This is a project specification document for the Repair to Inlet Lock 2 at Chesapeake & Ohio Canal National Historical Park in Potomac, Maryland (PMIS No. 342577). The work includes replacement of deteriorated lock gates and miter sill, repair of stone masonry, removal of sediment and debris around the gates and locks, and repairs to berms upstream of Violette's Lock (Lock 23). The project is structured with one base contract line item (CLi 001) and four optional items: Dry Stack Wall Repairs (CLi 002), Additional Repointing and Dutchman Repairs (CLi 003), Lower Gate Removal (CLi 004), and Additional Repointing 25' of Bridge (CLi 005), all priced as lump-sum items with no separate measurement of quantities. The contract prohibits intentional canal dewatering from May 1 through July 31 to protect the recreational season and interpretive boat program at Great Falls, requiring surface water supply through the inlet lock to downstream portions of the canal during those dates.
The contractor must submit an Accident Prevention Plan before the pre-construction conference, including a comprehensive Flood Plan with daily monitoring of the Potomac River using specified NOAA gauges and installation of temporary onsite gauges, emergency contact procedures, and flood threshold triggers. Construction schedule requirements mandate submission of a Critical Path Method (CPM) baseline schedule within 30 days of contract award using Microsoft Project or Primavera software, with monthly updates, 2-week look-ahead schedules, and time impact analyses for delays. Additional contractor responsibilities include submission of Historic Preservation Treatment Plan, quality assurance reports, shop drawings and product data, samples, Construction Schedule of Values, payroll reports, and compliance with OSHA safety requirements, international building codes, and the National Historic Preservation Act, with weekly progress meetings and documented daily construction reports required throughout the project duration.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHESAPEAKE & OHIO CANAL NATIONAL HISTORICAL
PARK
POTOMAC, MARYLAND
REPAIR TO INLET LOCK 2
CHOH
PMIS NO. 342577
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
NATIONAL CAPITAL AREA – REGION 1
02/06/2026
Division Section Title
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 01 27 00 01 32 16 01 32 33 01 33 00 01 35 23 01 35 91 01 40 00 01 50 00 01 57 23 01 70 00
SUMMARY OF WORK
DEFINITION OF CONTRACT LINE ITEMS
CONSTRUCTION SCHEDULE
PHOTO DOCUMENTATION
SUBMITTALS
SAFETY REQUIREMENTS
HISTORIC PRESERVATION TREATMENT PROCEDURES
QUALITY REQUIREMENTS
TEMPORARY SERVICES, FACILITIES AND CONTROLS
TEMPORARY STORM WATER POLLUTION PREVENTION
EXECUTION AND CLOSEOUT REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 19 SELECTIVE STRUCTURE DEMOLITION
DIVISION 04 - MASONRY
04 03 05 REPOINTING OF EXISTING STONE MASONRY
04 03 07 STONE MASONRY
04 10 00 MORTAR
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 19 00 TIMBER MITER GATES
DIVISION 09 - FINISHES
09 96 00 PAINTING
DIVISION 31 - EARTHWORK
31 05 19.13 GEOTEXTILES FOR EARTHWORK
31 10 00 SITE CLEARING
31 20 00 31 23 19
EARTHWORK
DEWATERING
31 25 00 EROSION AND SEDIMENT CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 20 SEEDING AND TOPSOIL
END OF TABLE OF CONTENTS
01 11 00 - 1
SUMMARY OF WORK CHOH – 342577
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, and other Division 01 Specification Sections, apply to this Section.
1.2 DESCRIPTION: This section covers the following:
A. Location and Description of Work B. Coordination C. Project Meetings D. Construction Facilities and Temporary Controls E. Materials and Equipment F. Quality Requirements G. Accident Prevention H. Archeological Protection I. Permits and Responsibilities
1.3 LOCATION AND DESCRIPTION OF WORK
A. The work of this contract is located at Chesapeake & Ohio Canal National Historical Park
Inlet Lock 2 – Mile Marker 22.12 near Violette’s Lock (Lock 23), Potomac MD 20854
B. The work of this contract includes, but not limited to the following work, as detailed in the specification sections and as shown on the attached drawings:
1. Repair of Inlet Lock 2 of the C&O Canal. Replace the deteriorated Lock gates and miter sill and repair stone masonry. Remove sediment and debris around the gates and Lock. Work will include repairs to the berms upstream of Violette’s Lock (Lock 23).
