This solicitation is for the rehabilitation of the Antietam Visitor Center located at Antietam National Battlefield in Sharpsburg, Maryland. The solicitation number is 140P2020R0080 and was issued by the National Park Service National Office within the Department of the Interior.
The project will involve renovating the existing visitor center building, which was constructed in the 1960s. Work will include repairs and upgrades to the building exterior, roofing system, HVAC system and electrical system. The interior will be renovated to improve accessibility and update exhibits. Asbestos abatement and lead paint remediation will also be required. The pre-bid site visit will be held on March 23rd and bids are due by April 13th. It is anticipated that the winning contractor will be selected in June and work will commence in July.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Antietam National Battlefield Sharpsburg, MD
Rehabilitate Antietam Visitor Center
ANTI – 225963
PROJECT SPECIFICATIONS
FINAL CONSTRUCTION DOCUMENTS
APPENDIX A
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
FINAL CONSTRUCTION DOCUMENTS
May 22, 2020
ANTI - 225963
05222020
00 01 10 - 1
APPENDIX TABLE OF CONTENTS
DOCUMENT 00 01 10 – APPENDIX TABLE OF CONTENTS
VOLUME 1 of 1
APPENDIX A:
HAZMAT REGULATIONS SUMMARY
PHOTO DOCUMENTATION LOG OF ENVIRONMENTAL SERVICES
FINAL ENVIRONMENTAL SERVICES REPORT
dencela Snapshot
05222020
00 01 10 - 2
APPENDIX TABLE OF CONTENTS
04242020
APP001
HAZMAT REGULATIONS SUMMARY
APP001 – HAZMAT REGULATIONS SUMMARY
APP001
HAZMAT REGULATIONS SUMMARY
CHOH PMIS 165235 Demolish Partially Collapsed Buildings Damaged by February 2010 Storms
Material Type of
Regulation Regulation Party Responsible Summary Regulation Party Responsible Summary Regulation Party Responsible Summary Regulation Party Responsible Summary
Federal
National Emission Standards for Hazardous Air Pollutants (NESHAP; 40 CFR 61 Subpart M (61.141 and 61.145) ; OSHA 29 CFR 1910.1001 and 29 CFR 1926.1101
DOT 49 CFR parts 171 and 172 NESHAP; 40 CFR 61 Subpart M (61.141, 61.150 and 61.154)
MD State Maryland Department of the Environment (MDE) ‐ (COMAR 26.11.21 Control of Asbestos)
Maryland Department of the Environment (MDE) ‐ (COMAR
26.11.21 Control of Asbestos)
Maryland Department of the Environment (MDE) ‐ (COMAR
26.11.21 Control of Asbestos)
Federal 40 CFR 745 (not applicable); OSHA 29 CFR
1926.62 and 29 CFR 1910.134
LBP activities are the subject of several federal regulations and guidelines, which include disposal of lead based paint waste
(RCRA) and lead exposure of workers (OSHA). The volume of LBP‐related hazardous waste should be minimized to the extent most feasibly and economically possible, through segregation of waste streams. OSHA requires if lead is present in detectable levels, the Contractor must perform a negative exposure assessment to ensure that their workers will not be exposed to airborne lead above the allowable personal exposure limits
MD State Not applicable because the buildings are not target housing or child‐occupied
Lead disposal regulations found in the Code of Maryland Regulations 26.02.07
Specifications should make HazMat or T&D contractor responsible to identify compliant facilities.
Transporters must be permitted; regulates waste transportation and tracking
Transporters must be permitted; regulates waste transportation and tracking
Owner decision as reflected in project specifications
Metal with LBP can be recycled as scrap metal.
Non‐recyclable debris should be tested or disposed of as hazardous waste.
Asbestos waste may be disposed of at a permitted municipal solid waste landfill.
For a landfill to accept the asbestos waste, it must be packaged in accordance with applicable EPA, OSHA, and MD requirements.
Lead‐based paint can be assumed to fail TCLP under RCRA (D008) and can be managed as hazardous waste, or the waste itself can be tested. Maryland has authorization for RCRA. Metal with LBP can be recycled.
Deconstruction
Specifications should make HazMat/ ACM abatement contractor responsible for compliance, permitting, and notifications
Specifications should make the HazMat removal contractor responsible
Federal and state regulations apply to certain demolition and renovation projects in facilities containing asbestos‐ containing materials (ACMs). The rules require that friable ACMs, and some categories of non‐friable ACMs, be removed before a building is demolished.
OSHA regulates employee exposure to asbestos and in 1994 revised its final rule on asbestos. Maryland regulates licensing, notification and permits.
ACM ‐Projection Room and Janitor’s Closet, Office 01, Office 02, Office 02 Closet, Office 03 and Associated Hallway, Observation Room and
Closet, Exhibit Room 01 and Exhibit Room 02, Bookstore and Bookstore Office ‐ Floor Tile, Mastic Assoc.
With Floor Tile ‐ Throughout
Exterior, Expansion Joint @ Building Base
Lead‐based paints (exterior and interior)
Recycling
Specifications should make T&D contractor responsible
Landfill DisposalTransportation
Specifications should make T&D contractor responsible
Lead Notification regulations found in the Code of Maryland
Regulations 26.02.07
Specifications should make abatement or T&D contractor responsible to identify compliant facilities.
Type of
Regulation Regulation Party Responsible Summary
Federal
National Emission Standards for Hazardous Air Pollutants (NESHAP; 40 CFR 61 Subpart M (61.141 and 61.145) ; OSHA 29 CFR 1910.1001 and 29 CFR 1926.1101
MD State Maryland Department of the Environment (MDE) ‐ (COMAR 26.11.21 Control of Asbestos)
Federal 40 CFR 745 (not applicable); OSHA 29 CFR
1926.62 and 29 CFR 1910.134
LBP activities are the subject of several federal regulations and guidelines, which include disposal of lead based paint waste
(RCRA) and lead exposure of workers (OSHA). The volume of LBP‐related hazardous waste should be minimized to the extent most feasibly and economically possible, through segregation of waste streams. OSHA requires if lead is present in detectable levels, the Contractor must perform a negative exposure assessment to ensure that their workers will not be exposed to airborne lead above the allowable personal exposure limits.
MD State Not applicable because the buildings are not target housing or child‐occupied
Lead‐based paints (exterior and interior)
Specifications should make the HazMat removal contractor responsible
Deconstruction
ACM ‐ Feidt Curing Shed ‐ Debris on Floor, Anthony House ‐ Tar to Porch
Flashing and Pipe Insulation
Specifications should make HazMat/ ACM abatement contractor responsible for compliance, permitting, and notifications
Federal and state regulations apply to certain demolition and renovation projects in facilities containing asbestos‐ containing materials (ACMs). The rules require that friable ACMs, and some categories of non‐friable ACMs, be removed before a building is demolished.
OSHA regulates employee exposure to asbestos and in 1994 revised its final rule on asbestos. Maryland regulates licensing, notification and permits.
