B08_Attach_1_Statement_of_Work.pdf

PDF 440 KB Posted

Attached to
Susanville/Doyle Interagency Fire Station Construc Federal contract opportunity
Solicitation number
140L1223B0001
Issued by
Department of the Interior Bureau of Land Management California Region

About this file

This statement of work outlines the requirements for construction of a new fire station facility and fitness center at the Susanville/Doyle Interagency Fire Station in Doyle, California. The Bureau of Land Management seeks to construct a new administrative area and four engine bays to improve response times. Additional requirements include site improvements, utility installations, building systems commissioning, and three additive alternates for landscaping, fill stand upgrades, and converting an existing engine barn into a fitness center. The contractor must adhere to construction administration procedures, site cleanup requirements, and codes and standards outlined. A one year warranty is required. The anticipated period of performance is seven calendar days from notice to proceed, with work occurring Monday through Friday from 7:30 AM to 4:30 PM.

View the file

Other files for this federal contract opportunity

Other files attached to Susanville/Doyle Interagency Fire Station Construc, newest first.
File Type Posted
B09_Amend_02_Section_J_-_Attachment_4_-_Office_Trailer_Information_0002.pdf PDF
B09_Amend_02_Revised_Section_J_0002.pdf PDF
Sol_140L1223B0001_Amd_0002.pdf PDF
B09_Amend_0002_Revised_Response_to_Question_17_0002.docx DOCX document
B09_Amend_0001_Questions_and_Answers_0001.docx DOCX document
B09_Amend_0001_B08_Attach_1_Statement_of_Work_Revised_19_Jul_2023_0001.docx DOCX document
B09_Amend_0001_Site_Visit_Sign_in_Sheet_0001.pdf PDF
B03_Attach_2_Wage_Determination_CA20230007_Rev_15_30_June_2023_0001.pdf PDF
B09_Amend_0001_B08_Attach_1_SOW_EX_6_Draft_SWPPP_Vol_3_0001.docx DOCX document
Sol_140L1223B0001_Amd_0001.pdf PDF
B09_Amend_0001_Revised_Pages_0001.pdf PDF
B09_Amend_0001_B08_Attach_1_SOW_EX_6_Draft_SWPPP_Vol_2_0001.docx DOCX document
B09_Amend_0001_B08_Attach_1_SOW_EX_6_Draft_SWPPP_Vol_1_0001.docx DOCX document
B09_Amend_0001_B08_Attach_1_SOW_EX_6_Draft_SWPPP_Vol_4_0001.docx DOCX document
B08_Attach_1_SOW_EX_3_Supplemental_Specifications_Doyle_Fitness_Center.pdf PDF
B08_Attach_1_SOW_EX_1_Project_Specifications_Doyle_Fire_Station.pdf PDF
B03_Attach_2_Wage_Determination_CA20230007_Rev_12_5_May_2023.pdf PDF
B08_Attach_3_Pricing_Schedule.xlsx XLSX spreadsheet
B08_Attach_1_SOW_EX_4_Supplemental_Drawings_Doyle_Fitness_Center.pdf PDF
B08_Attach_1_SOW_EX_2_Project_Drawings_Doyle_Fire_Station.pdf PDF
Sol_140L1223B0001.pdf PDF
B08_Attach_1_SOW_EX_5__As-Builts_Drawings.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Susanville/Doyle Interagency Fire Station Construction

Doyle, California

May 2023

BUREAU OF LAND MANGEMENT

Northern California District

5/26/23

STATEMENT OF WORK

SUSANVILLE/DOYLE INTERAGENCY FIRE STATION CONSTRUCTION

Table of Contents

1.0 Project Background

2.0 Project Location

3.0 General Scope of Work

3.1 Summary of Work

3.2 Additive Alternates

3.3 Construction Administration

3.4 Site Cleanup

3.5 Project Access and Staging

3.6 Pre-Proposal Site Visit

3.7 Codes/Standards

3.8 Warranties

3.9 Project Closeout

4.0 CONTRACTUAL

4.1 Period of Performance

5.0 Standard Definitions and Technical Exhibits

Exhibit 1: Project Specifications (Doyle Fire Station)

Exhibit 2: Project Drawings (Doyle Fire Station)

Exhibit 3: Supplemental Specifications (Doyle Fitness Center)

Exhibit 4: Supplemental Drawings (Doyle Fitness Center)

Exhibit 5: As-Built Drawings

1.0 Project Background

The Bureau of Land Management (BLM) is seeking construction services to install a new fire station facility at the Susanville/Doyle Interagency Fire Station in Doyle, CA. In order to meet the capacity and direct protection area demand, there is a need to construct a new fire station at the existing Doyle Fire station location. This will improve response times and initial attack effectiveness requirements in Northern California District’s area of responsibility. This

Interagency fire station will administratively house BLM and Forest Service personnel.