1.4 COORDINATION
A. Coordinate construction operations included in various sections of these specifications to assure efficient and orderly installation of each part of the work. Coordinate construction operations included under different sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in the sequence required to obtain the best results where installation of one part of the work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to assure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. To mitigate impacts to the recreational season and the interpretive boat program at Great Falls, MD; the canal cannot be intentionally dewatered from May 1 – July 31.
Surface water supply from the river, through the inlet lock, into the canal is required to be provided to the downstream portions of the canal during those dates.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative
01 11 00 - 2 procedures with other construction activities to avoid conflicts and assure orderly progress of the work. Such administrative activities include, but are not limited to, the following:
1. Preparation of contractor’s construction schedule.
2. Installation and removal of temporary facilities.
3. Progress meetings.
4. Project closeout activities.
1.5 PROJECT MEETINGS
A. General: Contracting Officer’s Representative (COR) will schedule and conduct meetings and conferences at project site, unless otherwise indicated.
1. Attendees: Authorized representatives of Acquisition Division and park staff; Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties shall attend the conference shall be familiar with project and authorized to conclude matters relating to work.
B. Pre-Construction Conference: Contracting Officer’s Representative will schedule a Pre-
Construction Conference before starting construction, at a time convenient to park staff and contractor. The conference will be held at project site or another convenient location.
1. Agenda: Subjects to be discussed will include the following:
a. Correspondence – General Procedure.
b. Contracting Officer’s Authorized Representatives.
c. Changes.
d. Submittals for Approval (General).
e. Submittals for Approval (Shop Drawings and Samples).
f. Subcontractors.
g. Labor Standards.
h. Payroll Reports.
i. Working Hours
j. Plans and Specifications.
k. Accident Prevention.
l. Park Rules and Regulations.
m. Contractor Parking and Personnel Passes
n. Payments to Contractor.
o. Liquidated Damages – Construction.
p. Tentative Construction Schedule.
C. Pre-Installation Conferences: A pre-installation conference at the project site or held virtually (via
MS Teams or equivalent) before each construction activity that requires coordination with other construction is required. A preparation meeting will be conducted before the initiation of field work associated with each definable feature of work to discuss the notable features of the work such as:
1. Erosion and Sediment Control Installation & Dewatering.
2. Tree Removal
3. Concrete forming, placement, and finishing.
4. Repointing of existing stone masonry.
5. Stone masonry repairs.
6. Site Clearing
7. Earth Moving Activities
8. Foundation Repair
9. Seeding and Topsoiling
ii. These preparation meetings are required. Agenda shall include review of contract
01 11 00 - 3 requirements (plans, specifications, etc.), required submittals and status of approval;
responses to and RFI’s, schedule for performing the work, weather limitations, D. Progress Meetings: Progress meetings will be carried out weekly during active construction. The
Contracting Officer’s Representative will schedule and conduct progress meetings at designated intervals. Coordinate dates of meetings with preparation of payment requests.
1.6 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS (See Section 01 50 00)
A. References:
1. FAR Clause: 52.236-9 – Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
2. FAR Clause: 52.236-10 – Operations and Storage Areas
3. FAR Clause: 52.236-14 – Availability and Use of Utility Services
1.7 MATERIALS AND EQUIPMENT
A. Reference: FAR Clause: 52.236-5 – Material and Workmanship
1.8 QUALITY REQUIREMENTS
A. Contractor shall be responsible for all work to comply with the latest edition of the International
Building Code (IBC) and family of International Codes including but not limited to: International Plumbing Code, International Electrical Code and International Mechanical Code. Work shall conform to the Life Safety Code.
B. Testing and inspecting services may be required to verify compliance with requirements specified or indicated. These services do not relieve the Contractor of responsibility for compliance with the Contract requirements.
1. Specific quality-control requirements for individual construction activities as specified in the
Sections may also cover production of standard products.
2. Requirements for Contractor to provide quality-control services as directed by Contracting Officer’s Representative or authorities having jurisdictions are not limited by provisions of this Section.