Type of
Regulation Regulation Party Responsible Summary
Federal DOT 49 CFR parts 171 and 172
MD State Maryland Department of the
Environment (MDE) ‐ (COMAR 26.11.21 Control of Asbestos)
Federal
MD State
Transportation
ACM ‐ Feidt Curing Shed ‐ Debris on Floor, Anthony House ‐ Tar to Porch
Flashing and Pipe Insulation
Specifications should make T&D contractor responsible
Transporters must be permitted;
regulates waste transportation and tracking
Lead‐based paints (exterior and interior)
Lead Notification regulations found in the Code of Maryland Regulations 26.02.07
Specifications should make T&D contractor responsible
Transporters must be permitted;
regulates waste transportation and tracking
Type of
Regulation Regulation Party Responsible Summary
Federal NESHAP; 40 CFR 61 Subpart M (61.141,
61.150 and 61.154)
MD State Maryland Department of the
Environment (MDE) ‐ (COMAR 26.11.21 Control of Asbestos)
Federal
MD State Lead disposal regulations found in the Code of Maryland Regulations 26.02.07
Landfill Disposal
ACM ‐ Feidt Curing Shed ‐ Debris on Floor, Anthony House ‐ Tar to Porch
Flashing and Pipe Insulation
Specifications should make abatement or T&D contractor responsible to identify compliant facilities.
Asbestos waste may be disposed of at a permitted municipal solid waste landfill.
For a landfill to accept the asbestos waste, it must be packaged in accordance with applicable EPA, OSHA, and MD requirements.
Lead‐based paints (exterior and interior)
Specifications should make HazMat or T&D contractor responsible to identify compliant facilities.
Lead‐based paint can be assumed to fail TCLP under RCRA (D008) and can be managed as hazardous waste, or the waste itself can be tested. Maryland has authorization for RCRA. Metal with LBP can be recycled.
Type of
Regulation Regulation Party Responsible Summary
Federal
MD State
Federal
MD State
Recycling
ACM ‐ Feidt Curing Shed ‐ Debris on Floor, Anthony House ‐ Tar to Porch
Flashing and Pipe Insulation
Owner decision as reflected in project specifications
Metal with LBP can be recycled as scrap metal. Non‐recyclable debris should be tested or disposed of as hazardous waste.
Lead‐based paints (exterior and interior)
APP002
PHOTO DOCUMENTATION OF ENVIRONMENTAL INVESTIGATION
SERVICES
APP002 – PHOTO DOCUMENTATION OF ENVIRONMENTAL INVESTIGATION SERVICES
APP002
PHOTO DOCUMENTATION OF ENVIRONMENTAL INVESTIGATION
SERVICES
REPORT OF ENVIRONMENTAL INVESTIGATION SERVICES
ANTIETAM VISITOR CENTER,
ANTIETAM NATIONAL BATTLEFIELD, SHARPSBURG, MD
PHOTODOCUMENTATION LOG
Photograph 1: Front View of Antietam Visitor Center
Photograph 2: Antietam Visitor Center, Non-LBP and Non-ACM Beige/Gray Paint on Wood Trellis
– Exterior
Photograph 3: Antietam Visitor Center, Non-ACM deteriorated Stone and Mortar at Observation
Roof
Photograph 4: Antietam Visitor Center, Non-ACM Skylight Flashing – Exterior
Photograph 5: Antietam Visitor Center, Non-ACM Perimeter Flashing – Exterior
Photograph 6: Antietam Visitor Center, Non-ACM Built-Up Roofing – Exterior
Photograph 7: Antietam Visitor Center, Non-ACM Drain Flashing – Exterior
Photograph 8: Antietam Visitor Center, Non-ACM Vent Stack Roofing – Exterior
Photograph 9: Antietam Visitor Center, Non-ACM Roofing Shingles (Black) and Felt Paper under
Roofing Shingles (Black)– Exterior
Photograph 10: Antietam Visitor Center, ACM Expansion Joint @ Building Base (Beige/Gray) – Exterior
Photograph 11: Antietam Visitor Center, ACM 12” x 12” Black Floor Tile and Mastic Associated with Floor Tile - Projection Room and Janitor’s Closet
Photograph 12: Antietam Visitor Center, ACM Floor Tile Under Linoleum and Mastic Associated with Floor Tile - Office 01, Office 02, Office 02 Closet, Office 03 and Associated Hallway.
Photograph 13: Antietam Visitor Center, ACM 9” x 9” Tan with White Floor Tile and Mastic
Associated with Floor Tile Under Carpet - Observation Room and Closet
Photograph 14: Antietam Visitor Center, ACM Floor Tile Under Carpet and Mastic Associated with
Floor Tile - Exhibit Room 01 and Exhibit Room 02
Photograph 15: Antietam Visitor Center, ACM 9” x 9” Grey Floor Tile Under Carpet and Mastic
Associated with Floor Tile - Bookstore and Bookstore Office
Photograph 16: Antietam Visitor Center, Clean Ceiling Plenum – Interior
Photograph 17: Antietam Visitor Center, Metal Ductwork - Interior
Photograph 18: Antietam Visitor Center, Stone Flooring Under Carpet in Lobby.
Photograph 19: Antietam Visitor Center, LBP Paint on Wood Wall and Ceiling at Lobby.
Photograph 20: Antietam Visitor Center, Universal Waste Batteries (200 Count) at Janitor’s Closet.
APP003
FINAL ENVIRONMENTAL SERVICES REPORT
APP003 – FINAL ENVIRONMENTAL SERVICES REPORT
APP003
FINAL ENVIRONMENTAL SERVICES REPORT
FINAL REPORT OF
ENVIRONMENTAL INVESTIGATION SERVICES
AT
ANTIETAM VISITOR CENTER
Prepared For:
NATIONAL PARK SERVICE
Prepared By:
96 Morton Street, 8th Floor New York, New York 10014
Tel. (212) 612-7900
NPS PMIS NO. ANTI-225963
LOUIS BERGER PROJECT NO. 2004584.011
Final Submission: September 13, 2019
Final Report of Environmental Assessment Services at Antietam Visitor Center
September 13, 2019
Mr. Anthony V. Bochicchio, AIA National Park Service Denver Service Center Design and Construction 12795 West Alameda Parkway Lakewood, CO 80228
Subject: Final Report of Environmental Assessment Services at Antietam Visitor Center Antietam National Battlefield, Sharpsburg, MD Louis Berger Project No. 2004584.011
Dear Mr. Bochicchio:
Louis Berger (LB) has completed a building materials/environmental survey at the Antietam Visitor Center, located in the Antietam National Battlefield, Sharpsburg, MD. This investigation involved visual surveys as well as laboratory sample analysis of suspect Asbestos-Containing Materials (ACM), Lead-Based Paints, and the quantification of Universal Waste in this building, which is targeted for rehabilitation.
The attached report presents descriptions and results of the material sampling procedures and analysis. Relevant general project information is provided, followed by our findings, assessments and recommendations. Laboratory analysis data and certifications are provided in the Appendices.
If you have any questions concerning this report or if we may be of further assistance to you, please contact us.