2.0 Project Location

The site is located at the Southeast corner of the intersection of Highway 395 and Doyle Grade

Road. The coordinates are: 40.026937° Latitude; -120.105510° Longitude.

3.0 General Scope of Work

The Project consists of furnishing labor, equipment, supplies and materials to construct a new fire station building on the existing premises which consists of an administrative area and four engine bays and performing all site improvements, all of which are detailed in the attached design documents. Specifications and drawings for the fire station and site improvements are contained in Exhibit 1 and Exhibit 2, respectively. Additive alternates are included in the design documents and supplemental design information.

3.1 Summary of Work

The work required includes, but is not limited to the following:

• General clearing, grubbing, and grading to meet grading plan and site drainage.

• Install temporary facilities, controls, and storm water pollution prevention.

• Selective demolition of existing site components.

• Trench and installation of onsite underground utilities serving the new building.

• Preparation of soil pads and construction of foundations, slabs, and structures.

• Constructing the new fire station building structure.

• Install new electrical transformer and coordinating with the local power for a new service drop location.

• Install new sanitary sewer lines, septic tank and leech field

• Relocating existing propane tank and coordinating with the facility personnel.

• Install retaining wall and site fencing.

• Install electric gate and fencing with associated conduit runs including runs for future security access system

• Install all other associated items in the drawing including HVAC units, bollards, manual and powered gates, gravel parking bays, ABA parking spaces, bumper blocks, electrical charging stations, trash enclosure, site lighting and solar lights, gravel driving surface, concrete pad for storage containers and all associated utility lines.

• Area of disturbance shall conform to the Stormwater Pollution Prevention Plan (SWPPP).

• Demolish and properly dispose of the septic tank and sewer piping per CA requirements.

Relocate existing hazmat sheds with BLM direction.

• Commissioning, startup, and testing of all components installed under the contract.

3.2 Additive Alternates

The Project includes three additive alternates. The requirements for Alternates #1 and #2 are covered in the project Specifications and Drawings, Exhibit 1 and Exhibit 2, respectively. A separate design was prepared for Alternate #3 to convert the existing engine barn into the Doyle

Fitness Center. The Doyle Fitness Center specifications and drawings are contained in Exhibit 3 and Exhibit 4, respectively.

• Additive Alternate 1: Site Planting o The work for Alternate 1 is covered in the following:

▪ Specifications (Exhibit 1) Section 01 23 00.

▪ Drawing Sheets (Exhibit 2): L-100, L-101, L-102, L-201, L-202

• Additive Alternate 2: Fire Engine Fill Stand Improvements o The work for Alternate 1 is covered in the following:

▪ Specifications (Exhibit 1) Section 01 23 00.

▪ Drawing Sheets (Exhibit 2): L-100, L-101, L-102, L-201, L-202

• Additive Alternate 3: Doyle Fitness Center o The Doyle Fitness Center work identified in the supplemental Specifications

(Exhibit 3) and Drawings (Exhibit 4). The existing engine barn will be converted to include a new fitness center. The existing metal building consists of 4 engine bays and an area enclosed with a demising wall and topped with a mezzanine. As-

Built plans for the existing 4-bay engine barn is provided in Exhibit 5.

o The Fitness Center will occupy the enclosed area and one engine bay. The existing demising wall and mezzanine will be demolished, a new demising wall installed between two engine bays, and the existing electric panel will be enclosed in a closet.

New electrical and mechanical upgrades will be installed. Windows and doors will be installed, as detailed on the drawings.

o Sequencing Requirements: The old engine barn must remain in operation during construction of the new fire station. Once the new fire station is completed, the

BLM fire staff will move out of the old engine barn within 2 weeks, and the contractor can begin the Fitness Center construction.