C. Submittals (See Section 013300 Submittals for detailed requirements)
1. Qualification Data: For testing agencies specified in “Quality Assurance” Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
2. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, confirming that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services.
D. Quality Assurance
1. Fabricator Qualification: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capability to produce required units.
01 11 00 - 4
2. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved manufacturer to inspect installation of manufacturer’s products that are similar in material, design, and extent to those indicated for this Project.
3. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
4. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance.
5. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material design, and extent.
6. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities that are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
a. Requirement for specialists shall not supersede building codes and similar regulations governing the Work, nor interfere with local trade-union jurisdictional settlements and similar conventions.
7. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed.
8. Pre-construction Testing: Testing agency shall perform pre-construction testing for compliance with specified requirements for performance and test methods.
a. Contractor responsibilities include the following:
1. Provide test specimens and assemblies representative of proposed materials and construction. Provide sizes and configurations of assemblies to adequately demonstrate capability of product to comply with performance requirements.
2. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying work.
b. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Contracting Officer’s Representative, with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
E. Quality Control
1. Contractor Responsibilities: Unless otherwise indicated, provide quality-control services specified and required by these contract documents.
a. Contractor shall provide a qualified project manager or superintendent on site during active
01 11 00 - 5 daily construction activities.
b. Contractor shall engage a qualified-independent testing agency to perform these quality-control services.
c. Contractor must maintain a set of contract plans and specifications on the job-site at all times during the contract period. Contractor shall provide copies of the contract plans and specifications to all sub-contractors.
2. Manufacturer’s Field Services: Where indicated, engage a factory authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing.
3. Testing Agency Responsibilities: Cooperate with Contracting Officer’s Representative and
Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
a. Notify Contracting Officer’s Representative and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
b. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
c. Submit a certified written report, in duplicate, of each test, inspections, and similar quality-control service through Contractor.
d. Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the work.
4. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction of accommodate testing and inspecting.
1.9 ACCIDENT PREVENTION
A. Submit required Accident Prevention Plan.
B. All work shall be in accordance with standard Occupational Safety and Health Administration
(OSHA) guidelines and regulations.
1.10 ARCHEOLOGICAL PROTECTION
A. Contractor shall note any large scale excavation activities in the two week lookahead that is distributed weekly to the NPS so that the park archeologist staff are apprised of ongoing earth disturbance and has the opportunity to monitor.
B. Retain any minor artifacts such as bottles, pottery, etc. onsite in a secure location until NPS staff can examine it to determine it’s fate.
C. Reference: DOI Clause: 1489.236-73 – Archeological Findings
1. Archeological Discovery: In the event that unanticipated archeological resources are uncovered during construction operations, the contractor will suspend operations at the discovery site (within 100 feet of the discovery location), notify the Contracting Officer, Contracting Officer’s Representative, Park’s Cultural Resource Specialist/NHPA coordinator, and the park POC, and continue operations in other areas, until such time as the National Park Service has completed its compliance responsibilities under Section 106 of the 1966 National Historic Preservation Act, as amended. Provide photos of any potential archeological discoveries immediately to the government. Do not proceed with work in the area of the discovery until written permission is provided from the CO. Area should be protected from vandalism, theft, visitor viewing, and the elements until the situation is resolved.
2. Unanticipated Discovery of Human Remains (Anthropic Discovery): Should any human
01 11 00 - 6 remains or other objects subject to the Native American Graves and Repatriation Act (NAGPRA) be encountered, excavations will stop and the Contracting Officer, Contracting Officer’s Representative, Park’s Cultural Resource Specialist/NHPA coordinator, and the park POC, will be notified immediately. In addition, NPS Law Enforcement, the Montgomery County Chief Medical Examiner, and the NPS Communication Center shall also be notified.
01 11 00 - 7
DO NOT TOUCH, LEAVE THE REMAINS IN PLACE. The Contracting Officer, in consultation with the Park Archeologist or his representative, and the Park Superintendent shall determine the appropriate course of action, following the Department of the Interior’s guidelines on the treatment of human remains and appropriate Federal legislation. The Contractor shall ensure that human remains or other objects subject to NAGPRA are treated with appropriate respect and according to federal law. The Contractor shall use reasonable efforts to ensure that the general public is excluded from viewing any burial site or associated funerary objects. The remains and objects shall also be protected from rain or other weather events.