Sincerely, LOUIS BERGER (LB)
Prakash Saha Associate Vice President, Emergency Management & IH Services
Louis Berger Page 3 December 02, 2019
TABLE OF CONTENTS
Page
1.0 EXECUTIVE SUMMARY
2.0 ASBESTOS INVESTIGATION PROCEDURES AND SAMPLE ANALYSIS METHODS
2.1 INSPECTION SCOPE AND MATERIAL ASSESSMENT
2.2 INSPECTION RESULTS
2.3 CONDITION, QUANTITY AND FRIABILITY TABLE
2.4 SAMPLE ANALYSIS TABLE……………………………
2.5 AREAS NOT ACCESSIBLE………………………………
3.0 LEAD FIELD INSPECTION PROCEDURES
3.1 INSPECTION SUMMARY
3.2 INSPECTION RESULTS
3.3 CONDITION ASSESSMENT TABLE
3.4 AREAS NOT ACCESSIBLE………………………………
3.5 CONCLUSIONS AND RECOMMENDATIONS...………
4.0 UNIVERSAL WASTES
5.0 CONCLUSIONS AND RECOMMENDATIONS
6.0 LIMITATIONS, EXCEPTIONS, ASSUMPTIONS AND CERTIFICATION
APPENDICES
Appendix A: Asbestos Sample Analysis Results in Tabular Form Appendix B: Lead Sample Analysis Results in Tabular Form Appendix C: Bulk Sample Chain of Custodies & Laboratory Results Appendix D: Laboratory Accreditations & Personnel Certifications Appendix E: Sample Location Drawings Appendix F: Asbestos and Lead Containing Materials Location Drawings Appendix G: Photographic Documentation Appendix H: Previously Completed Pertinent Hazmat Reports
Louis Berger Page 4 December 02, 2019
1.0 EXECUTIVE SUMMARY
Louis Berger (LB) has performed an environmental inspection for the presence or absence of Asbestos-Containing Materials (ACM), Lead-based Paints (LBP), and universal wastes at Antietam Visitor Center, Antietam National Battlefield, Sharpsburg, MD. The inspection was conducted at the request of the National Park Service for use in their upcoming Rehabilitate Visitor Center project. The scope of work for this project received by LB was based on the Scope of Services received from EYP Architecture & Engineering. The intent of this inspection was to locate, identify and quantify ACM, LBP and universal wastes that will be impacted during the upcoming project.
Michael Johnson and Alexander Smolyar performed this survey on July 29, 2019. Michael Johnson is a certified Asbestos Inspector and Designer, and USEPA-certified Lead Risk Assessor (LBP-R- I198619-1). Alexander Smolyar certified Asbestos Inspector, and USEPA-certified Lead Risk Assessor (LBP-R-129050-1).
Analytical results of the bulk samples collected indicate that the following materials contain asbestos in the amount greater than 1% [ACM]:
• Expansion Joint @ Building Base (Gray/Beige) – Throughout Exterior
Analytical results of the bulk samples collected indicate that the following materials contain less than 1% asbestos [Non-ACM]:
• Chimney Mortar (Gray) – Observation Room Roof
• Caulking @ Chimney (Gray) – Observation Room Roof
• Caulking at Perimeter of Roof (Gray) – Observation Room Roof
• Chimney Flashing (Black) – Observation Room Roof
• Bottom Membrane (Black) – Observation Room Roof
• Felt Paper (Gray/Black) – Observation Room Roof
• Insulation (Beige) – Observation Room Roof
• Top Membrane (Black) – Observation Room Roof
• Tar @ Bottom Layer (Black) – Main Roof and Auditorium Roof
• Felt Paper (Gray/Black) – Main Roof and Auditorium Roof
• Perlite Insulation (Tan) – Main Roof and Auditorium Roof
• Insulation (Beige) – Main Roof and Auditorium Roof
• Top Membrane (Black) – Main Roof and Auditorium Roof
• Metal Cap Flashing Caulking (Gray) – Main Roof and Auditorium Roof
• Old Tar on Parapet Wall (Black) – Main Roof and Auditorium Roof
• Coping Stone Caulking (Gray) – Main Roof and Auditorium Roof
• Perimeter Flashing (Black) – Main Roof and Auditorium Roof
• Mechanical Flashing (Black) – Main Roof and Auditorium Roof
• Vent Stack Flashing (Black) – Main Roof and Auditorium Roof
• Stone Mortar at Stone Wall (Gray) – Main Roof and Auditorium Roof
• Roof Drain Flashing (Black) – Main Roof and Auditorium Roof
• Skylight Flashing (Black) – Main Roof and Auditorium Roof
• Exterior Paint (Beige) – Throughout Exterior
• Exterior Window Frame Glazing (Black) – Throughout Exterior
• Tar @ Building Base (Black) – Throughout Exterior
• Exterior Façade Stone Mortar (Gray) – Throughout Exterior
Louis Berger Page 5 December 02, 2019
• Gypsum Board (Beige) – Auditorium Exterior Exit Overhang
• Exterior Window Frame Caulking (White) – Throughout Exterior
• Exterior Door Frame Caulking (Gray) – Throughout Exterior
• Sidewalk Expansion @ Shed Structures (Gray) –Exterior @ Storage Sheds
• Roofing Shingles (Black) –Exterior @ Storage Sheds
• Felt Paper under Roofing Shingles (Black) –Exterior @ Storage Sheds
• Stone Mortar (Red) – Auditorium
• Leveling Compound on Concrete Floor (Gray) – Auditorium
• Carpet Glue (Yellow) – Auditorium
• Caulking Around Toilet Fixtures (White) – Interior Throughout Bathrooms
• Ceramic Wall Tile Backing (White) – Interior Throughout Bathrooms
• Ceramic Wall Tile Grout (White) – Interior Throughout Bathrooms
• Ceramic Floor Tile Grout (Gray) – Interior Throughout Bathrooms
• Ceramic Floor Tile Backing Under 1st Layer (Gray) – Interior Throughout Bathrooms
• Ceramic Floor Tile Backing Under 2nd Layer (Gray) – Interior Throughout Bathrooms
• Fiberglass Duct Insulation Wrap (Silver) – Interior Throughout
• Perlite Insulation Within Ceiling Plenum (Gray/Brown) – Interior Throughout
• Interior Window Frame Caulking (White) – Interior Throughout
• Ceiling Plaster (White and Brown Coats) – Interior Throughout
• Interior Brick Mortar (Gray) – Interior Throughout
• Cinder Block Mortar (Gray) – Interior Throughout
The results of the visual inspection and results from previously completed survey report by ARC Environmental, Inc., dated February 2017 have determined that the following ACM exist in the building:
• 12” x 12” Black Floor Tile and Mastic Associated with Floor Tile – Projection Room and Janitor’s Closet
• Floor Tile Under Linoleum and Mastic Associated with Floor Tile - Office 01, Office 02, Office 02 closet, Office 03 and Associated Hallway
• 9” x 9” Tan with White Floor Tile and Mastic Associated with Floor Tile Under Carpet – Observation Room and Closet
• Floor Tile Under Carpet and Mastic Associated with Floor Tile – Exhibit Room 01 and Exhibit Room 02