3.3 Construction Administration

The Contractor shall adhere to the Division 01 - General Requirements of the project

Specifications (Exhibit 1). Additional requirements are as follows:

a. The Doyle Fire Station Facility is a must-cover station that will remain in operation during construction of the new Fire Station. The Contractor shall coordinate operations with the

COR and fire facility manager. The personnel will require access to the existing engine barn and the crew quarters during construction.

b. The Contractor shall be responsible for security and protection of the construction area.

c. No dumping of waste products of any type will be permitted. All waste shall be transported to an approved sanitary landfill for disposal off BLM project site.

d. Materials for construction, and equipment may be stockpiled and staged at the project site in an area designated and coordinated by the COR.

e. Contractor shall take precautions to protect all work and materials during the construction period.

f. The Contractor is responsible for safeguarding the public and employees from construction operations.

g. Coordinate all activities with COR. Contractor shall be responsible for replacing with in kind any damaged items caused to public or private properties by Contractor or his/her representatives.

h. Provide the working schedule a minimum of seven calendar days prior to start of the work.

i. Contractor to adhere to all DOI and BLM policies for pandemic mitigation. May include wearing masks at all times indoors. Contractor to verify requirements with COR prior to start of work.

j. Submittals and Meetings:

a. Submittals for all materials outlined in the project Specifications (Exhibit 1).

b. Daily construction reports submitted weekly to the COR.

c. Contractor to hold biweekly progress teleconferences and provide agenda and meeting notes.

d. Develop a proposed maintenance plan for each major system i.e. HVAC system, water heater, fans, propane in soft copy form in Word and Excel.

e. Operation & Maintenance (O&M) manuals for all systems, packaged in a single master O&M document organized into sections and tabbed for reference.

f. Red lines and finalized As-Built drawings.

g. Bonds, warranties, guarantees and operation & maintenance data.

h. Special materials testing reports and documentation.

i. Testing and commissioning documentation.

3.4 Site Cleanup

a. Project site cleanup includes the removal and proper disposal of all construction trash, debris, and residue off the BLM project site. Items such as miscellaneous construction materials are considered the property of Contractor and shall be removed from the project site.

b. During the Work, Contractor is required to furnish dumpsters or other trash receptacles and to empty such containers either as they become full or weekly, whichever is more frequent.

Contractor shall not place materials of any kind into private or Government trash bins or dumpsters. Contractor to supply their own restrooms during construction activities. Clean up site at the end of each workday.

c. Cover up open trenches at the end of each workday. Steel plates may be used with COR approval. Use appropriate flagging, cones and signage around the construction area to notify BLM employees of construction limits.

d. All damages caused to the existing property caused by the Contractor or his/her representatives and staff shall be repaired free of charges to BLM to the satisfaction of the

COR. Call a utility locate and identify any utilities prior to starting construction. Any damaged utilities shall be repaired as soon as possible at no cost to the Government and to the BLM satisfaction.

3.5 Project Access and Staging

Coordinate with BLM on access to the site during construction and determine a viable staging area. Staging area shall not affect the ongoing operations at the existing quarters or engine bays.

3.6 Pre-Proposal Site Visit

Any prospective contractor that submits a proposal for this project shall have visited the site and to gain a thorough understanding of the requirements. A pre-proposal site meeting is scheduled as stated in the solicitation document.

3.7 Codes/Standards

All work performed, equipment, and materials used under this scope of work shall be in accordance with applicable building codes, industry standards, County, and all governing agencies.

3.8 Warranties

Provide a minimum contractor guarantee for all work under this contract for one year from date of the installation. Provide all standard manufacturer warranties and any special warranty requirements in the project Specifications.

3.9 Project Closeout

a. Removal of Protection Items: Remove any temporary items installed for protection of the

Work during construction.

b. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for cleaning and demolition. Do not burn waste materials. Do not bury debris or excess materials on the Government’s property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from the site and dispose of lawfully. Clean the site of rubbish, litter, and other foreign substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits.

4.0 CONTRACTUAL

4.1 Period of Performance

a. Work shall commence no later than 7 calendar days from the issuance of the Notice To

Procced (NTP).

b. Perform work Monday through Friday, from 7:30 AM to 4:30 PM, except on legal

Government holidays. Other working hours and/or arrangements may be made if agreed upon by the COR.

c. Delays due to matters outside of Contractor’s control may be considered by the Contracting

Officer (CO), with written request by Contractor.

5.0 Standard Definitions and Technical Exhibits

Standard Definitions:

Physical Condition

The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR.. Physical condition may be determined by visual as well as diagnostic means.

Contracting Officer (CO)

The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

Contracting Officer’s Representative (COR)

The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

Quality Assurance (QA)

Surveillance of Contractor performance to determine performance requirements are met.

Performance Requirements Summary (PRS) (see Technical Exhibit below)

The PRS identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.

Quality Control

Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.

Technical Exhibits:

Exhibit 1: Project Specifications (Doyle Fire Station)

Exhibit 2: Project Drawings (Doyle Fire Station)

Exhibit 3: Supplemental Specifications (Doyle Fitness Center)

Exhibit 4: Supplemental Drawings (Doyle Fitness Center)

Exhibit 5: As-Built Drawings