3. Contractor shall plan, schedule, and execute work to prevent stoppages at one area from stopping all work at construction site.
1.11 PERMITS AND RESPONSIBILITIES
A. As prescribed in FAR 36.507: Permits and Responsibilities (Nov 1991): The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence.
The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
B. Permits, Licenses, and Certificates: It is the contractor’s responsibility to obtain and pay for all permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work. The Contractor shall be responsible for renewal of all required construction permits during the performance period of the contract. Submit all copies for the Contracting Officer’s Representative’s records.
C. For the purpose of this contract, the Contractor will not be considered an agent of the Government.
Therefore, the Contractor will comply with the appropriate Federal, State, and local laws.
D. Potential Permits: The permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist the contractor in determining which permits will be required for the contract’s chosen means and methods. The list shall not be considered complete, as it is the responsibility of the contractor to determine means and methods and obtain the required permits. It is the responsibility of the Contractor to obtain all permits required to legally conduct the work. It’s also the responsibility of the Contractor to renew all required construction permits from all agencies with jurisdiction for the duration of the project.
1. Construction trailer, Utilities hookup permit –Construction trailers must be self-contained.
2. Water Appropriation Permit – If pumping of water from the Potomac River is desired by the Contractor – Coordination with Maryland Department of the Environment Compliance Inspector will be required. Application to appropriate and use waters of the state is responsibility of the contractor to acquire, if necessary.
3. Contractor is responsible for ensuring any spoil locations of excess material generated from the site is disposed of in accordance with local, state, and federal regulations. Any off-site spoil locations must be submitted to the CO and evidence of required permits for the site provided in writing to the government.
4. Government Furnished Permits have been applied for via Joint Permit Application for Maryland Department of the Environment Waterway & Wetland & U.S. Army Corps of Engineers.
Applications for Maryland Department of the Environment Erosion and Sediment Control have also been submitted, as well as a waiver for stormwater management. Once authorized, the https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2036_5.html#wp1076721
01 11 00 - 8 contractor will be responsible for any modifications and fees that alter the original permits due to changes for convenience in the means and methods to perform the work.
E. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.
F. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Contracting Officer, COR, and Park to avoid conflicts and to ensure orderly execution of the Work.
2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.
3. Submit copies of all obtained permits to the Government.
PART 2 – PRODUCTS (Not Applicable)
PART 3 – EXECUTION (Not Applicable)
END OF SECTION 01 11 00
01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS CHOH – 342577
PART 1 GENERAL
1.01 SUMMARY
SECTION 012700
DEFINITION OF CONTRACT LINE ITEMS
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.01 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 001: Inlet Lock 2 Repair (BASE)
1. This item consists of all repair work & materials at Inlet Lock 2 & associated work sites and not included in Contract Line Items 2, 3, 4 and 5.
2. No separate measurement of quantities shall be made. Payment shall be made at the contract lump sum price.
B. Contract Line Item Number 002: Dry stack Wall Repairs (Option A)
1. This item consists of all work & materials involved in the repair of the dry stack armoring walls as shown in the plans.
2. No separate measurement of quantities shall be made. Payment shall be made at the contract lump sum price.
C. Contract Line Item Number 003: Additional Repointing and Dutchman Repairs (Option B)
1. This item consists of all work and materials involved in performing the additional repointing and dutchman repairs outlined in the plans.
2. No separate measurement of quantities shall be made. Payment shall be made at the contract lump sum price.
D. Contract Line Item Number 004: Lower Gate Removal (Option C)
1. This item consists of all work and materials involved in performing the additional gate removal and disposal outlined in the plans.
2. No separate measurement of quantities shall be made. Payment shall be made at the contract lump sum price.
E. Contract Line Item Number 005: Additional Repointing 25’ of Bridge (Option D)
1. This item consists of all work and materials involved in performing the additional repointing repairs outlined in the plans.
2. No separate measurement of quantities shall be made. Payment shall be made at the contract lump sum price.
END OF SECTION
01 32 18 - 1
CONSTRUCTION SCHEDULE CHOH – 342577
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
01 32 18 - 2
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: Schedules and reports submitted shall be posted on the NPS/DSC management software website in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.