• 9” x 9” Grey Floor Tile Under Carpet and Mastic Associated with Floor Tile – Bookstore and Bookstore Office
The results of the visual inspection and results from previously completed survey report by ARC Environmental, Inc., dated February 2017 have determined that the following Non-ACM exist in the building:
• 2’ x 2’ Deep Patterned ceiling Tiles – Throughout Interior
• 4” Black Cove base and Associated Mastic – Throughout Interior
• Gypsum Board and Joint Compound – Throughout Interior
• 2’ x 2’ Black Pinhole and Gouge Ceiling Tile – Throughout Interior
• 2’ x 4’ Black Pinhole and Gouge ceiling Tiles – Throughout Interior
• 4” Dark Grey Cove base and Associated Mastic – Throughout Interior
• 1’ x 1’ Spline Ceiling Tile – Throughout Interior
• 6” x 6” Patterned Linoleum – Throughout Interior
Louis Berger Page 6 December 02, 2019
• 2’ x 2’ Pinhole Ceiling Tiles – Throughout Interior
• 2’ x 4’ Wormhole Ceiling Tile – Throughout Interior
• 4” Gray Cove Base and Associated Mastic – Throughout Interior
• 6” Tan Cove Base and Associated Mastic– Throughout Interior
• 2’ x 2’ Black Rough Textured Ceiling Tile – Throughout Interior
• Carpet Mastic – Throughout Interior (Except Auditorium)
• Wall Plaster (Brown and White Coats)
• Ceiling Plaster – Throughout Interior (Except Bathrooms)
• 6” Patterned Linoleum
The results of the visual inspection, results from previously completed survey report by ARC Environmental, Inc., dated February 2017, XRF readings and paint chip sample analysis have determined that the following Lead-Based Paints exist in the building:
• Red/Blue Metal Pipe Paint – Mechanical Room
• Black Metal Pipe Paint – Slop Sink Closet
• White Ceramic Tile Wall – Men’s Bathroom
• Beige/Gray Wood Wall – Lobby
The results of the visual inspection, results from previously completed survey report by ARC Environmental, Inc., dated February 2017, XRF readings and paint chip sample analysis have determined that the following testing combinations are not coated with lead-based paint (less than
0.7 mg/cm²):
• Brown Metal Door Casing – Slop Sink Closet
• Tan Gypsum Board Wall – Slop Sink Closet, Visitor’s Center Office 01 and 02
• White Metal Door, Door Jamb, Door Casing – Visitor’s Center Office 01 and 02
• White Vinyl Base Board – Visitor’s Center Office 01
• Grey Wood Closet Shelf – Visitor’s Center Office 02
• Grey Metal Door, Door Jamb, Door Casing – Mechanical Room and Storage Closet by
Elevator
• Grey Gypsum Board Wall – Break Room, Mechanical Room and Storage Closet by
Elevator
• Grey Metal Door, Door Jamb, Door Casing – Men’s Rest Room, Gift Shop Office and
Gift Shop
• White Gypsum Board Wall – Men’s Rest Room, Gift Shop Office and Gift Shop
• White Plaster Ceiling – Men’s Rest Room
• Grey Metal Door, Door Jamb, Door Casing – Museum and Lobby/Hallway
• Tan Gypsum Board Wall – Museum
• Grey Plaster Ceiling - Lobby/Hallway
• Beige Metal Door, Door Jamb, Door Casing – Observation Room
• Tan Metal Window Casing – Observation Room
• Tan Gypsum Wall - Observation Room
• Beige/Gray Wood Wall – Exterior Façade
• Beige/Gray Wood Door/Door Frame – Exterior Façade
Louis Berger Page 7 December 02, 2019
• Beige/Gray Wood Window Frame – Exterior Façade
• Beige/Gray Wood Trellis – Exterior
• Beige/Gray Wood Window/Window Frame – Interior
• Beige/Gray Wood Door/Door Frame – Interior
• Green Cinder Block Wall – Observation Room Closet
• Red Metal Railing – Janitor’s Closet
• White Cinder Block Wall – Mechanical Room
2.0 ASBESTOS FIELD INVESTIGATION PROCEDURES AND SAMPLE ANALYSIS
METHODS
Guidelines used for the inspection were established by the Environmental Protection Agency (EPA) in the Guidance for Controlling Asbestos Containing Materials in Buildings, Office of Pesticides and Toxic Substances, Doc 560/5-85-024, and 40 CFR Part 763, Asbestos Hazard Emergency Response Act (AHERA).
Field information was organized in accordance with the AHERA methodology of homogenous area (HA). During the survey, reasonable effort was made to identify all locations and types of ACM materials associated with the scope of work. Sampling has included multiple samples of the same materials with locations chosen at random. However, due to inconsistencies of a manufacturer's processes and the contractor’s installation methods, materials of similar construction may contain various amounts of asbestos. Furthermore, some materials that were not originally specified to contain asbestos may in fact contain this mineral.
Bulk samples of suspect ACM were analyzed using polarized light microscopy (PLM) coupled with dispersion staining, as described in 40 CFR Part 763 and the National Emissions Standard for Hazardous Air Pollutants (NESHAPS). NESHAPS is the standard industry protocol for the determination of asbestos in building materials. A suspect material is immersed in a solution of known refractive index and subjected to illumination by polarized light. The color displays that result are compared to a standardized atlas whereby the specific variety of asbestos is determined. It should also be recognized that PLM is primarily a qualitative identification method whereby asbestos percentage, if any, is estimated. While EPA regulations governing ACM consider materials containing greater than 1-percent as asbestos, accurately quantifying asbestos content below 5-percent has been shown to be unreliable.
The laboratory performing this analysis procedure was Atlas Environmental Lab, Corp., located at 255 W 36th Street Suite 1503, New York, NY 10018. The laboratory has received accreditation from the following agencies:
National Voluntary Laboratory Accreditation Program (Lab Code 500092-0) American Industrial Hygiene Association Accredited Laboratory (Lab No. 208306)
Louis Berger Page 8
2.1 INSPECTION SCOPE AND MATERIAL ASSESSMENT FOR ASBESTOS
The areas inspected for ACM materials which may exist:
• Antietam Visitor Center, Antietam National Battlefield, Sharpsburg, MD, throughout Interior and Exterior, Roofs
The inspection was characterized by observations of accessible areas. Predominant suspect materials were sampled and quantified.
