask me.
0:28:26.180 --> 0:28:32.450
Smith, Michael E
I'll provide this when you either register or or if you've already registered, I'll provide it in the current calendar.
0:28:32.460 --> 0:28:35.870
Smith, Michael E
Invite that's standing, and I also provided via email.
0:28:37.910 --> 0:28:41.280
Smith, Michael E
Ohm again, this is the Yankee freedom information.
0:28:41.570 --> 0:28:48.700
Smith, Michael E
Again, I I it's my understanding they are full, but if you want to reach out to them, here's their website.
0:28:49.350 --> 0:28:55.960
Smith, Michael E
If you've already signed up for the Yankee Freedom, here's their information for reminders of that day.
0:28:56.30 --> 0:28:57.540
Smith, Michael E
You know check in by 7.
0:28:57.550 --> 0:28:58.660
Smith, Michael E
Bored by 7:30?
0:28:58.670 --> 0:28:59.800
It's departing by 8.
0:28:59.990 --> 0:29:2.490
You guys should be out there by 10:30.
0:29:2.590 --> 0:29:6.970
Smith, Michael E
Again, we're not meeting for the site visit no earlier than 1045.
0:29:7.720 --> 0:29:14.730
Smith, Michael E
Umm, you guys most likely will miss the, uh, the Fort Jefferson Tour, but you guys will be coming on the site visit with us.
0:29:15.290 --> 0:29:20.700
Smith, Michael E
Umm, so that's where estimating no longer than the 3:00 PM departure.
0:29:20.710 --> 0:29:24.570
Smith, Michael E
So we'll guys will have you guys back to the Yankee freedom by that 3:00 PM departure.
0:29:25.540 --> 0:29:26.20
Smith, Michael E
Umm.
0:29:26.920 --> 0:29:31.500
Smith, Michael E
And I'm going to go into, uh, the questions next.
0:29:31.510 --> 0:29:35.930
Smith, Michael E
So I imagine there will probably be questions so I can go back to the slides if needed.
0:29:35.940 --> 0:29:46.970
Smith, Michael E
But before we hop into questions, I'm I'm gonna ask that if you have a question, raise your hand or just type it into the chat.
0:29:47.410 --> 0:29:47.820
Smith, Michael E
Umm.
0:29:47.830 --> 0:30:7.660
Smith, Michael E
And if I call on, you know, state your name and the company you're with and then your question and if you're asking more than just a clarification on any of these slides, I also ask that you also submit that question formally to myself and the contracting Officer, John Babcock, and you can see our emails here.
0:30:7.890 --> 0:30:15.870
They're also included on this list citation information, so I'm going to go ahead and start looking back at teams and uh, see if we have any questions.
0:30:15.930 --> 0:30:16.90
Smith, Michael E
It's.
0:30:24.610 --> 0:30:26.740
Smith, Michael E
It's like we got radio silence.
0:30:26.750 --> 0:30:28.660
Smith, Michael E
Anything else, Chrissy?
0:30:28.710 --> 0:30:34.360
Smith, Michael E
UM, the park wanna mention UM, HDI.
0:30:34.370 --> 0:30:34.990
Smith, Michael E
Anything else?
0:30:37.940 --> 0:30:39.460
Smith, Michael E
Oh, Matt, go ahead.
0:30:42.990 --> 0:30:43.690
Shafer, Matthew W
Thanks Mike.
0:30:44.290 --> 0:30:44.880
Shafer, Matthew W
Hi everybody.
0:30:44.890 --> 0:30:48.160
Shafer, Matthew W
My name is Matt Chair from the project specialist for this project as well.
0:30:49.480 --> 0:30:50.540
Shafer, Matthew W
Sorry I was late to the call.
0:30:50.840 --> 0:30:53.520
Shafer, Matthew W
Umm, part of the what?
0:30:54.840 --> 0:30:59.60
Shafer, Matthew W
Uh, like, also visited on for the site information is that.