D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit three paper copies of the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data.
Provide two paper copies.
F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision, submit two paper copies of a Time Impact Analysis. Incorporate a Fragmentary Network (Fragnet) into currently accepted Construction Schedule that demonstrating how Contractor proposes to incorporate a modification, change, delay, or Contractor request.
1.4 QUALITY ASSURANCE
A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
01 32 18 - 3
3. Discuss constraints, including phasing, work stages, area separations, interim milestones and partial Government occupancy/substantial completions.
4. Review delivery dates for Government-furnished products.
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review time required for obtaining and activating permits.
10. Review and finalize list of construction activities to be included in schedule.
11. Review baseline schedule comments, resolve issues and progress on incorporating them
12. Review procedures for updating schedule.
13. Discuss reporting requirements and establish protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency of using scheduling software. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of work from parties involved.
3. Coordinate each construction activity in network with other activities and schedule in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the
01 32 18 - 4 component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-based, time-scaled Critical Path Method network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the Critical Path Method schedule within the limitations of the Contract Time.
4. Show sequence and interdependence of activities required for completion of work. Ensure work sequences are logical and Construction Baseline Schedule shows a coordinated plan of the work.
5. Resource loading of each activity shall include personnel by labor category and equipment type and capacity proposed to complete the activity in duration shown.
6. Consider seasonal weather conditions in planning and scheduling work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of work within contract time.
7. Time Frame: Proposed duration assigned to each activity shall be Contractor's best estimate of time required to complete activity considering the scope and resources planned for activity.
01 32 18 - 5
a. An early finish date may be shown but the late finish date shall be same date as last day of contract period. An early completion schedule shall contain:
1) Insert an activity titled "Project Float" as a successor to last activity in early project completion schedule network.
2) Add a milestone titled "Contract End Date" as a successor to the activity "Project Float".
3) Add duration to the activity "Project Float" as required so the milestone "Contract End Date" equals the last day of Contract Period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Project Calendars: Develop and incorporate the following calendars:
1) Administrative Calendar: Include calendar based on a 7-day week to be used on activities based on calendar days. Apply this calendar to administrative tasks or other tasks not affected by non-working days (Federal Holidays, weather, etc.).
2) Project Calendar: Include calendar based on planned work week for the project. Include Federal Holidays, weekends, and non-workdays indicated in contract documents. Apply this calendar to activities not anticipated to be affected by weather. Be clear when identifying number of work days in work week.
3) Weather Calendar: Utilize Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to Contracting Officer. Apply this calendar to activities anticipated to be affected by weather.
e. Activity Duration: Define so no activity is longer than 14 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
f. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities can include submittals, approvals, purchasing, fabrication, and delivery.
g. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Baseline Schedule.
h. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Specification 01 77 00 "Closeout Procedures.")
8. Constraints: Include constraints and work restrictions indicated in Contract Documents and as follows in schedule and show how the sequence of Work is affected.
a. Phasing: Arrange list of activities on schedule by phase.
b. Work under More Than One Contract: Include a separate activity for each contract.
c. Work Restrictions: Show effect of the following on the schedule:
01 32 18 - 6
1) Coordination with existing construction
2) Limitations of continued occupancies
3) Uninterruptible services
4) Partial occupancy before Substantial Completion
5) Use of premises restrictions
6) Provisions for future construction
7) Seasonal variations
8) Environmental control
9) Permit provisions
d. Work Stages: Indicate important stages of construction for each major portion of the
Work.
1) Subcontract awards
2) Submittals
3) Purchases
4) Mockups
5) Fabrication
6) Sample testing
7) Deliveries
8) Installation
9) Tests and inspections
10) Adjusting
11) Curing
12) Building flush-out.
13) Building commissioning activities.
9. Milestones: Include milestones indicated in Contract Documents in schedule, including, but not limited to, Notice to Proceed, Substantial Completion.
C. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receiving Contractor's proposed Construction Baseline Schedule, Contracting Officer shall review initial Construction Baseline Schedule.
2. Within seven calendar days after review, Contractor shall revise and resubmit Construction Baseline Schedule in accordance with comments presented from review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, when discovered by Contractor or Contracting Officer, shall be corrected by Contractor within seven calendar days and shall not affect contract period.