Materials examined during the inspection included:
• Chimney Mortar (Gray) – Observation Roof
• Caulking @ Chimney (Gray) – Observation Roof
• Caulking at Perimeter of Roof (Gray) – Observation Roof
• Chimney Flashing (Black) – Observation Roof
• Bottom Membrane (Black) – Observation Roof
• Felt Paper (Gray/Black) – Observation Roof
• Insulation (Beige) – Observation Roof
• Top Membrane (Black) – Observation Roof
• Tar @ Bottom Layer (Black) – Main Roof
• Felt Paper (Gray/Black) – Main Roof and Auditorium Roof
• Perlite Insulation (Tan) – Main Roof and Auditorium Roof
• Insulation (Beige) – Main Roof and Auditorium Roof
• Top Membrane (Black) – Main Roof and Auditorium Roof
• Metal Cap Flashing Caulking (Gray) – Main Roof and Auditorium Roof
• Old Tar on Parapet Wall (Black) – Main Roof and Auditorium Roof
• Coping Stone Caulking (Gray) – Main Roof and Auditorium Roof
• Perimeter Flashing (Black) – Main Roof and Auditorium Roof
• Mechanical Flashing (Black) – Main Roof and Auditorium Roof
• Vent Stack Flashing (Black) – Main Roof and Auditorium Roof
• Stone Mortar at Stone Wall (Gray) – Main Roof and Auditorium Roof
• Roof Drain Flashing (Black) – Main Roof and Auditorium Roof
• Skylight Flashing (Black) – Main Roof and Auditorium Roof
• Exterior Paint (Beige) – Throughout Exterior
• Exterior Window Frame Glazing (Black) – Throughout Exterior
• Tar @ Building Base (Black) – Throughout Exterior
• Exterior Façade Stone Mortar (Gray) – Throughout Exterior
• Gypsum Board (Beige) – Auditorium Exterior Exit Overhang
• Exterior Window Frame Caulking (White) – Throughout Exterior
• Exterior Door Frame Caulking (Gray)
• Sidewalk Expansion @ Shed Structures (Gray) –Exterior @ Storage Sheds
• Roofing Shingles (Black) –Exterior @ Storage Sheds
Louis Berger Page 9 December 02, 2019
• Felt Paper under Roofing Shingles (Black) –Exterior @ Storage Sheds
• Stone Mortar (Red) – Auditorium
• Leveling Compound on Concrete Floor (Gray) – Auditorium
• Carpet Glue (Yellow) – Auditorium
• Caulking Around Toilet Fixtures (White) – Interior Throughout Bathrooms
• Ceramic Wall Tile Backing (White) – Interior Throughout Bathrooms
• Ceramic Wall Tile Grout (White) – Interior Throughout Bathrooms
• Ceramic Floor Tile Grout (Gray) – Interior Throughout Bathrooms
• Ceramic Floor Tile Backing Under 1st Layer (Gray) – Interior Throughout Bathrooms
• Ceramic Floor Tile Backing Under 2nd Layer (Gray) – Interior Throughout Bathrooms
• Fiberglass Duct Insulation Wrap (Silver) – Interior Throughout
• Perlite Insulation Within Ceiling Plenum (Gray/Brown) – Interior Throughout
• Interior Window Frame Caulking (White) – Interior Throughout
• Ceiling Plaster (White and Brown Coats) – Interior Throughout
• Interior Brick Mortar (Gray) – Interior Throughout
• Cinder Block Mortar (Gray) – Interior Throughout
• 12” x 12” Black Floor Tile and Mastic Associated with Floor Tile – Projection Room and
Janitor’s Closet
• Floor Tile Under Linoleum and ACM Mastic Associated with Floor Tile - Office 01, Office 02, Office 02 closet, Office 03 and Associated Hallway
• 9” x 9” Tan with White Floor Tile and Mastic Associated with Floor Tile Under Carpet –
Observation Room and Closet
• Floor Tile Under Carpet and ACM Mastic Associated with Floor Tile – Exhibit Room 01 and Exhibit Room 02
• 9” x 9” Grey Floor Tile Under Carpet and ACM Mastic Associated with Floor Tile –
Bookstore and Bookstore Office
• Expansion Joint @ Building Base (Gray/Beige)
• 2’ x 2’ Deep Patterned ceiling Tiles – Throughout Interior
• 4” Black Cove base and Associated Mastic – Throughout Interior
• Gypsum Board and Joint Compound – Throughout Interior
• 2’ x 2’ Black Pinhole and Gouge Ceiling Tile – Throughout Interior
• 2’ x 4’ Black Pinhole and Gouge ceiling Tiles – Throughout Interior
• 4” Dark Grey Cove base and Associated Mastic – Throughout Interior
• 1’ x 1’ Spline Ceiling Tile – Throughout Interior
• 6” x 6” Patterned Linoleum – Throughout Interior
• 2’ x 2’ Pinhole Ceiling Tiles – Throughout Interior
• 2’ x 4’ Wormhole Ceiling Tile – Throughout Interior
• 4” Gray Cove Base and Associated Mastic – Throughout Interior
• 6” Tan Cove Base and Associated Mastic– Throughout Interior
• 2’ x 2’ Black Rough Textured Ceiling Tile – Throughout Interior
• Carpet Mastic – Throughout Interior (Except Auditorium)
• Wall Plaster (Brown and White Coats)
• Ceiling Plaster – Throughout Interior (Except Bathrooms)
Louis Berger Page 10
• 6” Patterned Linoleum
2.2 ASBESTOS INSPECTION RESULTS
The asbestos inspection involved a thorough visual examination of all areas which may be impacted by any potential renovation. The following suspect materials were inspected and/or sampled and analyzed for asbestos content:
Homogenous Material Location Material Asbestos Content
A Observation Room Roof Chimney Mortar (Gray) NAD
B Observation Room Roof Caulking @ Chimney (Gray) NAD
C Observation Room Roof Caulking at Perimeter of Roof (Gray) NAD
D Observation Room Roof Chimney Flashing (Black) NAD
E Observation Room Roof Bottom Membrane (Black) NAD
F Observation Room Roof Felt Paper (Gray/Black) NAD
G Observation Room Roof Insulation (Beige) NAD
H Observation Room Roof Top Membrane (Black) NAD
I Main Roof and Auditorium Roof Tar @ Bottom Layer (Black) NAD
J Main Roof and Auditorium Roof Felt Paper (Gray/Black) NAD
K Main Roof and Auditorium Roof Perlite Insulation (Tan) NAD
L Main Roof and Auditorium Roof Insulation (Beige) NAD
M Main Roof and Auditorium Roof Top Membrane (Black) NAD
N Main Roof and Auditorium Roof Metal Cap Flashing Caulking (Gray) NAD
O Main Roof and Auditorium Roof Old Tar on Parapet Wall (Black) NAD
P Main Roof and Auditorium Roof Coping Stone Caulking (Gray) NAD
Q Main Roof and Auditorium Roof Perimeter Flashing (Black) NAD
R Main Roof and Auditorium Roof Mechanical Flashing (Black) NAD
S Main Roof and Auditorium Roof Vent Stack Flashing (Black) NAD
Louis Berger Page 11 December 02, 2019
Homogenous Material Location Material Asbestos Content
T Main Roof and Auditorium Roof Stone Mortar at Stone Wall (Gray) NAD
U Main Roof and Auditorium Roof Roof Drain Flashing (Black) NAD
01 Main Roof and Auditorium Roof Metal Drains Non-Suspect
V Main Roof and Auditorium Roof Skylight Flashing (Black) NAD
02 Main Roof and Auditorium Roof Skylight Non-Suspect
03 Main Roof and Auditorium Roof Skylight Glazing Not-Observed
04 Throughout Roofs Electrical Wire Insulation Assoc. w/ Lighting Fixtures Non-Suspect
W Throughout Exterior Exterior Paint (Beige) NAD
X Throughout Exterior Exterior Window Frame Glazing (Black) NAD
