Attachment_12_-_RFIs_18-30_0004.pdf
PDF 245 KB Posted
- Solicitation number
- 140P4326R0009
About this file
This is a Solicitation Questions and Answers document for a federal construction contract with the National Park Service.
Project Overview and Identification: Solicitation Number 140P4326R0009 covers Security Upgrades at Lowell National Historical Park (PARK-PMIS: 314055/335201). The Q&A document, dated 06/08/2026, addresses technical and logistical inquiries from prospective contractors. Questions will be received until June 17, 2026, at 5:00 PM EDT, with pre-proposal questions required a minimum of 7 days prior to the proposal due date. Two site visit walk-throughs were provided on May 5, 2026, and May 20, 2026, with no additional site visits planned.
Key Project Requirements and Clarifications: The work involves security system installations across multiple facilities including Boott Mill #6/Counting House, Mogan Cultural Center, KSAH, and Maintenance Facility (220 Aiken Street). Specifications require electrified door hardware (crashbars and electric strikes per Spec Section 08 71 00), with electric strikes to be installed on smaller door leaves for split doors (322, 323, 327). The referenced work scope under CLIN 00020 must be performed prior to 11/15/2026. The contractor must provide dust containment, daily cleanup, temporary enclosures for selective demolition areas, and secured doorways at curatorial offices. The Government will provide a project superintendent office space within Boott Mill #6 with desk and chair if available. There are no Government-furnished items, no liquidated damages, and no hazardous materials in the existing stucco system at 220 Aiken Street. Fire alarm service is provided by HURTVET SUBCONTRACTING, LLC (Stephanie Mills, 603-767-8778), while elevator service information is pending. All service shutdowns must be coordinated in advance with the Park.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NUMBER: 140P4326R0009
PARK - PMIS: 314055 / 335201
PROJECT TITLE: The Na onal Park Service, Lowell Na onal Historical Park - Security Upgrades, SOCILITATION QUESTIONS 02: 06/08/2026
LOWE 314055
Q18. Is there a Reflected Ceiling Plan for the building(s) areas that have drop or hard ceilings. If refers to the RCP on Drawing E8.01. I did not see one in the 2 sets.
A18. (previously answered in Question “Q7 dated 05/21/2026) The details shown on DRAWING E8.01/DETAILS 1, 2, & 3 are typical details. The locations where hard ceilings exist are:
1. Boott Mill #6 / Counting House - wall access panels as required to access.
2. Mogan Cultural Center – ceiling access panels shall be coordinated with the
COR in the field once distribution plans are established.
3. KSAH - wall access panels as required at exterior doors receiving new PAC units.
4. Maintenance Facility (220 Aiken) – drop ceiling in main entry may be accessed, remaining (2) doors are open to structure above with no drop or hard ceilings.
Q19. On the plans for the access-controlled doors the Symbol “L” represents electrified hardware. I’m assuming it’s an electrified door hinge? What is the electrified door hinge feeding? Some instances it could be an electric crash bar and in some it could be an electrified mortice lock.
A19. Please REF. Spec Section 08 71 00 – Door Hardware, 1.1B; 1.4C; 2.1E; and 3.6 Door Hardware Sets.
Q20 The Symbol P in an octagon stands for Electrified panic hardware, Is that an electrified Crash bar or an electric Crashbar with arms/pins that go to the door frame and the floor? We checked Division 8 and the door hardware schedule it does not have any info. Can you provide an example using double doors A20. Electrified panic hardware is a “crashbar”. Spec Section 08 71 00, 2.4 Exit Devices A.6 references electrical options. We recommend reviewing the plans and Spec Section 08 71 00 in entirety including Door Hardware Sets.
Q21. On the doors that are split where 1 door is larger than its mate, Are you looking for the electric strike to be installed on the smaller door or are we going with an electrified mortice lock?