4. Upon acceptance of the Construction Baseline Schedule, Contracting Officer saves schedule as a baseline and updates on a monthly basis. Construction schedule update will be used to evaluate Contractor's monthly applications for payment based upon information developed at monthly Construction Schedule update meeting.
D. Cost Correlation: In the heading of the schedule, provide a cost correlation line, indicating planned and actual costs. On the line, show dollar volume of Work performed as of dates used to prepare payment requests.
01 32 18 - 7
1. Contractor shall assign cost to construction activities on Construction Baseline Schedule.
Costs shall not be assigned to submittal activities unless specified otherwise but may, with Contracting Officer’s approval, be assigned to fabrication and delivery activities. Costs shall be included for testing and commissioning activities, operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training (if applicable).
2. Each activity cost shall reflect an accurate value based on the Contract Price Schedule.
3. Total cost assigned to activities shall equal total Contract Price.
E. Recovery Schedule: When periodic schedule update indicates Work is 14 or more calendar days behind current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule shall also be submitted. Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery shall be accomplished.
F. Computer Software: Prepare schedules using a program developed specifically to manage construction schedules.
1. Use Microsoft Project or Primavera, for (Windows 7 and newer.)
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide a 2 week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize look-ahead schedule to facilitate and take notes on discussions held during progress meeting.
B. Monthly Schedule Updates:
1. General: Update Construction Schedule on monthly basis to reflect construction progress and activities throughout entire contract period and until project substantial completion.
The status date of each schedule update shall be the 7th day preceding the progress payment request date.
2. Procedure: Contractor shall meet with Contracting Officer each month at Construction Schedule update meeting to review progress made through the status date of the Construction Schedule update, including dates activities were started or completed and percentage of work completed on each activity started or completed.
3. Reports: Concurrent schedule revisions, prepare tabulated reports showing:
a. Identification of activities that have changed
b. Changes in early and late start dates
c. Changes in early and late finish dates
d. Changes in activity durations in workdays
e. Changes in the critical path
f. Changes in total float or slack time
g. Changes in the Contract Time
01 32 18 - 8
4. Narrative: Report shall include a brief description of actual progress made during update period; actual and potential delaying activities; impediments to progress; issues related to inclement weather; progress toward established milestones and project float. Report shall include a brief description of work anticipated to be performed in the next month. Minor revisions to the schedule should be identified for evaluation and acceptance or rejection.
5. As Work progresses, indicate Actual Completion percentage for each activity.
6. If schedule update shows a late finish date after contract completion date, include:
a. Known delays
b. Actions to get back on schedule
c. Pending modifications
d. Impediments or constraints affecting progress
7. Progress Payments: Monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made. If Contractor fails to provide schedule updates or revisions, a portion of the monthly payment may be retained until corrections have been made.
C. Distribution: Distribute copies of accepted schedule to Contracting Officer, Contracting Officers Representative, Construction Management Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to same parties and post in same locations. Delete parties from distribution when they have completed their assigned portion of the Work.
D. Construction Schedule Revisions:
1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted Construction Schedule no longer represents actual prosecution and progress of the work, Contracting Officer will request, and Contractor shall submit, a revision to the Construction Schedule. Contractor may also request reasonable revisions to currently accepted Construction Schedule in event the Contractor's planning for the work is revised.
If Contractor desires to make changes, Contractor shall notify Contracting Officer in writing, stating reason for proposed revision. Accepted revisions shall be incorporated into currently accepted Construction Schedule for next monthly schedule update.
2. Procedure: If revision to currently accepted Construction Schedule is contemplated, Contractor or Contracting Officer shall advise the other in writing at least seven calendar days prior to next monthly schedule update meeting, describing revision and reasons for the revision. Government-requested revisions will be presented in writing to the Contractor, who shall respond in writing within seven calendar days.
3. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing:
a. Identification of activities changed
b. Changes in early and late start dates
c. Changes in early and late finish dates
d. Changes in activity durations in workdays
e. Changes in critical path
f. Changes in total float or slack time
01 32 18 - 9
3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS
AND CONTRACTOR REQUESTS:
1. Requirements: When contract modifications or changes are initiated, delays experienced, or Contractor desires to revise currently accepted Construction Schedule, Contractor shall submit to Contracting Officer a written time impact analysis illustrating the influence of modification, change, delay, or Contractor request on contract time.
