B08_Attachment_2_-_LOWE_335201_-_Project_Specifications.pdf
PDF 2 MB Posted
- Solicitation number
- 140P4326R0009
About this file
This file is a comprehensive Project Specifications document for the Lowell National Historical Park Security Upgrade project (LOWE 335201), prepared by the National Park Service Denver Service Center. The project involves constructing security and egress doors at the Boott Mill #6 (3rd and 5th floors) and Boott Mill Counting House (Mezzanine level) in Lowell, Massachusetts. The work includes three primary contract line items: CLIN 0001 for Boott Mill #6 3rd Floor (new demising partition with 4 hollow metal doors), CLIN 0002 for Boott Mill #6 5th Floor (modification of existing partition with 2 hollow metal doors), and CLIN 0003 for Counting House Mezzanine (modification of existing partition with 1 hollow metal door). An optional CLIN 0004 covers door closure hardware purchased by the general contractor and installed by the Park. All doors include vision panels, welded hollow metal frames, fire-resistant smoke-tight assemblies, integration with existing fire alarm systems, and provisions for future PAC card access systems.
The specifications detail extensive Division 01 requirements including project management and coordination, construction scheduling using Critical Path Method, safety requirements with prohibition on hot work, quality control procedures, waste management and recycling goals, indoor air quality management during construction, noise control limits (maximum 70 dB(A) at 50 feet for extended periods), submittal procedures with specified review timeframes, temporary facilities and dust partitions, and comprehensive closeout documentation. Materials specifications cover cold-formed steel framing (minimum Grade 1 framing with ASTM A1003 structural steel), mineral wool sound attenuation insulation (ROCKWOOL Comfortbatt minimum R-10), gypsum board (Type X 5/8-inch for fire-rated assemblies), hollow metal doors and frames (NAAMM-HMMA 803 or SDI A250.8 Level 2 construction), door hardware including mortise locks, hinges, exit devices, closers with hold-open arms, and interior finish carpentry with 1-inch oak baseboard trim to match existing. Interior painting utilizes low-odor/low-VOC institutional latex products in Benjamin Moore colors (Wedding Veil Eggshell for walls/ceilings, Essex Green Semi-Gloss for trim). The project requires NPS approvals for all submittals, coordination with park facilities and security systems, maintenance of building occupancy during construction with temporary dust partitions, weather-tight construction, weekly progress meetings, and final documentation including project record drawings, operation and maintenance manuals, and warranties. Standard contract terms apply with lump-sum payment based on monthly percent-complete invoicing, and the contractor bears responsibility for obtaining necessary permits, complying with federal and state environmental regulations, and managing all coordination with park operations and security systems.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LOWELL NATIONAL HISTORIC PARK
LOWELL, MA
CONSTRUCT SECURITY AND EGRESS DOORS AT CH
MEZZANINE AND BOOTT MILL #6 / FLOORS 3 AND 5
LOWE 335201
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
dlieb Underline dlieb Text Box
CLINS REVISED 12/03/2025 BY DML
Table of Contents (TOC) | NPS DSC Division 1 Specifications | 051121 page 1 of 1
NPS DSC Division 1 Specifications Table of Contents (TOC)
National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21
PMIS - LOWE 335201
Table of Contents (TOC) 01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition Of Contract Line Items 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 57 19.11 Indoor Air Quality Management 01 57 19.12 Noise And Acoustics Management 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management And Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance (O&M) Data 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 06 10 00 Rough Carpentry 06 20 23 Interior Finish Carpentry 07 21 00 Thermal Insulation 08 11 13 Hollow Metal Doors and Frames 08 71 11 Door Hardware 09 29 00 Gypsum Board 09 91 23 Interior Painting
LOWE 335201 01 11 00 - 1
SUMMARY OF WORK
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21
LOWE 335201
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
11. Soils Investigation Report
12. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Lowell National Historical Park, Boott Mill #6, 115 John Street, Lowell, MA 01852.
B. The Work consists of:
1. Boott Mill #6, 3rd Floor - The project includes the construction of a new demising partition at the Boott Mill #6, 3rd floor lobby to provide a required code separation between the lobby and educational classrooms and administrative offices.
a. Metal stud framing, sound attenuation batt insulation with GWB, fire resistant smoke tight assembly.
b. (4) new HM doors with vision panels, welded HM frames to provide required egress and limit secure access. Secure door will be tied to existing fire alarm system and provide for future PAC card access system.
2. Boott Mill #6, 5th Floor - The project includes the modification of an existing demising partition at the Boott Mill #6, 5th floor lobby to provide a required code separation between the lobby and educational classrooms and administrative offices correcting the existing egress doors. Scope in this area includes:
a. Selective demolition of existing wood doors, frames and hardware. Selective demolition of existing unrated glass windows.