A21. For doors 322, 323, and 327, Please reference the door schedule on A5.01. The RX function denoted as “YES” refers to a Request-to-Exit (RTE) switch built into an exit device. Spec Section 08 71 00, Hardware Set HW-03 indicates electric strikes. The electric strike should be installed on the smaller door leaf.
PROJECT TITLE: The Na onal Park Service, Lowell Na onal Historical Park - Security Upgrades, SOCILITATION QUESTIONS 02: 06/08/2026
Q22. Is there another walk through at all A22. Response:
1. The Government provided (2) site visit walk-throughs for the solicitation on:
a. May 5, 2026 at 11am EST
b. May 20, 2026 at 10am EST
2. The are no additional site visits planned.
3. As identified in the Solicitation under INSTRUCTIONS FOR THE SUBMISSION OF
OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE SELECTION, B.
Questions, questions will continue to be received and responded until June 17, 2026, 5pm EDT:
a. Pre-proposal questions shall be submitted a minimum of 7 days prior to the due date and time for proposals. Submit questions only through email to both of the following: Contracting Officer, Samuel McKenzie, Samuel_McKenzie@ios.doi.gov
Q23. Reference Maintenance Shop; Please provide HAZMAT survey of the existing stucco system – GENERAL A23. The existing exterior mortar stucco and insulation system at 220 Aiken Street was installed in 2012. There are no hazardous materials associated with the system. Prior testing and abatement was performed previously in the facility.
Q24. Will the Government provide the fire alarm service company and the elevator service company to perform shut down services for work under this contract?
Q25. Please provide name and contact for the Fire Alarm and Elevator service company
A24 / A25. Government responses:
1. Fire Alarm Company:
a. The Park’s current service provided is: HURTVET SUBCONTRACTING, LLC., 1389 CENTER DRIVE PARK CITY UT 84098-7660 ATT: Stephanie Mills phone 603-767-8778
2. Elevator Service Company – the Park is in the process of finalizing an elevator service contract and will provide that information to the successful offeror.
3. Regarding temporary shutdowns, the GC will be required to coordinate shut downs under the contract. The building and facilities will remain active during the contract. Any anticipated interruptions in elevator or fire alarm service will need to be coordinated in advance with the Park.
Q26. Reference section 011100; Para. 1.3 , B #1- Please confirm this work scope will be performed prior to 11/15/26.
A26. The referenced scope of work is included in this solicitation as CLIN 00020.
PROJECT TITLE: The Na onal Park Service, Lowell Na onal Historical Park - Security Upgrades, SOCILITATION QUESTIONS 02: 06/08/2026
Q27. Reference section 011100; Para. 1.4 , #2 – Please provide list of government furnished items.
A27. There are no Government furnished items identified at this time that would be covered by the referenced Spec Section.
Q28. Please provide Liquidated Damage daily cost A28. There are no liquidated damages on this solicitation / contract.
Q29. Please confirm that the Government will remove and or protect all F,F,&E located with in construction work areas.
A29. The Government will work with the GC to make areas for running cabling and wiring accessible based on GC’s detailed CPM schedule and 2-3 week look ahead schedule.
1. GC should account for any and all dust containment and daily clean-up in areas that are occupied.
2. Areas where there will be selective demo and construction, for example, new walls, door frames, etc. GC will be responsible for providing temporary dust enclosures and site controls.
3. At the curatorial offices on Boott Mill #6 third floor, rooms 322, 323 and 327, GC will be responsible for maintaining secured doorways capable of locking at the end of each day and when workers not in the areas. Locking will need to be coordinated with the COR (and Park LE and curatorial staff).
Q30. Will the government provide an office space for the contractors project superintendent A30. The Government will provide a room or space where the GC’s project superintendent can be based within the Boott Mill #6 facility only. The Government will provide a desk, and office chair if available. Otherwise, the GC will be responsible for providing their own furniture (tables, chairs, etc.).
Reviewed and responded by:
David Michael Lieb, RA, Contracting Officer’s Representative
| 2026-06-08T15:00:00-0400 | |
| DAVID LIEB |