2. Time Extensions: Activity delays, resulting in a late completion date projection, shall not automatically mean an extension of contract time is warranted or due to Contractor. It is possible a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in absorbing a part of available total float that may exist within an activity chain of the Schedule, not causing any effect on contract time. Time extensions will be granted in accordance with terms of contract.
3. Extension of contract time will be granted only to the extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
4. Procedure: Each time impact analysis shall be submitted within time period stated in a request for proposal, or time period designated under the clauses entitled Changes or Default. In cases where Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, time impact analysis shall be incorporated into currently accepted Construction Schedule at next monthly schedule update.
5. Contract Modifications: Prepare time-impact analysis using fragnets to demonstrate effect of proposed change on overall Construction Schedule for each proposed contract modification concurrent with submission.
END OF SECTION 01 32 16
01 32 33 - 1
PHOTO DOCUMENTATION CHOH – 342577
SECTION 01 32 33 – PHOTO DOCUMENTATION
1.1 SUMMARY
A. Section includes administrative and procedural requirements for:
1. Existing condition images
2. Periodic construction images
B. See Section 01 70 00 "Execution and Closeout Procedures" for a complete listing of closeout documents.
1.2 SUBMITTALS
A. Construction Images: Submit images electronically within seven days of taking the image.
Include:
1. Date, time and number (sequentially number all images) in filename.
2. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
3. Submit digital images exactly as originally recorded in digital camera, without alteration, or modifications using image-editing software.
B. Closeout: Submit complete set of digital image electronic files as a Project Record Document.
Submit on Hard-drive or FTP as well as Digital Video Disc (DVD).
1. Provide index as separate file on Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.
2. Submit images that have the same aspect ratio as the sensor, un-cropped.
2.1 FORMAT REQUIREMENTS
A. Media: DVD-R Archival Gold
B. Media Labels: Archival DVD labeling markers, archival labels, or direct print.
C. Images: Provide sRGB (standard Red Green Blue) color images in JPEG (Joint Photographic Experts Group) format. Minimum sensor size of 8 megapixels, and at image resolution of not less than 3200 by 2400, and 300 dpi (dots per inch).
01 32 33 - 2
PHOTO DOCUMENTATION CHOH – 342577
PART 3 - EXECUTION
3.1 CONSTRUCTION IMAGES
A. General: Take digital images using the maximum range of depth of field, in-focus, to clearly show the Work. No blurry or out-of-focus areas accepted.
1. Maintain index with each set of Construction images and identify the number, date, time, and description for each.
2. Maintain one set of images accessible in field office at Project site available for reference.
B. Existing Condition Images: Before commencement of construction take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points.
1. Flag construction limits before recording construction images.
2. At each site, take a minimum of ten separate images to show existing conditions adjacent to work area before starting Work.
3. Take a minimum of ten separate images of existing historic structures on either side of work areas to accurately record physical conditions at start of construction.
4. Take a minimum of twenty-four separate images of the existing conditions of the staging areas, roadways, and towpath access.
5. Collect photos prior to removal of existing vegetation, remove vegetation, and then collect photos of the face of the existing features.
6. Include horizontal and vertical scales for reference. This can be as simple as including measuring tapes or philarods in the photos that show a scale in the X and Y planes.
C. Periodic Construction Images: Take a minimum of 25 color, digital images weekly, with timing each month adjusted to coincide with cutoff date associated with each Application for Payment.
Select vantage points to show status of construction and progress since last images were taken.
Daily photos during wall disassembly and during excavation activities.
D. Additional Images: Contracting Officer may issue requests for additional images.
1. Three days advance, where feasible.
2. In emergency situations, take additional images within 24 hours of request.
3. Additional images include, but are not limited to:
a. Immediate follow-up when on-site events result in construction damage or losses.
b. Fabrication locations away from Project site.
c. Substantial Completion of a major phase or component of Work.
d. Extra record images at time of final acceptance.
e. Prior to anticipated heavy rainfall or…