LOWE 335201 01 11 00 - 2
b. New Metal stud infill framing, sound attenuation batt insulation with GWB, to maintain the existing fire resistant smoke tight assembly.
c. (2) new HM doors with vision panels, welded HM frames to provide required egress and limit secure access. Secure door will be tied to existing fire alarm system and provide for future PAC card access system.
3. Boott Mill Counting House, Mezzanine level - The project includes the modification of an existing demising partition at the Boott Mill Counting House Mezzanine, to provide a new secure entry / exit location between the public lobby at the first level and museum exit and mezzanine function areas. Scope in this area includes:
a. Selective demolition of existing wood pocket doors, frames and hardware.
b. New Metal stud infill framing, sound attenuation batt insulation with GWB, to maintain the existing non-rated assembly. Installation of new baseboard wood trim to match existing.
c. (1) new HM doors with vision panels, welded HM frames to provide required egress and limit secure access. Secure door will be tied to existing fire alarm system and provide for future PAC card access system.
4. Bid Option 1 – Misc. Door Hardware - closures
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in 1 phase in the following order.
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.
B. Preceding Work: N/A
C. Concurrent Work: N/A
D. Future Work: N/A
1.5 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials: N/A
B. Government-Furnished Materials: N/A
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
dlieb Cross-Out
LOWE 335201 01 11 00 - 3
B. General: Contractor shall have limited use of site for construction operations. Limit use of premises to work in areas indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to work in areas indicated on drawings.
C. Storage of Materials: Confine storage of materials to: coordinate material delivery and storage areas with Park facilities maintenance division.
D. Parking: GC staff parking may be provided in the HCID Municipal Garage in Park Visitor areas and coordinated through the Superintendent’s Office. There is limited vehicle staging and parking on-site at the Boott Mill #6 and all construction activities will need to be coordinated through the COR.
E. Stockpiling: N/A
F. Preservation of Natural Features: N/A
G. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule AND COORDINATE deliveries with Park Facilities Supervisor to minimize use of driveways and entrances.
2. Schedule AND COORDINATE deliveries with Park Facilities Supervisor to minimize space and time requirements for storage of materials and equipment on-site.
H. Construction Camp: Establishment of a camp within park will not be permitted.
I. Construction Camp: N/A
J. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
K. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
1.7 PUBLIC USE OF SITE
A. The building will be OPEN to the public and park staff during construction.
B. Contractor shall conduct their operations to ensure the least inconvenience to public and facility operations. Temporary dust barriers and maintained egress or temporarily re-directed egress closures may be permitted, when required, upon specific approval of Contracting Officer.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
LOWE 335201 01 11 00 - 4
1. Full Government Occupancy: Government will occupy buildings under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.
b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.
B. New Buildings N/A
1.9 CONDUCT OF OPERATIONS
A. Contractor shall conduct their operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business/calendar days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.10 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: as approved by CO
2. Early Morning Hours: as approved by CO
3. Hours for Demolition: no restrictions
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and Park Utility Supervisor of proposed locations and times for selective demolition if temporary shut downs of breakers and systems may be required.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
LOWE 335201 01 11 00 - 5
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours and length of Utility Shutdowns: Coordinate with CO/COR and Park Utility
Supervisor.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: N/A – GC should conduct all correspondence electronically through either email or an approved SharePoint / transfer site by the CO.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using Project Website.
PART 2 - SOILS INVESTIGATION REPORT (Not Used)
PART 3 - ADDITIONAL REPORTS (Not Used)
PART 4 - PRODUCTS (Not Used)
PART 5 - EXECUTION (Not Used)
END OF SECTION 01 11 00
LOWE 335201 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
LOWE 335201
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
LOWE 335201 01 26 01 - 2
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
LOWE 335201 01 26 01 - 3
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized
LOWE 335201 01 26 01 - 4
by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
LOWE 335201 01 26 01 - 5
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………8%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
LOWE 335201 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
LOWE 335201 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
LOWE 335201
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 0001: Boott Mill #6 – 3rd Floor Wall Scope of Work
1. This item consists of :
a. Boott Mill #6, 3rd Floor - The project includes the construction of a new demising partition at the Boott Mill #6, 3rd floor lobby to provide a required code separation between the lobby and educational classrooms and administrative offices.
a. Metal stud framing, sound attenuation batt insulation with GWB, fire resistant smoke tight assembly.
b. (4) new HM doors with vision panels, welded HM frames to provide required egress and limit secure access. Secure door will be tied to existing fire alarm system and provide for future PAC card access system.