D1 Throughout Exterior Exterior Window Frame Caulking (White)
Y Throughout Exterior Tar @ Building Base (Black) NAD
Z Throughout Exterior Expansion Joint @ Building Base (Gray/Beige) 6% Chrysotile
B1 Throughout Exterior Exterior Façade Stone Mortar (Gray) NAD
E1 Throughout Exterior Exterior Door Frame Caulking (Gray) NAD
C1 Exterior @ Auditorium
Gypsum Board (Beige) @ Auditorium Exterior Exit Overhang NAD
F1 Exterior @ Sheds Sidewalk Expansion @ Shed Structures (Gray) NAD
G1 Exterior @ Sheds Roofing Shingles (Black) NAD
H1 Exterior @ Sheds Felt Paper under Roofing Shingles (Black) NAD
K1 Interior - Auditorium Stone Mortar (Red) NAD
L1 Interior - Auditorium Leveling Compound on Concrete Floor (Gray) NAD
M1 Interior - Auditorium Carpet Glue (Yellow) NAD
N1 Interior Throughout Bathrooms Caulking Around Toilet Fixtures (White) NAD
O1 Interior Throughout Bathrooms Ceramic Wall Tile Backing (White) NAD
P1 Interior Throughout Bathrooms Ceramic Wall Tile Grout (White) NAD
Q1 Interior Throughout Bathrooms Ceramic Floor Tile Grout (Gray) NAD
R1 Interior Throughout Bathrooms
Ceramic Floor Tile Backing Under 1st Layer (Gray) NAD
S1 Interior Throughout Bathrooms
Ceramic Floor Tile Backing Under 2nd Layer (Gray NAD
Louis Berger Page 12 December 02, 2019
Homogenous Material Location Material Asbestos Content
05 Interior Throughout Carpet Non-Suspect
06 Interior Throughout Electrical Wire Insulation Assoc. w/ Lighting Fixtures, Switches and Panels Non-Suspect
07 Interior Throughout Metal Ducts Within Ceiling Plenum Non-Suspect
08 Interior Throughout Fiberglass Fire Door Insulation Non-Suspect
09 Interior Throughout Brick Non-Suspect
B2 Interior Throughout Brick Mortar (Gray) NAD
10 Interior Throughout Cinder Block Non-Suspect
D2 Interior Throughout Cinder Block Mortar NAD
U1 Interior Throughout Fiberglass Duct Insulation Cover (Silver) NAD
W1 Interior Throughout Interior Window Frame caulking (White) NAD
11 Interior Throughout 4” Black Cove base and Associated Mastic NAD
12 Interior Throughout 4” Black Cove base and Associated Mastic NAD
13 Interior Throughout Gypsum Board and Joint Compound NAD
14 Interior Throughout 2’ x 2’ Black Pinhole and Gouge Ceiling Tile NAD
15 Interior Throughout 2’ x 4’ Black Pinhole and Gouge Ceiling Tiles NAD
16 Interior Throughout 4” Dark Grey Cove base and Associated Mastic NAD
17 Interior Throughout 1’ x 1’ Spline Ceiling Tile NAD
18 Interior Throughout 6” x 6” Patterned Linoleum NAD
19 Interior Throughout 2’ x 2’ Pinhole Ceiling Tiles NAD
20 Interior Throughout 2’ x 4’ Wormhole Ceiling Tile NAD
21 Interior Throughout 4” Gray Cove Base and Associated Mastic NAD
22 Interior Throughout 6” Tan Cove Base and Associated Mastic NAD
23 Interior Throughout 2’ x 2’ Black Rough Textured Ceiling Tile NAD
24 Interior Throughout Wall Plaster (Brown and White Coats) NAD
25 Interior Throughout 6” Patterned Linoleum NAD
Throughout Interior (Except Observation Room Closet, Men’s Toilet and Gift Shop
Office)
Ceiling Plaster (Brown and White Coats) NAD
X1 Observation Room
Closet, Men’s Toilet and Gift Shop Office
Ceiling Plaster (Brown) NAD
Y1 Observation Room
Closet, Men’s Toilet and Gift Shop Office
Ceiling Plaster (White) NAD
Louis Berger Page 13 December 02, 2019
Homogenous Material Location Material Asbestos Content
27 Throughout Interior (Except Auditorium) Carpet Mastic NAD
V1 Gift Shop Ceiling Plenum
Perlite Insulation Within Ceiling Plenum (Gray/Brown) NAD
X1 Observation Room
Closet, Men’s Toilet and Gift Shop Office
Ceiling Plaster (Brown) NAD
Y1 Observation Room
Closet, Men’s Toilet and Gift Shop Office
Ceiling Plaster (White) NAD
28 Projection Room and Janitor’s Closet 12” x 12” Black Floor Tile
ACM
Contaminated by Associated Mastic
29 Projection Room and Janitor’s Closet Mastic Associated with Floor Tile 7% Chrysotile
Office 01, Office 02, Office 02 closet, Office 03 and Associated Hallway
Linoleum NAD
Office 01, Office 02, Office 02 closet, Office 03 and Associated Hallway
Floor Tile Under Linoleum 3% Chrysotile
Office 01, Office 02, Office 02 closet, Office 03 and Associated Hallway
Mastic Associated with Floor Tile 2% Chrysotile
33 Observation Room and Closet
9” x 9” Tan with White Floor Tile Under Carpet 5% Chrysotile
34 Observation Room and Closet Mastic Associated with Floor Tile 7% Chrysotile
Exhibit Room 01 and Exhibit Room
Floor Tile Under Carpet 3% Chrysotile
Exhibit Room 01 and Exhibit Room
Mastic Associated with Floor Tile 2% Chrysotile
37 Bookstore and Bookstore Office 9” x 9” Grey Floor Tile Under Carpet 4% Chrysotile
38 Bookstore and Bookstore Office Mastic Associated with Floor Tile 3% Chrysotile
Bold=Positive for ACM NAD=No Asbestos Detected NA/PS=Not Analyzed/Positive Stop Trace=Trace amount of asbestos
Louis Berger Page 14 December 02, 2019
2.3 CONDITION, QUANTITY AND FRIABLITY ASSESSMENT TABLE
For each inspection conducted, the inspector classifies ACM materials by friability and condition.
This helps to determine the extent of damage in certain areas as well as the potential for further damage and Asbestos release due to disturbance of the material. The following table summarizes the confirmed ACM and their approximate quantities.
Material Location Quantity Friability Condition 12” x 12” Black Floor Tile and Mastic Associated with
Floor Tile
Projection Room and Janitor’s Closet 210 SF Non-
Friable Damaged
Floor Tile Under Linoleum and Mastic Associated with
Floor Tile
Office 01, Office 02, Office 02 Closet, Office 03 and Associated Hallway
450 SF Non- Friable Good
9” x 9” Tan with White Floor Tile and Mastic
Associated with Floor Tile Under Carpet
Observation Room and Closet 1,190 Non- Friable Good
Floor Tile Under Carpet and Mastic Associated with
Floor Tile
Exhibit Room 01 and Exhibit Room 02 1,540 Non-
Friable Good
9” x 9” Grey Floor Tile Under Carpet and Mastic
Associated with Floor Tile
Bookstore and Bookstore Office 1,100 Non-
Friable Good
Expansion Joint @ Building Base (Gray/Beige) Throughout Exterior 450 LF /
35 SF
Non-
Friable Damaged
Condition Definitions:
Good: None/Minimal apparent damage to ACM Damaged: Up to 10% localized damage or up to 25% of the entire ACM is damaged Significantly Damaged: Over 10% localized damage or over 25% of the entire ACM is damaged
Notes:
Quantities are an approximation and should be confirmed by contractor during pre-abatement walk through.
Asbestos abatement contractor shall be responsible to remove all layers of materials to substrate.
2.4 SAMPLE ANALYSIS TABLE
Laboratory analysis results, in tabular form, are included in Appendix A.