0:30:59.360 --> 0:31:9.860
Shafer, Matthew W
Uh, can't anybody who has their their own craft is able to come out to visit the park if they're unable to make it.
0:31:9.870 --> 0:31:17.990
Shafer, Matthew W
The on the naked freedom or the city Charter, and we do have some requirements for if you're planning to use your for your own craft.
0:31:18.580 --> 0:31:19.420
Shafer, Matthew W
I'm Mike.
0:31:28.430 --> 0:31:28.580
Smith, Michael E
You.
0:31:19.430 --> 0:31:28.820
Shafer, Matthew W
I'm I I know we got the that email from the from park stuff that we wanna include that in the amendment you'll be sending out next day or so.
0:31:29.380 --> 0:31:30.310
Smith, Michael E
Yeah, I can do that.
0:31:30.320 --> 0:31:31.880
Smith, Michael E
I I saw the information.
0:31:31.890 --> 0:31:36.570
Smith, Michael E
So umm, I'll try to gather as much information for this next amendment to include him.
0:31:36.810 --> 0:31:43.400
Smith, Michael E
Ohh is much information as we can about the site visit coming up and now it's gonna be a hot topic and getting out there.
0:31:43.410 --> 0:31:54.170
Smith, Michael E
It's kind of difficult and that's gonna be important for this site for this solicitation and we are encouraging everyone to attend the the formal site visit, getting out of the island.
0:31:54.180 --> 0:31:55.950
It's beautiful location.
0:31:55.960 --> 0:31:58.730
Smith, Michael E
Also, you know seeing the site, it's gonna be important for this bid.
0:31:58.740 --> 0:32:8.530
Smith, Michael E
We're looking for very accurate pricing, competitive bids, so we encourage everyone to get out to the site and take a look and bring your subcontractor or whoever needs to be.
0:32:8.540 --> 0:32:15.800
Smith, Michael E
I know I said, limited to two, so try to coordinate how you can, but you know we are encouraging the site visit.
0:32:18.890 --> 0:32:19.640
Smith, Michael E
Anything else, man?
0:32:19.650 --> 0:32:20.470
Smith, Michael E
I didn't mean to catch you up.
0:32:28.130 --> 0:32:29.850
Shafer, Matthew W
No, I just wanted to bring that up.
0:32:30.580 --> 0:32:31.420
Smith, Michael E
But thanks man.
0:32:37.120 --> 0:32:40.360
Smith, Michael E
I'm going to check the chat again, see if there's any questions in there.
0:32:41.860 --> 0:32:43.930
Smith, Michael E
Don't see anything or anyone typing.
0:32:43.940 --> 0:32:54.500
Smith, Michael E
I'm seeing what's going radius on, so I'm going to give it about another 1520 seconds and then uh, you know, it's been a quick uh quick meeting.
0:32:54.620 --> 0:32:58.420
You know, I'll give back the rest of your guys's day if I don't see anything else.
0:33:2.200 --> 0:33:7.220
Smith, Michael E
Again, I'm gonna go ahead and cut off the recording and I'll see any other questions.
0:33:7.560 --> 0:33:10.150
Smith, Michael E
I appreciate everybody's attendance today.
0:33:10.540 --> 0:33:14.110
Smith, Michael E
If you have any questions, please don't hesitate to reach out to me.
0:33:14.880 --> 0:33:21.350
Smith, Michael E
You know my information is included on the solicitation and on these slides, which you can find on today's calendar invite.
0:33:21.560 --> 0:33:24.270
Smith, Michael E
Thank you everyone for attending and I hope you have a great rest of your day.
0:33:26.670 --> 0:33:27.240
Thanks all.
| Virtual Industry Day Attendance List |
| VIRTUAL INDUSTRY DAY - Solicita |
Virtual Industry Day Transcripts
File details come from the government source that posted it. Updated .