2. Measurement for payment will be made by percent complete as invoiced monthly.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item Number 0002: Boott Mill #6 – 3rd Floor Wall Scope of Work
1. This item consists of Boott Mill #6, 5th Floor - The project includes the modification of an existing demising partition at the Boott Mill #6, 5th floor lobby to provide a required code separation between the lobby and educational classrooms and administrative offices correcting the existing egress doors. Scope in this area includes:
a. Selective demolition of existing wood doors, frames, and hardware. Selective demolition of existing unrated glass windows.
b. New Metal stud infill framing, sound attenuation batt insulation with GWB, to maintain the existing fire-resistant smoke tight assembly.
dlieb Callout
CLIN 60
dlieb Callout
CLIN 60
dlieb Cross-Out
LOWE 335201 01 27 00 - 2
012721 DEFINITION OF CONTRACT LINE ITEMS
c. (2) new HM doors with vision panels, welded HM frames to provide required egress and limit secure access. Secure door will be tied to existing fire alarm system and provide for future PAC card access system.
2. Measurement for payment will be made by percent complete as invoiced monthly.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item Number 0003: Boott Mill Counting House, Mezzanine level Scope of Work
1. Boott Mill Counting House, Mezzanine level - The project includes the modification of an existing demising partition at the Boott Mill Counting House Mezzanine, to provide a new secure entry / exit location between the public lobby at the first level and museum exit and mezzanine function areas. Scope in this area includes:
a. Selective demolition of existing wood pocket doors, frames and hardware.
b. New Metal stud infill framing, sound attenuation batt insulation with GWB, to maintain the existing non-rated assembly. Installation of new baseboard wood trim to match existing.
c. (1) new HM doors with vision panels, welded HM frames to provide required egress and limit secure access. Secure door will be tied to existing fire alarm system and provide for future PAC card access system.
2. Measurement for payment will be made by percent complete as invoiced monthly.
3. Payment will be made at the contract lump sum price.
D. Option A: GC Provided Door Closure Hardware / NPS installed
1. Contract Line Item Number 0004: Misc. Door Hardware - closures
a. This item consists of GC purchased door closure hardware for (8) defined doors as outlined on the Contract Documents. Hardware will be installed by Park.
b. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
dlieb Callout
CLIN 60
dlieb Callout
CLIN 60
dlieb Cross-Out dlieb Cross-Out
LOWE 335201 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 4-21-23
LOWE 335201
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
4. Section 01 91 14 "Total Building Commissioning" for coordinating the work with Owner’s
Commissioning Authority.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
LOWE 335201 01 31 00 - 2
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
LOWE 335201 01 31 00 - 3
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
e. Indicate required installation sequences.
2. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.
3. Follow NPS DSC Electronic Drawing Standards.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, mechanical, plumbing, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: N/A
7. Electrical Work:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 millimeters) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System: N/A
9. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to:
LOWE 335201 01 31 00 - 4
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 1 documents:
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
11. Indoor Air Quality (IAQ) Management Plan
12. Contractors Commissioning Plan
13. Historic Preservation Treatment Plan (HPTP)
14. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
E. Provide items listed to Contracting Officer at least one week prior to Pre-Construction Conference, or as directed by Contracting Officer.
1. Failure to submit items may result in:
a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.
b. Work shall not commence until written Notice to Proceed has been issued and Certificates of Insurance and SF1413 documents are received for Contractor and all Subcontractors.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
LOWE 335201 01 31 00 - 5
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: SUBMIT VIA EMAIL OR APPROVED SHAREPOINT TRANSFER SITE
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
LOWE 335201 01 31 00 - 6
1.6 PROJECT WEB SITE (NOT APPLICABLE)
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. Acceptance/rejection of work
17. Progress meetings
18. Submittal procedures
19. NPS Final Accessibility Inspection
20. Environmental requirements
21. Permit requirements
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials
25. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
LOWE 335201 01 31 00 - 7
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Possible conflicts
i. Compatibility requirements
j. Time schedules
k. Weather limitations
l. Manufacturer's written instructions
m. Warranty requirements
n. Compatibility of materials
o. Acceptability of substrates
p. Temporary facilities and controls
q. Space and access limitations
r. Regulations of agency(ies) with jurisdiction
s. Testing and inspecting requirements
t. Installation procedures
u. Coordination with other work
v. Required performance results
w. Protection of adjacent work
x. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
LOWE 335201 01 31 00 - 8
1.8 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; [familiarity with Environmental Management Systems (EMSs) such as International Organization for Standardization (ISO) 14001]; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Indoor Air Quality (IAQ) Management Plan.
d. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
f. Training for Contractor personnel in accordance with position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Indoor Air Quality (IAQ) Management
4. Noise and Acoustics Management
5. Temporary Storm Water Pollution Prevention Environmental Management
6. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Indoor Air Quality (IAQ) Management
c. Noise and Acoustics Management
d. Temporary Storm Water Pollution Prevention
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan.
LOWE 335201 01 31 00 - 9
1.9 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: N/A
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
LOWE 335201 01 32 18 - 1
051121 CONSTRUCTION SCHEDULE
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21
LOWE 335201
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
LOWE 335201 01 32 18 - 2
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: Schedules and reports submitted shall be posted on the NPS/DSC management software website in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit two digital copies of baseline schedule, large enough to show entire schedule for entire construction period.