2.5 AREAS NOT ACCESSIBLE
At the time of inspection, Berger’s inspection team was not able to access the ceiling plenum in the Men’s and Women’s Bathroom at Antietam Visitor Center.
3.0 LEAD FIELD INSPECTION PROCEDURES
The lead-based paint inspection is an interior and exterior investigation to identify all lead-based paint on a surface-by-surface basis by paint chip sampling methodology.
Louis Berger Page 15 December 02, 2019
The lead in soil inspection consisted of collecting composite soil samples from bare soil in the dripline/foundation area or the building. Soil samples were collected with a scooping technique.
Soil samples was collected up to a depth of approx. ½ inches, following the US EPA HUD (US Dept. of Housing and Urban Development) Scoop Sampling Guidelines (Appendix 13.3).
The lead regulatory levels provided below are those used when preparing this lead-based paint evaluation or when evaluating data collected.
EPA Levels
Lead-Based Paint Guideline for Maryland Equal to or less than 0.7 mg/cm2
The laboratory performing this analysis procedure was Atlas Environmental Lab, Corp., located at 255 W 36th Street Suite 1503, New York, NY 10018. The laboratory has received accreditation from the following agencies:
National Voluntary Laboratory Accreditation Program (Lab Code 500092-0) American Industrial Hygiene Association Accredited Laboratory (Lab No. 208306)
3.1 INSPECTION SUMMARY
The areas inspected for LBP included:
• Antietam Visitor Center, Interior and Exterior
The inspection was characterized by observations of accessible areas. Suspect surfaces were tested using Paint Chip Sampling.
Coated surfaces examined during the inspection included:
• Brown Metal Door Casing – Slop Sink Closet
• Tan Gypsum Board Wall – Slop Sink Closet, Visitor’s Center Office 01 and 02
• White Metal Door, Door Jamb, Door Casing – Visitor’s Center Office 01 and 02
• White Vinyl Base Board – Visitor’s Center Office 01
• Grey Wood Closet Shelf – Visitor’s Center Office 02
• Grey Metal Door, Door Jamb, Door Casing – Mechanical Room and Storage Closet by
Elevator
• Grey Gypsum Board Wall – Break Room, Mechanical Room and Storage Closet by
Elevator
• Grey Metal Door, Door Jamb, Door Casing – Men’s Rest Room, Gift Shop Office and
Gift Shop
• White Gypsum Board Wall – Men’s Rest Room, Gift Shop Office and Gift Shop
• White Plaster Ceiling – Men’s Rest Room
• Grey Metal Door, Door Jamb, Door Casing – Museum and Lobby/Hallway
Louis Berger Page 16 December 02, 2019
• Tan Gypsum Board Wall – Museum
• Grey Plaster Ceiling - Lobby/Hallway
• Beige Metal Door, Door Jamb, Door Casing – Observation Room
• Tan Metal Window Casing – Observation Room
• Tan Gypsum Wall - Observation Room
• Beige/Gray Wood Wall – Exterior Façade
• Beige/Gray Wood Door/Door Frame – Exterior Façade
• Beige/Gray Wood Window Frame – Exterior Façade
• Beige/Gray Wood Trellis – Exterior
• Beige/Gray Wood Window/Window Frame – Interior
• Beige/Gray Wood Door/Door Frame – Interior
• Green Cinder Block Wall – Observation Room Closet
• Red Metal Railing – Janitor’s Closet
• White Cinder Block Wall – Mechanical Room
• Red/Blue Metal Pipe Paint – Mechanical Room
• Black Metal Pipe Paint – Slop Sink Closet
• White Ceramic Tile Wall – Men’s Bathroom
• Beige/Gray Wood Wall – Lobby
Based upon Paint Chip Sampling results and XRF readings from a completed survey report by ARC Environmental, Inc., dated February 2017, lead has been confirmed to exist in the following tested combinations within the building:
• Red/Blue Metal Pipe Paint – Mechanical Room
• Black Metal Pipe Paint – Slop Sink Closet
• White Ceramic Tile Wall – Men’s Bathroom
• Beige/Gray Wood Wall – Lobby
Based upon paint chip sample analysis results and previously completed report by ARC Environmental, Inc., dated February 2017, lead was not detected in the following tested combinations within the building via paint chip sample analysis results:
• Brown Metal Door Casing – Slop Sink Closet
• Tan Gypsum Board Wall – Slop Sink Closet, Visitor’s Center Office 01 and 02
• White Metal Door, Door Jamb, Door Casing – Visitor’s Center Office 01 and 02
• White Vinyl Base Board – Visitor’s Center Office 01
• Grey Wood Closet Shelf – Visitor’s Center Office 02
• Grey Metal Door, Door Jamb, Door Casing – Mechanical Room and Storage Closet by
Elevator
• Grey Gypsum Board Wall – Break Room, Mechanical Room and Storage Closet by
Elevator
• Grey Metal Door, Door Jamb, Door Casing – Men’s Rest Room, Gift Shop Office and
Gift Shop
• White Gypsum Board Wall – Men’s Rest Room, Gift Shop Office and Gift Shop
• White Plaster Ceiling – Men’s Rest Room
Louis Berger Page 17 December 02, 2019
• Grey Metal Door, Door Jamb, Door Casing – Museum and Lobby/Hallway
• Tan Gypsum Board Wall – Museum
• Grey Plaster Ceiling - Lobby/Hallway
• Beige Metal Door, Door Jamb, Door Casing – Observation Room
• Tan Metal Window Casing – Observation Room
• Tan Gypsum Wall - Observation Room
• Beige/Gray Wood Wall – Exterior Façade
• Beige/Gray Wood Door/Door Frame – Exterior Façade
• Beige/Gray Wood Window Frame – Exterior Façade
• Beige/Gray Wood Trellis – Exterior
• Beige/Gray Wood Window/Window Frame – Interior
• Beige/Gray Wood Door/Door Frame – Interior
• Green Cinder Block Wall – Observation Room Closet
• Red Metal Railing – Janitor’s Closet
• White Cinder Block Wall – Mechanical Room
3.2 INSPECTION RESULTS
The lead inspection involved a thorough visual examination of all accessible areas impacted by the demolition project. The following suspect surfaces were tested for lead content:
LOCATION COMPONENT NAME COLOR SUBSTRATE RESULT
Mechanical Room Pipe Red/Blue Metal LBP*
Slop Sink Closet Pipe Black Metal LBP*
Men’s Bathroom Wall White Ceramic LBP*
Lobby Wall Beige/Gray Wood LBP
Slop Sink Closet Door Casing Brown Metal Non-LBP*
Slop Sink Closet, Visitor’s Center Office
01 and 02 Wall Tan Gypsum
Board Non-LBP*
Visitor’s Center Office 01 and 02
Door, Door Jamb, Door Casing White Metal Non-LBP*
Visitor’s Center Office 01 Base Board White Vinyl Non-LBP*
Visitor’s Center Office 02 Closet Shelf Grey Wood Non-LBP*
Mechanical Room and Storage Closet by
Elevator
Door, Door Jamb, Door Casing Grey Metal Non-LBP*
Louis Berger Page 18 December 02, 2019
LOCATION COMPONENT NAME COLOR SUBSTRATE RESULT
Break Room, Mechanical Room and
Storage Closet by Elevator
Wall Grey Gypsum Board Non-LBP*
Men’s Rest Room, Gift Shop Office and Gift
Shop
Door, Door Jamb, Door Casing Grey Metal Non-LBP*
Men’s Rest Room, Gift Shop Office and Gift
Shop Wall White Gypsum
Board Non-LBP*
Men’s Rest Room Ceiling White Plaster Non-LBP* Museum and
Lobby/Hallway Door, Door Jamb, Door
Casing Grey Metal Non-LBP*
Museum Wall Tan Gypsum Board Non-LBP*
Lobby/Hallway Ceiling Grey Plaster Non-LBP*
Observation Room Door, Door Jamb, Door Casing Beige Metal Non-LBP*
Observation Room Window Casing Tan Metal Non-LBP*
Observation Room Wall Tan Gypsum Board Non-LBP*
Exterior Wall Beige/Gray Wood Non-LBP
Exterior Door/Door Frame Beige/Gray Wood Non-LBP
Exterior Window Frame Beige/Gray Wood Non-LBP
Exterior Trellis Beige/Gray Wood Non-LBP
Interior Window/Window Frame Beige/Gray Wood Non-LBP
Interior Door/Door Frame Beige/Gray Wood Non-LBP Observation Room
Closet Wall Green Cinder Block Non-LBP
Janitor’s Closet Railing Red Metal Non-LBP
Mechanical Room Wall White Cinder Block Non-LBP Bold=Positive for LBP *LBP or Non-LBP=Confirmed via previous survey reports
3.3 CONDITION ASSESSMENT TABLE
For the inspection conducted, the inspector classifies the LBP and the condition of the surface.
The following table summarizes only the confirmed LBP.
Louis Berger Page 19 December 02, 2019
Location Component Name Substrate Color Condition Results Quantity
Mechanical Room Pipe Metal Red/Blue Fair/Good LBP 50 SF
Slop Sink Closet Pipe Metal Black Fair/Good LBP 50 SF
Men’s Bathroom Wall Ceramic White Fair/Good LBP 400 SF
Lobby Wall Wood Beige/Gray Fair/Good LBP 1,200 SF
3.4 AREAS NOT ACCESSIBLE
At the time of inspection, Berger’s inspection team was able to access all areas at Antietam Visitor Center.
3.5 CONCLUSIONS AND RECOMMENDATIONS
Various Lead-based Paints have been identified in our inspection effort.
Any work which disturbs painted surfaces containing lead shall be performed, and waste managed and transported in accordance with the Occupational Safety and Health Administration (OSHA), 29 CFR 1926.62 (Lead in Construction Standard), and EPA’s 40 CFR 745 regulation, and New York State 6 NYCRR 364. Personal air monitoring should be conducted when disturbing lead based paints and lead containing materials as per 29CFR1926.62 (OSHA).
Prior to any excavation activities, a site-specific health and safety plan (HASP) must be submitted by Contractor which will meet the requirements set forth by the Occupational Safety and Health Administration (OSHA) and any other applicable regulations. The HASP should identify the possible locations and risks associated with potential contaminants that may be encountered and the administrative and engineering controls that will be utilized to mitigate concerns.
In addition, all waste generated as part of the project, regardless of the lead content in the paint, shall be tested in accordance with the EPA Resource Conservation and Recovery Act (RCRA) to determine the classification of the waste. Under RCRA, any waste material that when tested by Toxicity Characteristics Leaching Procedure (TCLP) results in a leachate lead concentration of five (5) parts per million or greater must be disposed of at an EPA licensed hazardous waste facility.
The finer renovation debris and paint chips that result from renovation of components with measurable quantities of lead can be tested by TCLP, or can be assumed hazardous waste and disposed of accordingly. If the scope of work is increased to include removal of actionable building components, we recommend that a TCLP test be performed on one typical component (e.g. metal, sheetrock, masonry, etc.) to determine proper disposal for all similar components.
Louis Berger Page 20
The incurred cost for disposal of lead based paint materials/debris may depend upon the TCLP results for materials/debris collected and the total weight of items which return TCLP results above the EPA allowed 5 parts per million.
The cost of the TCLP depends on the laboratory and location; but typically, a lead TCLP analysis may cost from $40 to $80. Any waste material that when tested by TCLP results in a leachate lead concentration of five (5) parts per million or greater must be disposed of at an EPA licensed hazardous waste facility. Cost of disposal may range for $5,000 to $7,000 per ton of waste.
5.0 UNIVERSAL WASTES
Universal Wastes (i.e., batteries, thermostats, lamps, ballasts, mercury-containing equipment, radioactive sources, CFCs) are regulated pursuant to the USEPA Universal Waste Requirements (40 CFR Part 273), and New York State 6 NYCRR Parts 370 series regulations. Similarly, these sampling procedures may also be used to determine disposal/management or clean-up options for Universal Wastes. Typical equipment that might contain universal wastes are emergency light batteries, CFC containing refrigerators, water fountains, mercury containing bulbs, thermostats and thermometers. Please see the below table itemizing the number of assumed universal wastes:
Facility (Floor/Level)
Fluorescent Bulbs
/Lamps
CFC
Containing Materials
Mercury Containing Materials
PCB
Containing Materials
Radioactive Materials
Miscellaneous Materials
Observation Room 8 Lamps None None None None
Ballasts-8;
Smoke detectors-1;
Fire Extinguisher-1
Gift Shop Office 2 Lamps 1 Split A/C
Unit None None None Ballasts-2;
Smoke detectors-1;
Fire Extinguisher-1
Gift Shop 8 Lamps 1 Split A/C Unit None None None
Ballasts-8;
Smoke detectors-1;
Exit Sign-1
Offices and Vestibules 11 lamps None None None None
Ballasts-11;
Smoke detectors-4;
Fire Extinguisher-1
Exhibit Rooms 27 Lamps None None None None
Ballasts-27;
Smoke detectors-4;
Fire Extinguisher-1;
Exit Sign-1
Lobby 17 Lamps 1 Water Cooler None None None
Ballasts-17;
Smoke detectors-2;
Exit Sign-1
Entry Way 2 Lamps None None None None Ballasts-2;
Exit Sign-1
Mechanical Room 3 Lamps 1 Air
Handler None None None Ballasts-3;
Smoke Detector-1;
Batteries- 50
Louis Berger Page 21 December 02, 2019
Facility (Floor/Level)
Fluorescent Bulbs
/Lamps
CFC
Containing Materials
Mercury Containing Materials
PCB
Containing Materials
Radioactive Materials
Miscellaneous Materials
Janitor’s Closet 2 Lamps None None None None
Ballasts-2;
Smoke Detectors- 3;
Batteries- 200
Hallway 2 Lamps None None None None Ballasts-2;
Fire Extinguisher-1
Men’s Room 3 Lamps None None None None Ballasts-3
Women’s Room 3 Lamps None None None None Ballasts-3
Auditorium 8 Lamps None None None None Ballasts-8;
Exit Signs- 2;
Smoke Detectors- 2
6.0 CONCLUSIONS AND RECOMMENDATIONS
Various ACM and LBP have been identified in our inspection effort that will be impacted by the upcoming site restoration project. These materials, reported in Section 2.0 and Section 3.0 of this report, will require complete abatement prior to the start of the project as per all…